High formwork system and construction method thereof

By using a high-supported form system with cantilever operation platform and large-section steel shelving beam combined with a high-altitude cantilevered steel platform in the construction of high-rise residential buildings, the problems of high-rise residential construction difficulty and low safety factor are solved, and a large-scale Stable construction and safe improvement of cross-section reinforced concrete components.

CN111779248BActive Publication Date: 2024-11-29SHANGHAI CONSTRUCTION NO 7 (GROUP) CO LTD
View PDF 1 Cites 0 Cited by

Patent Information

Application Number
CN202010624701.8
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2020-07-01
Publication Date
2024-11-29
Estimated Expiration
2040-07-01

AI Technical Summary

Technical Problem

In the construction of high-rise residential buildings, the construction of high-support formwork system is difficult and has low safety factors, resulting in frequent engineering accidents and cannot meet the construction needs of large-section reinforced concrete components.

Method used

Adopt a high-support formwork system including cantilever operation platform, scaffolding, steel beam brackets and concrete beam column wooden formwork arrangement, through cantilever main beam, horizontal beam, platform board, bracket main body, bracket diagonal brace, concrete beam column wooden formwork Support foundation and other components, erect high-altitude cantilever steel platforms and large-section steel shelving beams, and construct them in combination with tower cranes and embedded parts.

Benefits of technology

It has achieved stable construction of high-altitude large-section reinforced concrete components, reduced construction difficulty, improved safety factor, and had the advantages of excellent economicality, material saving and environmental protection, and the support effect was more stable.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN111779248B_ABST
    Figure CN111779248B_ABST
Patent Text Reader

Abstract

The present application provides a high-support formwork system and a construction method thereof, wherein the high-support formwork system includes: a cantilever operating platform, a scaffolding, a steel beam bracket and a concrete beam-column wooden formwork rack; the scaffolding is erected on the cantilever operating platform, and the steel beam bracket is installed above the cantilever operating platform to support the suspended beam structure; the steel beam bracket includes a bracket body and a bracket diagonal brace, the two ends of the bracket body are respectively inserted into the shear wall and fixedly connected to the shear wall, one end of the bracket diagonal brace is fixedly connected to the bracket body, and the other end of the bracket diagonal brace is fixedly connected to the embedded part of the shear wall; the concrete beam-column wooden formwork rack is installed on the steel beam bracket. In the high-support formwork system and the construction method thereof provided in the present application, a large-section steel shelving beam is used in combination with a high-altitude cantilever steel platform to solve the problem that large-section reinforced concrete components at high altitude cannot be constructed, which can not only achieve good practical effects, but also has many advantages such as low construction difficulty, economy, environmental protection, and high safety factor.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of building construction, and in particular to a high-support formwork system and a construction method thereof. Background Art

[0002] In the field of high-rise residential construction, in order to highlight the individual design of individual buildings or meet the requirements of regional overall planning, different shapes of concrete flower rack beams, three-dimensional grid structures or steel components are usually designed on the eaves, roofs and other parts to form a unique and extremely modern appearance design with excellent visual effects.

[0003] However, this has led to civil engineering and decoration construction problems such as the lifting of large steel structures at high altitude, the installation of formwork for suspended reinforced concrete structures at high altitude, and high-altitude decoration and renovation of the exterior eaves of the roof protrusions. Not only is the construction process itself technically difficult, but it also involves a large amount of high-altitude operations, and the requirements for fall prevention and safety control are also very high.

[0004] As the scale of the building increases, the rigidity, strength and stability requirements of the high-support formwork system in reinforced concrete construction become higher, and the difficulty of implementing the formwork construction also increases accordingly, especially the "high-support formwork of large-section reinforced concrete components suspended in the air", which generally has the disadvantages of high construction difficulty and low safety factor. Due to lack of proficiency in high-support formwork system construction technology or insufficient engineering experience, engineering accidents often occur, endangering the safety of the building, and in serious cases, causing damage to life and property. Summary of the invention

[0005] The purpose of the present invention is to provide a high-support formwork system and a construction method thereof, so as to solve the problems of high construction difficulty and low safety factor in the existing high-support formwork system.

[0006] In order to solve the above technical problems, the present invention provides a high-support formwork system, which includes: a cantilevered operating platform, a scaffold, a steel beam bracket and a concrete beam column wooden formwork rack;

[0007] The cantilever operating platform comprises a cantilever main beam, a horizontal connecting beam and a platform plate, wherein the horizontal connecting beam is vertically arranged with the cantilever main beam, the cantilever main beam comprises an anchoring section and a cantilevering section, the anchoring section of the cantilever main beam is fixed on a designated floor slab, the cantilevering section of the cantilever main beam extends out of the designated floor slab, and the horizontal connecting beam and the platform plate are both fixed to the cantilevering section of the cantilever main beam;

[0008] The scaffolding is erected on the cantilevered operating platform and is fixedly connected to the horizontal connecting beam;

[0009] The steel beam bracket is installed above the cantilever operating platform to support the cantilever beam structure;

[0010] The steel beam bracket includes a bracket body and a bracket diagonal brace, the two ends of the bracket body are respectively inserted into the shelf grooves reserved in the shear wall and fixedly connected to the shear wall, one end of the bracket diagonal brace is fixedly connected to the bracket body, and the other end of the bracket diagonal brace is fixedly connected to the embedded part of the shear wall;

[0011] A concrete beam-column and wooden formwork support foundation is laid on the bracket body, and the concrete beam-column and wooden formwork rack is installed on the concrete beam-column and wooden formwork support foundation.

[0012] Optionally, in the high formwork system, the cantilevered operating platform further comprises a platform diagonal brace, tie rods and steel cables;

[0013] One end of the platform diagonal brace is fixedly connected to the lower surface of the cantilever main beam, and the other end of the platform diagonal brace is fixedly connected to the embedded part of the lower floor slab;

[0014] One end of the tie rod is fixedly connected to the platform diagonal brace, and the other end of the tie rod is fixedly connected to the cantilever main beam;

[0015] The cantilever operating platform also includes a steel wire rope, one end of which is connected to the main beam, and the other end of which is fixedly connected to the embedded parts of the upper floor.

[0016] Optionally, in the high formwork system, the concrete beam-column wooden formwork supporting foundation includes a plurality of steel pipes, and the plurality of steel pipes are arranged at intervals along the span direction of the steel beam bracket.

[0017] Optionally, in the high formwork system, the scaffolding comprises: a plurality of vertical poles, a plurality of horizontal poles, wall-attached tie-joints and scaffolding boards;

[0018] The plurality of vertical poles are all arranged vertically, and the bottom ends thereof are fixedly connected to the horizontal connecting beam;

[0019] The plurality of cross bars are all arranged horizontally and fixedly connected to the plurality of vertical bars through first fasteners;

[0020] One end of the wall-attached tie is fixedly connected to the vertical pole, and the other end of the wall-attached tie is fixedly connected to the main structure of the building;

[0021] The scaffolding planks are laid on the horizontal link beams.

[0022] Optionally, in the high formwork system, the plurality of vertical poles are all located at the intersection of the cantilevered main beam and the horizontal connecting beam.

[0023] Optionally, in the high formwork system, the scaffolding further comprises hard isolation and safety nets;

[0024] The hard isolation is arranged on the wall-attached connection, and the safety net is arranged on the inner side of the plurality of vertical poles and is fixedly connected to the plurality of vertical poles.

[0025] Optionally, in the high formwork system, it further includes: a first steel pipe bent frame and a second steel pipe bent frame;

[0026] The first steel pipe bent frame is arranged on the cantilever main beam, and is used to support the cantilever main beam and the upper floor slab of the designated floor slab;

[0027] The second steel pipe rack is arranged in the corridor of the main structure, and is used to support the designated floor slab and the floor slab below it.

[0028] Optionally, in the high formwork system, the projections of the first steel tube rack and the second steel tube rack in the vertical direction both fall within the anchoring section of the cantilever main beam.

[0029] Optionally, in the high formwork system, the cantilevered main beam is fixedly connected to the designated floor slab by at least four U-shaped bolts.

[0030] Optionally, in the high-support formwork system, the cantilever main beam is made of No. 20 I-beam, the horizontal connecting beam is made of No. 16 I-beam, the bracket body is made of No. 56 I-beam, and the bracket diagonal brace is made of No. 22 I-beam.

[0031] Optionally, in the high formwork system, the platform diagonal braces are made of No. 20 I-beams, and the tie rods are made of No. 16 channel steels.

[0032] Accordingly, the present invention also provides a construction method of a high-support formwork system, the construction method of the high-support formwork system comprising:

[0033] Step 1: construct the main concrete structure of the floor, and set embedded parts in the main concrete structure of the floor;

[0034] Step 2: Install the cantilevered operating platform on the designated floor;

[0035] Step 3: erecting an upper scaffold on the cantilever operating platform and constructing an upper main structure, wherein the upper main structure is provided with grooves for steel beam brackets and grooves for the first cantilever beam;

[0036] Step 4: Install a steel beam bracket below the first suspended beam;

[0037] Step 5: construct a large-section suspended beam on the steel beam bracket.

[0038] Optionally, in the construction method of the high formwork system, the process of installing the cantilevered operating platform on the designated floor slab includes:

[0039] Processing the cantilevered main beam, the platform diagonal brace and the tie rod on the ground, and forming the cantilevered main beam, the platform diagonal brace and the tie rod into a plurality of platform supports;

[0040] Hoisting the plurality of platform supports into place by means of a tower crane;

[0041] Fixing the cantilevered main beam to the designated floor slab by at least four U-bolts;

[0042] The lower end of the platform diagonal brace is fixedly connected to the embedded parts of the lower floor slab;

[0043] Laying horizontal connecting beams and platform plates on the cantilevered main beams in sequence;

[0044] The steel wire rope is connected between the cantilevered main beam and the embedded parts of the upper floor slab.

[0045] Optionally, in the construction method of the high formwork system, before installing the cantilevered operating platform on the designated floor slab and after constructing the main concrete structure of the floor, it also includes: installing a second steel pipe rack in the corridor of the main structure.

[0046] Optionally, in the construction method of the high formwork system, before erecting an upper layer of scaffolding on the cantilever operating platform and after installing the cantilever operating platform on a designated floor slab, it also includes: installing a first steel pipe rack on the cantilever main beam.

[0047] Optionally, in the construction method of the high formwork system, the process of setting up an upper layer of scaffolding on the cantilever operating platform includes:

[0048] Fixing a plurality of vertical poles on the horizontal connecting beam, and fixing a plurality of cross bars to the plurality of vertical poles through a first fastener;

[0049] Use the two-step two-span pre-embedded method or the through-wall connection method to make the wall-attached pull-joint;

[0050] Laying scaffolding boards fully on the top surface of the horizontal connecting beam; and

[0051] Install hard isolation, toe boards and safety nets in sequence.

[0052] Optionally, in the construction method of the high formwork system, the process of installing a steel beam bracket below the first suspended beam includes:

[0053] Processing the bracket body and bracket diagonal braces on the ground to form a steel beam bracket;

[0054] Hoisting the steel beam bracket into place by a tower crane;

[0055] Inserting the two ends of the bracket body into the reserved recesses of the upper main structure respectively, and fixing the lower end of the bracket diagonal brace to the embedded parts of the shear wall by welding; and

[0056] The shelving grooves are leveled and filled with high-fine stone concrete.

[0057] Optionally, in the construction method of the high formwork system, the process of constructing a large-section suspended beam on the steel beam bracket includes:

[0058] Laying a plurality of steel pipes on the steel beam bracket as the support foundation for the first concrete beam and column wooden formwork;

[0059] Support the first concrete beam and column wooden formwork on the support foundation of the first concrete beam and column wooden formwork;

[0060] Carry out concrete pouring; and

[0061] Concrete curing is carried out until the concrete strength of the first suspended beam reaches the design requirements.

[0062] Optionally, in the construction method of the high-support formwork system, during the concrete curing process, it also includes: continuing to erect scaffolding on the cantilever operating platform, constructing an upper layer of structural concrete and a second cantilever beam.

[0063] Compared with the prior art, the present invention has the following advantages and beneficial effects:

[0064] 1. The present invention adopts large-section steel beams combined with high-altitude cantilever steel platforms to solve the problem that large-section reinforced concrete components at high altitudes cannot be constructed. It can not only achieve good practical effects, but also has many advantages such as low construction difficulty, excellent economy, material saving and environmental protection, and high safety factor;

[0065] 2. In addition to using the designated floor slab on which the cantilevered operating platform itself is located as support, the high-support formwork system of the present invention also uses the floor slab below and above the designated floor slab for support, so that the support effect is better and the support is more stable. BRIEF DESCRIPTION OF THE DRAWINGS

[0066] Figure 1 A schematic diagram of the elevation layout of a high-support formwork system according to an embodiment of the present invention;

[0067] Figure 2 A schematic diagram of the plan layout of a high-support formwork system according to an embodiment of the present invention;

[0068] Figure 3 A schematic cross-sectional layout diagram of a high-support formwork system according to an embodiment of the present invention;

[0069] Figure 4 for Figure 1Schematic diagram of the structure of the middle area A;

[0070] Figure 5 for Figure 3 Schematic diagram of the structure of the middle area B;

[0071] Figure 6 This is a structural diagram of the wall-attached pull-joint using the two-step two-span pre-embedded method;

[0072] Figure 7 It is a structural schematic diagram of the wall-attached pull-joint using the through-wall connection method;

[0073] Figure 8 It is a structural schematic diagram of a concrete beam-column wooden formwork bent frame according to an embodiment of the present invention;

[0074] Fig. 9 It is a structural schematic diagram corresponding to step 1 in the construction method of the high-support formwork system according to an embodiment of the present invention;

[0075] Fig.10 It is a structural schematic diagram corresponding to step 3 in the construction method of the high-support formwork system of an embodiment of the present invention;

[0076] Fig.11 It is a structural schematic diagram corresponding to step 4 in the construction method of the high-support formwork system of an embodiment of the present invention. DETAILED DESCRIPTION

[0077] The high-support formwork system and the construction method thereof proposed by the present invention are further described in detail below in conjunction with the accompanying drawings and specific embodiments.

[0078] Please refer to Figures 1 to 3 , which is a schematic diagram of the structure of the high-support formwork system of an embodiment of the present invention. Figures 1 to 3As shown, the high formwork system 100 includes: a cantilever operating platform, a scaffolding, a steel beam bracket and a concrete beam-column wooden formwork rack; the cantilever operating platform includes a cantilever main beam 11, a horizontal connecting beam 12 and a platform plate (not shown in the figure), the horizontal connecting beam 12 is vertically arranged with the cantilever main beam 11, the cantilever main beam 11 includes an anchoring section and a cantilevering section, the anchoring section of the cantilever main beam 11 is fixed to a designated floor slab, the cantilevering section of the cantilever main beam 11 extends out of the designated floor slab, the horizontal connecting beam 12 and the platform plate are both fixed to the cantilevering section of the cantilever main beam 11; the steel beam bracket is installed on the cantilever operating platform Above the working platform, the steel beam bracket includes a bracket body 31 and a bracket diagonal brace 32, both ends of the bracket body 31 are respectively inserted into the shelf grooves reserved in the shear wall and fixedly connected to the shear wall, one end of the bracket diagonal brace 32 is fixedly connected to the bracket body 31, and the other end of the bracket diagonal brace 32 is fixedly connected to the embedded parts of the shear wall; a concrete beam-column wooden formwork supporting foundation is laid on the bracket body 31, and the concrete beam-column wooden formwork rack is installed on the concrete beam-column wooden formwork supporting foundation; the scaffolding is erected on the cantilever operating platform and fixedly connected to the horizontal connecting beam 12.

[0079] Specifically, the cantilever main beam 11 includes a plurality of steel sections, which are arranged side by side with equal spacing, and each steel section includes an anchoring section and a cantilever section. The anchoring section is located on a designated floor slab (for example, the floor slab of the 26th floor) and is fixedly connected to the designated floor slab through an anchor (U-bolt), and the cantilever section extends out of the designated floor slab.

[0080] In this embodiment, the length of the cantilevered main beam 11 is 12 m, of which the length of the anchoring section is 6.7 m and the length of the cantilevered section is 5.3 m.

[0081] In this embodiment, the cantilever main beam 11 includes 7 No. 20a I-beams, and the 7 No. 20a I-beams are all arranged in the horizontal direction.

[0082] Preferably, the cantilever main beam 11 is fixedly connected to the designated floor slab by at least four U-shaped bolts, that is, each No. 20a I-beam is fixedly connected to the designated floor slab by at least four U-shaped bolts.

[0083] Please refer to Figure 5 , which is Figure 3 Schematic diagram of the structure of area B. Figure 5 As shown, the U-bolt 16 is embedded in the designated floor slab, the bottom of the U-bolt 16 is pressed by two steel bars 18 embedded in the designated floor slab, the cantilevered main beam 11 is inserted into the U-bolt 16, and the side of the cantilevered main beam 11 is tightened by a wooden wedge.

[0084] In this embodiment, the length of the steel bar 18 is 3 m and the diameter is 20 mm.

[0085] Please continue to refer to Figure 3 The spacing D1 of the cantilever main beam 11 (the distance between adjacent No. 20a I-beams) is 1500m, and the cantilever main beam 11 adjacent to the shear wall is a side beam, and the spacing D2 between the side beam and the shear wall is 500mm.

[0086] Please refer to Figure 2 and Figure 3 The horizontal connecting beam 12 is vertically arranged with the cantilever main beam 11, and the horizontal connecting beam 12 is fixed to the cantilever main beam 11 by welding, and the platform plate (not shown in the figure) is laid on the cantilever main beam 11 and fixedly connected to the cantilever main beam 11 by wire binding. The horizontal connecting beam 12 also includes a plurality of steel sections, which are arranged side by side and at equal intervals.

[0087] In this embodiment, the horizontal connecting beam 12 includes 6 No. 16 I-beams, and the 6 No. 16 I-beams are all arranged in the horizontal direction. The length of the horizontal connecting beam 12 (that is, the length of the No. 16 I-beam) is 10 meters, and the spacing D3 of the horizontal connecting beam 12 (the distance between adjacent No. 16 I-beams) is between 500 and 800 mm.

[0088] Please continue to refer to Figure 3 The cantilever operating platform also includes a platform diagonal brace 13, a tie rod 14 and a steel wire rope 15. The upper end of the platform diagonal brace 13 is fixedly connected to the lower surface of the cantilever main beam 11, and the lower end of the platform diagonal brace 13 is fixedly connected to the first embedded part of the lower floor (for example, the floor of the 25th floor). The angle between the platform diagonal brace 13 and the horizontal plane is α. One end of the tie rod 14 is fixedly connected to the platform diagonal brace 13, and the other end of the tie rod 14 is fixedly connected to the cantilever section of the cantilever main beam 11. One end of the steel wire rope 15 is fixedly connected to the cantilever main beam 11, and the other end of the steel wire rope 15 is fixedly connected to the second embedded part of the upper floor (for example, the floor of the 27th floor). With the help of the pulling action of the steel wire rope 15, the structural stability of the cantilever operating platform can be further improved to prevent it from overturning.

[0089] In this embodiment, the cantilever operating platform is a high-altitude cantilever steel platform, and the bottom of each cantilever main beam 11 is provided with a platform diagonal brace 13 and a tie rod 14, which can reduce the slenderness ratio of the diagonal brace and ensure the safety of the diagonal brace.

[0090] In this embodiment, the platform brace 13 is made of No. 20 I-steel, the tie rod 14 is made of No. 16 channel steel, and the angle between the platform brace 13 and the horizontal plane is 45°.

[0091] Please refer to Figure 3 , Figure 6 and Figure 7 The scaffolding includes a plurality of vertical poles 21, a plurality of horizontal poles 22, a wall-attached tie-joint (not shown in the figure) and a scaffolding board (not shown in the figure). The plurality of vertical poles 21 are all vertically arranged, and their bottom ends are fixedly connected to the horizontal connecting beam 12. The plurality of horizontal poles 22 are all horizontally arranged, and are fixedly connected to the plurality of vertical poles 21 through a first fastener (not shown in the figure). The scaffolding board is fully spread on the top surface of the horizontal connecting beam 12. One end of the wall-attached tie-joint is fixedly connected to the scaffolding, and the other end of the wall-attached tie-joint is fixedly connected to the shear wall. The wall-attached tie-joint is used to transfer the tension and pressure generated by the scaffolding during use, and can enhance the overall stability of the scaffolding.

[0092] In this embodiment, the wall-attached connection is implemented by a two-step two-span pre-embedded method or a through-wall connection method. Figure 6 As shown, the wall-attached connection constructed by the two-step two-span pre-embedded method includes a wall connecting rod 231, a second fastener 232 and a pre-embedded steel pipe 233. The pre-embedded steel pipe 233 is pre-embedded in the shear wall. One end of the wall-attached rod 231 is fixedly connected to the pre-embedded steel pipe 233 through a second fastener 232, and the other end of the wall-attached rod 231 is fixedly connected to the vertical pole 21 of the scaffold through another second fastener 232. Thus, the scaffold is connected to the main structure of the building through the wall-attached connection.

[0093] like Figure 7 As shown, the wall-attached connection implemented by the through-wall connection method includes a wall connecting rod 231 and a second fastener 232. One end of the wall connecting rod 231 passes through the shear wall and is fixedly connected to the shear wall through the second fastener 232. The other end of the wall connecting rod 231 is fixedly connected to the vertical rod 21 of the scaffolding through the second fastener 232. Thus, the scaffolding is connected to the main structure through the wall-attached connection.

[0094] In this embodiment, the plurality of vertical poles 21 and the plurality of cross bars 22 are all steel pipes, the plurality of vertical poles 21 are arranged in 6 rows in the horizontal direction and 7 rows in the vertical direction, the longitudinal spacing is 1.5m, the lateral spacing is 500-1500mm, the step distance of the plurality of cross bars 22 is 1.5m, and the first fastener is a right-angle fastener. Preferably, the plurality of vertical poles 21 are all located at the intersection of the cantilever main beam 11 and the horizontal connecting beam 12.

[0095] Please continue to refer to Figure 3 , Figure 6 and Figure 7The scaffolding also includes hard isolation (not shown in the figure), toeboards (not shown in the figure) and safety nets (not shown in the figure). The hard isolation is arranged on the wall-attached connection. The hard isolation includes two steel pipes, a third fastener and a steel fence. The two steel pipes are both horizontally arranged and fixedly connected by the third fastener. The steel fence is laid on the two steel pipes. The toeboards are arranged at the bottom of the multiple vertical poles 21 and fixedly connected to the multiple vertical poles 21. The safety net is arranged on the inner side of the multiple vertical poles 21 and fixedly connected to the multiple vertical poles 21.

[0096] In the present embodiment, the scaffolding is arranged at the four corners along the vertical full-length of the outer frame. The scaffolding board is a steel fence scaffolding board. The footboard adopts a seven-ply board with a height of 180 mm. The seven-ply board is arranged along the four sides of the scaffolding board. The safety net is a green dense mesh safety net. The full height range of the vertical pole 21 is fully hung with a green dense mesh safety net to form a fully enclosed operating space to ensure the safety of workers' operation.

[0097] Please refer to Figure 3 and Figure 8 The scaffolding also includes a sweeping rod 24, a capping rod 25, a horizontal rod 26, a horizontal scissors brace (not shown in the figure) and a vertical scissors brace. The sweeping rod 24 is arranged at the bottom of the scaffolding layer, the capping rod 25 is arranged at the top of the scaffolding layer, and the horizontal rod 26 is arranged between the sweeping rod 24 and the capping rod 25. The horizontal scissors brace and the vertical scissors brace are arranged in accordance with the requirements of the building specifications.

[0098] In this embodiment, the distance between the sweeping rod 24 and the scaffolding board is 200 mm, the distance between the capping rod 25 and the adjustable top support is less than 500 mm, and the step distance of the horizontal rod 26 is less than 1200 mm.

[0099] Please refer to Figure 1 and Figure 4 The steel beam bracket includes a bracket body 31 and two bracket diagonal braces 32. The bracket body 31 is horizontally arranged, and its two ends are respectively inserted into the shelf grooves reserved by the shear wall and fixedly connected to the shear wall. One end of the two bracket diagonal braces 32 is fixedly connected to the bracket body 31, and the other ends of the two bracket diagonal braces 32 are fixedly connected to the embedded parts of the shear wall. The two bracket diagonal braces 32 are symmetrically arranged and are required to provide sufficient supporting force and supporting area.

[0100] In this embodiment, the bracket body 31 is made of No. 56 I-beam, the bracket diagonal brace 32 is made of No. 22 I-beam, and the angle between the bracket diagonal brace 32 and the horizontal plane is in the range of 10° to 75°.

[0101] Preferably, the two bracket diagonal braces 32 have the same structural dimensions, and the two bracket diagonal braces 32 are located at the same height.

[0102] Please refer to Figure 1 and Figure 8 A concrete beam-column and wooden formwork support foundation is laid on the bracket body 31, and the concrete beam-column and wooden formwork support foundation includes a plurality of steel pipes 41. The plurality of steel pipes 41 are laid flat on the bracket body 31 and arranged in sequence along the span direction of the steel beam bracket, and adjacent steel pipes 41 maintain a certain distance.

[0103] In this embodiment, the plurality of steel pipes 41 are arranged in parallel and equidistantly, and each of the steel pipes 41 has a length of 750 mm.

[0104] In this embodiment, the multiple short steel pipes 41 also serve as the main keel of the formwork, and the concrete beam-column wooden formwork frame 42 is installed on the multiple steel pipes 41. The concrete beam-column wooden formwork frame 42 adopts a conventional wooden formwork frame system, which is composed of horizontal rods, vertical rods, sweeping rods, plywood formwork, tension bolts and other components.

[0105] It should be noted that the specifications, dimensions, angles and spacings of the above-mentioned cantilevered main beam 11, horizontal connecting beam 12, platform diagonal brace 13, tie rod 14, vertical pole 21, cross bar 22, footboard, sweeping rod 24, capping rod 25, horizontal rod 26, bracket body 31, bracket diagonal brace 32 and steel pipe 41 are only for example and not for limitation. Those skilled in the art can set the specifications, dimensions, angles and spacings of the cantilevered main beam 11, horizontal connecting beam 12, platform diagonal brace 13, tie rod 14, vertical pole 21, cross bar 22, bracket body 31, bracket diagonal brace 32 and steel pipe 41 according to actual needs, as long as they meet the requirements of building specifications.

[0106] Please continue to refer to Figure 2 The high formwork system 100 also includes a first steel pipe frame 51 and a second steel pipe frame 52. The top of the first steel pipe frame 51 abuts against the upper floor of the designated floor, and the bottom of the first steel pipe frame 51 abuts against the cantilevered main beam 11, and is used to support the cantilevered main beam 11 and the upper floor of the designated floor. The second steel pipe frame 52 is arranged in the corridor of the main structure, and is used to support the designated floor and its lower floor. The first steel pipe frame 51 forms an effective downward pressure connection with the anchoring section of the cantilevered main beam 11, forming an additional support measure to resist the warping force of the anchoring section. The second steel pipe frame 52 and the first steel pipe frame 51 together form an additional support measure to prevent structural damage.

[0107] Preferably, the second steel pipe frame 52 is arranged in the 3rd floor corridor of the main structure. For example, the designated floor is the floor of the 26th floor, and the second steel pipe frame 52 is arranged between the floors of the 24th floor, the 25th floor and the 26th floor to support the floors of the 24th floor to the 26th floor.

[0108] Preferably, the projections of the first steel tube rack 51 and the second steel tube rack 52 in the vertical direction both fall within the anchoring section of the cantilever main beam 11 .

[0109] In this embodiment, the cantilever operating platform is erected on the designated floor of the building, and the steel beam bracket is installed above the cantilever operating platform as the load-bearing foundation for the suspended large-section concrete beam-column and wooden formwork rack. The cantilever operating platform not only serves as a construction operating platform, but also bears the deadweight of the suspended concrete structure and all construction load pressures.

[0110] For the construction of large-section suspended beams, formwork support is a key link. In the existing technology, suspended concrete structures are constructed using ground-based scaffolding or cantilevered platforms + formwork racks. However, for large-volume and heavy suspended concrete structures, the existing construction methods cannot guarantee safety, that is, the existing high-support formwork system cannot meet the construction requirements.

[0111] In the high-support formwork system 100 provided in this embodiment, the steel beam bracket is a large-section steel beam, which is combined with a high-altitude cantilever steel platform to solve the problem that large-section reinforced concrete components (high-support formwork) at high altitude cannot be constructed. It can not only achieve good practical effects, but also has many advantages such as low construction difficulty, excellent economy, material saving and environmental protection, and high safety factor. It has advantages in safety, economy and practicality. In addition, in addition to using the designated floor slab where the cantilever operating platform itself is located as support, the high-support formwork system 100 also uses the floor slab below the designated floor slab and the floor slab above the designated floor slab for support, so that the support effect is better and the support is more stable.

[0112] Accordingly, the present application also provides a construction method for a high-support formwork system. Figures 1 to 3 , Figures 9 to 11 The construction method of the high-support formwork system 100 includes:

[0113] Step 1: construct the main concrete structure of the floor, and set embedded parts in the main concrete structure of the floor;

[0114] Step 2: Install the cantilevered operating platform on the designated floor;

[0115] Step 3: erecting an upper scaffold on the cantilever operating platform and constructing an upper main structure, wherein the upper main structure is provided with grooves for steel beam brackets and a groove for the first cantilever beam;

[0116] Step 4: Install a steel beam bracket below the first suspended beam;

[0117] Step 5: Lay the first concrete beam and column wooden formwork support foundation on the steel beam bracket;

[0118] Step 6: Support the first concrete beam and column wooden formwork on the foundation of the first concrete beam and column wooden formwork, and pour concrete.

[0119] Specifically, first, Fig. 9 As shown, when constructing the main concrete structure of the floor, a first embedded part 1a and a second embedded part (not shown in the figure) are respectively arranged on the edges of the floor slabs. The first embedded part 1a is located on the lower floor slab of the designated floor slab and is used as a welding point for the lower diagonal brace of the cantilevered main beam. The second embedded part is located on the upper floor slab of the designated floor slab and is used to connect the steel wire rope 15.

[0120] Next, install the cantilevered operating platform on the designated floor. The specific process of installing the cantilevered operating platform includes:

[0121] Step S21, processing the cantilever main beam 11, the platform diagonal brace 13 and the tie rod 14 on the ground, and fixing one end of the tie rod 14 to the platform diagonal brace 13 by welding, fixing the other end of the tie rod 14 to the cantilever section of the cantilever main beam 11, fixing one end of the platform diagonal brace 13 to the cantilever section of the cantilever main beam 11, and each cantilever main beam 11 (i.e., a single No. 20a I-beam) is fixedly welded to a platform diagonal brace 13 and a tie rod 14 to form a platform support;

[0122] Step S22: hoist each platform support to the designated floor slab by a tower crane;

[0123] Step S23, fixing the cantilever main beam 11 to the designated floor slab (for example, the floor slab of the 26th floor) by at least four U-shaped bolts;

[0124] Step S24, fixing the lower end of the platform brace 13 to the first embedded part 1a in the lower floor slab (for example, the floor slab of the 25th floor) by welding;

[0125] Step S25, laying the horizontal connecting beam 12 and the platform plate on the cantilever main beam 11 in sequence;

[0126] Step S26, connecting the steel wire rope 15 between the cantilevered main beam 11 and the second embedded part of the upper floor slab.

[0127] Before installing the cantilevered operating platform, additional support measures can be added to the completed structural floor to prevent structural damage. The specific process of adding additional support measures includes: setting a second steel pipe rack 52 in the corridor of the main structure to support the designated floor and the floor below it.

[0128] After installing the cantilever operating platform, additional supporting measures may be further added in the completed structural floor. The specific process of adding additional supporting measures includes: fixing a first steel pipe bent frame 51 on the cantilever main beam 11 to support the cantilever main beam 11 and the upper floor of the designated floor.

[0129] like Figure 3 As shown, the projections of the first steel pipe frame 51 and the second steel pipe frame 52 in the vertical direction are both required to fall within the anchoring section of the cantilever main beam 11 .

[0130] Then, the upper scaffolding and the edge protection frame are set up on the cantilever operating platform, and the edge protection frame is used to hang the protection net. The specific process of setting up the upper scaffolding on the cantilever operating platform includes:

[0131] Step S31, fixing a plurality of vertical poles 21 on the horizontal connecting beam 12, and fixing a plurality of cross bars 22 to the plurality of vertical poles 21 through a first fastener;

[0132] Step S32, using a two-step two-span pre-embedded method or a through-wall connection method to perform wall-attached pull-joining;

[0133] Step S33, fully laying the scaffolding planks on the top surface of the horizontal connecting beam 12;

[0134] Step S34: install hard isolation, footboards and safety nets in sequence.

[0135] During the process of erecting the upper scaffolding on the cantilever operating platform, the upper main structure is constructed, and grooves for steel beam brackets and the first suspended beam are reserved in the shear wall of the upper main structure according to the design.

[0136] Please refer to Figure 1 and Fig.10 The groove of the steel beam bracket includes a placing groove 102, and the placing groove 102 is located below the groove 101 of the first suspended beam and is used to place the bracket body 31 of the steel beam bracket.

[0137] After the template of the shelf groove is removed, the steel beam bracket is installed. The specific process of installing the steel beam bracket includes:

[0138] Step S41, processing the bracket body 31 and the two bracket diagonal braces 32 on the ground, and fixing one end of the two bracket diagonal braces 32 on the bracket body 31 to form a steel beam bracket;

[0139] Step S42, hoisting the steel beam bracket into place by a tower crane;

[0140] Step S43, inserting the two ends of the bracket body 31 into the reserved recesses of the upper main structure (shear wall) respectively;

[0141] Step S44, leveling, and using high-fine stone concrete to cast and compact the shelf grooves.

[0142] Before the high-fine stone concrete is used to pour and compact the shelf groove, the horizontal reinforcement in the shear wall should be restored and extended, and the bracket brace 32 is fixedly connected to the embedded parts of the shear wall. Figure 4 As shown, the lower end of the bracket brace 32 is fixedly connected to the third embedded part 1d of the main structure (shear wall) by welding.

[0143] like Fig.11 As shown, the bracket body 31 of the steel beam bracket is placed in the placing groove 102. After the placing groove 102 is poured and compacted with the high-fine stone concrete, the steel beam bracket is fixedly installed under the groove 101 of the first suspended beam and is connected to the shear wall as a whole.

[0144] In this embodiment, the width of the shelf groove is 200 mm and the depth is 700 mm, and the width of the groove of the first cantilever beam is 600 mm and the depth is 400 mm.

[0145] After the steel beam bracket is installed, the large-section suspended beam structure is constructed. The specific process of constructing the large-section suspended beam structure includes: first, laying a plurality of short steel pipes on the steel beam bracket, and the plurality of short steel pipes are laid flat along the span direction of the steel beam bracket as the first concrete beam-column wooden formwork support foundation; then, supporting the first concrete beam-column wooden formwork on the first concrete beam-column wooden formwork support foundation, and the first concrete beam-column wooden formwork (including the bottom formwork and the side formwork) is tied with steel bars; then, concrete pouring is carried out, and during the concrete pouring process, the hanging column dowel bars are reserved, and then, concrete curing is carried out until the concrete strength of the first suspended beam and hanging column reaches the design requirements.

[0146] During the concrete curing process, scaffolding can be continued to be erected on the cantilever operating platform to construct the upper layer of structural concrete and the second cantilever beam and hanging column. After the second cantilever beam and hanging column are completed, scaffolding can be continued to be erected on the cantilever operating platform to construct the third cantilever beam and hanging column, and the remaining structural shear walls and floor slabs can be constructed to the designed structural top elevation.

[0147] Please continue to refer to Figure 1 When erecting scaffolding, safety protection structures such as steel pipe hard tie knots 28 are added to the frame.

[0148] In this embodiment, three suspended beams are constructed, namely a first suspended beam 10, a second suspended beam 20 and a third suspended beam 30. The dimensions of the first suspended beam and the second suspended beam are both 600mm×400mm, and the dimension of the third suspended beam is 600mm×1000mm.

[0149] In other embodiments, only one suspended beam, two suspended beams, or more than four suspended beams may be constructed according to design requirements.

[0150] After all the suspended beams and hanging columns are constructed, the concrete beam and column wooden formwork rack 42, steel beam bracket, scaffolding, horizontal connecting beam 12 and scaffolding board, and cantilever main beam 11 are removed in sequence.

[0151] In summary, in the high-support formwork system and its construction method provided by the present invention, the method of using large-section steel beams in combination with high-altitude cantilevered steel platforms solves the problem that large-section reinforced concrete components at high altitudes cannot be constructed. It not only can achieve good practical effects, but also has many advantages such as low construction difficulty, excellent economy, material saving and environmental protection, and high safety factor.

[0152] The above content is a further detailed description of the present application in combination with specific preferred implementation methods, and it cannot be determined that the specific implementation of the present application is limited to these descriptions. For ordinary technicians in the technical field to which the present application belongs, several simple deductions or substitutions can be made without departing from the concept of the present application, which should be deemed to fall within the scope of protection of the present application.

Claims

1. A high-support formwork system, characterized in that: include: Cantilever operating platform, scaffolding, steel beam brackets and concrete beam and column wooden formwork racks; The cantilever operating platform comprises a cantilever main beam, a horizontal connecting beam and a platform plate, wherein the horizontal connecting beam is vertically arranged with the cantilever main beam, the cantilever main beam comprises an anchoring section and a cantilevering section, the anchoring section of the cantilever main beam is fixed on a designated floor slab, the cantilevering section of the cantilever main beam extends out of the designated floor slab, and the horizontal connecting beam and the platform plate are both fixed to the cantilevering section of the cantilever main beam; The scaffolding is erected on the cantilevered operating platform and is fixedly connected to the horizontal connecting beam; The steel beam bracket is installed above the cantilever operating platform to support the cantilever beam structure; The steel beam bracket includes a bracket body and a bracket diagonal brace, the two ends of the bracket body are respectively inserted into the shelf grooves reserved in the shear wall and fixedly connected to the shear wall, one end of the bracket diagonal brace is fixedly connected to the bracket body, and the other end of the bracket diagonal brace is fixedly connected to the embedded part of the shear wall; The bracket body is provided with a concrete beam-column wooden formwork support foundation, and the concrete beam-column wooden formwork rack is installed on the concrete beam-column wooden formwork support foundation; The cantilever operating platform also includes a platform diagonal brace, a tie rod and a steel wire rope; one end of the platform diagonal brace is fixedly connected to the lower surface of the cantilever main beam, and the other end of the platform diagonal brace is fixedly connected to the embedded part of the lower floor slab; one end of the tie rod is fixedly connected to the platform diagonal brace, and the other end of the tie rod is fixedly connected to the cantilever main beam; the cantilever operating platform also includes a steel wire rope, one end of the steel wire rope is connected to the main beam, and the other end of the steel wire rope is fixedly connected to the embedded part of the upper floor slab; The high formwork system also includes: a first steel pipe frame and a second steel pipe frame; the first steel pipe frame is arranged on the top of the cantilever main beam, and is used to support the cantilever main beam and the upper floor of the designated floor; the second steel pipe frame is arranged in the corridor of the main structure, and is used to support the designated floor and its lower floor.

2. The high-support formwork system according to claim 1, characterized in that: The concrete beam-column wooden formwork supporting foundation comprises a plurality of steel pipes, and the plurality of steel pipes are arranged at intervals along the span direction of the steel beam bracket.

3. The high-support formwork system according to claim 1, characterized in that: The scaffolding comprises: a plurality of vertical poles, a plurality of horizontal poles, wall-attached tie-joints and scaffolding boards; The plurality of vertical poles are all arranged vertically, and the bottom ends thereof are fixedly connected to the horizontal connecting beam; The plurality of cross bars are all arranged horizontally and fixedly connected to the plurality of vertical bars through first fasteners; One end of the wall-attached tie is fixedly connected to the vertical pole, and the other end of the wall-attached tie is fixedly connected to the main structure of the building; The scaffolding planks are laid on the horizontal link beams.

4. The high-support formwork system according to claim 3, characterized in that: The plurality of vertical poles are all located at the intersection of the cantilevered main beam and the horizontal connecting beam.

5. The high-support formwork system according to claim 3, characterized in that: The scaffolding also includes hard isolation and safety nets; The hard isolation is arranged on the wall-attached connection, and the safety net is arranged on the inner side of the plurality of vertical poles and is fixedly connected to the plurality of vertical poles.

6. The high-support formwork system according to claim 1, characterized in that: The projections of the first steel tube rack and the second steel tube rack in the vertical direction both fall within the anchoring section of the cantilever main beam.

7. The high formwork system as described in claim 1, wherein the cantilevered main beam is fixedly connected to the designated floor slab by at least four U-bolts.

8. The high-support formwork system according to claim 1, characterized in that: The cantilever main beam is made of No. 20 I-beam, the horizontal connecting beam is made of No. 16 I-beam, the bracket body is made of No. 56 I-beam, and the bracket diagonal brace is made of No. 22 I-beam.

9. The high-support formwork system according to claim 1, characterized in that: The platform diagonal brace is made of No. 20 I-beam, and the tie rod is made of No. 16 channel steel.

10. A construction method of a high-support formwork system according to any one of claims 1 to 9, characterized in that: include: Step 1: construct the main concrete structure of the floor, and set embedded parts in the main concrete structure of the floor; Step 2: Install the cantilevered operating platform on the designated floor; Step 3: erecting an upper scaffold on the cantilever operating platform and constructing an upper main structure, wherein the upper main structure is provided with grooves for steel beam brackets and grooves for the first cantilever beam; Step 4: Install a steel beam bracket below the first suspended beam; Step 5: construct a large-section suspended beam on the steel beam bracket.

11. The construction method of the high-support formwork system according to claim 10, characterized in that: The process of installing a cantilevered operating platform on a given floor slab includes: Processing the cantilevered main beam, the platform diagonal brace and the tie rod on the ground, and forming the cantilevered main beam, the platform diagonal brace and the tie rod into a plurality of platform supports; Hoisting the plurality of platform supports into place by means of a tower crane; Fixing the cantilevered main beam to the designated floor slab by at least four U-bolts; The lower end of the platform diagonal brace is fixedly connected to the embedded parts of the lower floor slab; Laying horizontal connecting beams and platform plates on the cantilevered main beams in sequence; The steel wire rope is connected between the cantilevered main beam and the embedded parts of the upper floor slab.

12. The construction method of the high-support formwork system according to claim 10, characterized in that: Before installing the cantilevered operating platform on the designated floor slab and after constructing the main concrete structure of the floor, it also includes: installing a second steel pipe rack in the corridor of the main structure.

13. The construction method of the high-support formwork system according to claim 10, characterized in that: Before setting up the upper scaffolding on the cantilever operating platform and after installing the cantilever operating platform on the designated floor slab, the method further includes: installing a first steel pipe rack on the cantilever main beam.

14. The construction method of the high-support formwork system according to claim 10, characterized in that: The process of erecting the upper scaffolding on the cantilever operating platform includes: Fixing a plurality of vertical poles on the horizontal connecting beam, and fixing a plurality of cross bars to the plurality of vertical poles through a first fastener; Use the two-step two-span pre-embedded method or the through-wall connection method to make the wall-attached pull-joint; Laying scaffolding boards fully on the top surface of the horizontal connecting beam; and Install hard isolation, toe boards and safety nets in sequence.

15. The construction method of the high-support formwork system according to claim 10, characterized in that: The process of installing the steel beam bracket below the first suspended beam includes: Processing the bracket body and bracket diagonal braces on the ground to form a steel beam bracket; Hoisting the steel beam bracket into place by a tower crane; Inserting the two ends of the bracket body into the reserved recesses of the upper main structure respectively, and fixing the lower end of the bracket diagonal brace to the embedded parts of the shear wall by welding; and The shelving grooves are leveled and filled with high-fine stone concrete.

16. The construction method of the high-support formwork system according to claim 10, characterized in that: The process of constructing a large-section suspended beam on the steel beam bracket includes: Laying a plurality of steel pipes on the steel beam bracket as the support foundation for the first concrete beam and column wooden formwork; Support the first concrete beam and column wooden formwork on the support foundation of the first concrete beam and column wooden formwork; Carry out concrete pouring; and Concrete curing is carried out until the concrete strength of the first suspended beam reaches the design requirements.

17. The construction method of the high-support formwork system according to claim 16, characterized in that: The process of concrete curing also includes: continuing to erect scaffolding on the cantilever operating platform, constructing an upper layer of structural concrete and a second cantilever beam.