Pre-pressing device for 0 # block bracket of continuous rigid frame bridge and construction method

By using a bracket and back frame system combined with a hydraulic jack prepression device in the construction of continuous rigid bridges, the problems of high safety risks and long construction periods of high altitude lifting operations during the bracket prepression process are solved, and the construction cycle is shortened and Reduced costs.

CN118932887APending Publication Date: 2024-11-12CHINA 19TH METALLURGICAL CORP
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411307572.4
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-09-19
Publication Date
2024-11-12

AI Technical Summary

Technical Problem

In the construction of continuous rigid structure bridges, there is a problem of high safety risks and long construction periods during the bracket pre-pressing process.

Method used

A prepressing device including a bracket, a back frame system and a prepressure loading system is designed to apply prepressure on the top of the pier column through hydraulic jacks and rebound beam components, reducing high-altitude lifting operations and shortening construction cycle.

Benefits of technology

It significantly shortens the construction cycle, reduces high-altitude lifting operations, reduces construction costs, and improves construction safety.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118932887A_ABST
    Figure CN118932887A_ABST
Patent Text Reader

Abstract

The invention discloses a pre-pressing device for a 0 # block bracket of a continuous rigid frame bridge and a construction method, and belongs to the technical field of design and construction of bridge engineering structures. According to the pre-pressing device for the 0 # block bracket of the continuous rigid frame bridge and the construction method, the construction period is relatively short, and high-altitude hoisting operation is obviously reduced. The pre-pressing device comprises a bracket or a falsework, the bracket or the falsework is detachably arranged at the corresponding position of the top of the pier column, the pre-pressing device further comprises a back frame system and a pre-pressing loading system, and the back frame system and the bracket or the falsework are arranged at the top of the pier column in the mode that the position of the back frame system is matched with that of the bracket or the falsework. And the bracket or the falsework applies pre-pressure of a specified load through the pre-pressure loading system under the matching of the back frame system.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to a preloading device, in particular to a preloading device for a 0# block bracket of a continuous rigid frame bridge, belonging to the technical field of design and construction of bridge engineering structures. The present invention also relates to a construction method for preloading a 0# block bracket using the preloading device for a 0# block bracket of a continuous rigid frame bridge. Background Art

[0002] With the continuous expansion of the scale and speed of transportation engineering construction in my country, bridge engineering has become a very important construction link. In the construction process, special structures of bridges are often required due to terrain restrictions. In the construction of continuous rigid frame bridges, cantilever casting construction is an indispensable link. Cantilever casting construction must first cast 0# blocks. The 0# block casting formwork support system usually adopts brackets or false frames. After the bracket is installed, it is necessary to pre-press the bracket to test the stability and bearing capacity of the bracket. Only after the pre-pressing is qualified can the 0# block related construction process be carried out.

[0003] At present, the pre-loading of 0# block brackets usually adopts the traditional pile loading pre-loading method, which involves a large amount of high-altitude lifting operations, has high safety risks, and takes a long time to complete. Summary of the invention

[0004] The technical problem to be solved by the present invention is to provide a pre-stressing device for the 0# block bracket of a continuous rigid frame bridge, which has a relatively short construction period and significantly reduces high-altitude lifting operations, and a construction method for pre-stressing the 0# block bracket using the pre-stressing device for the 0# block bracket of a continuous rigid frame bridge.

[0005] The technical solution adopted to solve the above technical problems is: a prestressing device for the 0# block bracket of a continuous rigid frame bridge, including a bracket or a pseudo-frame, the bracket or pseudo-frame is detachably arranged at the corresponding position on the top of the pier, the prestressing device also includes a back frame system and a prestressing loading system, the back frame system is arranged on the top of the pier in accordance with the position of the bracket or pseudo-frame, and the bracket or pseudo-frame applies a prestressing force of a specified load through the prestressing loading system with the cooperation of the back frame system.

[0006] Furthermore, the preloading system includes a hydraulic station and a jacking and loading assembly. The jacking and loading assembly is connected between the back frame system and the bracket or pseudo frame at a specified position, and the jacking and loading assembly is connected to the hydraulic station.

[0007] A preferred embodiment of the above scheme is that the jacking and loading assembly includes a multiple of four hydraulic jacks, and at least one hydraulic jack connected between the back frame system and the bracket or pseudo-frame is arranged at each of the four specified positions around the top of a single pier. Each hydraulic jack is connected to a hydraulic station respectively, and an oil pressure gauge is connected in series on the pipeline connecting each hydraulic jack and the hydraulic station.

[0008] Furthermore, the back frame system includes pre-embedded fine-rolled threaded steel components and a rebound beam system. The pre-embedded fine-rolled threaded steel components are embedded in the top of each pier at a specified position. The rebound beam system is arranged directly above the bracket or pseudo-frame through the pre-embedded fine-rolled threaded steel components. The hydraulic jacks of the preload loading system are connected between the rebound beam system and the bracket or pseudo-frame at a specified position.

[0009] A preferred embodiment of the above scheme is that the rebound beam system includes a counter-preload longitudinal beam group and a transverse shoulder beam group, the embedded fine-rolled threaded steel assembly includes multiple embedded fine-rolled threaded steels, and a connecting thread is provided on the top of each embedded fine-rolled threaded steel. The counter-preload longitudinal beam group is arranged directly above the bracket or pseudo frame through the transverse shoulder beam group and the embedded fine-rolled threaded steel at the corresponding position with the cooperation of the connecting thread and the fixing nut.

[0010] Furthermore, the anti-prestressing longitudinal beam group includes multiple anti-prestressing longitudinal beams, and the transverse shoulder beam group includes multiple transverse shoulder beams, each of which is welded from two I-beams, and through holes are respectively provided at specified positions of the transverse shoulder beams welded from the I-beams, and each transverse shoulder beam crimped onto the anti-prestressing longitudinal beam is fixed by each embedded fine-rolled threaded steel bar in cooperation with the through holes and fixing nuts.

[0011] A construction method for prestressing the 0# block bracket by using the prestressing device for the 0# block bracket of the continuous rigid frame bridge, wherein the construction method firstly embeds 2 or 4 high-quality rolled threaded steel bars at each prestressing point pre-set on the top of each pier according to the load size, and then arranges each hydraulic jack at a specified position on the bracket or pseudo-frame that has been erected in advance, and then presses each anti-prestressed longitudinal beam on each hydraulic jack in cooperation with each transverse shoulder beam and each high-quality rolled threaded steel bar, and after each anti-prestressed longitudinal beam is fixed and qualified and the elevation of the specified position of the bracket or pseudo-frame is detected, the hydraulic station is started to prestress the specified position on the bracket or pseudo-frame at a specified pressure through each hydraulic jack, and the deformation of the specified position on the bracket or pseudo-frame under different load conditions is measured until the load reaches the specified value and the load is maintained for 24 hours.

[0012] The preferred embodiment of the above scheme is that the maximum preload is 1.2 times the specified load, and the measurement of the deformation at the specified position on the bracket or pseudo-frame includes at least the deformation under four load states of 10%, 50%, 100% and 120% respectively.

[0013] Furthermore, when the loading loads are 10%, 50% and 100%, respectively, the deformation monitoring is performed after the load is maintained for 30 minutes, and when the loading load is 120%, the deformation monitoring is performed after the load is maintained for 60 minutes.

[0014] The preferred method of the above scheme is to measure the deformation at the specified position every 4 hours during the 24-hour load-holding process after loading to the set value, and then unload symmetrically from the outside to the inside in stages after the bracket or pseudo-frame reaches stability and no longer deforms, and observe the deformation.

[0015] The beneficial effects of the present invention are as follows: the technical solution provided by the present application takes the existing completed bracket or pseudo frame as the detection object, and then combines the structural characteristics of the bracket or pseudo frame being detachably arranged at the corresponding position on the top of the pier column, and constitutes the preloading device of the present application by adding a back frame system and a preloading loading system, and arranges the back frame system on the top of the pier column in accordance with the position of the bracket or pseudo frame, and finally applies the preloading pressure of the prescribed load to the bracket or pseudo frame through the preloading loading system with the cooperation of the back frame system. The problem in the prior art that a large amount of high-altitude hoisting operations are required when carrying out the preloading test of the bracket or pseudo frame, thus causing high safety risks in the operation and long test period, is solved. The preloading device of the present application is used to carry out the preloading test of the bracket or pseudo frame, and since a large amount of preloading counterweights do not need to be hoisted, it can not only significantly shorten the construction period, but also significantly reduce the high-altitude hoisting operations and reduce the investment in construction costs. BRIEF DESCRIPTION OF THE DRAWINGS

[0016] Figure 1 It is a front view of the preloading device for the 0# bracket of the continuous rigid frame bridge of the present invention;

[0017] Figure 2 for Figure 1 AA section view;

[0018] Figure 3 The present invention is a flow chart of pre-pressing a bracket or a pseudo-frame using the pre-pressing device for the 0# block bracket of a continuous rigid frame bridge of the present invention.

[0019] Marked in the figure are: bracket or falsework 1, pier 2, hydraulic jack 3, embedded fine-rolled threaded steel bar 4, anti-prestressed longitudinal beam 5, and transverse shoulder beam 6. DETAILED DESCRIPTION

[0020] like Figure 1 , Figure 2 as well as Figure 3The present invention provides a prestressing device for the 0# bracket of a continuous rigid frame bridge, which has a relatively short construction period and significantly reduces the high-altitude hoisting work, and a construction method for prestressing the 0# bracket using the prestressing device for the 0# bracket of a continuous rigid frame bridge. The prestressing device includes a bracket or pseudo-frame 1, which is detachably arranged at a corresponding position on the top of the pier column. The prestressing device also includes a back frame system and a prestressing loading system. The back frame system is arranged on the top of the pier column 2 in accordance with the position of the bracket or pseudo-frame. The bracket or pseudo-frame 1 applies a prestressing force of a specified load through the prestressing loading system in cooperation with the back frame system. The technical solution provided by the present application takes the existing completed bracket or pseudo frame as the detection object, and combines the structural characteristics of the bracket or pseudo frame that can be detachably arranged at the corresponding position on the top of the pier column, and constitutes the prestressing device of the present application by adding a back frame system and a prestressing loading system, and arranges the back frame system on the top of the pier column in accordance with the position of the bracket or pseudo frame, and finally applies the prestressing force of the prescribed load to the bracket or pseudo frame through the prestressing loading system with the cooperation of the back frame system. The problem in the prior art that a large amount of high-altitude hoisting operations are required when carrying out the prestressing test of the bracket or pseudo frame, thus causing high safety risks in the operation and long test period, is solved. The prestressing device of the present application is used to carry out the prestressing test of the bracket or pseudo frame. Since a large amount of prestressing counterweight does not need to be hoisted, it can not only significantly shorten the construction period, but also significantly reduce the high-altitude hoisting operations and reduce the investment in construction costs.

[0021] Combined with the actual situation at the preloading site, in order to improve the stability and controllability during the preloading process, the preloading loading system of the present application includes a hydraulic station and a jacking loading component. The jacking loading component is connected between the back frame system and the bracket or pseudo frame 1 at a specified position, and the jacking loading component is connected to the hydraulic station. At this time, the preferred method is that the jacking loading component includes a multiple of four hydraulic jacks 3, and at least one hydraulic jack 3 connected between the back frame system and the bracket or pseudo frame 1 is arranged at each of the four specified positions around the top of a single pier column. Each hydraulic jack 3 is connected to the hydraulic station, and an oil pressure gauge is connected in series on the pipeline connecting each hydraulic jack 3 to the hydraulic station.

[0022] Further, as the key structure improved in the present application, in order to ensure the absolute safety of the preloading construction and at the same time effectively ensure the preloading effect, the back frame system described in the present application includes a pre-embedded fine-rolled threaded steel component and a rebound beam system, the pre-embedded fine-rolled threaded steel component is pre-embedded at the top of each pier column at a specified position, the rebound beam system is arranged directly above the bracket or pseudo frame through the pre-embedded fine-rolled threaded steel component, and each hydraulic jack of the preloading loading system is connected between the rebound beam system and the bracket or pseudo frame at a specified position. At this time, the preferred mode is that the rebound beam system described in the present application includes an anti-preloading longitudinal beam group and a transverse shoulder beam group, the pre-embedded fine-rolled threaded steel component includes a plurality of pre-embedded fine-rolled threaded steels 4, and a connecting thread is respectively arranged at the top of each pre-embedded fine-rolled threaded steel 4, and the anti-preloading longitudinal beam group is respectively arranged directly above the bracket or pseudo frame 1 through the transverse shoulder beam group and the pre-embedded fine-rolled threaded steel 4 at the corresponding position in cooperation with the connecting thread and the fixing nut. More specifically, the anti-prestressing longitudinal beam group includes a plurality of anti-prestressing longitudinal beams 5, and the transverse shoulder beam group includes a plurality of transverse shoulder beams 6, each of which is welded from two I-beams, and through holes are respectively provided at specified positions of the transverse shoulder beams 6 welded from each I-beam, and each transverse shoulder beam 6 crimped onto the anti-prestressing longitudinal beam 5 is respectively fixed by each embedded fine-rolled threaded steel bar 4 in cooperation with the through holes and fixing nuts.

[0023] Based on the above-mentioned prestressing device, the construction method of prestressing the 0# block bracket in the present application is to first embed 2 or 4 high-quality rolled threaded steel bars at each pre-set prestressing point on the top of each pier according to the load size, and then arrange each hydraulic jack at the specified position on the pre-erected bracket or pseudo-frame, and then press each anti-prestressing longitudinal beam on each hydraulic jack with the cooperation of each transverse shoulder beam and each high-quality rolled threaded steel bar, after each anti-prestressing longitudinal beam is fixed and qualified and the elevation of the specified position of the bracket or pseudo-frame is detected, start the hydraulic station to prestress the specified position on the bracket or pseudo-frame according to the specified pressure through each hydraulic jack, and measure the deformation of the specified position on the bracket or pseudo-frame under different load conditions until the load reaches the specified value and the load is maintained for 24 hours. Combined with the requirements of existing technical specifications, in order to ensure that no abnormal conditions will occur during the subsequent construction process, the maximum pre-loading load in the pre-loading construction of this application is 1.2 times the specified load, and the measurement of the deformation of the specified position on the bracket or pseudo-frame includes at least the deformation under four load states of 10%, 50%, 100% and 120%. The loading sequence is to hold the load for 30 minutes when the load is 10%, 50% and 100% respectively, and then monitor the deformation; when the load is 120%, hold the load for 60 minutes and then monitor the deformation. After each loading to the set value, measure the deformation of the specified position every 4 hours during the 24-hour load holding process. After the bracket or pseudo-frame reaches stability and no longer deforms, unload symmetrically from the outside to the inside in stages, and observe the deformation.

[0024] In order to solve the above-mentioned construction problems, this application summarizes theoretical research and field practice applications. After the bracket is installed, the bracket pre-stressing adopts tensioning jacks for counter-pressure. According to the force analysis calculation results, the maximum force load of a single corbel is calculated. A rebound beam is set on the top of the pier, and a single corbel is counter-prestressed according to different loads. The bracket pre-stressing load should be simulated and distributed according to the concrete load of the beam section, and the maximum pre-stressing load is 1.2 times the construction load. The bracket elevation is measured before, during and after pre-stressing, and the corresponding deformation data is recorded to provide more accurate data for adjusting the formwork elevation and linear control. By analyzing and processing the observed data, the elastic deformation and inelastic deformation are finally determined. At present, from the perspective of the actual on-site application and construction of the combined structure, the practical effect of the process is significant, and the cost of making the stress pre-stressing is low and can be reused, which has a significant effect on safe production, reducing construction cost investment and shortening the construction period.

[0025] The technical solution of the present application is further described below through specific embodiments:

[0026] By using the stress-controlled 0# bracket preloading construction device, graded preloading is adopted. The bracket elevation is measured before, during and after preloading, and the corresponding deformation data is recorded to provide more accurate data for adjusting the formwork elevation and linear control. The elastic deformation and inelastic deformation are finally determined by analyzing and processing the observed data.

[0027] During the construction of a continuous rigid frame bridge, after the construction of the main pier is completed, the bracket needs to be installed on the top of the pier to set up a 0# block construction platform. The 0# block construction can only be carried out after the bracket preloading is completed. The purpose of bracket preloading is to test the overall stability of the bracket, eliminate the inelastic deformation of the bracket, and determine the elastic deformation value. This method uses hydraulic jacks to counter-preload the bracket with graded loading. Before, during and after preloading, the bracket elevation is measured and the corresponding deformation data is recorded to provide more accurate data for adjusting the formwork elevation and linear control. By analyzing and processing the observed data, the elastic deformation and inelastic deformation are finally determined. The stress-controlled bracket preloading method is used for preloading, which requires the accurate position of the pre-embedded fine-rolled threaded steel on the top of the main pier. Four jacks are used for preloading each single pier, and each pair of brackets must be preloaded symmetrically inside and outside at the same time. The materials used in this method can be reused, and the machinery and tools are commonly used in construction. It is more economical than conventional pile load preloading, and the construction period is shorter and the operation is simpler. The most important thing about the preloading construction method of the 0# bracket of the continuous rigid frame bridge based on stress control is to calculate in detail the construction load that each group of brackets needs to bear, and then convert it into the stress that each jack needs to apply. A rebound beam is set on the top of the pier, and a single corbel is reversely preloaded according to different loads. During the preloading process, stress control and bracket deformation monitoring should be carried out.

[0028] Embodiment 1

[0029] like Figure 3 As shown, it is the specific construction steps of stress-controlled preloading of the 0# bracket of the continuous rigid frame bridge of this application.

[0030] The specific process is:

[0031] Selection of finely tied threaded steel bars:

[0032] Depending on the load size, 2 or 4 rods are arranged at each preload point. 32mm finely rolled threaded steel bars.

[0033] Pre-embedding and bundling of the anchor end of fine-rolled threaded steel:

[0034] Before pouring the capping concrete for the pier column, the lower end anchoring system of the precision-tied threaded steel bars shall be embedded and numbered according to the distribution diagram of the anti-support preloading points.

[0035] Back pressure distribution beam and jack installation:

[0036] During the construction of the pier top, the anti-support preloading point reaction device has been embedded. Four groups of fine-rolled threaded steel bars are embedded in the concrete of the pier top along the bridge, with an embedded length of not less than 1.5m. Two I32b steel bars are used to form a counter-pressure shoulder beam, which is preloaded with the 0# cross beam by hydraulic jack loading. Four jacks are used for preloading each single pier, and each pair of brackets must be preloaded symmetrically inside and outside at the same time.

[0037] 1) Use 2 I32b I-beams as preload distribution beams, and set up distribution beams on the 0# support according to the anti-support preload point distribution diagram. The distribution beams are arranged along the longitudinal main beam of the 0# support and set up on the transverse main beam.

[0038] 2) No. 10 channel steel is used to connect every two distribution beams every 50cm to prevent instability during the tensioning process.

[0039] 3) Install the jack after the distribution beam is installed.

[0040] Installation of the tensioning end of the finished rolled threaded steel bar:

[0041] The top of the fine-rolled threaded steel bar is connected to the counter-pressure longitudinal beam and the transverse shoulder beam with special nuts to build a stress counter-pressure system.

[0042] Gradual tensioning, load holding and unloading:

[0043] 1) The bracket preload shall be simulated and distributed according to the concrete load of the beam section, and the maximum preload shall be 1.2 times the construction load. Preloading can be carried out in grades of 10%, 50%, 100%, and 120%. After the first three grades are loaded, they shall be held for 30 minutes for deformation monitoring, and after the last grade is loaded, they shall be held for 60 minutes for deformation monitoring.

[0044] 2) After being tensioned to the design value, the load is maintained for 24 hours. According to the set elevation observation points, a dedicated person observes the deformation of the support on site and measures the deformation every 4 hours.

[0045] 3) After the bracket reaches stability and no longer deforms after holding the load for 24 hours, it is unloaded symmetrically from the outside to the inside and the deformation is observed.

[0046] Bracket deformation monitoring measurement and data analysis:

[0047] Before preloading, during preloading, and after unloading, the support elevation is measured and the corresponding deformation data is recorded to provide more accurate data for adjusting the formwork elevation and linear control. The elastic deformation and inelastic deformation are finally determined by analyzing and processing the observed data.

Claims

1. A preloading device for a bracket of a continuous rigid frame bridge block 0#, comprising a bracket or pseudo-frame (1), the bracket or pseudo-frame (1) being detachably arranged at a corresponding position on the top of a pier, characterized in that: The prestressing device also includes a back frame system and a prestressing loading system. The back frame system is arranged on the top of the pier (2) in a manner adapted to the position of the bracket or pseudo frame (1). The bracket or pseudo frame (1) applies a prestressing force of a specified load through the prestressing loading system in cooperation with the back frame system.

2. The preloading device for the 0# bracket of the continuous rigid frame bridge according to claim 1 is characterized in that: The preloading system comprises a hydraulic station and a jacking loading component. The jacking loading component is connected between the back frame system and the bracket or pseudo frame (1) at a specified position. The jacking loading component is connected to the hydraulic station.

3. The preloading device for the 0# bracket of the continuous rigid frame bridge according to claim 2 is characterized in that: The lifting and loading assembly comprises a multiple of four hydraulic jacks (3), at least one hydraulic jack (3) connected between the back frame system and the bracket or pseudo frame (1) is arranged at four specified positions around the top of a single pier column, each hydraulic jack (3) is connected to a hydraulic station, and an oil pressure gauge is connected in series on the pipeline connecting each hydraulic jack (3) and the hydraulic station.

4. The preloading device for the 0# bracket of a continuous rigid frame bridge according to claim 1, 2 or 3, characterized in that: The back frame system comprises a pre-embedded fine-rolled threaded steel component and a rebound beam system. The pre-embedded fine-rolled threaded steel component is pre-embedded at the top of each pier (2) at a specified position. The rebound beam system is arranged directly above the bracket or pseudo frame (1) through the pre-embedded fine-rolled threaded steel component. Each hydraulic jack (3) of the preload system is connected between the rebound beam system and the bracket or pseudo frame (1) at a specified position.

5. The preloading device for the 0# bracket of the continuous rigid frame bridge according to claim 4 is characterized in that: The rebound beam system comprises a reverse preload longitudinal beam group and a transverse shoulder beam group. The embedded fine-rolled threaded steel assembly comprises a plurality of embedded fine-rolled threaded steels (4). A connecting thread is arranged at the top of each embedded fine-rolled threaded steel (4). The reverse preload longitudinal beam group is arranged directly above the bracket or pseudo frame (1) through the transverse shoulder beam group and the embedded fine-rolled threaded steels (4) at the corresponding position in cooperation with the connecting thread and the fixing nut.

6. The preloading device for the 0# bracket of the continuous rigid frame bridge according to claim 5 is characterized in that: The anti-preloading longitudinal beam group comprises a plurality of anti-preloading longitudinal beams (5), and the transverse shoulder beam group comprises a plurality of transverse shoulder beams (6), each of which is welded from two I-beams, and through holes are respectively provided at specified positions of the transverse shoulder beams (6) welded from the I-beams, and each transverse shoulder beam (6) crimped onto the anti-preloading longitudinal beam (5) is respectively fixed by each pre-embedded fine-rolled threaded steel bar (4) in cooperation with the through holes and fixing nuts.

7. A construction method for pre-pressing the 0# bracket using the pre-pressing device for the 0# bracket of a continuous rigid frame bridge as claimed in claim 6, characterized in that: The construction method is to first embed 2 or 4 fine-rolled threaded steel bars at each pre-set pre-stressing point on the top of each pier column according to the load size, and then arrange each hydraulic jack at a specified position on a bracket or pseudo frame that has been erected in advance, and then press each anti-prestressed longitudinal beam on each hydraulic jack with the cooperation of each transverse shoulder beam and each fine-rolled threaded steel bar, and after each anti-prestressed longitudinal beam is fixed and qualified and the elevation of the specified position of the bracket or pseudo frame is detected, start the hydraulic station to pre-stress the specified position on the bracket or pseudo frame at a specified pressure through each hydraulic jack, and measure the deformation of the specified position on the bracket or pseudo frame under different load conditions until the load reaches the specified value and is held for 24 hours.

8. The construction method according to claim 7, characterized in that: The maximum preload is 1.2 times the specified load, and the measurement of the deformation at the specified position on the bracket or pseudo-frame includes at least the deformation under four load states of 10%, 50%, 100% and 120% respectively.

9. The construction method according to claim 8, characterized in that: When the loading loads were 10%, 50% and 100%, deformation monitoring was performed after holding the load for 30 minutes. When the loading load was 120%, deformation monitoring was performed after holding the load for 60 minutes.

10. The construction method according to claim 9, characterized in that: After loading to the set value, measure the deformation at the specified position every 4 hours during the 24-hour load holding process. After the bracket or false frame reaches stability and no longer deforms, unload symmetrically from the outside to the inside and observe the deformation.