Super high-rise vertical pipeline unloading device

By combining supports, anchors, and pressure plates, the limitations and corrosion problems of pipeline unloading methods in super high-rise buildings are solved, achieving reliable unloading and durability of multi-material pipelines, and convenient installation.

CN221991097UActive Publication Date: 2024-11-12HUNAN CHANGSHUN ENG CONSTRUCT JIANLI CO LTD
View PDF 0 Cites 1 Cited by

Patent Information

Application Number
CN202420639644.4
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-03-29
Publication Date
2024-11-12
Estimated Expiration
2034-03-29

AI Technical Summary

Technical Problem

Existing unloading methods for vertical pipelines in super high-rise buildings have limitations. In particular, the clamp unloading method has limited unloading capacity and is not suitable for large-diameter pipelines, while the welded steel plate unloading method affects the pipeline's anti-corrosion coating and exacerbates corrosion.

Method used

It adopts a combination of brackets, anchors, pressure plates and through-plate sleeves. The pipe load is transferred to the pressure plate and floor through the anchoring steel sleeve and wedge clamps. Reliable unloading is achieved by utilizing frictional resistance. It is suitable for pipes of various materials and specifications.

Benefits of technology

It enables widely applicable pipeline unloading, avoids damage to the anti-corrosion coating caused by welding, ensures the durability and stability of the pipeline, and is easy to install.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221991097U_ABST
    Figure CN221991097U_ABST
Patent Text Reader

Abstract

A super high-rise vertical pipeline unloading device comprises a support, an anchorage device and a bearing plate. The support is a single support or a combined support, the single support is formed by installing and welding four pieces of profile steel, the combined support is formed by installing and welding a plurality of pieces of profile steel, and force transmission profile steel is arranged in the middle of the support. The anchorage device comprises a combined steel sleeve and wedge-shaped paired clamping pieces, wherein the combined steel sleeve is composed of two symmetrical semicircular sleeves with or without lugs; the combined steel sleeve is made of a welded steel pipe or a combined sleeve, the diameter of the steel sleeve is 1-2 specifications larger than that of the pipeline, and the height is not smaller than 2 / 3 of the diameter of the pipeline; the wedge-shaped paired clamping piece consists of a wedge-shaped outer clamping piece and a wedge-shaped inner clamping piece which are equal in height; and the bearing plate is arranged between the steel sleeve and the bracket. The utility model solves a series of problems that the unloading mode of the super high-rise vertical pipeline is limited, the unloading fails, the pipeline is corroded and is not durable due to pipeline unloading, and the like.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model belongs to the technical field of building construction and relates to a super high-rise vertical pipeline unloading device. Background Art

[0002] During the installation of vertical water supply and drainage pipes in super high-rise buildings, it is necessary to effectively unload the water supply and drainage pipes with heavy weight to avoid deformation and damage of the pipes that may affect their normal use and service life.

[0003] At present, there are two ways to unload the water supply and drainage pipes in super high-rise buildings. The first is the clamp unloading method used due to the limitation of the weldability of the pipe (such as super high-rise cast iron drainage pipes), which we simply call the clamp unloading method; this method uses a clamp to fix the pipe on the bracket on the adjacent wall, so that the pipe load is transferred to the wall through the clamp bracket system. The second method is to weld a symmetrical pair of stiffening steel plates on the pipe, so that the stiffening steel plates become the fulcrum for pipe unloading, and unload the pipe load to the floor through the stiffening plates and the steel brackets supported on the floor. We simply call this method the welded steel plate unloading method.

[0004] Both unloading methods have great defects and limitations. The clamp unloading method has three defects. First, due to the small contact surface between the clamp and the bracket and the pipeline, the unloading capacity is limited and it cannot be applied to the unloading of pipelines with larger diameters. Second, as a cantilever arm hinged to the bracket, the clamp is easy to tilt downward as the pipeline sinks and lose its unloading function. Third, due to the influence of spatial layout, the adjacent walls of some pipelines are lightweight partition walls or aerated concrete filling walls, which affects the reliability of the bracket setting. The welded steel plate unloading method has two defects: First, it is only applicable to weldable metal pipes, and cannot be used for cast iron pipes and non-metallic pipes. Second, when welding the stiffening force-transmitting steel plate on the metal pipe, the welding heat will cause the anti-corrosion coating on the inner and outer walls of the heated area of ​​the pipe to be damaged, and the inner anti-corrosion coating cannot be repaired. In addition, since the pipeline unloading relies on the additional force-transmitting steel plate to transmit force, there is stress in the local pipe wall welded with the stiffening force-transmitting steel plate. The combined effect of the two directly aggravates the corrosion of the metal pipe, seriously affecting the corrosion resistance and durability of the metal pipe. Utility Model Content

[0005] In view of the limitations of the two existing pipeline unloading methods, the purpose of the utility model is to provide a super-high-rise vertical pipeline unloading device to solve the technical problems of super-high-rise vertical pipeline unloading methods being limited, unloading failure, pipeline corrosion and durability caused by pipeline unloading.

[0006] The technical solution adopted by the utility model to solve the above technical problems is:

[0007] It includes a bracket, an anchor, a pressure plate, and a through-plate sleeve; the bracket is a single bracket or a combined bracket, the single bracket is formed by welding four steel sections, and the combined bracket is formed by welding multiple steel sections, a force-transmitting steel section is arranged in the middle of the bracket, and a supporting steel leg is arranged at the lower part of the bracket; the anchor includes a combined steel sleeve and a wedge-shaped pair of clamps, the combined steel sleeve is composed of two symmetrical semicircular sleeves with ears or without ears, the semicircular steel sleeve with ears needs to be welded with connecting ears with bolt holes at both ends, and the circular steel sleeve without ears is fastened by symmetrical welding; the combined steel sleeve is made of welded steel pipe or combined sleeve, the diameter of the steel sleeve is 1~2 specifications larger than the diameter of the pipeline, and the height is not less than 2 / 3 of the diameter of the pipeline; the wedge-shaped pair of clamps is composed of equal-height wedge-shaped outer clamps and inner clamps; the pressure plate is arranged between the steel sleeve and the bracket; the through-plate sleeve is placed between the floor slab and the bracket, and the through-plate sleeve is 1~2 specifications larger than the diameter of the pipeline.

[0008] Furthermore, the number of groups of clips arranged in the steel sleeve is determined according to the diameter of the pipe: when the pipe diameter is less than 200 mm, 2 to 3 groups of clips are arranged; when the pipe diameter is greater than 200 mm, 3 to 5 groups of clips are arranged; the sum of the widths of each group of clips is not less than 2 / 3 of the circumference of the outer diameter of the pipe and is evenly distributed.

[0009] Furthermore, the material of the clip includes two types: hard plastic rubber clip or metal clip; the total thickness of the inner and outer clips after the two ends are flush and overlapped is not less than 1.15 times the difference between the inner diameter of the sleeve and the outer diameter of the pipe.

[0010] Furthermore, the thickness of the pressure plate is 1.5 times the thickness of the pipe wall; the side length of the pressure plate is the outer dimension of the bracket or not less than the outer dimension of the bracket minus half of the width of the pressure plate supporting profile; the inner cavity of the pressure plate is circular, and the diameter of the inner cavity of the pressure plate is controlled between (D+20) and (D+40), where D is the pipe diameter.

[0011] The working principle of the utility model is as follows: an anchoring device consisting of an anchoring steel sleeve and a wedge-shaped pair of clamping pieces is installed on the pipeline, so that the anchoring device becomes a force-releasing component attached to the pipeline, and the pipeline load is transmitted to the pressure plate, bracket and floor arranged below the anchoring ring in sequence through the friction resistance between the device and the pipeline.

[0012] The beneficial effects of adopting the utility model are:

[0013] (1) Wide range of applications: It can be widely used in the unloading of pipes of different materials and specifications, such as weldable metal pipes, non-weldable metal pipes (cast iron pipes), plastic pipes, etc. It can also be used for the unloading of pipes without wall brackets. In addition to pipes, it can also be used for the unloading of large-sized cables.

[0014] (2) Reliable unloading: On the one hand, the pre-stress applied by the deadweight of the pipeline creates pre-stress between the pipeline and the wedge-shaped clamp, which plays a role of pre-compression and tightening. On the other hand, the friction between the wedge-shaped clamp and the pipeline will increase accordingly with the increase of pipeline load, ensuring continuous unloading of the pipeline.

[0015] (3) It will not affect the durability of the pipeline like the unloading method of welded stiffening steel plates.

[0016] (4) Easy to assemble and adjust: The installation process of the bracket, pressure plate and anchor device is simple. After the installation of the pipes with socket and clamp interfaces is completed, the internal stress of the interface installation can be adjusted automatically. BRIEF DESCRIPTION OF THE DRAWINGS

[0017] Figure 1 Axonometric drawing for pipeline unloading construction.

[0018] Figure 2 Section drawing for pipeline unloading construction.

[0019] Figure 3 Enlarged perspective view of the bracket.

[0020] Figure 4 This is a three-dimensional diagram of the anchoring device.

[0021] In the figure: 1- floor slab, 2- plate-penetrating casing, 3- pipe, 4- bracket, 5- pressure plate, 6- steel sleeve, 7- outer clip, 8- inner clip. DETAILED DESCRIPTION

[0022] The following further describes the invention in conjunction with the embodiments.

[0023] Figure 1 , Figure 4 As shown: a super high-rise vertical pipeline unloading device, including a bracket 4, an anchor, a pressure plate 5, and a through-plate sleeve 2. The bracket 4 is a single bracket or a combined bracket. The single bracket is formed by welding four steel sections, and the combined bracket is formed by welding multiple steel sections. The middle part of the bracket 4 is provided with a force transmission steel section according to the support needs of the pipeline, and the lower part of the bracket 4 is provided with a supporting steel leg 2; the anchor includes a combined steel sleeve 6 and a wedge-shaped pair of clamps. The combined steel sleeve 6 is composed of two symmetrical semicircular sleeves with ears or without ears. The semicircular steel sleeve with ears needs to be welded with connecting ears with bolt holes at both ends, and the circular steel sleeve without ears is fastened by symmetrical welding; the combined steel sleeve 6 is made of welded steel pipe or combined sleeve, and its diameter is 1~2 specifications larger than the diameter of the pipeline; the wedge-shaped pair of clamps is composed of equal-height wedge-shaped outer clamps 7 and inner clamps 8; the pressure plate 5 is arranged between the steel sleeve and the bracket. The plate penetration sleeve 2 is placed between the floor 1 and the bracket 4 , and the plate penetration sleeve 2 is 1 to 2 specifications larger than the diameter of the pipe 3 .

[0024] The material of the clip includes two finished materials: hard plastic rubber clip or metal clip; the total thickness of the inner and outer clips after the two ends are flush and overlapped is not less than 1.15 times the difference between the inner diameter of the sleeve and the outer diameter of the pipe. The hard plastic rubber clip is made of artificial synthetic chloroprene rubber or vulcanized natural rubber.

[0025] The method of unloading the fire riser using the unloading device of the utility model is carried out in the following order: pre-embedding of the plate-penetrating sleeve, bracket installation, adjustment - pressure plate installation - pre-penetration of the steel sleeve - segmented installation of the pipeline, adjustment - setting of the clip - adding pre-pressure - connection of the pipeline port; the key steps include:

[0026] 1) Pre-buried bushing: Figure 3 As shown, the through-plate sleeve 2 is pre-buried according to the position of the drawing before pouring concrete, ensuring that the pre-buried position of the through-plate sleeve 2 is concentric with the installation of the fire protection pipe. The fireproof plugging of the pipe 3 passing through the floor sleeve 1 is implemented from the bottom of the board.

[0027] 2) Bracket installation and adjustment: according to the number and diameter of fire risers, the unloading load value of components, the design load value of floor 1, the installation space of bracket 4 and the diameter of casing. Bracket 4 is a conductive part for pipeline 3 to unload to the floor. Bracket 4 is composed of steel profiles. The steel profiles can be selected from steel square tubes, steel rectangular tubes, channel steels, I-beams, H-beams, etc. of different models and specifications.

[0028] 3) Pressure plate installation: The thickness of the pressure plate 5 shall not be less than 1.5 times the thickness of the pipe wall; the side length of the pressure plate 5 shall be the outer dimension of the bracket or not less than the outer dimension of the bracket minus half of the width of the pressure plate 5 supporting profile; the inner space of the pressure plate 5 shall be a circular hole, such as Figure 1 shown.

[0029] 4) Pre-piercing of steel sleeve: When the diameter of the pipe 3 is small, select a steel sleeve 6 with a diameter one size larger; when the diameter of the pipe 3 is large, select a steel sleeve 6 with a diameter two sizes larger. The height of the steel sleeve 6 shall not be less than 2 / 3 of the diameter of the pipe 3.

[0030] 5) Set the clips: first set the outer clip 7, then set the inner clip 8. The number of clips set in the steel sleeve is determined according to the diameter of the pipe; when the pipe diameter is less than 200mm, set 2~3 groups of clips; when the pipe diameter is greater than 200mm, set 3~5 groups of clips; the sum of the widths of each group of clips shall not be less than 2 / 3 of the circumference of the outer diameter of the pipe, and the clips shall be evenly spaced and evenly spaced.

Claims

1. A super high-rise vertical pipeline unloading device, characterized in that: It includes a bracket, an anchor, a pressure plate, and a through-plate sleeve; the bracket is a single bracket or a combined bracket, the single bracket is formed by welding four steel sections, and the combined bracket is formed by welding multiple steel sections, a force-transmitting steel section is arranged in the middle of the bracket, and a supporting steel leg is arranged at the lower part of the bracket; the anchor includes a combined steel sleeve and a wedge-shaped pair of clamps, the combined steel sleeve is composed of two symmetrical semicircular sleeves with ears or without ears, the semicircular steel sleeve with ears needs to be welded with connecting ears with bolt holes at both ends, and the circular steel sleeve without ears is fastened by symmetrical welding; the combined steel sleeve is made of welded steel pipe or combined sleeve, the diameter of the steel sleeve is 1~2 specifications larger than the diameter of the pipeline, and the height is not less than 2 / 3 of the diameter of the pipeline; the wedge-shaped pair of clamps is composed of equal-height wedge-shaped outer clamps and inner clamps; the pressure plate is arranged between the steel sleeve and the bracket; the through-plate sleeve is placed between the floor slab and the bracket, and the through-plate sleeve is 1~2 specifications larger than the diameter of the pipeline.

2. The super high-rise vertical pipeline unloading device according to claim 1 is characterized in that: The number of groups of clips arranged in the steel sleeve is determined according to the diameter of the pipeline: when the pipeline diameter is less than 200mm, 2 to 3 groups of clips are arranged; when the pipeline diameter is greater than 200mm, 3 to 5 groups of clips are arranged; the sum of the widths of each group of clips is not less than 2 / 3 of the circumference of the outer diameter of the pipeline, and the clips are arranged at equal intervals.

3. The super high-rise vertical pipeline unloading device according to claim 1 is characterized in that: The materials of the clips include hard plastic rubber clips or metal clips; the total thickness of the inner and outer clips after the two ends are flush and overlapped is not less than 1.15 times the difference between the inner diameter of the sleeve and the outer diameter of the pipe.

4. The super high-rise vertical pipeline unloading device according to claim 1 is characterized in that: The thickness of the pressure plate is 1.5 times the thickness of the pipe wall; the side length of the pressure plate is the outer dimension of the bracket or not less than the outer dimension of the bracket minus half of the width of the pressure plate support profile; the inner cavity of the pressure plate is circular, and the diameter of the inner cavity of the pressure plate is controlled between (D+20) and (D+40), where D is the pipe diameter.

Citation Information

Cited By

  • Super high-rise vertical pipeline unloading device and unloading method

    CN118066370A