Double-layer pile stabilizing platform for offshore steel pipe pile sinking and construction method
Through the combination of floating structure carrying and locking firmware and deviation correction devices of the double-layer pile stabilization platform, the problem of the removal of positioning platform in offshore steel pipe pile construction affects efficiency, achieve efficient positioning and deviation correction, and improve construction efficiency and stability.
Patent Information
- Application Number
- CN202411166706.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-23
- Publication Date
- 2024-11-26
AI Technical Summary
In the construction of offshore steel pipe piles, the demolition and reorganization steps of positioning platforms and positioning piles in the prior art affect construction efficiency, resulting in inefficient pile sinking process of steel pipe piles.
The double-layer pile stabilization platform is adopted to carry positioning seats and positioning piles through a floating structure, and the movement and positioning of the positioning seats and positioning piles are achieved by using locking firmware, deviation correction device and climbing device, reducing the separation steps of the positioning seats and positioning piles. Improve the construction efficiency of steel pipe piles.
It realizes efficient positioning and correction of steel pipe piles, reduces the center of gravity during construction, improves overall mobility stability and construction efficiency, reduces assembly troubles, and facilitates the inlet and exit and insertion of steel pipe piles.
Smart Images

Figure CN119021173A_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the field of offshore facility construction, and in particular to a double-layer pile stabilization platform for offshore steel pipe pile sinking and a construction method. Background Art
[0002] In the construction of offshore wind power facilities, due to the particularity of the construction environment and technical requirements, effective measures need to be taken according to the project plan to strengthen the construction nodes and process attention to ensure the smooth progress of the installation of offshore wind power facilities. This involves the pile foundation construction in the fields of construction engineering and marine engineering. In these fields, piles are an important part of the load-bearing and fixed structure, and their construction quality and stability have a vital impact on the safety and service life of the entire project.
[0003] In the actual construction process, due to the influence of various factors, such as geological conditions, climatic conditions, construction equipment performance, etc., the pile sinking process may have deviations, such as tilting, offset, etc. In the pile sinking construction of large steel pipe piles, in order to ensure the construction quality of the piles, the pile sinking process needs to be precisely adjusted, so it is necessary to build a positioning platform at the construction location at sea. Usually, multiple positioning piles are first driven vertically into the sea, and then the positioning cylinders on the sides of the positioning platform are sleeved on the corresponding positioning piles, and then the positioning cylinders and positioning piles are locked, and then the positioning grooves at the positioning platform are used to guide and position the steel pipe piles, and then the steps of pile insertion and sinking are gradually completed. By repeating the above steps, the construction of multiple steel pipe piles is completed, thereby forming the foundation of the offshore structure.
[0004] Regarding the above-mentioned related technologies, there are the following defects: after the construction of each steel pipe pile is completed, the temporary positioning platform and positioning piles need to be dismantled, and then moved to the next steel pipe pile construction position to perform the positioning pile insertion and positioning platform assembly steps, which affects the construction efficiency of the steel pipe piles, so there is still room for improvement. Summary of the invention
[0005] In order to improve the construction efficiency of steel pipe piles, the present application provides a double-layer pile stabilization platform for offshore steel pipe pile sinking and a construction method.
[0006] The present application provides a double-layer pile stabilization platform for offshore steel pipe pile sinking and a construction method using the following technical solutions: A double-layer pile stabilization platform for offshore steel pipe pile sinking, comprising: A positioning seat, wherein the positioning seat is penetrated and provided with a positioning groove in the vertical direction, wherein the positioning groove is used to position the steel pipe pile, and one side of the positioning groove is open to allow the steel pipe pile to enter and exit; A deviation correction device, which is used to correct the deviation of the steel pipe pile in the positioning groove; A plurality of positioning piles, wherein the plurality of positioning piles are used to limit the positioning seat; A plurality of positioning tubes, wherein the plurality of positioning tubes are vertically arranged on the positioning seat, the plurality of positioning tubes correspond to the plurality of positioning piles one by one, and the positioning piles are vertically inserted into the corresponding positioning tubes; The floating structure is used to carry the positioning seat, and the floating structure is provided with a locking piece for locking the positioning pile; when the positioning seat is limited, the locking piece releases the restriction on the positioning pile, and the lower end of the positioning pile is inserted downward into the riverbed.
[0007] By adopting the above technical scheme, the floating structure is used to carry the positioning seat, and the multiple positioning piles are locked by the locking pieces, so that the positioning seat and the positioning piles can move to the construction area with the floating structure as a whole, and then the locking pieces are unlocked, and the positioning piles are vertically inserted into the riverbed under the guidance of the positioning cylinder, thereby achieving the fixation of the position of the positioning seat, and then the positioning grooves and correction devices at the positioning seat are used to achieve the positioning and correction of the steel pipe piles to ensure that the steel pile body can be vertically inserted into the riverbed, wherein one side of the positioning groove is open, so as to facilitate the entry and exit of the steel pipe piles, the positioning of the steel pipe piles, and the separation between the steel column pile body and the positioning seat, without the need to disassemble the positioning seat and the positioning piles, reducing various troubles such as assembly and positioning, which is conducive to improving the construction efficiency of the steel pipe piles.
[0008] Preferably, a climbing device is provided between the positioning seat and the positioning pile, and the climbing device is used to drive the positioning seat to move up and down to adjust the distance between the positioning seat and the floating structure.
[0009] By adopting the above technical solution, when the positioning seat and the positioning pile follow the movement of the floating structure, the positioning seat can be lowered by using the climbing device so that the positioning seat is close to the floating structure, thereby lowering the center of gravity of the pile stabilizing platform to improve the stability of the pile stabilizing platform during overall movement. When the steel pipe piles are inserted and driven, the height of the positioning seat is increased by using the climbing device to facilitate the positioning operation of the steel pipe piles.
[0010] Preferably, the climbing device comprises a winch arranged on the surface of the positioning seat and a connecting member arranged at the positioning pile, and a traction rope of the winch is connected to the connecting member.
[0011] By adopting the above technical solution, the lifting function of the positioning seat is realized by winding and releasing the traction rope through the winch. The winch is used to drive the lifting height range to meet the lifting height requirements of the positioning seat.
[0012] Preferably, when the positioning cylinder moves to the connecting member, the positioning cylinder is locked to the connecting member.
[0013] By adopting the above technical solution, the load generated by the construction of the positioning seat and the steel pipe pile is transmitted to the positioning pile through the connecting member, which is beneficial to improving the structural stability of the positioning seat.
[0014] Preferably, the floating structure is vertically provided with a guide portion, and the positioning seat is provided with a sliding member for vertically slidingly cooperating with the guide frame.
[0015] By adopting the above technical solution, the sliding member and the vertically arranged guide part are slidably matched, and the guiding effect of the guide part is utilized to realize the stable lifting and lowering of the positioning seat, which is beneficial to improving the movement stability of the positioning seat.
[0016] Preferably, the positioning seat is arranged on a floating structure, and the floating structure is provided with an avoidance groove directly opposite to the positioning groove, and the avoidance groove is for the steel pipe pile to pass through.
[0017] By adopting the above technical solution, the positioning seat is set above the floating structure, which is beneficial to improving the stability of the positioning seat in the process of following the movement of the floating structure. In addition, by setting an avoidance groove on the floating structure for the steel pipe piles to pass through, the obstruction of the floating structure to the normal insertion of the steel pipe piles is overcome, thereby facilitating the insertion construction of the steel pipe piles.
[0018] Preferably, the deviation-correcting device comprises a plurality of oil cylinders, wherein the plurality of oil cylinders are horizontally arranged and distributed around the locating groove, and the telescopic ends of the plurality of oil cylinders are oriented toward the axial line of the locating groove.
[0019] By adopting the above technical solution, several oil cylinders are extended to push the outer peripheral surface of the steel pipe pile at the positioning groove, and the steel pipe pile is adjusted to a vertical state, so that the axis of the steel pipe pile coincides with the axis of the positioning groove, which is conducive to achieving the purpose of correcting the deviation of the steel column pile body.
[0020] A method for offshore steel pipe pile sinking construction, using an offshore steel pipe pile sinking double-layer pile stabilization platform, comprising the following steps: S1: The floating structure carries the positioning piles and positioning seats to the construction location; S2: Remove the restrictions between the positioning piles and the floating structure, and insert the lower ends of the positioning piles into the riverbed one by one; S3: The steel pipe pile is moved into the positioning groove, and the deviation correction device corrects the deviation of the steel pipe pile to keep the steel pipe pile in a vertical state; S4: insert and drive the steel pipe piles into the riverbed to complete the steel pipe pile construction; S5: Pull the positioning piles upward until each positioning pile is pulled away from the riverbed, and lock the positioning piles at the floating structure; S6: Repeat S1 to S5 until the construction of several steel pipe piles is completed.
[0021] By adopting the above technical scheme, the positioning seat and the positioning pile are moved as a whole to the construction area by using the floating structure, and then the positioning pile is vertically inserted into the riverbed, so as to fix the position of the positioning seat. Then, the positioning groove and the correction device at the positioning seat are used to realize the positioning and correction of the steel pipe pile to ensure that the steel pile body can be vertically inserted into the riverbed. Among them, one side of the positioning groove is open to facilitate the separation between the steel column pile body and the positioning seat. There is no need to disassemble the positioning seat and the positioning pile, which reduces various troubles such as assembly and positioning, and is conducive to improving the construction efficiency of the steel pipe pile.
[0022] In summary, the present application includes at least one of the following beneficial technical effects: 1. The floating structure is used to carry the positioning seat, and the multiple positioning piles are locked by the locking pieces, so that the positioning seat and the positioning piles can move to the construction area with the floating structure as a whole, and then the locking pieces are unlocked, and the positioning piles are vertically inserted into the riverbed under the guidance of the positioning tube, thereby fixing the position of the positioning seat, and using the positioning groove and the correction device at the positioning seat to realize the positioning and correction of the steel pipe piles, so as to ensure that the steel pile body can be vertically inserted into the riverbed. Among them, one side of the positioning groove is open, so as to facilitate the entry and exit of the steel pipe piles, the positioning of the steel pipe piles, and the separation between the steel column pile body and the positioning seat. There is no need to disassemble the positioning seat and the positioning piles, which reduces various troubles such as assembly and positioning, and is conducive to improving the construction efficiency of the steel pipe piles; 2. By arranging a climbing device between the positioning seat and the positioning pile, when the positioning seat and the positioning pile move with the floating structure, the positioning seat can be lowered by the climbing device so that the positioning seat is close to the floating structure, thereby lowering the center of gravity of the pile stabilizing platform to improve the stability of the pile stabilizing platform during overall movement. When the steel pipe pile is inserted and driven, the height of the positioning seat is raised by the climbing device to facilitate the positioning operation of the steel pipe pile; 3. By setting an avoidance groove on the floating structure for the steel pipe piles to pass through, the barrier of the floating structure to the normal driving of the steel pipe piles is overcome, thereby facilitating the driving construction of the steel pipe piles. BRIEF DESCRIPTION OF THE DRAWINGS
[0023] Figure 1 It is a schematic diagram of the overall structure of a double-layer pile stabilizing platform for offshore steel pipe pile sinking according to an embodiment of the present application.
[0024] Figure 2 It is a plan view of a double-layer pile stabilization platform for offshore steel pipe pile sinking according to an embodiment of the present application.
[0025] Explanation of the accompanying drawings: 1. Positioning seat; 11. Sliding member; 12. Positioning groove; 2. Positioning cylinder; 3. Positioning pile; 4. Climbing device; 41. Winch; 42. Towing rope; 43. Connecting member; 5. Floating structure; 51. Guide part; 52. Avoidance groove; 53. Avoidance hole; 6. Locking piece; 7. Correction device; 8. Rubber layer. DETAILED DESCRIPTION
[0026] The following is combined with Figure 1-2 This application is described in further detail.
[0027] The present application discloses a double-layer pile stabilizing platform for offshore steel pipe pile sinking, referring to Figure 1 , including a positioning seat 1, a deviation correction device 7, a plurality of positioning piles 3, a plurality of positioning tubes 2 and a floating structure 5. Specifically, the positioning seat 1 is a double-layer structure and is provided with a positioning groove 12 in the vertical direction for positioning the steel pipe piles. The positioning groove 12 is circular, and one side of the positioning groove 12 is open for the steel pipe piles to enter and exit.
[0028] The deviation correcting device 7 includes a plurality of oil cylinders, which are horizontally arranged and distributed around the positioning groove 12, and the telescopic ends of the plurality of oil cylinders are oriented toward the axis of the positioning groove 12. In this embodiment, four oil cylinders are arranged on the surfaces of both layers of the positioning seat 1, and the oil cylinders of both layers of the positioning seat 1 are extended at the same time to push the outer peripheral surface of the steel pipe pile at the positioning groove 12, so as to adjust the steel pipe pile to a vertical state, so that the axis of the steel pipe pile coincides with the axis of the positioning groove 12, so as to achieve the purpose of the deviation correcting device 7 correcting the deviation of the steel column pile body.
[0029] There are four positioning tubes 2 and four positioning piles 3, and there is a one-to-one correspondence between the positioning tubes 2 and the positioning piles 3. In this embodiment, the diameter of the steel pipe pile is greater than the diameter of the positioning pile 3.
[0030] The four positioning cylinders 2 are respectively fixed at the four corners of the positioning seat 1 in a vertical state, and the positioning piles 3 are vertically inserted into the corresponding positioning cylinders 2. The positioning cylinders 2 guide the positioning piles 3 so that the positioning piles 3 can slide stably in the vertical direction. By vertically inserting the lower ends of the four positioning piles 3 into the riverbed one by one, the positioning seat 1 can be limited.
[0031] In this embodiment, the floating structure 5 adopts a large buoy with a hollow interior, which is used to carry the positioning seat 1. Among them, a guide portion 51 is vertically installed on the surface of the floating structure 5, and a sliding member 11 for vertical sliding cooperation with the guide frame is provided at the bottom of the positioning seat 1. The positioning seat 1 is limited on the floating structure 5 by the guide portion 51, and can move up and down relative to the guide portion 51. Specifically, the guide portion 51 is a guide column vertically fixed on the surface of the floating structure 5, and the sliding member 11 is a sliding cylinder vertically slidably sleeved on the outer peripheral surface of the guide column, which is conducive to improving the stability of the up and down movement of the positioning seat 1.
[0032] The floating structure 5 is provided with an avoidance groove 52 directly opposite to the positioning groove 12, and the profile of the avoidance groove 52 is consistent with the profile of the positioning groove 12, and the avoidance groove 52 can be passed through by the steel pipe pile. In addition, the floating structure 5 is provided with four avoidance holes 53, and the four avoidance holes 53 correspond to the four positioning tubes 2 one by one. The axis of the avoidance hole 53 coincides with the axis of the corresponding positioning tube 2, and the avoidance hole 53 can be vertically passed through by the corresponding positioning pile 3. The opening of the avoidance groove 52 and the avoidance hole 53 overcomes the obstruction of the floating structure 5 to the normal insertion and driving of the steel pipe pile, and facilitates the insertion and driving construction of the steel pipe pile.
[0033] It should be emphasized that the avoidance hole 53 is not connected to the internal cavity of the floating structure 5 . The inner wall of the avoidance hole 53 is covered with a rubber layer 8 , which is wrapped around the outer peripheral surface of the positioning pile 3 to reduce the gap of the floating structure 5 .
[0034] The floating structure 5 is equipped with a locking piece 6 for locking the positioning pile 3. The locking piece 6 is specifically a chain. The outer peripheral surface of the positioning pile 3 is embedded with a locking ring that cooperates with the chain. The locking ring is located in the positioning pile 3. One end of the locking piece 6 is connected to the surface of the floating structure 5, and the other end is detachably connected to the fastener on the surface of the positioning pile 3, so as to maintain the stability between the positioning pile 3 and the floating structure 5. When the locking piece 6 locks the positioning pile 3, the lower end of the positioning pile 3 is separated from the riverbed, so that the positioning seat 1 and the positioning pile 3 move with the floating structure 5. When the positioning seat 1 is limited, the locking piece 6 releases the restriction on the positioning pile 3, and the lower end of the positioning pile 3 is inserted downward into the riverbed. It is beneficial to improve the stability of the positioning seat 1 and the floating structure 5, so as to facilitate the construction of steel pipe piles.
[0035] A climbing device 4 is installed between the positioning seat 1 and the positioning pile 3. The climbing device 4 includes a winch 41 installed on the surface of the positioning seat 1 and a connecting member 43 arranged at the positioning pile 3. The connecting member 43 adopts a steel bull leg, and the traction rope 42 of the winch 41 is connected to the connecting member 43. By winding and releasing the traction rope 42 by the winch, the lifting function of the positioning seat 1 can be realized to adjust the distance between the positioning seat 1 and the floating structure 5. When the positioning seat 1 and the positioning pile 3 move with the floating structure 5, the climbing device 4 can be used to lower the positioning seat 1 so that the positioning seat 1 is close to the floating structure 5, thereby lowering the center of gravity of the pile stabilizing platform to improve the stability of the pile stabilizing platform when it moves as a whole. When the steel pipe pile is inserted and driven, the height of the positioning seat 1 is increased by the climbing device 4 to perform the positioning operation of the steel pipe pile.
[0036] When the positioning tube 2 moves to the connecting member 43, a plurality of locking buckles are used to lock the positioning tube 2 to the connecting member 43, so that the load generated by the positioning seat 1 and the steel pipe pile construction is transmitted to the positioning pile 3 through the connecting member 43, which is beneficial to improve the structural stability of the positioning seat 1.
[0037] A method for offshore steel pipe pile sinking construction, using an offshore steel pipe pile sinking double-layer pile stabilization platform, comprising the following steps: S1: The floating structure 5 is dragged by a transport ship, and the floating structure 5 carries the positioning piles 3 and the positioning seats 1 to the construction location.
[0038] S2: Then, the locking pieces 6 between the positioning piles 3 and the floating structure 5 are released one by one, thereby releasing the restrictions of the positioning piles 3, and the lower ends of the positioning piles 3 are inserted into the riverbed one by one. When releasing the positioning piles 3 one by one, the two positioning piles 3 at the diagonal positions are released first, and the pile hammer is used to slowly hammer them into the riverbed to reduce the situation where the floating structure 5 overturns to one side.
[0039] S3: After the four positioning piles 3 are firmly fixed on the riverbed, the hoist is started to drive the positioning seat 1 to move upward, and the positioning cylinder 2 is locked at the connecting member 43 of the positioning pile 3, and then the steel pipe pile construction step is carried out.
[0040] The ship crane lifts the steel pipe pile to a vertical state, the lower end of the steel pipe pile sinks into the sea first, and then slowly moves to the positioning seat 1, and the steel pipe pile moves into the positioning groove 12 from the opening of the positioning groove 12. After the steel pipe pile is moved into the positioning groove 12, the correction device 7 is started, and multiple oil cylinders on the side of the positioning groove 12 push the steel pipe pile at the same time to correct the deviation of the steel pipe pile and keep it in a vertical state.
[0041] S4: Drive the steel pipe piles vertically into the riverbed to complete the steel pipe pile construction.
[0042] S5: Pull the positioning piles 3 upwards by the ship crane, pull the four positioning piles 3 out of the riverbed one by one, and then use the locking pieces 6 to lock the positioning piles 3 at the floating structure 5. Then use the transport ship to tow the floating structure 5 to the next construction location.
[0043] S6: Repeat S1 to S5 until the construction of several steel pipe piles is completed.
[0044] The above are all preferred embodiments of the present application, and the protection scope of the present application is not limited thereto. Therefore, any equivalent changes made according to the structure, shape, and principle of the present application should be included in the protection scope of the present application.
Claims
1. A double-layer pile stabilization platform for offshore steel pipe pile sinking, characterized in that: include: A positioning seat (1), wherein the positioning seat (1) is provided with a positioning groove (12) extending through the positioning seat in a vertical direction, the positioning groove (12) being used to position the steel pipe pile, and one side of the positioning groove (12) being open to allow the steel pipe pile to enter and exit; A deviation correction device (7), the deviation correction device (7) being used to correct the deviation of the steel pipe pile in the positioning groove (12); A plurality of positioning piles (3), wherein the plurality of positioning piles (3) are used to limit the position of the positioning seat (1); A plurality of positioning tubes (2), wherein the plurality of positioning tubes (2) are vertically arranged on the positioning seat (1), the plurality of positioning tubes (2) correspond to the plurality of positioning piles (3) one by one, and the positioning piles (3) are vertically inserted into the corresponding positioning tubes (2); A floating structure (5) is used to carry a positioning seat (1), and the floating structure (5) is provided with a locking piece (6) for locking a positioning pile (3); when the positioning seat (1) is limited, the locking piece (6) releases the restriction on the positioning pile (3), and the lower end of the positioning pile (3) is inserted downward into the riverbed.
2. A double-layer pile stabilization platform for offshore steel pipe pile sinking according to claim 1, characterized in that: A climbing device (4) is provided between the positioning seat (1) and the positioning pile (3), and the climbing device (4) is used to drive the positioning seat (1) to move up and down, so as to adjust the distance between the positioning seat (1) and the floating structure (5).
3. A double-layer pile stabilization platform for offshore steel pipe pile sinking according to claim 2, characterized in that: The climbing device (4) comprises a hoist (41) arranged on the surface of the positioning seat (1) and a connecting member (43) arranged at the positioning pile (3); a traction rope (42) of the hoist (41) is connected to the connecting member (43).
4. A double-layer pile stabilization platform for offshore steel pipe pile sinking according to claim 3, characterized in that: When the positioning tube (2) moves to the connecting member (43), the positioning tube (2) is locked to the connecting member (43).
5. A double-layer pile stabilization platform for offshore steel pipe pile sinking according to claim 1, characterized in that: The floating structure (5) is vertically provided with a guide portion (51), and the positioning seat (1) is provided with a sliding member (11) for vertically slidingly cooperating with the guide frame.
6. A double-layer pile stabilization platform for offshore steel pipe pile sinking according to claim 1, characterized in that: The positioning seat (1) is arranged on a floating structure (5), and the floating structure (5) is provided with an avoidance groove (52) directly opposite to the positioning groove (12), and the avoidance groove (52) is for the steel pipe pile to pass through.
7. A double-layer pile stabilization platform for offshore steel pipe pile sinking according to claim 1, characterized in that: The deviation correcting device (7) comprises a plurality of oil cylinders, which are arranged horizontally and distributed around the locating groove (12), and the telescopic ends of the plurality of oil cylinders are oriented toward the axial line of the locating groove (12).
8. A method for sinking steel pipe piles at sea, using a double-layer pile stabilizing platform for sinking steel pipe piles at sea as claimed in any one of claims 1 to 7, characterized in that: The following steps are involved: S1: The floating structure (5) carries the positioning pile (3) and the positioning seat (1) to the construction location; S2: The restriction between the positioning piles (3) and the floating structure (5) is released, and the lower ends of the positioning piles (3) are inserted into the riverbed one by one; S3: The steel pipe pile is moved into the positioning groove (12), and the deviation correction device (7) corrects the deviation of the steel pipe pile so that the steel pipe pile remains in a vertical state; S4: insert and drive the steel pipe piles into the riverbed to complete the steel pipe pile construction; S5: pulling the positioning piles (3) upward until each positioning pile (3) is pulled away from the riverbed, and locking the positioning piles (3) at the floating structure (5); S6: Repeat S1 to S5 until the construction of several steel pipe piles is completed.