Construction method of ultra-deep foundation pit close to subway business line
By dividing the construction area close to the subway business line into remote and adjacent areas, and using a support method combining concrete and steel support, the problems of foundation pit deformation control and long construction cycle are solved, and the construction time is shortened and safety hazards are reduced. effect.
Patent Information
- Application Number
- CN202411294809.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-09-14
- Publication Date
- 2024-11-12
AI Technical Summary
In the construction of ultra-deep foundation pits close to the subway business line, it is difficult for the existing technology to effectively control the deformation of the foundation pit and ensure the safety of the subway operation, and the construction period is long and the progress is affected.
The construction area is divided into a remote subway area and a nearby subway area, and the adjacent subway area is divided into several small foundation pits. The support method of combining concrete support and steel support is adopted, and the vertical support and axle force compensation device are combined to shorten the construction. Cycle and reduce safety hazards.
By dividing the construction area and adopting efficient support methods, the construction time is shortened, the safety hazards of subway operation are reduced, and the safety and construction efficiency of foundation pits are improved.
Smart Images

Figure CN118933017A_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the field of foundation pit technology, and in particular to a method for constructing an ultra-deep foundation pit adjacent to a subway operating line. Background Art
[0002] With the advancement of urbanization, the population density and population flow of cities are increasing. In order to promote the development of urban transportation, urban underground space has been rapidly developed. Many cities in my country have built and operated multiple rail construction. In many first- and second-tier cities such as Beijing, Shanghai, Guangzhou and Shenzhen, many basement foundation pits of newly built buildings are located within the 50m protection range of the subway. Many basements are even adjacent to the operating subway lines, posing a great risk to the safety of subway operations.
[0003] According to the requirements for subway structure protection, the cumulative change of settlement (or uplift) and horizontal displacement of subway structure is less than 10mm, and the cumulative change of horizontal diameter convergence is less than 10mm. This places very high demands on the support form, excavation deployment, and deformation control of deep foundation pits. The commonly used method at present is to use a multi-channel internal support support form for the entire large foundation pit. This form has many processes, long maintenance time, long construction cycle, and overall progress is affected. There is no effective control measure after the foundation pit is deformed. It is impossible to effectively guarantee the safety of the operating subway foundation pit. Summary of the invention
[0004] Based on this, it is necessary to provide a method for constructing an ultra-deep foundation pit close to a subway operating line to overcome the defects mentioned in the above background technology.
[0005] A method for constructing an ultra-deep foundation pit adjacent to a subway operating line comprises the following steps:
[0006] Step 1: Divide the excavation area into areas far from the subway and areas near the subway according to the distance, divide the area far from the subway into several large foundation pits according to the construction sequence, and divide the area corresponding to each large foundation pit in the area near the subway into several small foundation pits with the dividing line between the area far from the subway and the area near the subway as the axis of symmetry;
[0007] Step 2: Carry out vertical support construction along the boundary between the area far from the subway and the area close to the subway, between adjacent large foundation pits and between adjacent small foundation pits;
[0008] Step 3: Carry out layered excavation and support construction on the first large foundation pit;
[0009] Step 4: After the first large foundation pit is constructed to zero, several corresponding small foundation pits are constructed. The small foundation pits are excavated in layers, and each layer is supported by a steel support with a first axial force compensation device after excavation;
[0010] Step 5: After the small foundation pit is excavated, pour the foundation cushion layer, and embed the supporting I-beam components in the foundation cushion layer;
[0011] Step 6: Repeat steps 3 to 5 to construct the next large foundation pit and several corresponding small foundation pits until the entire excavation area is completed. 1. The present invention divides the area adjacent to the subway operating line into an area far from the subway and an area near the subway, and divides the area far from the subway into several large foundation pits, and divides the area near the subway into several small foundation pits, thereby reducing the scope of hidden dangers. After the construction work surface is divided, the resources invested at a single time are less, and the cycle of a single construction is shortened. The construction time is greatly shortened, and the safety hazards of subway operation are greatly reduced.
[0012] As a preferred embodiment of the ultra-deep foundation pit construction method adjacent to a subway operating line in the present invention, in step one, the large foundation pit is supported by concrete, and the small foundation pit is supported by a mixture of concrete and steel structure.
[0013] As a preferred embodiment of the ultra-deep foundation pit construction method adjacent to a subway operating line in the present invention, in step 2, the vertical support construction includes water-stop curtain construction, underground continuous wall construction and underground continuous wall partition construction.
[0014] As a preferred method of constructing an ultra-deep foundation pit adjacent to a subway operating line in the present invention, the step three specifically includes:
[0015] The large foundation pit is excavated in the form of supporting first and then digging, layering and block-by-layer, symmetric within a limited time, and retaining soil to protect the wall. After the concrete support is completed, the second axial force compensation device is arranged between the curtain and the concrete support.
[0016] As a preferred embodiment of the ultra-deep foundation pit construction method adjacent to a subway operating line in the present invention, the step three further comprises:
[0017] The final excavation of the large foundation pit is carried out within four times the layered excavation depth near the subway side to retain soil and protect the slope.
[0018] As a preferred embodiment of the ultra-deep foundation pit construction method adjacent to a subway operating line in the present invention, in step 4, the excavation of each layer and the installation of steel supports with a first axial force compensation device must be completed within twelve hours.
[0019] As a preferred embodiment of the method for constructing an ultra-deep foundation pit adjacent to a subway operating line in the present invention, in step five, the bracing I-beam assemblies are arranged along the radial direction of the subway operating line.
[0020] As a preferred embodiment of the ultra-deep foundation pit construction method adjacent to the subway operating line in the present invention, the bracing I-beam assembly includes I-beams, a pair of which are arranged at intervals, their ends away from each other abut against the inner wall of the small foundation pit, and a hydraulic jack is provided between their ends close to each other.
[0021] As a preferred method of constructing an ultra-deep foundation pit adjacent to a subway operating line in the present invention, the step five specifically includes:
[0022] Install the I-beam assemblies and place the isolation formwork at the hydraulic jack, then pour the foundation cushion. After the foundation cushion reaches the strength grade, remove the isolation formwork and hydraulic jack, and fill in the gaps.
[0023] As a preferred embodiment of the ultra-deep foundation pit construction method adjacent to a subway operating line in the present invention, the pouring of the foundation cushion layer must be completed within seventy-two hours.
[0024] Beneficial effects of the present invention:
[0025] 1. The present invention divides the area adjacent to the subway operating line into an area far from the subway and an area near the subway, and divides the area far from the subway into several large foundation pits, and divides the area near the subway into several small foundation pits, thereby reducing the scope of hidden dangers. After the construction work surface is divided, the resources invested at a single time are less, and the cycle of a single construction is shortened. The construction time is greatly shortened, and the safety hazards of subway operation are greatly reduced.
[0026] 2. The present invention can prevent the expansion of displacement deformation in a very short time by arranging an axial force compensation device between the steel support, the concrete support and the curtain. The operation is simple and intelligent, which greatly improves the safety of the foundation pit.
[0027] 3. The present invention forms effective axial force compensation for the bottom of the foundation pit side wall by pre-embedding the supporting I-beam components in the foundation cushion layer, which can effectively avoid deformation of the bottom of the foundation pit side wall caused by concrete shrinkage creep and bottom plate exposure. BRIEF DESCRIPTION OF THE DRAWINGS
[0028] In order to more clearly illustrate the embodiments of the present application or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present application. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.
[0029] Figure 1 A schematic diagram of the construction process of an embodiment of the present application; DETAILED DESCRIPTION
[0030] In order to make the above-mentioned purposes, features and advantages of the present application more obvious and easy to understand, the specific implementation methods of the present application are described in detail below in conjunction with the accompanying drawings. In the following description, many specific details are set forth to facilitate a full understanding of the present application. However, the present application can be implemented in many other ways different from those described herein, and those skilled in the art can make similar improvements without violating the connotation of the present application, so the present application is not limited by the specific embodiments disclosed below.
[0031] In the description of the present application, it should be understood that the terms "center", "longitudinal", "lateral", "length", "width", "thickness", "up", "down", "front", "back", "left", "right", "vertical", "horizontal", "top", "bottom", "inside", "outside", "clockwise", "counterclockwise", "axial", "radial", "circumferential" and the like indicate orientations or positional relationships based on the orientations or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present application and simplifying the description, and do not indicate or imply that the referred device or element must have a specific orientation, be constructed and operated in a specific orientation, and therefore should not be understood as a limitation on the present application.
[0032] In addition, the terms "first" and "second" are used for descriptive purposes only and should not be understood as indicating or implying relative importance or implicitly indicating the number of the indicated technical features. Therefore, the features defined as "first" and "second" may explicitly or implicitly include at least one of the features. In the description of this application, the meaning of "plurality" is at least two, such as two, three, etc., unless otherwise clearly and specifically defined.
[0033] In this application, unless otherwise clearly specified and limited, the terms "installed", "connected", "connected", "fixed" and the like should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection or an indirect connection through an intermediate medium, it can be the internal connection of two elements or the interaction relationship between two elements, unless otherwise clearly defined. For ordinary technicians in this field, the specific meanings of the above terms in this application can be understood according to specific circumstances.
[0034] In the present application, unless otherwise clearly specified and limited, a first feature being “above” or “below” a second feature may mean that the first and second features are in direct contact, or the first and second features are in indirect contact through an intermediate medium. Moreover, a first feature being “above”, “above”, and “above” a second feature may mean that the first feature is directly above or obliquely above the second feature, or simply means that the first feature is higher in level than the second feature. A first feature being “below”, “below”, and “below” a second feature may mean that the first feature is directly below or obliquely below the second feature, or simply means that the first feature is lower in level than the second feature.
[0035] It should be noted that when an element is referred to as being "fixed to" or "disposed on" another element, it may be directly on the other element or there may be a central element. When an element is considered to be "connected to" another element, it may be directly connected to the other element or there may be a central element at the same time. The terms "vertical", "horizontal", "upper", "lower", "left", "right" and similar expressions used herein are for illustrative purposes only and are not intended to be the only implementation method.
[0036] Example
[0037] The present embodiment provides a method for constructing an ultra-deep foundation pit adjacent to a subway operating line, which can effectively reduce the risk of foundation pit construction in an area adjacent to a subway operating line and improve construction safety. Figure 1 As shown, the following steps are included:
[0038] Area division: The excavation area adjacent to the subway operating line is divided into the area far from the subway and the area close to the subway according to the distance from the subway operating line. The area far from the subway and the area close to the subway are symmetrically axised. The area far from the subway is further divided into several large foundation pits according to the construction sequence, and the area corresponding to each large foundation pit in the area close to the subway is divided into several small foundation pits.
[0039] In this embodiment, since the area far from the subway is far from the subway operating line, the construction risk is low, and the large foundation pits all use concrete supports with good rigidity and a long construction period. Since the area near the subway is close to the subway operating line, the construction risk is relatively large. The first support of the small foundation pit uses concrete support. As the excavation depth increases, more flexible and fast-constructed steel supports are subsequently used to reduce the length of time the foundation pit is in an unsupported state and reduce the growth of deformation. The small foundation pit is a narrow pit with a width of between 15 and 20 meters and a length of about 50 meters. Its depth does not exceed the waist of the subway tunnel. The area of the large foundation pit needs to be controlled within 10,000 square meters.
[0040] Support construction: vertical support construction is carried out along the boundary between the area far away from the subway and the area close to the subway, between adjacent large foundation pits and between adjacent small foundation pits.
[0041] In this embodiment, the vertical support construction includes water-stop curtain construction, underground continuous wall construction and underground continuous wall partition construction. The water-stop curtain and underground connecting wall are used between adjacent large foundation pits and between adjacent small foundation pits. The underground continuous wall partition is used at the boundary away from the subway area and the area near the subway to divide the earth excavation interface and provide a force fulcrum for the horizontal support of large foundation pits and small foundation pits.
[0042] Construction of large foundation pits: Since large foundation pits are all supported by concrete, the excavation period is long. In order to avoid adverse effects on the construction progress, large foundation pits are constructed first. The large foundation pits are excavated in the form of support first and then excavation, layered and block-by-layer, symmetrical within a limited time, and retaining soil to protect the wall. Priority is given to forming supports perpendicular to the direction of the subway operating line, ensuring that the side adjacent to the subway is formed first. After the concrete support is completed, a second axial force compensation device is arranged between the curtain and the concrete support to facilitate monitoring and adjustment of the foundation pit conditions. The concrete support should reserve the installation position and trim the facade of the installation position so that the second axial force compensation device can fit better, the axial force can be transmitted evenly and effectively, and the "vacuum period" of the traditional concrete support where the initial strength does not meet the corresponding standards is made up, making the foundation pit retaining structure more stable and the deformation greatly reduced.
[0043] In this embodiment, the final excavation of the large foundation pit is carried out within a range of four times the layered excavation depth close to the subway side to retain soil and protect the slope, so as to ensure the safety of the subway operating line.
[0044] Small foundation pit construction: After the first large foundation pit is constructed to zero, the corresponding small foundation pits are constructed. The small foundation pits are excavated in layers. After each layer is excavated, steel supports with first axial force compensation devices are used for support. Each layer of excavation and installation of steel supports with first axial force compensation devices must be completed within twelve hours, and the first axial force compensation device must be guaranteed to work normally 24 hours a day. Excavation, support and compensation are carried out at the same time during construction, which can improve the control effect and reduce the displacement and deformation of the foundation pit.
[0045] Foundation cushion construction: Install the I-beam assemblies and place the isolation formwork at the hydraulic jack, then pour the foundation cushion. After the foundation cushion reaches the strength grade, remove the isolation formwork and hydraulic jack, and fill in the gaps.
[0046] In this embodiment, the bracing I-beam assembly is arranged along the radial direction of the subway operating line. The bracing I-beam assembly includes I-beams. A pair of the I-beams are arranged at intervals, and their ends far away from each other abut against the inner wall of the small foundation pit. A hydraulic jack is provided between their ends close to each other, and the hydraulic jack is pre-pressed according to actual on-site needs, thereby forming an effective and reliable support axial force compensation for the bottom of the foundation pit in the foundation cushion layer.
[0047] In this embodiment, the foundation cushion layer should be constructed quickly, and personnel and materials should be organized reasonably to complete the construction within 72 hours. The foundation cushion layer is poured as it is dug, and each cushion layer is no larger than 200 square meters. The foundation cushion layer is poured to the edge of the enclosure; the uplift of the pit bottom is strictly controlled to reduce the impact on the subway operating line, and the hydraulic jack is pre-buried to the top I-beam in the 300mm thick cushion layer to supplement the strength of the cushion layer concrete axial force support.
[0048] Repeat the above large foundation pit and small foundation pit construction until the entire excavation area is completed.
[0049] The traditional foundation pit is basically a whole foundation pit, the overall construction resource input is large, and the entire construction period is long, and the hidden danger cycle of safety risks is also long. In this embodiment, a large foundation pit and a small foundation pit are designed and constructed separately, which can reduce the scope of hidden dangers, and after the construction work surface is divided, the resources invested at a single time are less, and the cycle of a single construction is shortened. In particular, the excavation and support construction of small foundation pits can be completed within 36 hours, which greatly shortens the construction time and greatly reduces the safety hazards of subway operating lines.
[0050] In this embodiment, the large foundation pit and the small foundation pit are excavated at the beginning, the center position is excavated at one time, and the four sides are reserved for symmetrical excavation at the end. The blocks are reasonable, meeting the requirements of the last excavation of the subway side retaining wall and the priority completion of the main support perpendicular to the subway side within a limited time. It effectively avoids the construction time delayed by the continuous lifting of the excavation machinery during the jump excavation process. It is conducive to saving construction period, meeting the requirements of the subway, and can better control the deformation of the foundation pit.
[0051] The technical features of the above-described embodiments may be arbitrarily combined. To make the description concise, not all possible combinations of the technical features in the above-described embodiments are described. However, as long as there is no contradiction in the combination of these technical features, they should be considered to be within the scope of this specification.
[0052] The above-described embodiments only express several implementation methods of the present application, and the descriptions thereof are relatively specific and detailed, but they cannot be construed as limiting the scope of the patent application. It should be pointed out that, for a person of ordinary skill in the art, several variations and improvements can be made without departing from the concept of the present application, and these all belong to the protection scope of the present application. Therefore, the protection scope of the patent application shall be subject to the attached claims.
Claims
1. A method for constructing an ultra-deep foundation pit adjacent to a subway operating line. It is characterized in that The steps include: Step 1: Divide the excavation area into areas far from the subway and areas near the subway according to the distance, divide the area far from the subway into several large foundation pits according to the construction sequence, and divide the area corresponding to each large foundation pit in the area near the subway into several small foundation pits with the dividing line between the area far from the subway and the area near the subway as the axis of symmetry; Step 2: Carry out vertical support construction along the boundary between the area far from the subway and the area close to the subway, between adjacent large foundation pits and between adjacent small foundation pits; Step 3: Carry out layered excavation and support construction on the first large foundation pit; Step 4: After the first large foundation pit is constructed to zero, several corresponding small foundation pits are constructed. The small foundation pits are excavated in layers, and each layer is supported by a steel support with a first axial force compensation device after excavation; Step 5: After the small foundation pit is excavated, pour the foundation cushion layer, and embed the supporting I-beam components in the foundation cushion layer; Step 6: Repeat steps 3 to 5 to construct the next large foundation pit and several corresponding small foundation pits until the entire excavation area is completed.
2. The ultra-deep foundation pit construction method adjacent to the subway operating line according to claim 1, It is characterized in that In the step 1, the large foundation pit is supported by concrete, and the small foundation pit is supported by a mixture of concrete and steel structure.
3. The ultra-deep foundation pit construction method close to the subway operating line according to claim 1, It is characterized in that In the step 2, the vertical support construction includes water-stop curtain construction, underground continuous wall construction and underground continuous wall partition construction.
4. The ultra-deep foundation pit construction method adjacent to a subway operating line according to claim 1, It is characterized in that The step three specifically includes: The large foundation pit is excavated in the form of supporting first and then digging, layering and block-by-layer, symmetric within a limited time, and retaining soil to protect the wall. After the concrete support is completed, the second axial force compensation device is arranged between the curtain and the concrete support.
5. The method for constructing an ultra-deep foundation pit adjacent to a subway operating line according to claim 4, It is characterized in that The step three also includes: The final excavation of the large foundation pit is carried out within four times the layered excavation depth near the subway side to retain soil and protect the slope.
6. The method for constructing an ultra-deep foundation pit adjacent to a subway operating line according to claim 1, It is characterized in that In step 4, the excavation of each layer and the installation of steel supports with first axial force compensation devices must be completed within twelve hours.
7. The ultra-deep foundation pit construction method adjacent to a subway operating line according to claim 1, It is characterized in that In the step five, the bracing I-beam assemblies are arranged along the radial direction of the subway operating line.
8. The method for constructing an ultra-deep foundation pit adjacent to a subway operating line according to claim 7, It is characterized in that The bracing I-beam assembly comprises an I-beam, a pair of which is arranged at intervals, with their ends away from each other abutting against the inner wall of the small foundation pit, and a hydraulic jack being arranged between their ends close to each other.
9. The method for constructing an ultra-deep foundation pit adjacent to a subway operating line according to claim 7, It is characterized in that The step five specifically includes: Install the I-beam assemblies and place the isolation formwork at the hydraulic jack, then pour the foundation cushion. After the foundation cushion reaches the strength grade, remove the isolation formwork and hydraulic jack, and fill in the gaps.
10. The method for constructing an ultra-deep foundation pit adjacent to a subway operating line according to claim 9, It is characterized in that The pouring of the foundation cushion layer must be completed within seventy-two hours.