A guide hole arch frame erection device for initial support of tunnel and construction method thereof

By designing a mid-guide hole arch frame vertical device for initial support of the tunnel, the lifting and rotating mechanisms are used to achieve rapid installation of the arch frame, which solves the problems of high construction strength and long circulation time of the mid-guide hole in the double-sided wall guide method. , improve construction efficiency and safety.

CN112922644BActive Publication Date: 2024-11-19CHINA RAILWAY NO 5 ENG GRP LUQIAO ENG CO +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202110385249.9
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2021-04-09
Publication Date
2024-11-19
Estimated Expiration
2041-04-09

AI Technical Summary

Technical Problem

The construction strength of the intermediate guide holes in the double-sided wall guide holes is high and the circulation time is long. Especially during the construction of the intermediate guide holes, it is difficult to manually stand up, resulting in high construction speed and safety risks, and it is impossible to achieve mechanized construction.

Method used

A vertical frame device for the initial support of the tunnel is designed, including the frame groove, support system and connector. The lifting mechanism and rotating mechanism are used to achieve rapid installation and fine adjustment of the frame, which is suitable for the operating space of the vault position. Small occasions.

Benefits of technology

It reduces the work intensity and operation risks of workers, improves construction efficiency, realizes the rapid installation of intermediate guide hole arch frames, reduces the labor time and risks of artificial stand-up frames, and improves the construction speed.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN112922644B_ABST
    Figure CN112922644B_ABST
Patent Text Reader

Abstract

The present invention discloses a tunnel initial support middle guide hole arch frame erection device and a construction method thereof, wherein the arch frame erection device comprises an arch frame groove, a support system and a connector, wherein the arch frame groove comprises a vertical plate and a rib plate, wherein the vertical plate comprises a first vertical plate and a second vertical plate, wherein the first vertical plate and the second vertical plate are arranged parallel and parallel at a predetermined distance, wherein the rib plate is located between the first vertical plate and the second vertical plate, and wherein the two ends of the rib plate are respectively fixedly connected to the lower parts of the first vertical plate and the second vertical plate; wherein the support system comprises a lifting mechanism, a rotating mechanism and a mounting seat, wherein the lifting mechanism is erected on the supporting surface, wherein the mounting seat is fixedly connected to the top of the lifting mechanism by screws, and the rotating mechanism is fixed to the mounting seat; wherein the connector is located on the outer side of the first vertical plate and is fixedly connected to the arch frame groove, and is connected to the rotating mechanism by screws through a connecting rod. The present invention solves the problem that the operation space at the middle guide hole arch top position is small, and the erection frame and operation cannot be adopted, and the manual erection frame has high labor intensity, low efficiency and high risk factor.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the technical field of tunnel engineering, and in particular relates to a guide tunnel arch frame erection device in initial tunnel support and a construction method thereof. Background Art

[0002] The double-side wall pilot tunnel method is a construction technology that supports while excavating. Its principle is: use two middle partition walls to divide the entire tunnel section into three small sections: left, middle and right. The left and right pilot tunnels are constructed first, followed by the middle section. After the initial support arch is formed into a ring, the temporary supports of the pilot tunnels on both sides are removed to form a full section. The pilot tunnels on both sides are inverted goose egg shape, which is conducive to controlling the sinking of the arch.

[0003] The double-sidewall pilot method is suitable for driving tunnel excavation under Grade V surrounding rock conditions with poor surrounding rock. When constructing shallow buried large-span tunnels, the double-sidewall pilot method can control surface subsidence and maintain the stability of the heading face. Under the premise of higher requirements for traffic at present, it is widely used in three-lane and four-lane tunnels on highways and municipal roads.

[0004] The double-side wall pilot tunnel method is safe to construct, but it is slow and costly. The area of ​​each pilot tunnel is small, especially the middle pilot tunnel, which is difficult to construct. It is difficult to achieve large-scale mechanized construction of the step method and full-section excavation. It mainly relies on manual erection and mechanical coordination. There are great risks in both construction quality and construction safety. In addition, the manual construction cycle time of the middle pilot tunnel is long, which seriously restricts the overall tunnel excavation speed and becomes a bottleneck in the construction progress control of the double-side wall pilot tunnel method.

[0005] In this road project, the tunnel is a two-way 8-lane separated tunnel. The inner contour of the left and right lines of the tunnel is 11.45m high and 18.79m wide. The total length of the left line of the tunnel is 1983m, and the total length of the right line is 1769m. The geological structure of the tunnel is Niujiaopo anticline, and the surrounding rock grades are 4 and 5. Among them, the length of the surrounding rock of grade 5 is 936m, accounting for 49.9% of the total length of the tunnel. The tunnel entrance section Z5q and Z5 grade surrounding rock double side wall pilot pit method is used for excavation. Although the overall excavation width of the tunnel is large, the net width of the middle guide tunnel is only 4.12m, and the Z5q grade support belongs to the shallow buried reinforcement section. The surrounding rock is generally poor. The middle guide tunnel is excavated by the reserved core soil method. The operating space at the arch position is small, only about 1m, and it is impossible to use a frame machine for frame operation. It can only be carried out by manual frame operation, which has high labor intensity, long labor time and low efficiency. Summary of the invention

[0006] The purpose of the present invention is to provide a tunnel initial support middle guide tunnel arch frame erection device and a construction method thereof, and to use a mechanical installation middle guide tunnel arch frame to form support for the middle guide tunnel, so as to solve the problems of high work intensity and long cycle time in the middle guide tunnel construction of the double side wall pilot pit method.

[0007] The technical solution adopted by the present invention is a guide hole arch frame erection device for initial support of a tunnel, comprising:

[0008] An arch frame groove comprises a vertical plate and a rib plate, wherein the vertical plate comprises a first vertical plate and a second vertical plate, the first vertical plate and the second vertical plate are arranged parallel to each other at a predetermined distance, the rib plate comprises a first rib plate and a second rib plate, the first rib plate and the second rib plate are located between the first vertical plate and the second vertical plate, and are symmetrically arranged at the front end and the rear end lower part of the first vertical plate and the second vertical plate, respectively, the first rib plate and the second rib plate are arranged vertically, and the end surfaces of both sides of the first rib plate and the second rib plate are fixedly connected to the first vertical plate and the second vertical plate respectively;

[0009] The support system includes a lifting mechanism, a rotating mechanism and a mounting seat, wherein the lifting mechanism is vertically arranged on the support surface, the mounting seat is fixedly connected to the top of the lifting mechanism by screws, and the rotating mechanism is fixed on the mounting seat;

[0010] The connecting head is located at the outer side of the first vertical plate and is fixedly connected to the first vertical plate, and is connected to the rotating mechanism through a connecting rod by using screws.

[0011] Furthermore, the lifting mechanism includes a base, the top of the base is fixedly connected to a hydraulic cylinder, the hydraulic cylinder is connected to a hydraulic pump, an oil tank is arranged below the hydraulic pump and the oil tank is fixed on the base.

[0012] Furthermore, the rotating mechanism is composed of a motor and a motor output shaft connecting seat, the output shaft of the motor is inserted into the motor output shaft connecting seat, the bottom of the motor output shaft connecting seat is fixedly connected to a flange, and the flange is fixedly connected to the mounting seat.

[0013] Furthermore, the rib plate includes a first rib plate and a second rib plate, the first rib plate and the second rib plate are symmetrically arranged at the front end and the rear end of the first vertical plate and the second vertical plate respectively, and the first rib plate and the second rib plate are arranged vertically.

[0014] Furthermore, the rib plate is in a transverse I-shaped structure, the right end surface of the rib plate is welded to the first vertical plate, and the left end surface of the rib plate is welded to the second vertical plate.

[0015] Furthermore, the distance between the first vertical plate and the second vertical plate matches the width of the arch.

[0016] Furthermore, a plurality of positioning holes are transversely arranged on the upper parts of the first vertical plate and the second vertical plate, and positioning pins are arranged to match the positioning holes.

[0017] Furthermore, the connecting head includes a bottom plate and a side plate, the top of the bottom plate is fixedly connected to the bottom end of the first vertical plate, and the side plates are provided with two pieces, which are respectively fixed perpendicularly to the bottom plate and relatively fixed to the bottom plate, and corresponding mounting holes are provided on the two side plates, and the mounting holes are matched with fixing pins.

[0018] Furthermore, a reinforcing plate is provided at the connection between the bottom plate and the side plate of the connecting head, and the reinforcing plate includes an upper reinforcing plate, which is arranged at the connection between the bottom plate and the first vertical plate, a middle reinforcing plate, which is arranged in the middle of the bottom plate and the side plate, and a lower reinforcing plate, which is arranged at the lower part of the bottom plate and the side plate.

[0019] Furthermore, the mounting holes are respectively arranged between the upper reinforcement plate and the middle reinforcement plate, and between the middle reinforcement plate and the lower reinforcement plate;

[0020] A construction method for a guide tunnel arch frame erection device in initial tunnel support, comprising the following steps:

[0021] S1. Construction preparation: After the blasting excavation of the middle pilot hole is completed, the dangerous rocks on the face of the tunnel are cleared and the initial shotcrete is applied in time;

[0022] S2. Connection outside the arch hole: Assemble the connecting arch outside the middle guide hole to speed up the connection;

[0023] S3. Arch lifting: After the arch is connected, the excavator lifts the arch to make it upright, and directly lifts the arch using the arch groove. The arch is fixed by positioning pins passing through the positioning holes and the arch's own connection holes, and then the arch is lifted to the middle guide tunnel face by the lifting mechanism.

[0024] S4. Arch installation: fine-tune the arch position through the rotating mechanism, manually connect the bolts after completion, and use a wrench to rotate and reinforce;

[0025] S5. Anchor bolt construction: After the arch frame is installed and connected, the excavator is pushed out in time to start the system anchor bolt operation.

[0026] Compared with the prior art, the present invention has the following beneficial effects:

[0027] 1) The arch frame erection device proposed by the present invention has a simple structure, is easy to set up, and has low requirements for the use environment. When in use, the arch frame is quickly connected by the lower step, and is directly lifted to the arch top by the lifting mechanism. The middle guide hole arch frame is quickly installed after fine-tuning and rotating by the rotating mechanism. This solves the problem that the current middle guide hole arch top position has a small operating space and cannot be used for erection operations using an erection machine, while manual erection operations have high labor intensity and low efficiency. The present invention speeds up the cycle time while reducing the work intensity and number of workers. At the same time, due to mechanical operation, only simple manual cooperation is required, which reduces the risk of worker injury during manual erection.

[0028] 2) The present invention adopts a lifting mechanism and a rotating mechanism to form a support system. The lifting mechanism uses an electric-driven hydraulic pump to control the hydraulic cylinder to complete the lifting movement, which does not rely on the machinery in the cave, and the rotating mechanism realizes fine adjustment through the rotation of the motor to accurately install the arch frame;

[0029] 3) The rib plate adopts a first rib plate and a second rib plate to be fixed at the front end and the rear end of the first supporting plate and the second upright plate respectively, so as to achieve the purpose of stably and firmly connecting the first upright plate and the second upright plate, and the first rib plate and the second rib plate are symmetrically arranged vertically, which is conducive to supporting the arc-shaped arch frame;

[0030] 4) The rib plate is in a horizontal I-shaped structure, which increases the connection area between the left and right end surfaces of the rib plate and the second vertical plate and the first vertical plate, thereby enhancing the connection firmness;

[0031] 5) The distance between the first vertical plate and the second vertical plate matches the width of the arch frame, so that the arch frame is placed in the arch frame groove, which is conducive to the lifting of the arch frame;

[0032] 6) Positioning holes are arranged transversely on the upper parts of the first and second vertical plates, the positioning holes correspond to the connecting holes of the arch frame itself, and positioning pins are used to pass through the positioning holes and connecting holes on the vertical plates and the arch frame to prevent the arch frame from slipping during the lifting process;

[0033] 7) A reinforcing plate is provided at the connection between the bottom plate and the side plate of the connecting head to strengthen the connection firmness between the bottom plate and the side plate, increase the strength of the connecting head, and ensure that the connecting head can withstand the operation strength of the excavator arm on the connecting head. BRIEF DESCRIPTION OF THE DRAWINGS

[0034] Figure 1 It is a schematic diagram of the structure of the present invention;

[0035] Figure 2 It is a schematic diagram of the arch frame groove structure of the present invention;

[0036] Figure 3 This is a schematic diagram of the rib structure of the present invention;

[0037] Figure 4 It is a schematic diagram of the rotating structure of the present invention;

[0038] Figure 5 It is a schematic diagram of the connector structure of the present invention.

[0039] In the figure, it is marked: 1, arch frame groove, 11, vertical plate, 111, first vertical plate, 112, second vertical plate, 113, positioning hole, 114, positioning pin, 12, rib plate, 121, first rib plate, 122, second rib plate;

[0040] 2. Support system, 21. Lifting mechanism, 211. Base, 212. Traveling wheel, 213. Hydraulic cylinder, 214. Hydraulic pump, 215. Oil tank; 22. Rotating mechanism, 221. Motor, 222. Motor output shaft connecting seat, 223. Flange;

[0041] 3. Connector, 31. Bottom plate, 32. Side plate, 321. Mounting hole, 322. Fixing pin, 33. Reinforcement plate, 331. Upper reinforcement plate, 332. Middle reinforcement plate, 333. Lower reinforcement plate;

[0042] 4. Connecting rod. DETAILED DESCRIPTION

[0043] The present invention will be further explained below in conjunction with the accompanying drawings to facilitate better understanding by professionals in the field.

[0044] See also Figure 1-5 A tunnel initial support middle guide tunnel arch frame erection device comprises an arch frame groove 1, a support system 2, a connector 3 and a connecting rod 4.

[0045] The arch frame slot 1 includes a vertical plate 11 and a rib plate 12. The vertical plate 11 includes a first vertical plate 111 and a second vertical plate 112, which are two steel plates of the same structure and size. The thickness of the vertical plate 11 is not less than 5 cm and has sufficient strength. The first vertical plate 11 and the second vertical plate 12 are arranged in parallel and juxtaposed with a predetermined distance. The rib plate 12 is located between the first vertical plate 111 and the second vertical plate 112, and the two ends of the rib plate 12 are respectively fixedly connected to the lower parts of the first vertical plate 111 and the second vertical plate 112. In this embodiment, the rib plate 12 includes a first rib plate 121 and a second rib plate 122. The first rib plate 121 and the second rib plate 122 are respectively symmetrically arranged at the front and rear ends of the first vertical plate 111 and the second vertical plate 112 to stably and firmly connect the first vertical plate 111 and the second vertical plate 112 to maintain structural balance. The first rib plate 121 and the second rib plate 122 are arranged vertically, which is conducive to supporting the arc-shaped arch frame.

[0046] Furthermore, the rib plate 12 is in a horizontal I-shaped structure, the right end face of the rib plate 12 is welded to the first vertical plate 111, and the left end face of the rib plate 12 is welded to the second vertical plate 112. The I-shaped rib plate 12 increases the contact area between the rib plate 12 and the first vertical plate 111 and the second vertical plate 112, enhances the connection firmness, and facilitates welding.

[0047] The first vertical plate 111, the second vertical plate 112 and the rib plate 12 constitute an arch frame groove 1 with a predetermined depth, and the distance between the first vertical plate 111 and the second vertical plate 112 matches the width of the arch frame. The arch frame is placed horizontally in the arch frame groove 1, and the arch frame is clamped and lifted by the arch frame groove 1.

[0048] In order to prevent the arch frame from slipping during the lifting process, a plurality of positioning holes 113 are horizontally arranged on the upper parts of the first vertical plate 111 and the second vertical plate 112. The positioning holes 113 correspond to the connecting holes of the arch frame itself, and positioning pins 114 are arranged to match the positioning holes 113. The positioning pins 114 are passed through the positioning holes 113 and the connecting holes to fix the arch frame on the vertical plate 11.

[0049] The support system 2 includes a lifting mechanism 21, a rotating mechanism 22 and a mounting seat 23. The lifting mechanism 21 includes a base 211, which is erected on the support surface. A walking wheel 212 is provided at the bottom of the base 211. A hydraulic cylinder 213 is fixedly connected to the top of the base 211. The hydraulic cylinder 213 is connected to a hydraulic pump 214. An oil tank 214 is provided below the hydraulic pump 214 and the oil tank 215 is fixed on the base 211. The lifting mechanism 21 drives the hydraulic pump 214 by electricity, so that the hydraulic cylinder 213 rises and the arch frame is lifted through the arch frame slot 1. The mounting seat 23 is fixedly connected to the top of the lifting mechanism 21 by screws. The rotating mechanism 22 is fixed on the mounting seat 23. The rotating mechanism 22 is composed of a motor 221 and a motor output shaft connecting seat 222. The output shaft of the motor 221 is inserted into the motor output shaft connecting seat 222. The bottom of the motor output shaft connecting seat 222 is fixedly connected to a flange 223, and the flange 223 is fixedly connected to the mounting seat 23.

[0050] The connector 3 is located outside the first vertical plate 111 and is fixedly connected to the first vertical plate 111 , and is connected to the rotating mechanism 22 through the connecting rod 4 using screws. The connecting head 3 includes a bottom plate 31 and a side plate 32, the top of the bottom plate 31 is fixedly connected to the bottom end of the first vertical plate 111, and the side plates 32 are provided with two pieces, which are respectively perpendicular to the bottom plate 31 and relatively fixed on the side of the bottom plate 31 away from the first vertical plate 111, and the bottom plate 31 and the two side plates 32 form a U-shaped groove structure, and a reinforcing plate 33 is provided at the connection between the bottom plate 31 and the side plates 32 of the connecting head 3. Specifically, the reinforcing plate 33 includes an upper reinforcing plate 331, which is arranged at the connection between the bottom plate 31 and the first vertical plate 111, a middle reinforcing plate 332, which is arranged in the middle of the bottom plate 31 and the side plate 32, and a lower reinforcing plate 333, which is arranged at the lower part of the bottom plate 31 and the side plate 32, so as to increase the connection stability between the bottom plate 31 and the first vertical plate 111, the bottom plate 31 and the side plate 32, and increase the strength of the connecting head 3. In addition, corresponding mounting holes 321 are provided on the two side panels 32, and the mounting holes 321 are respectively arranged between the upper reinforcing plate 331 and the middle reinforcing plate 332, and between the middle reinforcing plate 332 and the lower reinforcing plate 333. The mounting holes 321 are matched with fixing pins 322, and the connecting rod 4 is fixedly connected by the fixing pins 322 after being inserted into the connecting head 3.

[0051] A construction method for a guide tunnel arch frame erection device in initial tunnel support, comprising the following steps:

[0052] S1. Construction preparation: After the blasting excavation of the middle guide tunnel is completed, the excavation face soil should be transported in time, the road should be leveled, the dangerous rocks on the excavation face should be cleared, and the initial shotcrete should be applied in time. Specifically, the thickness of the shotcrete for the 5-level surrounding rock is 28cm. After the excavation is completed, 4cm of shotcrete should be initially sprayed. After the steel frame is erected, the shotcrete should be sprayed layer by layer to the designed thickness. The thickness of the shotcrete for the arch crown should not be greater than 10cm.

[0053] S2. Connection of arch frame outside the tunnel: Since the arch frame of the middle guide tunnel is divided into two sections with a total length of 7.9m, it takes a long time to connect the tunnel face, so the arch frame is transported to the outside of the middle guide tunnel for connection to speed up the connection;

[0054] S3, arch support: After the arch is connected, the excavator lifts the arch to make it upright, and directly supports the arch by using the arch slot 1, and fixes the arch by using the positioning pin 113 through the positioning hole 114 and the connecting hole of the arch itself, and then supports the arch to the middle guide tunnel face;

[0055] S4, arch installation: start the lifting mechanism 21 to lift the connected arch to the tunnel face, and fine-tune the arch position by controlling the rotating mechanism 22, keep the arch installation spacing no more than 5cm, the arch inclination allowable deviation is ±2°, the assembly deviation is ±3mm, the installation deviation is ±50mm horizontally, and the vertical deviation is not less than the design value. After completion, manually connect the bolts and use a wrench to rotate and reinforce;

[0056] S5. Anchor bolt construction: After the arch frame is installed and connected, the excavator is pushed out in time, and the anchor bolt construction team enters the site to start the system anchor bolt operation.

[0057] The present invention can be used when the operating space at the arch position is small, only about 1m, and it is impossible to use a frame erection machine for frame erection operations, thereby solving the problems of high labor intensity, low efficiency, and high risk of manual frame erection in the prior art. In addition, the device of the present invention is compact, and can be quickly installed or disassembled. It is flexible and convenient, and does not occupy the cycle time. By quickly connecting the arch frame on the lower step and directly lifting it to the arch, it can be fine-tuned and rotated to achieve rapid installation of the middle guide hole arch frame, speeding up the cycle time while reducing the work intensity and number of workers. At the same time, due to mechanical operation, only simple manual cooperation is required, which reduces the risk of workers being injured in the middle of manual frame erection.

[0058] The embodiments described above are only some embodiments of the present invention, not all embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

Claims

1. A guide tunnel arch frame erection device for initial tunnel support, characterized in that: include: An arch frame groove (1) comprises a vertical plate (11) and a rib plate (12), wherein the vertical plate (11) comprises a first vertical plate (111) and a second vertical plate (112), the first vertical plate (111) and the second vertical plate (112) being arranged in parallel and juxtaposed with a predetermined distance, the rib plate (12) comprises a first rib plate (121) and a second rib plate (122), the first rib plate (121) and the second rib plate (122) being located between the first vertical plate (111) and the second vertical plate (112), and being symmetrically arranged at the front end and the rear end lower part of the first vertical plate (111) and the second vertical plate (112), respectively, the first rib plate (121) and the second rib plate (122) being arranged vertically, and the end surfaces of both sides of the first rib plate (121) and the second rib plate (122) being fixedly connected to the first vertical plate (111) and the second vertical plate (112), respectively; The support system (2) comprises a lifting mechanism (21), a rotating mechanism (22) and a mounting seat (23), wherein the lifting mechanism (21) is vertically arranged on the support surface, the mounting seat (23) is fixedly connected to the top of the lifting mechanism (21) by screws, and the rotating mechanism (22) is fixed on the mounting seat (23); A connecting head (3) is located outside the first vertical plate (111) and is fixedly connected to the first vertical plate (111), and is connected to the rotating mechanism (22) via a connecting rod (4) using screws; The lifting mechanism (21) comprises a base (211), a walking wheel (212) is arranged at the bottom of the base, a hydraulic cylinder (213) is fixedly connected to the top of the base (211), the hydraulic cylinder (213) is connected to a hydraulic pump (214), an oil tank (215) is arranged below the hydraulic pump (214), and the oil tank (215) is fixed on the base (211); The rotating mechanism (22) is composed of a motor (221) and a motor output shaft connecting seat (222); the output shaft of the motor (221) is inserted into the motor output shaft connecting seat (222); the bottom of the motor output shaft connecting seat (222) is fixedly connected to a flange (223); and the flange (223) is fixedly connected to the mounting seat (23); The connector (3) comprises a bottom plate (31) and a side plate (32); the top end of the bottom plate (31) is fixedly connected to the bottom end of the first vertical plate (111); the side plates (32) are provided with two pieces, which are respectively perpendicular to the bottom plate (31) and relatively fixed on the bottom plate (31); the two side plates (32) are provided with corresponding mounting holes (321); the mounting holes (321) are matched with fixing pins (322); a reinforcing plate (33) is provided at the connection between the bottom plate (31) and the side plate (32) of the connector (3); the reinforcing plate (33) comprises an upper reinforcing plate (331) arranged at the connection between the bottom plate (31) and the first vertical plate (111); a middle reinforcing plate (332) arranged in the middle of the bottom plate (31) and the side plate (32); and a lower reinforcing plate (333) arranged at the lower part of the bottom plate (31) and the side plate (32).

2. The device for erecting a guide tunnel arch frame in the initial support of a tunnel according to claim 1, characterized in that: The rib plate (12) is in a horizontal I-shaped structure, the right end surface of the rib plate (12) is welded to the first vertical plate (111), and the left end surface of the rib plate (12) is welded to the second vertical plate (112).

3. The device for erecting a guide tunnel arch frame in the initial support of a tunnel according to claim 1, characterized in that: The distance between the first vertical plate (111) and the second vertical plate (112) matches the width of the arch.

4. The device for erecting a guide tunnel arch frame in the initial support of a tunnel according to claim 1, characterized in that: A plurality of positioning holes (113) are transversely arranged on the upper parts of the first vertical plate (111) and the second vertical plate (112), and positioning pins (114) are arranged to match the positioning holes (113).

5. The device for erecting a guide tunnel arch frame in the initial support of a tunnel according to claim 1, characterized in that: The mounting holes (321) are respectively arranged between the upper reinforcing plate (331) and the middle reinforcing plate (332), and between the middle reinforcing plate (332) and the lower reinforcing plate (333).

6. A construction method for a guide tunnel arch frame erection device in initial tunnel support according to any one of claims 1 to 5, characterized in that: The following steps are involved: S1. Construction preparation: After the blasting excavation of the middle pilot hole is completed, the dangerous rocks on the face of the tunnel are cleared and the initial shotcrete is applied in time; S2. Connection outside the arch hole: Assemble the connecting arch outside the middle guide hole to speed up the connection; S3, arch frame lifting: after the arch frame is connected, the excavator lifts the arch frame to make it stand upright, and directly lifts the arch frame using the arch frame groove (1), and fixes the arch frame by using the positioning pin (114) passing through the positioning hole (113) and the arch frame's own connection hole, and then lifts the arch frame to the middle guide tunnel face by the lifting mechanism (21); S4, arch installation: fine-tune the arch position by rotating the mechanism (22), manually connect the bolts after completion, and use a wrench to rotate and reinforce; S5. Anchor bolt construction: After the arch frame is installed and connected, the excavator is pushed out in time to start the system anchor bolt operation.