A bored pile forming device and construction method for karst development areas

By using a drilling pile-in-fill pile-in-one device with a steel cage and a flexible sealing cavity in the karst development area, the problems of high construction difficulty and cost in the karst area are solved, and efficient pile-in-forming and low-cost construction results are achieved.

CN115262537BActive Publication Date: 2024-12-06GUANGXI COMM PLANNING SURVEYING & DESIGNING INST
View PDF 6 Cites 0 Cited by

Patent Information

Application Number
CN202210974182.7
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2022-08-15
Publication Date
2024-12-06
Estimated Expiration
2042-08-15

AI Technical Summary

Technical Problem

In karst development areas, the construction of drilling cast piles is difficult and costly, especially in areas where the foundation karst cavity and caves are dense and large in scale, it is difficult to effectively make piles with existing backfill flakes and concrete mortar backfill methods.

Method used

A drilled pile-in-fill pile-in-one device including a steel cage and a flexible sealing cavity is adopted. The flexible sealing cavity consists of flexible fiberglass plate, inner geotextile, outer geotextile, top support steel ring and bottom support steel ring. The mortar is filled with the cavity under high pressure to ensure sealing and structural stability and reduce the amount of added filler.

Benefits of technology

It significantly improves the pile formation efficiency and construction quality in karst development areas, reduces construction costs, and ensures the stability and sealing of pile foundations.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN115262537B_ABST
    Figure CN115262537B_ABST
Patent Text Reader

Abstract

The present invention relates to a bored pile construction device and construction method for karst development areas, comprising a steel cage, a top support steel ring, a bottom support steel ring, a flexible glass fiber reinforced plastic plate and a geotextile. During production, the main reinforcement of the steel cage is welded to the inner side walls of the top and bottom support steel rings, and the flexible glass fiber reinforced plastic plate is outwrapped on the outside of the steel cage, and together with the steel cage, the top support steel ring and the bottom support steel ring, forms a support system for the high-strength geotextile. The high-strength geotextile is fixed and sewn by means of a throat hoop to form an annular closed space on the periphery of the steel cage, wherein the top support steel ring is provided with a grouting channel and an exhaust channel connected to the enclosed space. The present invention can greatly reduce the amount of external fillers used in the construction of bored piles in karst development areas, significantly improve the pile construction efficiency in karst development areas such as beaded karst development areas, and ensure the quality of pile foundation construction. The device and construction method are low in cost, high in construction efficiency, and have wide promotion and application value.
Need to check novelty before this filing date? Find Prior Art

Description

Technical field:

[0001] The invention belongs to the field of pile foundation engineering in geotechnical engineering, in particular to a bored cast-in-place pile forming device and a construction method for a karst development area. Background technology:

[0002] As a major foundation form for long-span bridges and important buildings (structures), bored cast-in-place piles are currently widely used in housing construction, highways, railways, water transportation, municipal administration and other fields. They mainly bear the load on the top of the pile by using the lateral friction between the pile side wall and the rock and soil layer and the pile end resistance as the supporting force.

[0003] For bored cast-in-place piles in karst areas, backfilling with stone slabs and concrete mortar is often used to fill cavities and caves. This method is acceptable for small-scale areas or areas with low karst development. However, for karst development areas with dense karst cavities and caves in the foundation and large scale, the construction difficulty and construction cost of bored cast-in-place piles in karst development areas often increase sharply due to many unfavorable factors such as the huge scale of backfilling and the difficulty of backfilling construction, and even make it impossible to pile. Summary of the invention:

[0004] In order to effectively solve the problem of difficulty in forming bored cast-in-place piles in karst developed areas, the present invention discloses a bored cast-in-place pile forming device and a construction method for karst developed areas. The bored cast-in-place pile forming device and the construction method for karst developed areas can ensure the quality of bored cast-in-place piles in karst developed areas where foundation karst cavities and caves are densely distributed and large in scale, thereby improving construction quality and reducing construction costs.

[0005] A bored pile forming device for a karst development area comprises a steel cage and a flexible sealing cavity.

[0006] The flexible sealing cavity is arranged on the outer periphery of the steel cage, and comprises a flexible glass fiber reinforced plastic plate, an inner geotextile, an outer geotextile, a top supporting steel ring and a bottom supporting steel ring.

[0007] The top supporting steel ring is fixedly arranged on the outer periphery of the top of the steel cage, and the longitudinal section is inverted U-shape, with an inverted U-shaped cavity; the top surface of the top supporting steel ring is provided with vertically penetrating air outlet holes and grouting holes.

[0008] The bottom supporting steel ring is fixedly arranged on the outer periphery of the bottom of the steel cage, and has a U-shaped longitudinal section and a U-shaped cavity.

[0009] The flexible fiberglass plate, the inner geotextile and the outer geotextile are coaxially arranged from the inside to the outside.

[0010] Flexible fiberglass panels are covered on the outer wall of the steel cage.

[0011] The inner geotextile is covered on the outer wall surface of the flexible fiberglass plate.

[0012] The top end of the outer geotextile is covered on the outer wall surface of the top supporting steel ring, and the bottom end of the outer geotextile is covered on the outer wall surface of the bottom supporting steel ring.

[0013] The flexible glass fiber reinforced plastic plate covered with the inner layer geotextile, the top supporting steel ring, the outer layer geotextile and the bottom supporting steel ring together enclose the flexible sealing cavity.

[0014] The tensile strength of the flexible fiberglass sheet is greater than that of the outer geotextile.

[0015] The grouting hole is connected to the grouting device and is used for pouring mortar into the flexible sealing cavity.

[0016] Concrete is poured inside the steel cage.

[0017] The tensile strength of the outer geotextile in the warp direction is 100kN / m, and the tensile strength in the weft direction is 50kN / m.

[0018] The radial thicknesses of the inverted U-shaped cavity and the U-shaped cavity are equal and are both selected according to the diameter of the steel cage.

[0019] The top supporting steel ring and the bottom supporting steel ring are both welded and fixed to the outer wall of the steel cage.

[0020] A construction method for bored cast-in-place piles in a karst development area comprises the following steps.

[0021] Step 1: Make a steel cage.

[0022] Step 2: Making a flexible sealing cavity, specifically including the following steps:

[0023] Step 21, fix the top supporting steel ring: fix the top supporting steel ring with an inverted U-shaped longitudinal section on the top periphery of the steel cage; the top surface of the top supporting steel ring is provided with vertically penetrating air outlet holes and grouting holes.

[0024] Step 22, fix the bottom support steel ring: fix the bottom support steel ring with a U-shaped longitudinal section on the bottom periphery of the steel cage.

[0025] Step 23, covering with flexible glass fiber reinforced plastic sheet: Cover the outer wall of the steel cage with flexible glass fiber reinforced plastic sheet.

[0026] Step 24, covering with inner geotextile: Covering the outer wall of the flexible fiberglass plate with inner geotextile.

[0027] Step 25, covering with outer geotextile: covering the outer side of the top supporting steel ring and the bottom supporting steel ring with a vertical outer geotextile; the flexible fiberglass plate covered with the inner geotextile, the top supporting steel ring, the outer geotextile and the bottom supporting steel ring together form a sealed flexible sealing cavity; wherein the tensile strength of the flexible fiberglass plate is greater than the tensile strength of the outer geotextile.

[0028] Step 3, sealing test: Perform a sealing test on the flexible sealing cavity produced in step 2 to ensure that the sealing effect of the flexible sealing cavity meets the set requirements.

[0029] Step 4, drilling: In areas with developed foundation karst or densely populated caves and cavities, the full sleeve follow-up method is used for hole construction.

[0030] Step 5, pile placement: hoist the steel cage with the flexible sealing cavity into the drilled hole with the sleeve wall in step 4.

[0031] Step 6, grouting: first pull out the sleeve to the setting position of the pile top; then, use a grouting device to pour mortar into the flexible sealing cavity in step 5 through the grouting hole; during the mortar pouring process, the air in the flexible sealing cavity is discharged through the vent; when the flexible sealing cavity is completely filled with mortar and a stable slurry flows out of the vent, the vent is blocked.

[0032] Step 7, pressurized grouting: continue to pour mortar into the flexible sealing cavity, and pull out the sleeve of the set height while pouring; when the pressure in the flexible sealing cavity reaches the set pressure value, stop pouring and pull out all the sleeves; during the pressurized grouting process, since the tensile strength of the flexible fiberglass plate is greater than the tensile strength of the outer geotextile; the flexible fiberglass plate remains in a vertical state to prevent the pressurized mortar from squeezing and damaging the main reinforcement and stirrups in the steel cage; at the same time, the outer geotextile expands outward under the squeezing of the pressurized mortar, forming an arc-shaped bulge that can seal and plug the corresponding karst cavity in the foundation karst development area or the karst cave karst cavity densely distributed area.

[0033] Step 8: Pour concrete: Pour concrete in the steel cage to form piles.

[0034] In step 7, the set pressure value in the flexible sealing cavity is 0.8 MPa to 1.0 MPa.

[0035] In step 2, the radial thicknesses of the inverted U-shaped cavity and the U-shaped cavity are equal and are both selected according to the diameter of the steel cage; the larger the diameter of the steel cage, the larger the radial thickness of the inverted U-shaped cavity or the U-shaped cavity.

[0036] Assume that the diameter of the steel cage is D and the radial thickness of the inverted U-shaped cavity or U-shaped cavity is d, then select according to the following table:

[0037] D / m 0.6 0.9 1.2 1.5 1.8 d / mm 200 250 300 350 400

[0038] In step 8, the upper surface of the concrete is flush with the upper surface of the pouring mortar, and the distance between the lower surface of the concrete and the lower surface of the pouring mortar is 1m.

[0039] Beneficial effects:

[0040] The present invention can greatly reduce the amount of external fillers used in the construction of bored piles in karst development areas, significantly improve the pile forming efficiency in karst development areas such as beaded karst development areas, and ensure the quality of pile foundation construction. The device and construction method are low in cost, high in construction efficiency, and have wide promotion and application value. Description of the drawings:

[0041] Figure 1 The schematic diagram shows the effect of the bored pile forming device in the karst development area after construction of the present invention.

[0042] Figure 2 The schematic diagram of the structure of the bored pile forming device for karst development area of ​​the present invention is shown.

[0043] Figure 3 Shows Figure 2 Schematic diagram of the enlarged structure of the box area A.

[0044] Figure 4 Shows Figure 2 Schematic diagram of the enlarged structure of the box area B.

[0045] Figure 5 A schematic diagram showing the structure of the air vents and grouting holes on the top support steel ring.

[0046] Figure 6 Shows Figure 5 Schematic diagram of the enlarged structure of the box area C.

[0047] Among them are:

[0048] 10. Steel cage; 11. Main reinforcement; 12. Stirrups;

[0049] 20. Flexible sealing cavity;

[0050] 21. Flexible fiberglass sheet; 22. Inner geotextile;

[0051] 23. Outer geotextile; 231. Arc-shaped convexity;

[0052] 24. Top support steel ring;

[0053] 241. Air outlet; 241a. Exhaust hose; 241b. Wedge-shaped body;

[0054] 242. Grouting hole; 242a. Grouting connector; 242b. Grouting rubber plug;

[0055] 25. Bottom support steel ring; 26. Elastic throat clamp;

[0056] 30. Karst development area; 31. Karst cavity;

[0057] 40. Concrete; 50. Mortar. Specific implementation method:

[0058] In the description of the present invention, it should be understood that the terms "left side", "right side", "upper part", "lower part" and the like indicate the orientation or positional relationship based on the orientation or positional relationship shown in the drawings, which is only for the convenience of describing the present invention and simplifying the description, and does not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation. "First", "second" and the like do not indicate the importance of the components, and therefore cannot be understood as limiting the present invention. The specific dimensions used in this embodiment are only for illustrating the technical solution, and do not limit the scope of protection of the present invention.

[0059] like Figures 1 to 4 As shown, a bored pile construction device for karst development areas includes a steel cage 10, a flexible sealing chamber 20 and a grouting device.

[0060] The steel cage includes a plurality of vertically arranged main bars 11, a plurality of transversely arranged transverse bars (not shown in the figure) and stirrups 12 arranged around the periphery of the main bars.

[0061] The flexible sealing cavity is arranged on the outer periphery of the steel cage, and comprises a flexible glass fiber reinforced plastic plate, an inner geotextile, an outer geotextile, a top supporting steel ring and a bottom supporting steel ring.

[0062] The top supporting steel ring is preferably welded and fixed on the outer periphery of the top of the steel cage, and has an inverted U-shaped longitudinal section with an inverted U-shaped cavity.

[0063] The top surface of the top support steel ring is provided with Figure 5 and Figure 6 The vertically penetrating air outlet holes 241 and grouting holes 242 are shown.

[0064] An exhaust hose 241a is preferably inserted into the air outlet, and flexible wedge-shaped bodies 241b are preferably provided on the exhaust hoses located inside and outside the air outlet, so as to limit the position of the exhaust hoses and prevent slipping.

[0065] The grouting holes are preferably internal threaded holes for installing grouting devices.

[0066] The grouting device includes a grouting connector 242a and a grouting rubber plug 242b. The bottom end of the grouting connector is threadedly installed in the grouting hole, the top end of the grouting connector is provided with a grouting port, and a grouting rubber plug capable of lifting and lowering the height is provided below the grouting port, and the grouting rubber plug can seal the grouting port.

[0067] The bottom supporting steel ring is preferably welded and fixedly arranged on the outer periphery of the bottom of the steel cage, and has a U-shaped longitudinal section and a U-shaped cavity.

[0068] The flexible fiberglass plate, the inner geotextile and the outer geotextile are coaxially arranged from the inside to the outside.

[0069] The flexible glass fiber reinforced plastic plate is coated on the outer wall of the steel cage, and the flexible glass fiber reinforced plastic plate preferably adopts a large-diameter elastic throat hoop 26 to position the stirrups according to the set spacing. As an alternative, it can also be positioned by bonding or other methods.

[0070] The structures of the top and bottom ends of the flexible glass fiber reinforced plastic plate have the following two preferred embodiments.

[0071] Example 1

[0072] The top supporting steel ring is directly welded and fixed on the top periphery of the steel cage, and the bottom supporting steel ring is directly welded and fixed on the bottom periphery of the steel cage. The top end of the flexible glass fiber reinforced plastic plate extends into the inner wall of the inverted U-shaped cavity, and the bottom end extends into the inner wall of the U-shaped cavity.

[0073] Example 2

[0074] The top surface height of the flexible glass fiber reinforced plastic plate is lower than the top end surface of the top supporting steel ring. Therefore, the top end of the top supporting steel ring and the top end of the steel cage are welded, and the flexible glass fiber reinforced plastic plate is directly and completely covered on the outer periphery of the steel cage.

[0075] The inner geotextile is covered on the outer wall surface of the flexible fiberglass plate.

[0076] The top of the outer geotextile is covered on the outer wall of the top supporting steel ring, and the bottom of the outer geotextile is covered on the outer wall of the bottom supporting steel ring. The model of the outer geotextile is preferably high-strength and durable geotextile PET100-50, and its tensile strength in the warp direction is preferably 100kn / m, and its tensile strength in the weft direction is preferably 50kn / m.

[0077] The flexible glass fiber reinforced plastic plate covered with the inner layer geotextile, the top supporting steel ring, the outer layer geotextile and the bottom supporting steel ring together enclose the flexible sealing cavity.

[0078] The tensile strength of the flexible fiberglass sheet is greater than that of the outer geotextile.

[0079] The grouting device can inject mortar into the flexible sealing cavity through the grouting hole.

[0080] Concrete is poured inside the steel cage.

[0081] A construction method for bored cast-in-place piles in a karst development area comprises the following steps.

[0082] Step 1: Make a steel cage.

[0083] Step 2: Making a flexible sealing cavity, specifically including the following steps:

[0084] Step 21, fix the top supporting steel ring: preferably weld the top supporting steel ring with an inverted U-shaped longitudinal section to the top periphery of the steel cage (main reinforcement); the top surface of the top supporting steel ring is provided with vertically penetrating air vents and grouting holes.

[0085] Step 22, fix the bottom support steel ring: preferably weld the bottom support steel ring with a U-shaped longitudinal section to the bottom periphery of the steel cage (main reinforcement).

[0086] The radial thicknesses of the above-mentioned inverted U-shaped cavity and U-shaped cavity are equal and are both selected according to the diameter of the steel cage; the larger the diameter of the steel cage, the larger the radial thickness of the inverted U-shaped cavity or the U-shaped cavity.

[0087] Assuming that the diameter of the steel cage is D and the radial thickness of the inverted U-shaped cavity or the U-shaped cavity is d, it is preferred to select according to the following table:

[0088] D / m 0.6 0.9 1.2 1.5 1.8 d / mm 200 250 300 350 400

[0089] Step 23, coating with flexible glass fiber reinforced plastic plates: coating the outer wall of the steel cage with flexible glass fiber reinforced plastic plates at a set interval.

[0090] The above-mentioned flexible glass fiber reinforced plastic sheet is mainly used to resist the influence of the cavity grouting pressure on the main reinforcement and stirrups of the steel cage, and prevent the deformation of the main reinforcement and stirrups of the steel cage. During the manufacturing process, part of the flexible glass fiber reinforced plastic sheet should be overlapped with the top support steel ring and the bottom support steel ring.

[0091] Step 24, covering the inner geotextile: Covering the outer wall of the flexible fiberglass plate with the inner geotextile. The inner geotextile can be bonded to the outer wall of the flexible fiberglass plate, or elastic throat hoops can be used to limit the hoop reinforcement according to the set spacing.

[0092] Step 25, covering with outer geotextile: Cover the outer side of the top support steel ring and the bottom support steel ring with a vertical outer geotextile. The outer geotextile can be bonded to the outer wall surface of the corresponding support steel ring, or elastic throat clamps can be used to limit the stirrups according to the set spacing.

[0093] The flexible glass fiber reinforced plastic plate coated with the inner layer geotextile, the top supporting steel ring, the outer layer geotextile and the bottom supporting steel ring together enclose a sealed flexible sealing cavity; wherein the tensile strength of the flexible glass fiber reinforced plastic plate is greater than the tensile strength of the outer layer geotextile.

[0094] Step 3, sealing test: Perform a sealing test on the flexible sealing cavity produced in step 2 to ensure that the sealing effect of the flexible sealing cavity meets the set requirements.

[0095] Step 4, drilling: In areas with developed foundation karst or densely populated caves and cavities, the full sleeve follow-up method is used for hole construction.

[0096] Step 5, pile placement: hoist the steel cage with a flexible sealing cavity into the borehole with the sleeve wall in step 4. At the same time, the hole bottom residue is cleaned using the common hole cleaning process for bored piles.

[0097] Step 6, grouting: first pull out the sleeve to the setting position of the pile top. Then, use the grouting device to inject mortar into the flexible sealing cavity in step 5 through the grouting hole. Before grouting, turn on the air compressor to grout the flexible sealing cavity. During grouting, because the slurry ratio of the initial part is difficult to meet the design requirements and contains a lot of air, the grouting head should be connected to inject into the flexible sealing cavity only after the slurry flow rate and slurry quality in the grouting pipe are stable.

[0098] During the mortar pouring process, the air in the flexible sealing cavity is discharged through the vent hole; when the flexible sealing cavity is completely filled with mortar and a stable slurry flows out of the vent hole, the vent hole is blocked.

[0099] Step 7, pressurized grouting: continue to pour mortar into the flexible sealing cavity, and pull out the sleeve of the set height while pouring; when the pressure in the flexible sealing cavity reaches the set pressure value (preferably 0.8MPa~1.0Mpa), stop pouring and pull out all the sleeves; during the pressurized grouting process, since the tensile strength of the flexible fiberglass plate is greater than the tensile strength of the outer geotextile, the flexible fiberglass plate remains in a vertical state to prevent the pressurized mortar from squeezing and damaging the main bars and stirrups in the steel cage; at the same time, the outer geotextile expands outward under the squeezing of the pressurized mortar, forming an arc-shaped protrusion that can seal and plug the corresponding karst cavity in the foundation karst development area or the karst cave karst cavity densely distributed area.

[0100] Step 8: Pour concrete: Pour concrete in the steel cage to form piles.

[0101] The upper surface of the concrete is flush with the upper surface of the pouring mortar, and the distance between the lower surface of the concrete and the lower surface of the pouring mortar is about 1m.

[0102] The preferred embodiments of the present invention are described in detail above; however, the present invention is not limited to the specific details in the above embodiments. Within the technical concept of the present invention, various equivalent transformations can be made to the technical solutions of the present invention, and these equivalent transformations all belong to the protection scope of the present invention.

Claims

1. A bored pile forming device for karst development areas, Features: It includes a steel cage and a flexible sealing chamber; The flexible sealing cavity is arranged on the outer periphery of the steel cage, and includes a flexible glass fiber reinforced plastic plate, an inner geotextile, an outer geotextile, a top supporting steel ring and a bottom supporting steel ring; The top supporting steel ring is fixedly arranged on the outer periphery of the top of the steel cage, and the longitudinal section is in an inverted U shape, with an inverted U-shaped cavity; The top surface of the top supporting steel ring is provided with vertically penetrating air outlet holes and grouting holes; The bottom support steel ring is fixedly arranged on the outer periphery of the bottom of the steel cage, and has a U-shaped longitudinal section and a U-shaped cavity; The flexible fiberglass plate, the inner geotextile and the outer geotextile are coaxially arranged from the inside to the outside; Flexible fiberglass panels are wrapped around the outer wall of the steel cage; The inner geotextile is wrapped around the outer wall of the flexible fiberglass plate; The top end of the outer geotextile is covered on the outer wall surface of the top supporting steel ring, and the bottom end of the outer geotextile is covered on the outer wall surface of the bottom supporting steel ring; The flexible glass fiber reinforced plastic plate covered with an inner layer of geotextile, the top supporting steel ring, the outer layer of geotextile and the bottom supporting steel ring together enclose the flexible sealing cavity; The tensile strength of the flexible fiberglass sheet is greater than that of the outer geotextile; The grouting hole is connected to the grouting device and is used to pour mortar into the flexible sealing cavity; Concrete is poured inside the steel cage; The radial thickness of the inverted U-shaped cavity and the U-shaped cavity are equal and are both selected according to the diameter of the reinforcement cage; Assuming the diameter of the steel cage is D and the radial thickness of the inverted U-shaped cavity or U-shaped cavity is d, the selection is made as follows: When D=0.6m, d=200mm; When D=0.9m, d=250mm; When D=1.2m, d=300mm; When D=1.5m, d=350mm; When D=1.8m, d=400mm; It can reduce the amount of external fillers used in bored pile construction in karst-developed areas and improve the pile-forming efficiency in beaded karst-developed areas; The length of the side of the bottom supporting steel ring and the top supporting steel ring close to the steel cage is longer than the length of the side away from the steel cage, and is shorter than the flexible glass fiber reinforced plastic plate.

2. The bored pile forming device for karst development area according to claim 1, Features: The tensile strength of the outer geotextile in the warp direction is 100kN / m, and the tensile strength in the weft direction is 50kN / m.

3. The bored pile forming device for karst development area according to claim 1, Features: The top supporting steel ring and the bottom supporting steel ring are both welded and fixed to the outer wall of the steel cage.

4. A method for constructing bored piles in karst development areas, based on the bored pile construction device for karst development areas according to any one of claims 1 to 3, Features: The steps include: Step 1: Make a steel cage; Step 2: Making a flexible sealing cavity, specifically including the following steps: Step 21, fixing the top supporting steel ring: fixing the top supporting steel ring with an inverted U-shaped longitudinal section on the top periphery of the steel cage; the top surface of the top supporting steel ring is provided with vertically penetrating air outlet holes and grouting holes; Step 22, fixing the bottom support steel ring: fixing the bottom support steel ring with a U-shaped longitudinal section on the outer periphery of the bottom of the steel cage; Step 23, coating with flexible glass fiber reinforced plastic sheet: coating the outer wall of the steel cage with a flexible glass fiber reinforced plastic sheet; Step 24, covering with inner geotextile: covering the outer wall of the flexible fiberglass plate with inner geotextile; Step 25, covering with outer geotextile: covering the outer side of the top supporting steel ring and the bottom supporting steel ring with a vertical outer geotextile; the flexible glass fiber reinforced plastic plate covered with the inner geotextile, the top supporting steel ring, the outer geotextile and the bottom supporting steel ring together enclose to form a sealed flexible sealing cavity; wherein the tensile strength of the flexible glass fiber reinforced plastic plate is greater than the tensile strength of the outer geotextile; Step 3, sealing test: perform sealing test on the flexible sealing cavity produced in step 2, so that the sealing effect of the flexible sealing cavity meets the set requirements; Step 4, drilling: In areas with karst development or densely populated caves and cavities, the full sleeve follow-up method is used for drilling construction; Step 5, pile placement: hoist the steel cage with the flexible sealing cavity into the drilled hole with the sleeve wall in step 4; Step 6, grouting: first pull out the sleeve to the setting position of the pile top; then, use a grouting device to pour mortar into the flexible sealing cavity in step 5 through the grouting hole; during the mortar pouring process, the air in the flexible sealing cavity is discharged through the air outlet; when the flexible sealing cavity is completely filled with mortar and a stable slurry flows out of the air outlet, the air outlet is blocked; Step 7, pressurized grouting: continue to pour mortar into the flexible sealing cavity, and pull out the sleeve of the set height while pouring; when the pressure in the flexible sealing cavity reaches the set pressure value, stop pouring and pull out all the sleeves; during the pressurized grouting process, since the tensile strength of the flexible fiberglass plate is greater than the tensile strength of the outer geotextile; the flexible fiberglass plate remains in a vertical state to prevent the pressurized mortar from squeezing and damaging the main reinforcement and stirrups in the steel cage; at the same time, the outer geotextile expands outward under the squeezing of the pressurized mortar, forming an arc-shaped bulge that can seal and plug the corresponding karst cavity in the foundation karst development area or the karst cave karst cavity densely distributed area; Step 8: Pour concrete: Pour concrete in the steel cage to form piles.

5. The method for constructing bored piles in karst development areas according to claim 4, Features: In step 7, the set pressure value in the flexible sealing cavity is 0.8 MPa~1.0 MPa.

6. The method for constructing bored piles in karst development areas according to claim 4, Features: In step 2, the radial thicknesses of the inverted U-shaped cavity and the U-shaped cavity are equal and are both selected according to the diameter of the steel cage; the larger the diameter of the steel cage, the larger the radial thickness of the inverted U-shaped cavity or the U-shaped cavity.

7. The construction method of bored piles in karst development areas according to claim 4, Features: In step 8, the upper surface of the concrete is flush with the upper surface of the pouring mortar, and the distance between the lower surface of the concrete and the lower surface of the pouring mortar is 1m.

Citation Information

Patent Citations

  • Flexible pile casing for preventing concrete loss and mounting method of pile casing

    CN109577324A

  • Bored cast-in-place pile suitable for karst areas with connectivity channels and pile forming method thereof

    CN110820732A

  • Method for forming pile foundation in karst area

    CN114108675A

  • Cast-in-place pile forming device and pile forming method suitable for karst area

    CN114457790A

  • Mould bag pile suitable for karst area

    CN216108465U