Evaluation device, evaluation method, and program

The evaluation device calculates network reliability during disasters by using predicted damage values and machine learning, addressing the inadequacies of existing methods in assessing communication network integrity during emergencies, thereby enhancing disaster response and recovery efforts.

WO2024202043A1PCT designated stage expired Publication Date: 2024-10-03NIPPON TELEGRAPH & TELEPHONE CORP
View PDF 2 Cites 0 Cited by

Patent Information

Application Number
PCT/JP2023/013637
Authority / Receiving Office
WO · WO
Patent Type
Applications
Current Assignee / Owner
Filing Date
2023-03-31
Publication Date
2024-10-03

AI Technical Summary

Technical Problem

Existing methods for evaluating communication network reliability are inadequate during large-scale disasters like earthquakes, as they are based on normal conditions and fail to accurately assess the increased probability of network link interruptions.

Method used

An evaluation device and method that calculates the disconnection probability of network links based on predicted disaster damage values and connection data, using machine learning to determine the reliability of communication between nodes during emergencies.

Benefits of technology

Enables high-accuracy evaluation of network reliability during disasters, providing critical information for disaster response and recovery by quantifying the probability of communication link interruptions and overall network connectivity.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure JP2023013637_03102024_PF_FP_ABST
    Figure JP2023013637_03102024_PF_FP_ABST
Patent Text Reader

Abstract

This evaluation device (100) is for evaluating a network having a plurality of buildings and communication lines connecting the buildings. The evaluation device (100) is provided with: a first storage unit (1) for storing, when a disaster occurs, a damage prediction value of protection equipment for communication lines; a second storage unit (2) for storing connection data on each communication line; a disconnection probability calculation unit (4) for calculating the disconnection probability of each communication line on the basis of the damage prediction value and the connection data; and a reliability calculation unit (5) for calculating, on the basis of the disconnection probability of each communication line, the probability that the communication line is normally connected between two buildings.
Need to check novelty before this filing date? Find Prior Art

Description

Evaluation device, evaluation method, and program

[0001] The present disclosure relates to an evaluation device, an evaluation method, and a program.

[0002] 2. Description of the Related Art When a large-scale disaster such as an earthquake occurs, the reliability of communication networks is evaluated.

[0003] Non-Patent Document 1 discloses that a network is regarded as a graph G=(V,E) consisting of a node "V" and a link "E", and that the probability that specified nodes can communicate with each other is calculated in a situation where a failure rate qj (0<qj<1) of link j∈E is given. Non-Patent Document 2 discloses that, focusing on a specific node v∈V, the probability that node v will be unable to communicate with x or more other nodes is calculated.

[0004] The techniques disclosed in the above-mentioned Non-Patent Documents 1 and 2 are intended to evaluate the reliability of a network during normal times when no emergency situations such as disasters have occurred, and employ long-term statistical values ​​as the above-mentioned failure rate qj.

[0005] Furthermore, Non-Patent Document 3 discloses that machine learning is used to predict damage to underground conduits in which optical fibers for communication and the like are installed in the event of a disaster.

[0006] K. Nakamura, T. Inoue, M. Nishino, and N. Yasuda, “Efficient network reliability evaluation for client-server model,” in 2021 IEEE Global Communications Conference (GLOBECOM), 2021, pp. 1-6. K. Nakamura, T. Inoue, M. Nishino, N. Yasuda, and S.-i. Minato, “Exact and efficient network reliability evaluation per outage scale,” in 2023 IEEE International Conference on Computer Communications (ICC), 2023, to appear. Akira Ito, Dai Okutsu, Aiko Furukawa, Manabu Shoji, and Takanobu Suzuki, “Study on a damage prediction model using machine learning based on the results of earthquake inspections of underground telecommunication pipelines,” Transactions of the Japan Society of Civil Engineers, Proceedings of the JSCE A1 (Structural and Earthquake Engineering), vol. 78, no. 4, pp. I162-I172, 2022.

[0007] In the event of a disaster such as an earthquake, the probability of a communication network link being cut off increases dramatically compared to normal times. For this reason, the techniques disclosed in Non-Patent Documents 1 and 2, which are based on normal times, cannot properly evaluate the reliability of a network in the event of a disaster.

[0008] The technology disclosed in Non-Patent Document 3 can predict damage to underground pipelines in the event of a disaster, but does not evaluate the reliability of a communication network.

[0009] The present disclosure has been made in consideration of the above circumstances, and its purpose is to provide an evaluation device, an evaluation method, and a program that are capable of evaluating the reliability of a network with high accuracy in the event of a disaster.

[0010] An evaluation device of one embodiment of the present disclosure is an evaluation device that evaluates a network having a plurality of nodes and links connecting each node, and includes: a first memory unit that stores a damage prediction value of protection equipment for the links in the event of a disaster; a second memory unit that stores connection data for each of the links; an interruption probability calculation unit that calculates an interruption probability for each of the links based on the damage prediction value and the connection data; and a reliability calculation unit that calculates the probability that a link between two nodes will be normally connected based on the interruption probability for each of the links.

[0011] An evaluation method according to one aspect of the present disclosure is a method for evaluating a network having a plurality of nodes and links connecting each of the nodes, which, in the event of a disaster, stores a damage prediction value for the protection equipment of the links, stores connection data for each of the links, calculates a disconnection probability for each of the links based on the damage prediction value and the connection data, and calculates the probability that the link between two nodes will be connected normally based on the disconnection probability for each of the links.

[0012] One aspect of the present disclosure is a program for causing a computer to function as the evaluation device.

[0013] According to the present disclosure, it becomes possible to evaluate the reliability of a network with high accuracy when a disaster occurs.

[0014] FIG. 1 is a block diagram showing the configuration of an evaluation device and its peripheral devices according to an embodiment. FIG. 2 is an explanatory diagram showing multiple buildings and communication lines installed between the buildings. FIG. 3 is an explanatory diagram showing a communication line L1 and a conduit D1 installed between building B1 and building B2. FIG. 4 is a diagram showing the numbers of communication lines between buildings and the numbers of conduits. FIG. 5 is a diagram showing predicted damage values ​​for conduits. FIG. 6 is an explanatory diagram showing variables used in calculations using "XGboost". FIG. 7 is a flowchart showing the processing procedure of an evaluation device according to an embodiment. FIG. 8 is a graph showing unavailability rates by scale. FIG. 9 is a block diagram showing the hardware configuration of this embodiment.

[0015]

[0023] Hereinafter, an embodiment of the present disclosure will be described with reference to the drawings. Fig. 1 is a block diagram showing the configuration of an evaluation device and its peripheral devices according to an embodiment. The evaluation device 100 evaluates whether nodes connected to a network are properly connected by links in the event of a disaster or the like.

[0016] In this embodiment, a communication network that connects communication terminals installed in multiple buildings via communication lines will be described as an example of the network. A "building" is an example of a base where a communication terminal is installed. The communication terminals installed in multiple buildings are an example of nodes connected to the network, and a communication line is an example of a link connecting the nodes. Below, a communication terminal installed in "Building XX" will simply be referred to as "Building XX." In this embodiment, the probability that communication lines will be connected between buildings in the event of a disaster such as an earthquake is evaluated. Note that the present disclosure can also be applied to networks other than communication networks.

[0017] Figure 2 is an explanatory diagram showing multiple (four in the figure) buildings B1 to B4 and communication lines L1 to L4 installed between each of the buildings B1 to B4. Figure 3 is an explanatory diagram showing communication line L1 and conduit D1 (protection equipment) installed between buildings B1 and B2.

[0018] As shown in FIG. 2, a communication line L1 is installed between buildings B1 and B2, a communication line L2 is installed between buildings B2 and B3, a communication line L3 is installed between buildings B3 and B4, and a communication line L4 is installed between buildings B4 and B1.

[0019] As shown in Figure 3, the communication line L1 installed between buildings B1 and B2 is installed inside a conduit D1 buried underground. The conduit D1 is an example of a protective facility that protects the link (communication line L1). The communication line L1 includes three communication lines L1-1 to L1-3 connected in series. The conduit D1 includes three conduits D1-1 to D1-3 connected in series. The conduit D1 is buried underground and passes through the communication line L1.

[0020] The communication lines L1-1 to L1-3 are installed inside the pipelines D1-1 to D1-3, respectively. Maintenance manholes M1 to M4 are installed at the connections of the pipelines D1-1 to D1-3. While Fig. 3 shows an example in which the communication line L1 is installed so as to pass through the interiors of three pipelines D1-1 to D1-3, it may also pass through the interiors of two or less or four or more pipelines.

[0021] For simplicity of explanation, Fig. 3 shows only one communication line L1 and one duct D1 connecting two buildings B1 and B2. Multiple communication lines and ducts may be installed between multiple buildings. For example, although only communication line L1 is installed between buildings B1 and B2 in Fig. 2, two or more communication lines may be installed.

[0022] In this embodiment, underground conduits are used as an example of the equipment for installing communication lines L1-1 to L1-3 connecting buildings, but other equipment such as overhead lines may also be included. Furthermore, the communication lines L1 to L4 shown in Figure 2 may not only be lines connecting buildings, but also lines connecting buildings to data centers, etc. Although four buildings B1 to B4 are shown in Figure 2, the number of buildings (nodes) is not limited to four.

[0023] 1, the evaluation device 100 according to this embodiment includes a first storage unit 1, a second storage unit 2, a correction unit 3, an interruption probability calculation unit 4, and a reliability calculation unit 5. The evaluation device 100 is connected to a damage prediction unit 10.

[0024] The first storage unit 1 stores data indicating the connection status of communication lines between multiple buildings. Specifically, the first storage unit 1 stores data indicating the correspondence between the numbers of communication lines (line numbers), the buildings to be connected, and the numbers of the conduits through which the communication lines are installed, as shown in Figure 4. For example, communication line L1 (L1-1 to L1-3) is installed so as to pass through the inside of conduit D1 (D1-1 to D1-3) installed between buildings B1 and B2.

[0025] If the conduits to be installed between buildings are unknown, an appropriate one may be selected from a list of several conduits connecting buildings, following conventions in communication network design. For example, the conduit with the shortest distance or the conduit with the smallest damage prediction value is selected. Specifically, in the example shown in FIG. 3, if the conduits to be installed between buildings B1 and B2 are unknown, the communication line with the shortest distance (the link with the smallest total link length among multiple links) or the communication line with the smallest damage prediction value (the link with the smallest damage prediction value among multiple links) is selected from among the communication lines installed between other buildings, i.e., between buildings B2 and B3, between buildings B3 and B4, and between buildings B4 and B1. The "damage prediction value" is, for example, a numerical value shown in FIG. 5, and will be described in detail below.

[0026] The second storage unit 2 shown in FIG. 1 is connected to the damage prediction unit 10 and stores the prediction results calculated by the damage prediction unit 10 .

[0027] The damage prediction unit 10 calculates a predicted value of damage to each pipeline (hereinafter referred to as "damage prediction value") based on data for each pipeline installed between buildings. For example, the damage prediction value is calculated for pipelines D1-1 to D1-3 shown in FIG. 3. The damage prediction unit 10 calculates the damage prediction value using, for example, a model obtained by machine learning. In other words, the damage prediction value is a numerical value calculated by machine learning based on damage data from past disasters. Here, an example using "XGboost," a type of gradient boosting (GBDT), is described. Note that the method for calculating the damage prediction value is not limited to GBDT, and other calculation methods may be used.

[0028] (Explanation of XGboost) Assume a dataset consisting of n records with m variables. The n records are, for example, the number of earthquake disasters that have occurred in the past. The m variables are, for example, as shown in FIG. 6, the pipeline length, number of years elapsed, AVS30, fundamental natural period, average elevation, average tilt angle, PGV, PGA, measured seismic intensity, SI value, converted displacement, equivalent predominant period, ground strain, etc. The variables may also include data on the type of pipeline and estimated artificial flattening value. If these variables are used, m = 15.

[0029] The route length is the length of the pipeline. The number of years elapsed is the number of years that have passed since construction until the occurrence of the earthquake. AVS30 is the average S-wave velocity up to 30m underground. The fundamental natural period is the natural period of the ground. The average elevation is the average elevation obtained from the base map information. The average tilt angle is the average tilt angle obtained from the base map information. PGV is the maximum ground surface velocity. PGA is the maximum ground surface acceleration. The measured seismic intensity is the measured seismic intensity. The SI value is the spectral intensity. The converted displacement is (PGV 2 This is a value equivalent to the maximum displacement converted by (2πPGV / PGA). The equivalent predominant period is the period converted by (2πPGV / PGA). Ground strain is calculated based on the Seismic Design Guidelines for High-Pressure Gas Pipelines. Pipe types include steel pipes and vinyl pipes. Estimated artificial flattening values ​​are information on embankments, etc.

[0030] In the above condition settings, the variable of the (i=1, 2, . . . n)th record is expressed as an m-dimensional vector x, and the value y representing the presence or absence of damage in the i-th record as "0" or "1" is defined as y.

[0031] 6, 15 variables are used, so m = 15. Considering a decision tree, when xi is input, the constants wj (j = 1, 2, ... J) assigned to J unique vertices Rj of the tree are the output model, and are expressed by the following equation (1):

[0032]

[0033] "I" in equation (1) is an indicator function, which is a function that assumes "I = 1" when the condition (xi∈Rj) is met and "I = 0" otherwise. Therefore, the predicted value yi(^) calculated by the consensus φ of K decision trees f is expressed by the following equation (2).

[0034]

[0035] The depth of a tree, which is related to the number of vertices, the minimum value of the value wj obtained at the terminal vertex of the decision tree, and the total number K of decision trees used in the deliberation are parameters that affect the predicted value yi(^) by the model. However, during learning, to prevent overlearning, the output results of the obtained trees are reduced by a learning rate η, which takes a value between 0 and 1. That is, the following equation (3) is obtained.

[0036]

[0037] In this case, the objective function L(φ) is defined as in the following equation (4).

[0038]

[0039] In equation (4), "l(yi(^), yi)" is a differentiable loss function that measures the difference between "yi(^)" and "yi". For a decision tree f with J vertices and a vector w = (w1, w2, ... wJ) of values ​​obtained at the vertices, Ω(f) is the penalty term shown in equation (5) below.

[0040]

[0041] In this embodiment, the predicted value "yi(^)" calculated by the above-mentioned formula (2) is used. For example, as shown in Figure 3, if a communication line L1 (L1-1 to L1-3) is installed between building B1 and building B2, the damage prediction value for each of the pipelines D1-1 to D1-3 is calculated based on the data for the communication lines L1-1 to L1-3 and the data for the pipelines D1-1 to D1-3.

[0042] By the above calculation, the damage prediction value of each pipeline D1-1, D1-2, ... is calculated, for example, as shown in Figure 5. Hereinafter, the i-th (i = 1 to 3) damage prediction value in each pipeline will be referred to as "f i ". In the example shown in Figure 5, the damage prediction value f i of pipeline D1-1 is "f1 = 0.013", and the damage prediction value f2 of pipeline D1-2 is "f2 = 0.062".

[0043] 1, the second storage unit 2 stores the damage prediction value fi calculated by the damage prediction unit 10. For example, the damage prediction value fi shown in FIG.

[0044] The correction unit 3 corrects the damage prediction value fi stored in the second memory unit 2. That is, the damage prediction value fi calculated using the above-mentioned "XGboost" may not be expressed as a probability value. When predicting the damage probability using machine learning, if the number of actually damaged pipelines included in the training data is N, the condition is that the sum of the damage prediction values ​​of all pipelines must match the number of pipelines N. That is, the following equation (6) must be established.

[0045]

[0046] If equation (6) does not hold, the correction unit 3 corrects each damage prediction value f i so that the sum of the damage prediction values ​​becomes N. Specifically, the corrected damage prediction value f′ i is calculated using equation (7) below.

[0047]

[0048] The damage prediction value fi may be corrected by a calculation other than the above formula (7).

[0049] Furthermore, when a pipeline buried underground is damaged, the communication line (e.g., cable) installed in this pipeline is not necessarily cut off. For this reason, the probability of damage to the communication line and the pipeline protecting the communication line may not match. Explaining this using the example shown in Figure 3, for example, when the pipeline D1-1 is damaged, the communication line L1-1 installed inside this pipeline D1-1 may not be cut off.

[0050] If it is known from past statistics that the probability that the communication lines installed in a pipeline will be cut off when the pipeline is damaged is r (0<r≦1), the corrected damage prediction value f′i calculated by the above formula (7) is further multiplied by the correction coefficient r to correct all the damage prediction values ​​f′i. In other words, the damage prediction value "f''i = r * f′i" is calculated.

[0051] For example, if there is statistical data that shows that if the pipeline D1-1 is damaged (for example, if the pipeline D1-1 is destroyed by an earthquake), there is a 50% probability that the communication line L1-1 installed in this pipeline D1-1 will be cut off, the corrected damage prediction value f''i is calculated using a ``correction coefficient r = 0.5''.

[0052] The interruption probability calculation unit 4 calculates the probability that the line between buildings will be interrupted ("1-pj" described below) based on the above-mentioned line data and the corrected damage prediction value f''i. If a communication line is interrupted in at least one of the multiple conduits in which the communication line is installed, this communication line will be cut off. Using the example shown in Figure 3 as an example, if at least one of conduits D1-1 to D1-3 is damaged and the communication line installed in this conduit is cut off, the communication line L1 connecting buildings B1 and B2 will be cut off. Therefore, the communication line interruption probability can be calculated as follows.

[0053] The probability that the communication line L1-1 shown in Figure 3 will not be interrupted can be expressed as "1 - f''1". The probability that the communication line L1 (L1-1 to L1-3) between buildings B1 and B2 will not be interrupted, that is, the probability pj that communication line L1 is available, can be calculated using the following equation (8).

[0054]

[0055] The probability that the communication line L1 will be disconnected (disconnection probability) is (1-pj). In this way, the disconnection probability calculation unit 4 calculates the probability pj that communication is possible and the disconnection probability (1-pj) for all communication lines.

[0056] The reliability calculation unit 5 calculates the reliability of inter-building communication based on the above-mentioned communication possibility probability pj and the interruption probability (1-pj). The reliability calculation unit 5 calculates the communication possibility p(X) for each connection pattern of each link using the following equation (9).

[0057]

[0058] In equation (9), "X" is a code indicating the connection pattern of links (e.g., communication lines) installed between nodes (e.g., buildings) included in the network. Connection pattern X includes cases where any one or more of the communication lines constituting the network are disconnected, cases where all communication lines are disconnected, and cases where all communication lines are normal.

[0059] Also, "E" in formula (9) represents all links, X" is a link that exists between the target nodes (for example, between buildings B1 and B2 shown in FIGS. 2 and 3). X " is the set "E" in the set "E" X " indicates the set difference.

[0060] For example, if X in equation (9) is a state in which "all links (communication lines) are normal," p(X) indicates the probability that all links are normal.

[0061] The reliability calculation unit 5 substitutes p(X) calculated by the above formula (9) into the following formula (10) to calculate the probability RG,p(K) that communication is possible between the buildings.

[0062]

[0063] In equation (10), "K" indicates the combination of communication lines to be connected. For example, in FIG. 2, when predicting the state of the communication line between building B1 and building B3, K is set to B1, B2, and B3. K " is a symbol indicating a link that can communicate. K " indicates a link included in the blocking pattern X among the communicable links.

[0064] Equation (10) adds up the probabilities of only the links that are of interest. For example, if there are three communication paths, communication lines L11, L12, and L13 (not shown), between building B11 and building B12 (not shown), the probability that communication line L11 is available for communication, the probability that communication line L12 is available for communication, and the probability that communication line L13 is available for communication are all added up to calculate the total probability that communication is possible between building B11 and building B12 via at least one communication line.

[0065] Next, the operation of the evaluation device 100 according to this embodiment configured as described above will be described with reference to the flowchart shown in Fig. 7. Steps S11 and S12 shown in Fig. 7 represent the processing performed by the disaster prediction unit 10.

[0066] First, in step S11, the damage prediction unit 10 calculates a damage prediction value that predicts the probability of damage to each pipeline. The damage prediction unit 10 calculates the damage prediction value "f i " by using, for example, the above-mentioned "XGboost."

[0067] In step S12, the damage prediction unit 10 stores the calculated damage prediction value “f i ” in the second storage unit 2.

[0068] In step S13, the correction unit 3 corrects the damage prediction value "f i " stored in the second storage unit 2. Specifically, when the number of pipelines is N as described above, the damage prediction value "f i " is corrected using the above-described formula (7) to calculate the damage prediction value "f' i ". The damage prediction unit 10 further calculates the corrected damage prediction value "f" i " by multiplying the damage prediction value "f' i " by the correction coefficient r. As described above, the correction coefficient r indicates the probability that the communication line installed in this pipeline will be cut off when the pipeline is damaged.

[0069] In step S14, the outage probability calculation unit 4 calculates the probability pj that the communication line between each building is communicable and the outage probability (1-pj) using the above-mentioned formula (8) based on the information on the conduits installed between each building and the information on the communication lines stored in the first storage unit 1. For example, the outage probability of the communication line L1 installed between building B1 and building B2 shown in Figure 3 is calculated. The outage probability calculation unit 4 calculates the probability pj that the communication line is communicable and the outage probability (1-pj) for the communication lines installed between each building.

[0070] For example, in the network shown in FIG. 2, when the outage probability calculation unit 4 calculates the outage probability (1-pj) for each of the communication lines L1 to L4, the reliability calculation unit calculates the probability that the communication line between building B1 and building B2 will be successfully connected based on each outage probability (1-pj).

[0071] In step S15, the reliability calculation unit 5 substitutes "pj" and "1-pj" into the above-mentioned equations (9) and (10) to calculate the probability that the communication line installed between the buildings is communicable. That is, the reliability calculation unit 5 calculates the probability that the link between the two nodes is normally connected based on the disconnection probability of each link.

[0072] The reliability calculation unit 5 creates a graph showing the outage rate by size, as shown in FIG. 8, based on the above-mentioned outage probability (1-pj). The horizontal axis of the graph shown in FIG. 8 represents the "number of buildings," and the vertical axis represents the "probability of failure (%)." FIG. 8 shows the outage rates by size of buildings B1 to B4. For example, for building B2 shown by curve s2, the probability that communication will be lost with one or more buildings is 10.0%, the probability that communication will be lost with two or more buildings is 4.0%, and the probability that communication will be lost with two or more buildings is 2.0%.

[0073] The reliability calculation unit 5 displays the calculated probability as information indicating the reliability of the communication network on a display (not shown) or the like, and presents it to the user.

[0074] Thus, the evaluation device 100 according to this embodiment is an evaluation device 100 that evaluates a network having a plurality of nodes (e.g., buildings B1 to B4) and links (e.g., communication lines L1 to L4) connecting each node, and is equipped with a first memory unit 1 that stores a damage prediction value of link protection equipment (e.g., pipeline D1) in the event of a disaster, a second memory unit 2 that stores connection data for each link, an interruption probability calculation unit 4 that calculates the probability that each link will be interrupted based on the damage prediction value and the connection data, and a reliability calculation unit 5 that calculates the probability that a link between two nodes will be successfully connected based on the interruption probability of each link.

[0075] The evaluation device 100 according to this embodiment can calculate the probability that a communication line between any two buildings will be able to communicate (the probability that the line will be connected normally) in the event of a disaster such as an earthquake. That is, the reliability indicating whether links between multiple nodes in a network are connected normally can be quantitatively evaluated, and the evaluation results can be notified to the user. Therefore, the user can recognize the probability that the communication line between each building will be able to communicate in the event of a disaster. That is, it is possible to evaluate the reliability of the network with high accuracy in the event of a disaster.

[0076] The evaluation results provide useful information for consideration when reinforcing or restoring communication lines. For example, in the graph shown in FIG. 8, building B1 (curve s1) has a high downtime rate by size, and therefore it can be seen that it is likely to be isolated in the event of a disaster. Therefore, the user can be made aware of the need to take reinforcing measures, such as preparing a wireless backup line that will not be affected by the disaster. Furthermore, during restoration work after a disaster, measures can be taken, such as prioritizing the allocation of restoration work personnel to buildings with a high downtime rate by size.

[0077] In this embodiment, when there are multiple communication lines (links) connecting two buildings (nodes), the outage probability calculation unit 4 uses the damage prediction value of the communication line among the multiple communication lines that has the shortest total communication line length (total link length) to calculate the probability that each communication line will be outage, making it possible to more accurately calculate the probability that a communication line will be outage.

[0078] In this embodiment, when there are multiple communication lines (links) connecting two buildings (nodes), the outage probability calculation unit 4 uses the damage prediction value of the communication line with the lowest damage prediction value among the multiple communication lines to calculate the probability that the communication line will be cut off, making it possible to more accurately calculate the probability that the communication line will be cut off.

[0079] In this embodiment, a damage prediction value calculated by machine learning based on damage data from past disasters is used, making it possible to more accurately calculate the probability of communication line interruption.

[0080] In this embodiment, the correction unit 3 obtains a correction coefficient r, which is the probability that the communication line L1 (link) protected by the pipeline D1 will be cut off when the pipeline D1 (protective equipment) is damaged, and corrects the damage prediction value using the correction coefficient r, making it possible to more accurately calculate the probability that the communication line L1 will be cut off.

[0081] In this embodiment, the nodes installed in the network are communication terminals installed at multiple bases (buildings), and the links connecting the nodes are communication circuits connecting each communication terminal, so it is possible to calculate the probability that communication will be cut off between communication terminals installed at each base in the event of a disaster.

[0082] In this embodiment, a conduit that is buried underground and through which the communication line passes is used as the protection equipment for protecting the communication line, as shown in Fig. 3. Therefore, it is possible to calculate a predicted value of damage to the communication line based on the probability of damage to the conduit, and it is possible to more accurately calculate the probability of the communication line being cut off.

[0083] In the above embodiment, an earthquake is taken as an example of a disaster, but the present invention can also be applied to the occurrence of disasters other than earthquakes.

[0084] The evaluation device 100 of the present embodiment described above can be, for example, a general-purpose computer system including a CPU (Central Processing Unit, processor) 901, a memory 902, a storage 903 (HDD: Hard Disk Drive, SSD: Solid State Drive), a communication device 904, an input device 905, and an output device 906, as shown in FIG. 9 . The memory 902 and the storage 903 are storage devices. In this computer system, the CPU 901 executes a predetermined program loaded on the memory 902, thereby realizing each function of the evaluation device 100.

[0085] The evaluation device 100 may be implemented by one computer or by multiple computers. The evaluation device 100 may also be a virtual machine implemented on a computer.

[0086] The program for the evaluation device 100 can be stored in a computer-readable recording medium such as a HDD, SSD, USB (Universal Serial Bus) memory, CD (Compact Disc), or DVD (Digital Versatile Disc), or can be distributed via a network. The computer-readable recording medium is, for example, a non-transitory recording medium.

[0087] The present disclosure is not limited to the above-described embodiments, and various modifications are possible within the scope of the present disclosure.

[0088] REFERENCE SIGNS LIST 1 First storage unit 2 Second storage unit 3 Correction unit 4 Interruption probability calculation unit 5 Reliability calculation unit 10 Disaster prediction unit 100 Evaluation device B1 to B4 Building D1 Pipe line L1 to L3 Communication line M1 to M4 Manhole

Claims

1. An evaluation device for evaluating a network having a plurality of nodes and links connecting each of the nodes, comprising: a first memory unit for storing a damage prediction value of protection equipment for the links in the event of a disaster; a second memory unit for storing connection data for each of the links; an interruption probability calculation unit for calculating the interruption probability of each of the links based on the damage prediction value and the connection data; and a reliability calculation unit for calculating the probability that a link between two nodes will be normally connected based on the interruption probability of each of the links.

2. The evaluation device according to claim 1, wherein, when there are multiple links connecting two nodes, the interruption probability calculation unit calculates the interruption probability of each of the links by adopting the damage prediction value of the link with the smallest total link length or the smallest damage prediction value among the multiple links.

3. The evaluation device according to claim 1, wherein the damage prediction value is calculated by machine learning based on damage data from past disasters.

4. An evaluation device as described in any one of claims 1 to 3, further comprising a correction unit that acquires a correction coefficient indicating the probability that a link protected by the protection equipment will be cut off when the protection equipment is damaged, and corrects the damage prediction value using the correction coefficient, wherein the cutoff probability calculation unit calculates the cutoff probability of each of the links based on the corrected damage prediction value.

5. The evaluation device according to any one of claims 1 to 3, wherein the nodes are communication terminals installed at a plurality of locations, and the links are communication lines connecting the respective communication terminals.

6. The evaluation device according to claim 5, wherein the protection facility is a conduit buried underground through which the communication line is inserted.

7. A method for evaluating a network having a plurality of nodes and links connecting each of the nodes, comprising the steps of: storing damage prediction values ​​of protective equipment for the links when a disaster occurs; storing connection data for each of the links; calculating a disconnection probability for each of the links based on the damage prediction values ​​and the connection data; and calculating a probability that a link between two nodes will be normally connected based on the disconnection probability for each of the links.

8. A program for causing a computer to function as the evaluation device according to any one of claims 1 to 3.

Citation Information

Patent Citations

  • Apparatus for estimating earthquake damage of cable, and method and program thereof

    JP2009058486A

  • Pipeline vulnerability estimation system, pipeline vulnerability estimation method, model creation device, and program

    WO2021240650A1