Construction method of shallow buried underground structure
Through the guide device, the arc-type enclosure structure is rapidly constructed, which reduces the excavation amount and backfill steps of shallow buried underground structure construction, reduces the construction cycle and cost, and solves the problems of long construction cycles and complex support structures in the existing technology. .
Patent Information
- Application Number
- CN202410960518.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-17
- Publication Date
- 2024-11-15
AI Technical Summary
In the existing shallow buried underground structure construction methods, the excavation volume is large, the backfilling volume is large, the construction period is long, and the support structure requires multiple horizontal support, which increases the construction process and cycle.
The guide device is used to press the arc-shaped enclosure pipe into the soil to form an arc-shaped enclosure ring, which is constructed longitudinally along the underground structure, eliminating soil backfill and reducing lateral support, and rapid construction and waterproofing are achieved through the guide device.
The construction cycle is shortened, the amount of earth excavation and construction work is reduced, the construction cost is reduced, and the construction efficiency is improved.
Smart Images

Figure CN118958365A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of municipal engineering construction, and in particular to a construction method for a shallow buried underground structure. Background Art
[0002] The statements herein merely provide background information related to the present invention and do not necessarily constitute prior art.
[0003] At present, shallow underground structures such as integrated pipeline corridors with a shallow burial depth are generally constructed by open excavation. It is necessary to construct the support structure first, then excavate the foundation pit, and then construct the main structure in the excavation. The inventors found that when using this construction method, the excavation volume is large, the excavation backfill volume is large, the construction period is long, and the support structure is vertically arranged. In order to ensure the stability of the support structure, multiple horizontal supports need to be set, which increases the construction process and prolongs the construction period. Summary of the invention
[0004] In view of the shortcomings of the prior art, the present invention aims to provide a construction method for a shallow underground structure, thereby shortening the construction period.
[0005] In order to achieve the above object, the present invention is implemented through the following technical solutions:
[0006] An embodiment of the present invention provides a construction method for a shallow underground structure, comprising the following steps:
[0007] A guide device is placed on the ground, wherein the guide device has two arc-shaped guide tubes arranged opposite to each other;
[0008] Multiple arc-shaped retaining pipes are pressed into the soil in sequence through two guide pipes, and the retaining pipes pressed in on both sides form an arc-shaped retaining ring matching the underground structure;
[0009] Multiple arc-shaped retaining rings are sequentially constructed along the longitudinal direction of the underground structure until the retaining structure of the entire underground structure is completed;
[0010] Excavate the soil inside the retaining structure;
[0011] The underground structure is constructed inside the retaining structure, wherein the wall of the underground structure is constructed on the inner side of the retaining structure.
[0012] Optionally, the guiding device includes a positioning plate, and guide tubes are arranged at both ends of the positioning plate. The guide tubes are arc-shaped tubes, and the two guide tubes are symmetrically arranged relative to the center of the positioning plate.
[0013] Optionally, guide parts are provided on both sides of the guide tube, and the guide parts are provided with guide grooves.
[0014] Optionally, guide blocks are provided on both sides of the enclosure tube, and the guide blocks are embedded in the guide grooves. The guide block on one side of the enclosure tube is provided with a slot, and the outer end of the guide block on the other side can be inserted into the slot as a plug-in portion.
[0015] Optionally, the surrounding pipes corresponding to the two guide pipes of the guide device are constructed synchronously.
[0016] Optionally, the construction method of the retaining ring includes the following steps:
[0017] Step 1: Insert the first section of the enclosure tube into the guide tube;
[0018] Step 2: Align the end of the second section of the retaining pipe with the end of the first section of the retaining pipe, then apply pressure to the second section of the retaining pipe, the second section of the retaining pipe enters the guide pipe, and the first section of the retaining pipe is pressed into the soil.
[0019] Step 3: Repeat step 2 until the multiple retaining pipes corresponding to the guide pipe are pressed into the soil.
[0020] Optionally, the ends of all the surrounding tubes inserted through the guide tube on one side have a pointed structure, and the pointed structure of the surrounding tube can be inserted into the surrounding tube adjacent to it. Among the surrounding tubes inserted by the guide tube on the other side, the end of the first section of the surrounding tube does not have a pointed structure, and the ends of the remaining surrounding tubes all have a pointed structure.
[0021] Optionally, before excavating the soil inside the retaining structure, a supporting mechanism is provided on the top of the retaining structure.
[0022] Optionally, the support mechanism is fixed to the longitudinal beam at the top of the enclosure, and a plurality of cross beams are arranged between two longitudinal beams.
[0023] Optionally, the wall of the underground structure is cast on the inner side of the enclosure structure, and then the top plate of the underground structure is cast.
[0024] The beneficial effects of the present invention are as follows:
[0025] 1. The underground structure construction method of the present invention first constructs a retaining structure that matches the underground structure, and then directly constructs the underground structure on the inner side of the retaining structure. Since the side wall of the underground structure is constructed on the inner side of the retaining structure, the amount of earth excavation is small, and the step of backfilling the soil is omitted, thereby reducing the construction workload and shortening the construction period.
[0026] 2. The underground structure construction method of the present invention uses a guiding device to construct the retaining pipe on the ground, and the construction is convenient and quick. The retaining structure adopts an arc structure, which can effectively resist horizontal forces, thereby reducing the number of lateral supports in the horizontal support system of the retaining structure, reducing the construction volume, and shortening the construction period.
[0027] 3. In the underground structure construction method of the present invention, a guide block on one side of the enclosure pipe is provided with a slot, and the outer end of the guide block on the other side can be inserted into the slot as a plug-in portion, and adjacent enclosure rings can be plugged in through the slot and the guide block, thereby achieving waterproofing, eliminating the precipitation process, shortening the construction period, and reducing construction costs. BRIEF DESCRIPTION OF THE DRAWINGS
[0028] The accompanying drawings in the specification, which constitute a part of the present invention, are used to provide a further understanding of the present invention. The exemplary embodiments of the present invention and their descriptions are used to explain the present invention and do not constitute improper limitations on the present invention.
[0029] Figure 1 is a flow chart of the construction method of embodiment 1 of the present invention;
[0030] Figure 2 is a schematic structural diagram of a guide device according to embodiment 1 of the present invention;
[0031] Figure 3 This is a schematic diagram of the enclosure pipe structure of Example 1 of the present invention;
[0032] Figure 4 1 is a schematic structural diagram of a protective tube in which no pointed structure is provided in Example 1 of the present invention;
[0033] Figure 5 This is a schematic diagram of the construction process of the enclosure according to Embodiment 1 of the present invention;
[0034] Figure 6 This is a construction flow chart of a support mechanism and an underground structure according to Embodiment 1 of the present invention;
[0035] Among them, 1. positioning plate, 2. guide tube, 3. guide part, 4. guide groove, 5. enclosure tube, 6. guide block, 7. pointed structure, 8. longitudinal beam, 9. cross beam, 10. wall, 11. top plate. DETAILED DESCRIPTION
[0036] For the convenience of description, if the words "upper" and "lower" appear in the present invention, they only indicate that they are consistent with the upper and lower directions of the drawings themselves, and do not limit the structure. They are only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific orientation, be constructed and operate in a specific orientation. Therefore, it cannot be understood as a limitation on the present invention.
[0037] Example 1
[0038] This embodiment provides a construction method for a shallow underground structure. Figure 1 As shown, the following steps are included:
[0039] Step 1: Construct a retaining structure. In this embodiment, the retaining structure adopts an arc-shaped retaining structure. The retaining structure is composed of a plurality of retaining rings arranged along the longitudinal direction of the underground structure. Each retaining ring is composed of a plurality of arc-shaped retaining pipes arranged along the circumferential direction. During construction, each retaining ring is constructed in sequence along the longitudinal direction of the underground structure.
[0040] In this embodiment, the enclosure structure adopts an arc-shaped structure, which can effectively resist horizontal forces, thereby reducing the number of lateral supports, reducing construction workload, and shortening the construction period.
[0041] The specific construction method of each enclosure includes the following steps:
[0042] Step 1.1: Place a guide on the ground, such as Figure 2 As shown, the guide device includes a positioning plate 1, and guide tubes 2 are arranged at both ends of the upper surface of the positioning plate 1. The two guide tubes 2 are arc tubes arranged opposite to each other, and the shape of the arc tubes matches the shape of the retaining ring. The two guide tubes 2 are symmetrically arranged relative to the center of the positioning plate 1, and are used to guide the movement of the pressed retaining tube. Guide parts 3 are arranged on both sides of the tube wall of the guide tube 2, and the guide parts 3 are provided with guide grooves 4.
[0043] Step 1.2: Use two guide pipes 2 to synchronously construct the retaining pipes 5, and press the multiple retaining pipes 5 into the soil in sequence. The multiple retaining pipes 5 pressed into the soil by the guide pipes 2 on both sides form a retaining ring, such as Figure 3-Figure 4 As shown, the enclosure tube 5 is an arc-shaped tube that matches the shape of the guide tube 2, and guide blocks 6 are provided on both sides of the tube wall of the enclosure tube 5, wherein the guide block 6 on one side can be embedded in the guide groove 4 on one side of the guide tube, and the guide block 6 on the other side can be embedded in the guide groove 4 on the other side of the guide tube.
[0044] In this embodiment, a slot is provided at the outer end of the guide block on one side of the guide tube 2, and the outer end of the guide block 6 on the other side of the guide tube 2 serves as an inserting portion and can be inserted into the slot.
[0045] One side end of the retaining pipe 5 is provided with a pointed structure 7, and the pointed structure 7 of the retaining pipe 5 can be inserted into the retaining pipe 5 adjacent to it. In this embodiment, the ends of all the retaining pipes 5 used to pass through the guide pipe 2 on one side are provided with a pointed structure. Among the multiple retaining pipes used to pass through the guide pipe 2 on the other side, the first retaining pipe to be constructed is not provided with a pointed structure, and the remaining retaining pipes 5 are provided with a pointed structure.
[0046] like Figure 5 As shown, the specific construction steps of the multiple enclosure pipes 5 corresponding to each guide pipe are as follows:
[0047] Step 1.2.1: Insert the first section of the enclosure tube into the guide tube 2, wherein the guide blocks 6 on both sides of the first section of the enclosure tube are embedded in the guide grooves 4 on both sides of the guide tube 2. The first section of the enclosure tube on one side is provided with a spike structure 7, while the first section of the enclosure tube on the other side is not provided with a spike structure.
[0048] Step 1.2.2: Align the end of the second section of the retaining pipe with the end of the first section of the retaining pipe, and then press the second section of the retaining pipe into the guide pipe 2. At this time, under the action of pressure, the first section of the retaining pipe is pressed into the soil.
[0049] Step 1.2.3: Align the end of the third section of the retaining pipe with the end of the second section of the retaining pipe, and then press the third section of the retaining pipe into the guide pipe 2. At this time, under the action of pressure, the second section of the retaining pipe is pressed into the soil, and the first section of the retaining pipe moves in the soil.
[0050] Since the pointed structure 7 at the end of the second retaining pipe is inserted into the first retaining pipe, the moving direction of the first retaining pipe in the soil can be guided.
[0051] Step 1.2.4: Repeat steps 1.2.2 and 1.2.3 until multiple retaining pipes 5 corresponding to the guide pipe 2 are constructed. After the construction is completed, a retaining structure of the underground structure is formed. At this time, the pointed structure of the first section of the retaining pipe on one side is inserted into the end of the first section of the retaining pipe on the other side, and the guide device is removed for use in the next construction.
[0052] In this embodiment, step 1.2 is adopted to synchronously construct the multiple surrounding pipes 5 corresponding to the two guide pipes 2. The surrounding pipes corresponding to the two guide pipes 2 are synchronously constructed, which can balance the horizontal force.
[0053] Step 1.3: After one retaining ring is constructed, move the guide device and use the method in step 1.2 to construct the adjacent retaining rings until all retaining rings along the longitudinal direction of the underground structure are constructed.
[0054] When adjacent retaining rings are constructed, the guide device should be positioned so that the guide block on one side of the newly constructed retaining pipe can be inserted into the slot of the adjacent retaining pipe that has been completed. With this setting, adjacent retaining rings can be connected through the slots and guide blocks, thus achieving waterproofing, eliminating the precipitation process, shortening the construction period, and reducing construction costs.
[0055] Step 2: If Figure 6 As shown, a support mechanism is constructed on top of the formed enclosure structure.
[0056] In this embodiment, the support mechanism includes two longitudinal beams 8 and multiple cross beams 9. The longitudinal beams 8 are fixed to the ends of multiple enclosures and to the ends of the enclosure pipes 5 located above the ground. Since the enclosure structure has two ends, two longitudinal beams 8 are provided. The longitudinal beams 8 are detachably fixed to the ends of the enclosure structure by bolts or by welding.
[0057] A plurality of cross beams 9 are arranged between the two longitudinal beams 8 . The cross beams 9 are arranged perpendicular to the longitudinal beams 8 . The longitudinal beams 8 and the cross beams 9 are detachably fixedly connected by bolts or fixedly connected by welding.
[0058] In this embodiment, the enclosure structure adopts an arc-shaped structure, which can effectively resist horizontal forces. Compared with the traditional enclosure structure, the number of lateral supports in the horizontal support system of the enclosure structure is reduced, the construction volume is reduced, and the construction period is shortened.
[0059] Step 3: After the construction of the supporting structure is completed, the soil inside the retaining structure is excavated until the inner side of the retaining structure is exposed. Excavation can be carried out using existing excavation equipment, which will not be described in detail here.
[0060] Step 4: Construct underground structure inside the enclosure structure.
[0061] In this embodiment, the wall 10 of the underground structure is constructed on the inner side of the retaining structure. The wall 10 is cast with concrete, using the inner side of the retaining structure as one side formwork, and then the concrete is cast so that the wall of the underground structure fits the inner side of the retaining structure.
[0062] After the wall construction is completed, the top plate 11 of the underground structure is constructed. The top plate 11 is cast with concrete using existing construction methods, which will not be described in detail here.
[0063] The side walls of the underground structure are constructed on the inner side of the retaining structure, and the excavation volume matches the underground structure. Compared with the traditional excavation volume in which the foundation pit space is larger than the underground structure, the earth excavation volume is small and the soil backfilling step is omitted, which reduces the construction workload and shortens the construction period.
[0064] The above description is only the preferred embodiment of the present application and is not intended to limit the present application. For those skilled in the art, the present application may have various modifications and variations. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present application shall be included in the protection scope of the present application.
Claims
1. A construction method for a shallow underground structure, characterized in that: The following steps are involved: A guide device is placed on the ground, wherein the guide device has two arc-shaped guide tubes arranged opposite to each other; Multiple arc-shaped retaining pipes are pressed into the soil in sequence through two guide pipes, and the retaining pipes pressed in on both sides form an arc-shaped retaining ring matching the underground structure; Multiple arc-shaped retaining rings are sequentially constructed along the longitudinal direction of the underground structure until the retaining structure of the entire underground structure is completed; Excavate the soil inside the retaining structure; The underground structure is constructed inside the retaining structure, wherein the wall of the underground structure is constructed on the inner side of the retaining structure.
2. A construction method for a shallow underground structure as claimed in claim 1, characterized in that: The guide device comprises a positioning plate, and guide tubes are arranged at both ends of the positioning plate. The guide tubes are arc-shaped tubes, and the two guide tubes are symmetrically arranged relative to the center of the positioning plate.
3. A construction method for a shallow underground structure as claimed in claim 1, characterized in that: The guide tube is provided with guide parts on both sides, and the guide parts are provided with guide grooves.
4. A construction method for a shallow underground structure as claimed in claim 3, characterized in that: Guide blocks are arranged on both sides of the enclosure tube, and the guide blocks can be embedded in the guide grooves. The guide block on one side of the enclosure tube is provided with a slot, and the outer end of the guide block on the other side can be inserted into the slot as a plug-in portion.
5. A construction method for a shallow underground structure as claimed in claim 1, characterized in that: The retaining pipes corresponding to the two guide pipes of the guide device are constructed synchronously.
6. A construction method for a shallow underground structure as claimed in claim 1, characterized in that: The construction method of the retaining ring includes the following steps: Step 1: Insert the first section of the enclosure tube into the guide tube; Step 2: Align the end of the second section of the retaining pipe with the end of the first section of the retaining pipe, and then apply pressure to the second section of the retaining pipe, so that the second section of the retaining pipe enters the guide pipe and the first section of the retaining pipe is pressed into the soil; Step 3: Repeat step 2 until the multiple retaining pipes corresponding to the guide pipe are pressed into the soil.
7. A construction method for a shallow underground structure as claimed in claim 1, characterized in that: The ends of all the surrounding tubes inserted through the guide tube on one side have a pointed structure, and the pointed structure of the surrounding tube can be inserted into the surrounding tube adjacent to it. Among the surrounding tubes inserted by the guide tube on the other side, the end of the first section of the surrounding tube does not have a pointed structure, and the ends of the remaining surrounding tubes all have a pointed structure.
8. A construction method for a shallow underground structure as claimed in claim 1, characterized in that: Before excavating the soil inside the retaining structure, a supporting mechanism is set on the top of the retaining structure.
9. A construction method for a shallow underground structure as claimed in claim 8, characterized in that: The supporting mechanism is fixed to the longitudinal beam at the top of the enclosure, and a plurality of cross beams are arranged between the two longitudinal beams.
10. A construction method for a shallow underground structure as claimed in claim 1, characterized in that: The wall of the underground structure is cast on the inner side of the retaining structure, and then the top slab of the underground structure is cast.