Pipe gallery prefabricating and assembling construction technology
Through the combination of transportation, positioning and connection mechanisms, the construction difficulty, cost and safety issues in prefabricated assembly of pipe corridors are solved, and efficient and safe pipe corridor installation is achieved.
Patent Information
- Application Number
- CN202411357255.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-09-27
- Publication Date
- 2024-11-29
- Estimated Expiration
- 2044-09-27
AI Technical Summary
The existing prefabricated assembly construction technology of pipe corridors has problems such as high construction difficulty, high cost, low installation efficiency, high safety risks of lifting and assembly, and inconvenient docking.
The transportation mechanism, positioning clamping mechanism and connection mechanism are adopted to achieve accurate lifting, positioning and connection of prefabricated pipe gallery sections through technical means such as transportation rails, vacuum suction cups, laser sensors, hydraulic telescopic rods and threaded connections.
The positioning and connection efficiency of prefabricated pipe gallery segments is improved, construction risks are reduced, and construction safety and efficiency are enhanced.
Smart Images

Figure CN119041482A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of pipe gallery construction, and in particular to a pipe gallery prefabrication and assembly construction process. Background Art
[0002] A comprehensive pipeline corridor is an underground urban pipeline corridor, which is an accessible space built underground in the city, integrating various engineering pipelines such as electricity, communications, gas, heating, water supply and drainage, and is equipped with special inspection ports, lifting ports and monitoring systems. It is an important infrastructure and lifeline to ensure the operation of the city.
[0003] The current construction technology of prefabricated pipe corridors can save construction time compared to the construction technology of cast pipe corridors, but the construction is difficult and costly, the construction steps are cumbersome, and the installation efficiency is low. Since the components of prefabricated pipe corridors are usually large in size and heavy in weight, there are certain difficulties in their transportation and positioning. In the construction of prefabricated pipe corridors, there are certain safety risks in the hoisting and assembly operations, and the hoisting method cannot effectively connect the prefabricated pipe corridors, and adjustments are required, thereby reducing the construction efficiency of the pipe corridor. Summary of the invention
[0004] Based on the above-mentioned existing technical problems, the present invention proposes a prefabricated assembly construction process for a pipe gallery.
[0005] The present invention provides a pipe gallery prefabrication and assembly construction process, which includes the following construction steps:
[0006] S1. According to the project requirements, the detailed design of the pipeline corridor and the division of prefabricated sections are carried out, and the foundation pit construction is carried out at the construction site.
[0007] S2. Install supporting steel plates in the foundation pit according to the starting section of the tunnel, and use hoisting equipment to lift the prefabricated tunnel segments one by one and transport them to the top of the foundation pit.
[0008] S3. Transport the lifted prefabricated pipe gallery segment to the installation location through the transport mechanism.
[0009] S4. Install the prefabricated pipe gallery segment to the designated position through the positioning and clamping mechanism to ensure accurate docking.
[0010] S5. Connect the prefabricated pipe gallery segments through connecting mechanisms.
[0011] S6. Repeat steps S3 and S4 until the installation of the standard corridor stage is completed, and connect multiple prefabricated corridor segments under the action of the tensioning equipment to form an integral corridor.
[0012] Preferably, the transport mechanism includes transport tracks symmetrically installed on the outer surface of the foundation pit, the surfaces of the moving blocks on the two transport tracks are fixedly installed with mounting shells, the inner walls of the two mounting shells are symmetrically installed with telescopic cylinders, and one end of the piston rods of the two telescopic cylinders extends to the outside of the mounting shells and is fixedly connected to a clamping frame.
[0013] Through the above technical solution, the movement of the moving block on the transport track drives the installation shell to move, and the telescopic cylinder piston rod is extended and retracted to drive the clamping frame connected thereto to move.
[0014] Preferably, grooves are symmetrically distributed on the surfaces of the two clamping frames, screws are installed on the inner walls of the grooves through bearings, and driving motors are symmetrically installed on the outer surfaces of the clamping frames, one end of the output shaft of the driving motor is fixedly sleeved with one end of the screw, a threaded block is threadedly sleeved on the surface of the screw, the surface of the threaded block is slidably engaged with the inner wall of the groove, a mounting block is fixedly connected to one side surface of the threaded block, and a vacuum suction cup is embedded on one side surface of the mounting block.
[0015] Through the above technical scheme, the rotation of the output shaft of the driving motor drives the screw connected to it to rotate, the rotation of the screw drives the threaded block connected to it to move along the inner wall of the groove, the movement of the threaded block drives the installation block connected to it to move, and the movement of the installation block drives the vacuum suction cup to move, thereby facilitating the vacuum suction cup and the installation block to adsorb and clamp the prefabricated pipe gallery segment.
[0016] Preferably, reinforcement frames are installed on the surface of the clamping frame in a symmetrical manner in the upper and lower parts, and sliding grooves are provided on the upper and lower surfaces of the mounting block, and one side surface of the reinforcement frame is slidably engaged with the inner wall of the sliding groove.
[0017] Through the above technical solution, the installation block is supported by the reinforcement frame, and the sliding between the reinforcement frame and the slide groove facilitates the movement of the installation block.
[0018] Preferably, the positioning and clamping mechanism comprises a bracket arranged outside the transport track, and four moving wheels are symmetrically arranged on the bottom of the bracket.
[0019] Through the above technical solution, the moving wheel is driven to move, thereby facilitating the movement of the bracket.
[0020] Preferably, the upper and lower surfaces of the bracket are symmetrically installed with a first self-driving slide rail and a second self-driving slide rail, the slider surface of the first self-driving slide rail is fixedly connected to a connecting frame, the slider surface of the second self-driving slide rail is fixedly connected to a connecting plate, and the inner surface of the connecting frame is slidably connected to the outer surface of the bracket.
[0021] Through the above technical solution, the sliders on the first self-driving slide rail and the second self-driving slide rail move synchronously relative to each other, thereby driving the connecting plate and the connecting frame to move relative to each other.
[0022] Preferably, multi-stage hydraulic telescopic rods are fixedly installed on the lower surfaces of the connecting plate and the connecting frame, one end of each of the multi-stage hydraulic telescopic rods is fixedly connected to a connecting block, and a clamping plate is fixedly installed on the opposite side surfaces of the two connecting blocks, and L-shaped clamping blocks are distributed in a rectangular array on the opposite side surfaces of the two clamping plates, and the surface of the L-shaped clamping block is in contact with the surface of the prefabricated pipe gallery segment, and the surface of the L-shaped clamping block is in contact with the surface of the supporting steel plate.
[0023] Through the above technical scheme, the connection block connected to it is driven up and down by the extension and retraction of the multi-stage hydraulic telescopic rod, the up and down movement of the connecting block drives the clamping plate to move up and down, and the up and down movement of the clamping plate drives the L-shaped clamping block to move up and down, thereby driving the prefabricated pipe gallery segment clamped by the L-shaped clamping block to be placed on the supporting steel plate.
[0024] Preferably, a laser sensor is installed on the surface of the bracket close to the second self-driving slide rail.
[0025] Through the above technical solution, a laser sensor uses a laser beam to accurately measure the distance to determine the position of the prefabricated tunnel segment.
[0026] Preferably, the connection mechanism comprises connection components which are installed in a rectangular array on the upper surface of the prefabricated pipe gallery segment, and the inner walls of a plurality of the connection components are threadedly connected with steel bars.
[0027] Through the above technical solution, two prefabricated pipe gallery sections are connected together through the connection between the steel bars and the connecting components.
[0028] Preferably, a connecting threaded sleeve is threadedly connected between the two steel bars.
[0029] Through the above technical solution, the steel bars on the two prefabricated pipe gallery segments are connected together by connecting the threaded sleeves, so that the two prefabricated pipe gallery segments are connected together.
[0030] The beneficial effects of the present invention are:
[0031] 1. By setting up a transportation mechanism, it is convenient to clamp the hoisted prefabricated pipe gallery segment, so as to preliminarily position the prefabricated pipe gallery segment. The installation block is driven by the driving motor to move, so that the installation block clamps the prefabricated pipe gallery segment. At the same time, the vacuum suction cup on the installation block adsorbs the prefabricated pipe gallery segment and transports it under the action of the transportation track to achieve the positioning and transportation effect.
[0032] 2. By setting up a positioning and clamping mechanism, it is convenient to clamp the transported prefabricated pipe gallery segments. The position of the prefabricated pipe gallery segments is determined by a laser sensor. The extension and retraction of the multi-stage hydraulic telescopic rod drives the connecting block, the clamping plate and the L-shaped clamping block to pass through the clamping frame, and the relative movement of the sliders on the first self-driving slide rail and the second self-driving slide rail drives the L-shaped clamping block to clamp the prefabricated pipe gallery segments. Then, under the action of the multi-stage hydraulic telescopic rod, the prefabricated pipe gallery segments are placed on the supporting steel plate in the foundation pit, thereby achieving the positioning effect.
[0033] 3. By setting up a connecting mechanism, when two prefabricated pipe gallery segments are butt-jointed, the steel bars are threadedly connected to the connecting components in sequence, and then the two steel bars are connected together through the connecting threaded sleeves, so that the two prefabricated pipe gallery segments are installed together, thereby improving the butt-jointing efficiency of the prefabricated pipe gallery segments. BRIEF DESCRIPTION OF THE DRAWINGS
[0034] Figure 1 A schematic diagram of a pipe gallery prefabrication and assembly construction process proposed by the present invention;
[0035] Figure 2 A three-dimensional diagram of the installation shell structure of a pipe gallery prefabrication and assembly construction process proposed by the present invention;
[0036] Figure 3 A three-dimensional diagram of a clamping frame structure of a pipe gallery prefabrication and assembly construction process proposed by the present invention;
[0037] Figure 4 A three-dimensional diagram of the vacuum suction cup structure of a pipe gallery prefabrication and assembly construction process proposed by the present invention;
[0038] Figure 5 A three-dimensional diagram of the installation block structure of a pipe gallery prefabrication and assembly construction process proposed by the present invention;
[0039] Figure 6 A three-dimensional diagram of the thread block structure of a pipe gallery prefabrication and assembly construction process proposed by the present invention;
[0040] Figure 7 A three-dimensional diagram of a first self-driving slide rail structure of a pipe gallery prefabrication and assembly construction process proposed by the present invention;
[0041] Figure 8 A three-dimensional diagram of a clamping plate structure of a pipe gallery prefabrication and assembly construction process proposed by the present invention;
[0042] Fig. 9 A three-dimensional diagram of a second self-driving slide rail structure of a pipe gallery prefabrication and assembly construction process proposed by the present invention;
[0043] Fig.10 A three-dimensional diagram of the steel bar structure of a prefabricated assembly construction process for a pipe gallery proposed in the present invention.
[0044] In the figure: 1. Support steel plate; 2. Prefabricated pipe gallery segment; 3. Transport track; 301. Installation shell; 302. Telescopic cylinder; 303. Clamping frame; 304. Groove; 305. Screw; 306. Drive motor; 307. Threaded block; 308. Mounting block; 309. Vacuum suction cup; 310. Reinforcement frame; 311. Slide; 4. Bracket; 401. Moving wheel; 402. First self-driven slide rail; 403. Second self-driven slide rail; 404. Connecting frame; 405. Connecting plate; 406. Multi-stage hydraulic telescopic rod; 407. Connecting block; 408. Clamping plate; 409. L-shaped clamping block; 410. Laser sensor; 5. Connecting member; 51. Rebar; 52. Connecting threaded sleeve. DETAILED DESCRIPTION
[0045] The technical solutions in the embodiments of the present invention will be described clearly and completely below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, rather than all the embodiments.
[0046] Reference Figure 1-Figure 10 , a pipe gallery prefabrication assembly construction process, including the following construction steps:
[0047] S1. According to the project requirements, the detailed design of the pipeline corridor and the division of prefabricated sections are carried out, and the foundation pit construction is carried out at the construction site.
[0048] S2. Install the supporting steel plate 1 in the foundation pit according to the starting section of the pipe gallery, and lift the prefabricated pipe gallery segments 2 in sequence through the lifting equipment and transport them to the top of the foundation pit.
[0049] S3. Transport the lifted prefabricated pipe gallery segment 2 to the installation location through a transport mechanism.
[0050] S4. Install the prefabricated pipe gallery segment 2 to the designated position through the positioning and clamping mechanism to ensure accurate docking.
[0051] S5. Connect the prefabricated pipe gallery segments 2 through a connecting mechanism.
[0052] S6. Repeat steps S3 and S4 until the installation of the standard corridor stage is completed, and connect multiple prefabricated corridor segments 2 under the action of the tensioning equipment to form an integral corridor.
[0053] In order to facilitate the transportation of the prefabricated pipe gallery segment 2 that has been hoisted, the transportation mechanism includes transportation rails 3 that are symmetrically installed on the outer surface of the foundation pit. The surfaces of the moving blocks on the two transportation rails 3 are fixedly installed with installation shells 301. The inner walls of the two installation shells 301 are symmetrically installed with telescopic cylinders 302. One end of the piston rod of the two telescopic cylinders 302 extends to the outside of the installation shell 301 and is fixedly connected to a clamping frame 303. The installation shell 301 is moved by the movement of the moving blocks on the transportation rails 3, and the clamping frame 303 connected thereto is moved by the telescopic movement of the piston rod of the telescopic cylinder 302.
[0054] In order to clamp the prefabricated pipe gallery segment 2 that has been hoisted, grooves 304 are symmetrically distributed on the surfaces of the two clamping frames 303. Screws 305 are installed on the inner walls of the grooves 304 through bearings. Drive motors 306 are symmetrically installed on the outer surfaces of the clamping frames 303. One end of the output shaft of the drive motor 306 is fixedly sleeved with one end of the screw 305. A threaded block 307 is threadedly sleeved on the surface of the screw 305. The surface of the threaded block 307 is slidably engaged with the inner wall of the groove 304. One side of the threaded block 307 A mounting block 308 is fixedly connected to the surface, and a vacuum suction cup 309 is embedded on one side surface of the mounting block 308. The rotation of the output shaft of the driving motor 306 drives the screw 305 connected thereto to rotate. The rotation of the screw 305 drives the threaded block 307 connected thereto to move along the inner wall of the groove 304. The movement of the threaded block 307 drives the mounting block 308 connected thereto to move. The movement of the mounting block 308 drives the vacuum suction cup 309 to move, thereby facilitating the vacuum suction cup 309 and the mounting block 308 to adsorb and clamp the prefabricated pipe gallery segment 2.
[0055] In order to support the mounting block 308 and facilitate the movement of the mounting block 308, a reinforcing frame 310 is installed on the surface of the clamping frame 303 in a symmetrical distribution in the upper and lower directions. The upper and lower surfaces of the mounting block 308 are provided with sliding grooves 311, and one side surface of the reinforcing frame 310 is slidably engaged with the inner wall of the sliding groove 311.
[0056] By setting up a transportation mechanism, it is convenient to clamp the hoisted prefabricated pipe gallery segment 2, so as to preliminarily position the prefabricated pipe gallery segment 2, and the installation block 308 is driven to move by the driving motor 306, so that the installation block 308 clamps the prefabricated pipe gallery segment 2, and at the same time, the vacuum suction cup 309 on the installation block 308 adsorbs the prefabricated pipe gallery segment 2, and transports it under the action of the transportation track 3, so as to achieve the positioning and transportation effect.
[0057] In order to facilitate the movement of the positioning and clamping mechanism, the positioning and clamping mechanism includes a bracket 4 arranged outside the transport track 3, and four moving wheels 401 are symmetrically distributed on the bottom of the bracket 4. The bracket 4 is driven to move by moving the moving wheels 401.
[0058] In order to facilitate the clamping of the prefabricated pipe gallery segment 2 transported by the transportation mechanism, the first self-driving slide rail 402 and the second self-driving slide rail 403 are symmetrically installed on the upper and lower surfaces of the bracket 4, the slider surface of the first self-driving slide rail 402 is fixedly connected to the connecting frame 404, the slider surface of the second self-driving slide rail 403 is fixedly connected to the connecting plate 405, the inner surface of the connecting frame 404 is slidably connected to the outer surface of the bracket 4, the sliders on the first self-driving slide rail 402 and the second self-driving slide rail 403 move synchronously relative to each other, thereby driving the connecting plate 405 and the connecting frame 404 to move relative to each other.
[0059] In order to facilitate the placement of the prefabricated pipe gallery segment 2 on the supporting steel plate 1, multi-stage hydraulic telescopic rods 406 are fixedly installed on the lower surfaces of the connecting plate 405 and the connecting frame 404, one end of the two multi-stage hydraulic telescopic rods 406 are fixedly connected with a connecting block 407, and the opposite side surfaces of the two connecting blocks 407 are fixedly installed with a clamping plate 408, and the opposite side surfaces of the two clamping plates 408 are provided with L-shaped clamping blocks 409 distributed in a rectangular array. The surface of the L-shaped clamping block 409 contacts the surface of the prefabricated pipe gallery segment 2, and the surface of the L-shaped clamping block 409 contacts the surface of the supporting steel plate 1. The multi-stage hydraulic telescopic rod 406 is telescopically driven to move up and down, and the up and down movement of the connecting block 407 drives the clamping plate 408 to move up and down, and the up and down movement of the clamping plate 408 drives the L-shaped clamping block 409 to move up and down, thereby driving the prefabricated pipe gallery segment 2 clamped by the L-shaped clamping block 409 to be placed on the supporting steel plate 1.
[0060] In order to determine the position of the prefabricated pipe gallery segment 2, a laser sensor 410 is installed on the surface of the bracket 4 close to the second self-driving slide rail 403, and the laser sensor 410 uses a laser beam to accurately measure the distance.
[0061] By setting up a positioning and clamping mechanism, it is convenient to clamp the transported prefabricated pipe gallery segment 2, and the position of the prefabricated pipe gallery segment 2 is determined by the laser sensor 410. The extension and retraction of the multi-stage hydraulic telescopic rod 406 drives the connecting block 407, the clamping plate 408 and the L-shaped clamp block 409 to pass through the clamping frame 303, and the relative movement of the sliders on the first self-driving slide rail 402 and the second self-driving slide rail 403 drives the L-shaped clamp block 409 to clamp the prefabricated pipe gallery segment 2, and then the prefabricated pipe gallery segment 2 is placed on the supporting steel plate 1 in the foundation pit under the action of the multi-stage hydraulic telescopic rod 406, thereby achieving the positioning effect.
[0062] In order to connect two prefabricated pipe gallery segments 2 together, the connecting mechanism includes connecting components 5 installed in a rectangular array on the upper surface of the prefabricated pipe gallery segments 2, the inner walls of multiple connecting components 5 are threadedly connected with steel bars 51, and a connecting threaded sleeve 52 is threadedly sleeved between two steel bars 51. The position of the prefabricated pipe gallery segments 2 is adjusted by connecting the steel bars 51 with the connecting components 5, and the steel bars 51 on the two prefabricated pipe gallery segments 2 are connected together by connecting the threaded sleeve 52, so that the two prefabricated pipe gallery segments 2 are connected together.
[0063] By setting up a connecting mechanism, when two prefabricated pipe gallery segments 2 are butt-jointed, the steel bars 51 are threadedly connected to the connecting components 5 in sequence, and then the two steel bars 51 are connected together by connecting the threaded sleeves 52, so that the two prefabricated pipe gallery segments 2 can be installed together, thereby improving the butt-jointing efficiency of the prefabricated pipe gallery segments 2.
[0064] Working principle: When in use, first transport the prefabricated pipe gallery segment 2 to the middle of the transport mechanism through the lifting equipment, then start the telescopic cylinder 302, and the telescopic piston rod of the telescopic cylinder 302 drives the clamping frame 303 connected thereto to move, so that the mounting blocks 308 on the two clamping frames 303 contact each other, and then start the driving motor 306, and the output shaft of the driving motor 306 drives the screw 305 connected thereto to rotate, and the rotation of the screw 305 drives the threaded block 307 connected thereto to move along the inner wall of the groove 304, and the movement of the threaded block 307 drives the mounting block 308 connected thereto to move, and the movement of the mounting block 308 causes the reinforcing frame 310 to slide in the slide groove 311, and at the same time, the movement of the mounting block 308 drives the vacuum suction cup 309 to move, so as to facilitate the vacuum suction cup 309 and the mounting block 308 to adsorb and clamp the prefabricated pipe gallery segment 2;
[0065] Then, the installation housing 301 is moved by the movement of the moving block on the transport track 3, thereby driving the clamped prefabricated pipe gallery segment 2 to move;
[0066] When the laser sensor 410 on the bracket 4 detects the position of the prefabricated pipe gallery segment 2, one end of the multi-stage hydraulic telescopic rod 406 extends to drive the connecting block 407, the clamping plate 408 and the L-shaped clamping block 409 to pass through the clamping frame 303 until the four L-shaped clamping blocks 409 are aligned with the four corners of the prefabricated pipe gallery segment 2, and then the first self-driving slide rail 402 and the second self-driving slide rail 403 are started, so that the sliders on the first self-driving slide rail 402 and the second self-driving slide rail 403 drive the multi-stage hydraulic telescopic rod 406 thereon to move relative to each other, and the L-shaped clamping block 409 is driven to clamp the prefabricated pipe gallery segment 2 through the relative movement of the two multi-stage hydraulic telescopic rods 406;
[0067] Then, the vacuum suction cup 309 is released, so that the output shaft of the driving motor 306 rotates in the opposite direction to drive the mounting block 308 to reset, and then the piston rod of the telescopic cylinder 302 contracts to drive the clamping frame 303 to reset, so that the multi-stage hydraulic telescopic rod 406 continues to extend to drive the prefabricated pipe gallery segment 2 to move downward and contact the supporting steel plate 1;
[0068] Then the sliders on the first self-driving slide rail 402 and the second self-driving slide rail 403 drive the multi-stage hydraulic telescopic rod 406 thereon to move away from each other, and reset the piston rods of the multi-stage hydraulic telescopic rod 406, and then drive the bracket 4 to move to the next installation position through the moving wheel 401;
[0069] Then repeat the above steps to dock the second prefabricated pipe gallery segment 2 with the first prefabricated pipe gallery segment 2, and connect the two prefabricated pipe gallery segments 2 together through the threaded connection of the steel bar 51 and the connecting member 5, and connect the two steel bars 51 together through the connecting threaded sleeve 52.
[0070] The above description is only a preferred specific implementation manner of the present invention, but the protection scope of the present invention is not limited thereto. Any technician familiar with the technical field can make equivalent replacements or changes according to the technical scheme and inventive concept of the present invention within the technical scope disclosed by the present invention, which should be covered by the protection scope of the present invention.
Claims
1. A pipe gallery prefabrication and assembly construction process, characterized in that: The construction steps include: S1. Carry out detailed design of the pipe gallery and division of prefabricated sections according to project requirements, and carry out foundation pit construction at the construction site; S2. Install the supporting steel plate (1) in the foundation pit according to the starting section of the pipe gallery, and use the lifting equipment to lift the prefabricated pipe gallery segments (2) in sequence and transport them to the top of the foundation pit; S3, transporting the lifted prefabricated pipe gallery segment (2) to the installation location by means of a transport mechanism; S4. Install the prefabricated pipe gallery segment (2) to the designated position through the positioning and clamping mechanism to ensure accurate docking; S5, connecting the prefabricated pipe gallery segments (2) through a connecting mechanism; S6. Repeat steps S3 and S4 until the installation of the standard corridor stage is completed, and connect multiple prefabricated corridor segments (2) under the action of the tensioning equipment to form an integral corridor.
2. A pipe gallery prefabrication and assembly construction process according to claim 1, characterized in that: The transport mechanism comprises transport rails (3) symmetrically installed on the outer surface of the foundation pit, the surfaces of the moving blocks on the two transport rails (3) are fixedly installed with mounting shells (301), the inner walls of the two mounting shells (301) are symmetrically installed with telescopic cylinders (302), and one end of the piston rods of the two telescopic cylinders (302) extends outside the mounting shells (301) and is fixedly connected to a clamping frame (303).
3. The prefabricated assembly construction process of a pipe gallery according to claim 2 is characterized in that: The surfaces of the two clamping frames (303) are provided with grooves (304) in a symmetrical distribution on the left and right sides, and the inner wall of the groove (304) is installed with a screw (305) through a bearing. The outer surface of the clamping frame (303) is installed with a driving motor (306) in a symmetrical distribution on the left and right sides, and one end of the output shaft of the driving motor (306) is fixedly sleeved with one end of the screw (305). The surface of the screw (305) is threadedly sleeved with a thread block (307), and the surface of the thread block (307) is slidably engaged with the inner wall of the groove (304). A mounting block (308) is fixedly connected to the surface of one side of the thread block (307), and a vacuum suction cup (309) is embedded on the surface of one side of the mounting block (308).
4. The prefabricated assembly construction process of a pipe gallery according to claim 3 is characterized in that: The surface of the clamping frame (303) is symmetrically distributed with reinforcement frames (310) installed in the upper and lower parts, and the upper and lower surfaces of the mounting block (308) are both provided with sliding grooves (311), and one side surface of the reinforcement frame (310) is slidably engaged with the inner wall of the sliding groove (311).
5. The prefabricated assembly construction process of a pipe gallery according to claim 1 is characterized in that: The positioning and clamping mechanism comprises a bracket (4) arranged outside the transport track (3), and four moving wheels (401) are symmetrically arranged at the bottom of the bracket (4).
6. A pipe gallery prefabrication and assembly construction process according to claim 5, characterized in that: The upper and lower surfaces of the bracket (4) are symmetrically mounted with a first self-driving slide rail (402) and a second self-driving slide rail (403); the sliding surface of the first self-driving slide rail (402) is fixedly connected to a connecting frame (404); the sliding surface of the second self-driving slide rail (403) is fixedly connected to a connecting plate (405); and the inner surface of the connecting frame (404) is slidably sleeved with the outer surface of the bracket (4).
7. A pipe gallery prefabrication and assembly construction process according to claim 6, characterized in that: The lower surfaces of the connecting plate (405) and the connecting frame (404) are fixedly mounted with multi-stage hydraulic telescopic rods (406), one end of each of the two multi-stage hydraulic telescopic rods (406) is fixedly connected with a connecting block (407), and the surfaces of the two connecting blocks (407) on opposite sides are fixedly mounted with a clamping plate (408), and the surfaces of the two clamping plates (408) on opposite sides are arranged with L-shaped clamping blocks (409) in a rectangular array, the surface of the L-shaped clamping block (409) is in contact with the surface of the prefabricated pipe gallery segment (2), and the surface of the L-shaped clamping block (409) is in contact with the surface of the supporting steel plate (1).
8. The pipe gallery prefabrication and assembly construction process according to claim 6 is characterized by: A laser sensor (410) is installed on the surface of the bracket (4) close to the second self-driving slide rail (403).
9. The pipe gallery prefabrication and assembly construction process according to claim 1 is characterized by: The connection mechanism comprises connection components (5) which are installed in a rectangular array on the upper surface of the prefabricated pipe gallery segment (2), and the inner walls of a plurality of the connection components (5) are all threadedly connected with steel bars (51).
10. A pipe gallery prefabrication and assembly construction process according to claim 9, characterized in that: A connecting threaded sleeve (52) is threadedly sleeved between the two steel bars (51).
Citation Information
Patent Citations
Mounting car for prefabricated comprehensive pipe rack assembly
CN107893430A
Positioning construction system and method for prefabricated comprehensive pipe gallery under large longitudinal slope
CN116556414A
Lifting frame and pipe gallery GIL pipeline maintenance lifting device
CN116873738A
Building engineering pipe gallery mounting equipment
CN116924215A
Pipeline supporting piece for building pipe gallery construction
CN214500237U
Cited By
Fine adjustment positioning equipment and positioning method for erection of large-pipe-section prefabricated pipe gallery
CN120006769A
Precision-adjusting positioning equipment and positioning method for erecting large-segment prefabricated pipe gallery
CN120006769B
Pipe joint splicing device and method for assembly type pipe gallery
CN120311749A
Foldable hinge connecting device for large component and assembling method
CN121205397A