Geothermal heating system based on gravity assisted heat pipe

By setting up a medium heat exchange structure and heat exchange inner tube at the wellhead, using the heat pipe heat exchange device to collect heat in the well, combining sealed docking components and pipe bundle installation components, the difficulty of burying heat exchange pipes at the bottom of the well is solved, and efficient and convenient Geothermal heat extraction system reduces heat loss and installation complexity.

CN222027164UActive Publication Date: 2024-11-19TIANJIN SHIJI TIANYUAN GRP CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420086380.4
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-01-15
Publication Date
2024-11-19
Estimated Expiration
2034-01-15

AI Technical Summary

Technical Problem

The existing geothermal heat extraction system has a large weight and high cost in high temperature environments, and PE pipelines are prone to deformation and damage, and heat exchange pipelines need to be buried at the bottom of the well, resulting in troubles in installation and maintenance.

Method used

Design a geothermal heat extraction system based on gravity heat pipes. By setting up a medium heat exchange structure and heat exchange inner tube at the wellhead, heat transfer device is used to collect heat in the well, and the installation efficiency is improved through sealing docking components and pipe bundle installation components. Stability, avoid heat exchange pipes buried at the bottom of the well.

Benefits of technology

The purpose of taking heat and not water at the wellhead position is achieved, which reduces heat loss, facilitates daily maintenance, improves work efficiency and the stability of gravity heat pipe docking, and simplifies the installation process.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222027164U_ABST
    Figure CN222027164U_ABST
Patent Text Reader

Abstract

The utility model relates to a geothermal heating system based on a gravity assisted heat pipe. Comprising a wellhead cover plate, a medium heat exchange structure is installed on the wellhead cover plate in a penetrating mode, a medium backflow port and a medium outlet are connected to the medium heat exchange structure, and an overground user is installed between the medium backflow port and the medium outlet; a heat pipe heat exchange device is arranged in an inner cavity of the heat exchange inner pipe; the lower port of the heat exchange inner pipe is communicated and connected with a water feeding pipe and a water taking pump body; a sealing piece supporting piece is installed between the heat exchange inner pipe and the well pipe, and an inner cavity of the well pipe is divided into a water return cavity and a water storage cavity. The heat pipe heat exchange device comprises a plurality of sets of pipe bundle installation assemblies, a plurality of sets of butt joint sleeves are installed between every two adjacent sets of pipe bundle installation assemblies, a plurality of sets of gravity assisted heat pipes are arranged in all the pipe bundle installation assemblies in a penetrating mode, and the heat pipe heat exchange device further comprises sealing butt joint assemblies installed between the butt joint sleeves which are in butt joint. The purpose of taking heat without taking water can be achieved without burying a heat exchange pipeline at the bottom of the well, the working efficiency is high, and daily maintenance is facilitated.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model belongs to the technical field of geothermal facilities, and in particular relates to a geothermal heat extraction system based on gravity heat pipes. Background Art

[0002] As the energy stored in the earth itself, geothermal energy is a renewable energy source. The temperature of geothermal energy in the middle and deep layers is higher than that in the lower layers, and can be used in production and life such as power generation and house heating. Compared with traditional energy sources such as coal and oil, geothermal energy is clean and can be reused repeatedly, and is a renewable resource.

[0003] Geothermal energy utilization can be divided into two forms: groundwater extraction and heat extraction without water extraction. Among them, groundwater extraction heating technology uses geothermal water wells for heating. When the groundwater temperature is high, it can be directly heated. When the temperature is low, heat pumps can be used for heating. The advantages are: simple process, low cost, and high energy efficiency; the disadvantages are: it causes the groundwater level to drop, the ground to sink, and the formation of ground fissures. It is also difficult to recharge groundwater. A large amount of groundwater that cannot be recharged is discharged into the urban drainage network, which seriously wastes water resources. When extracting groundwater, the water pump needs to overcome the height difference between the well water surface and the ground heat pump unit, resulting in excessive pump power and high operating costs. The heat extraction without water extraction geothermal energy heating technology is to bury the heat exchange casing, that is, to directly extend the heat exchange pipe into the high-temperature rock environment, and extract the heat from the geothermal water through the medium circulating in the heat exchange pipe.

[0004] At present, most technologies use metal pipes for burial, but metal is heavy, difficult to install, and expensive. Another method is to use PE pipes. PE pipes are light, low-cost, and easy to install. However, in high temperature environments, the life and performance of PE pipes will change. Too long PE pipes have poor bearing capacity and are more likely to deform and damage closer to the bottom. Therefore, in view of this situation, it is urgent to develop a new geothermal heating system to meet the needs of actual use. Utility Model Content

[0005] The utility model provides a geothermal heat extraction system based on gravity heat pipes with a reasonable structural design to solve the technical problems existing in the known technology. The utility model can achieve the purpose of extracting heat without taking water without burying heat exchange pipes at the bottom of the well, and has high work efficiency and is convenient for daily maintenance.

[0006] The utility model adopts the following technical solutions to solve the technical problems existing in the known technologies: a geothermal heat extraction system based on gravity heat pipes includes a wellhead cover plate arranged at the wellhead position at the upper end of the well pipe, a medium heat exchange structure is installed through the wellhead cover plate, a medium return port and a medium outlet are connected to the medium heat exchange structure, and a ground user is installed between the medium return port and the medium outlet; it also includes a heat exchange inner pipe arranged in the well pipe, located below the medium heat exchange structure and with a gap matching with the medium heat exchange structure, a heat pipe heat exchange device is arranged in the inner cavity of the heat exchange inner pipe, and the upper end of the heat pipe heat exchange device extends to the inner cavity of the medium heat exchange structure; The lower port is connected to the upper water pipe, and a water intake pump body is installed at the lower port of the upper water pipe; a sealing support is installed between the heat exchange inner tube and the well pipe to divide the inner cavity of the well pipe into a return water chamber located above and a water storage chamber located below; a number of through holes connected to the return water chamber are opened on the well pipe; the heat pipe heat exchange device includes a plurality of tube bundle installation components connected by flanges, a plurality of butt-jointed sleeves are installed between two adjacent tube bundle installation components, a plurality of gravity heat pipes are inserted in each tube bundle installation component, and a sealing butt joint component is installed between the butt joint sleeves for sealing and connecting the two butt joint gravity heat pipes.

[0007] The advantages and positive effects of the utility model are as follows: the utility model provides a geothermal heat extraction system based on a gravity heat pipe. By setting a heat exchange inner pipe and a heat pipe heat exchange device arranged in the heat exchange inner pipe, heat collection operation can be performed on geothermal water pumped into the heat exchange inner pipe, and the purpose of extracting heat without extracting water can be achieved without burying a heat exchange pipeline at the bottom of the well; by setting a medium heat exchange structure, the heat transferred by the heat pipe heat exchange device can be absorbed, and the heat can be transmitted to the ground users for utilization. The medium heat exchange structure is close to the wellhead of the geothermal well, which is convenient for daily maintenance and reduces heat loss; the sealing docking assembly arranged in the heat pipe heat exchange device makes it more convenient and quick to dock and install multiple groups of gravity heat pipes, and can effectively improve the stability of the gravity heat pipe docking point and avoid affecting the sealing of the gravity heat pipe docking point; by setting a tube bundle installation assembly, multiple gravity heat pipes can be installed in a tube bundle, which improves the work efficiency of the geothermal well heat extraction operation of the utility model and is convenient for daily maintenance.

[0008] Preferably, the tube bundle installation assembly comprises two sets of installation flanges arranged opposite to each other, and a plurality of sets of water-permeable pipe sleeves distributed in the circumferential direction are connected between the two sets of installation flanges; and a plurality of water-permeable holes are provided on each of the water-permeable pipe sleeves.

[0009] Preferably: the sealed docking assembly includes two groups of sealing sleeves that are butt-connected, each sealing sleeve is a semicircular cylindrical structure; it also includes a clamping ring sleeved on the ends of the two butt-connected groups of gravity heat pipes, each clamping ring is respectively clamped with an annular groove opened on the inner wall of each sealing sleeve, and a clamping sealing gasket is arranged between the clamping ring and the annular groove.

[0010] Preferably: an inserting protrusion and an inserting groove which is plugged and matched with the inserting protrusion are arranged on the butt joint side surface of each sealing sleeve, and also includes a butt joint sealing ring arranged between the butt joint surfaces of the two groups of sealing sleeves.

[0011] Preferably, the heat pipe heat exchange device further comprises a plurality of fins installed at the upper end of the gravity heat pipe.

[0012] Preferably: the medium heat exchange structure includes a medium outer tube penetrating the wellhead cover plate, a sealing top plate fixedly connected to the top of the medium outer tube, and also includes a medium inner tube arranged in the inner cavity of the medium outer tube and fixedly connected to the sealing top plate, a channel for heat exchange medium to flow is arranged between the lower end of the medium inner tube and the bottom surface of the medium outer tube; the outer peripheral wall of the medium inner tube and the inner peripheral wall of the medium outer tube constitute a reflux channel for circulating the heat exchange medium; the medium reflux port is connected to the reflux channel, and the medium outlet is connected to the inner cavity of the medium inner tube.

[0013] Preferably: the ground users include a heat pump unit, users and a circulating water pump.

[0014] Preferably, a thermal insulation layer is provided on the outer walls of the inner heat exchange tube and the outer medium tube. BRIEF DESCRIPTION OF THE DRAWINGS

[0015] Figure 1 It is a schematic diagram of the main cross-sectional structure of the utility model;

[0016] Figure 2 It is a schematic diagram of the main cross-sectional structure of the heat pipe heat exchange device in the utility model;

[0017] Figure 3 yes Figure 2 A schematic diagram of the enlarged area in FIG.

[0018] Figure 4 It is a schematic diagram of the exploded structure of the sealing docking assembly in the utility model;

[0019] Figure 5 It is a three-dimensional structural schematic diagram of the heat pipe heat exchange device in the utility model;

[0020] Figure 6 It is a three-dimensional structural schematic diagram of the tube bundle installation assembly in the utility model.

[0021] In the figure: 1, water pump body; 2, water supply pipe; 3, water storage chamber; 4, heat pipe heat exchange device; 4-1, fin; 4-2, gravity heat pipe; 4-3, water permeable hole; 4-4, sealing docking assembly; 4-4-1, sealing sleeve; 4-4-2, clamping ring; 4-4-3, clamping sealing gasket; 4-4-4, plug-in protrusion; 4-4-5, plug-in groove; 4-4-6, docking sealing ring; 4-5, tube bundle installation assembly; 4-5- 1. Mounting flange; 4-5-2. Permeable pipe sleeve; 4-6. Butt sleeve; 5. Well pipe; 6. Sealing support; 7. Heat exchange inner pipe; 8. Insulation layer; 9. Spiral baffle; 10. Return water chamber; 11. Medium outer pipe; 12. Medium inner pipe; 13. Reflux channel; 14. Sealing top plate; 15. Wellhead cover; 16. Medium reflux port; 17. Medium outlet; 18. Circulating water pump; 19. Heat pump unit; 20. User. DETAILED DESCRIPTION

[0022] In order to further understand the content, features and effects of the present invention, the following embodiments are described in detail as follows:

[0023] See also Figure 1 The geothermal heat extraction system based on gravity heat pipe of the utility model includes a wellhead cover plate 15 arranged at the wellhead position of the upper end of the well pipe 5, and a medium heat exchange structure is installed through the wellhead cover plate 15. Among them, the medium heat exchange structure includes a medium outer tube 11 penetrating the wellhead cover plate 15, a sealing top plate 14 is fixedly connected to the top of the medium outer tube 11, and also includes a medium inner tube 12 fixedly connected to the sealing top plate 14 and arranged coaxially in the inner cavity of the medium outer tube 11, and a channel for heat exchange medium to flow is arranged between the lower end of the medium inner tube 12 and the bottom surface of the medium outer tube 11; in addition, in this embodiment, the outer peripheral wall of the medium inner tube 12 and the inner peripheral wall of the medium outer tube 11 constitute a reflux channel 13 for circulating the heat exchange medium.

[0024] like Figure 1 As shown, this embodiment also includes a medium return port 16 and a medium outlet 17 connected to the medium heat exchange structure, and a ground user is installed between the medium return port 16 and the medium outlet 17. The medium return port 16 is connected to the return channel 13, and the medium outlet 17 is connected to the inner cavity of the medium inner tube 12.

[0025] In this embodiment, the above-mentioned ground user is a prior art, mainly including a heat pump unit 19, a user 20 and a circulating water pump 18. The medium outlet 17 is connected to the water inlet of the user 20 through the heat pump unit 19, the water outlet of the user 20 is connected to the medium return port 16 through the heat pump unit 19, and the circulating water pump 18 is arranged between the medium return port 16 and the heat pump unit 19.

[0026] like Figure 1As shown, this embodiment also includes a heat exchange inner tube 7 disposed in the well pipe 5, which is located below the medium outer tube 11 in the medium heat exchange structure and has a clearance fit therewith. A heat pipe heat exchange device 4 is disposed in the inner cavity of the heat exchange inner tube 7, and the upper end of the heat pipe heat exchange device 4 extends to the inner cavity of the medium heat exchange structure and is sealed therewith. In order to slow down the upward flow speed of the geothermal water in the heat exchange inner tube 7, a spiral baffle 9 is installed on the inner peripheral wall of the heat exchange inner tube 7. The lower port of the heat exchange inner tube 7 is connected to the upper water pipe 2, and the water intake pump body 1 is installed at the lower port of the upper water pipe 2;

[0027] In order to prevent the heat loss caused by the geothermal water in the process of flowing upward, a thermal insulation layer 8 is provided on the outer wall of the heat exchange inner tube 7 and the medium outer tube 11 .

[0028] In addition, if Figure 1 As shown, a sealing member support 6 is installed between the heat exchange inner tube 7 and the well pipe 5, dividing the inner cavity of the well pipe 5 into a return water chamber 10 located at the top and a water storage chamber 3 located at the bottom. A plurality of through holes connected to the return water chamber 10 are provided on the well pipe 5. Through the above arrangement, it is convenient for the water pump body 1 to extract geothermal water containing a large amount of heat, so that the geothermal water flows upward along the upper water pipe 2 and the heat exchange inner tube 7. In the process of flowing upward, heat is extracted through the heat pipe heat exchange device 4, and flows out to the return water chamber 10 at the upper port of the heat exchange inner tube 7, so as to realize the reinjection of geothermal water.

[0029] like Figure 2 and Figure 3 As shown, in this embodiment, the heat pipe heat exchange device 4 includes a plurality of tube bundle installation components 4-5 connected by flanges, a plurality of butt sleeves 4-6 butt-connected are installed between two adjacent tube bundle installation components 4-5, a plurality of gravity heat pipes 4-2 are inserted in each tube bundle installation component 4-5, and a sealing butt assembly 4-4 is installed between the butt sleeves 4-6 for sealingly connecting the two butt gravity heat pipes 4-2.

[0030] like Figure 5 and Figure 6 As shown, in this embodiment, the above-mentioned tube bundle installation component 4-5 includes two sets of mounting flanges 4-5-1 arranged opposite to each other, and a plurality of sets of water-permeable pipe sleeves 4-5-2 distributed in a circumferential direction are connected and communicated between the two sets of mounting flanges 4-5-1; a plurality of water-permeable holes 4-3 are opened on the outer peripheral wall of each water-permeable pipe sleeve 4-5-2; the above-mentioned plurality of gravity heat pipes 4-2 are respectively inserted into the corresponding water-permeable pipe sleeves 4-5-2, and the two sets of gravity heat pipes 4-2 arranged coaxially between two different water-permeable pipe sleeves 4-5-2 are sealed and connected through the sealing docking component 4-4.

[0031] See also Figure 3 and Figure 4 In this embodiment, the sealing docking assembly 4-4 includes two sets of sealing sleeves 4-4-1 that are docked and connected, and each sealing sleeve 4-4-1 is a semicircular cylindrical structure. A plug-in protrusion 4-4-4 and a plug-in groove 4-4-5 that plugs with the plug-in protrusion 4-4-4 are provided on the docking side surface of each sealing sleeve 4-4-1, and a docking sealing ring 4-4-6 is provided between the docking surfaces of the two sets of sealing sleeves 4-4-1.

[0032] The sealed docking assembly 4-4 also includes a clamping ring 4-4-2 sleeved on the ends of the two docked groups of gravity heat pipes 4-2, each clamping ring 4-4-2 is respectively clamped with an annular groove opened on the inner wall of each sealing sleeve 4-4-1, and a clamping sealing gasket 4-4-3 is arranged between the clamping ring 4-4-2 and the annular groove. The heat pipe heat exchange device 4 also includes a plurality of fins 4-1 installed on the upper end of the gravity heat pipe 4-2.

[0033] Through the above arrangement, one end of the gravity heat pipe 4-2 can be butted against the end of another gravity heat pipe 4-2 and sealed, thereby avoiding the use of traditional welding connection methods or directly plugging one gravity heat pipe into another gravity heat pipe, ensuring the stability of the gravity heat pipe connection, avoiding the phenomenon of the gravity heat pipe falling off and separating, and avoiding the formation of holes at the welding position during the welding process.

[0034] When installing multiple groups of gravity heat pipes 4-2, multiple gravity heat pipes 4-2 are sequentially inserted into the water-permeable pipe sleeve 4-5-2. When docking two corresponding gravity heat pipes 4-2, one end of the gravity heat pipe 4-2 is docked with another gravity heat pipe 4-2, and then the sealing sleeve 4-4-1 is attached to the outer wall of one end of the gravity heat pipe 4-2, and the clamping ring 4-4-2 is inserted into the inside of the annular groove. The two gravity heat pipes 4-2 can be connected by the two sealing sleeves 4-4-1, the clamping ring 4-4-2 and the annular groove. The heat pipes 4-2 are docked; the above operations are repeated to realize the sealed docking installation of the two gravity heat pipes 4-2 located in the corresponding two permeable pipe sleeves 4-5-2, and then the tube bundle installation assembly 4-5 penetrated with the above gravity heat pipes 4-2 is docked and installed by means of screws and locking nuts. At this time, the sealed docking assembly 4-4 arranged between the two docked gravity heat pipes 4-2 is located in the space formed by the two docking sleeves 4-6; the above operations are repeated to realize the assembly of the heat pipe heat exchange device 4. By setting the sealed docking assembly 4-4, it is not only more convenient and quick to dock the gravity heat pipes 4-2, but also the stability of the docking point of the gravity heat pipes 4-2 can be effectively improved, and the sealing of the docking point of the gravity heat pipes 4-2 can be avoided; by setting the tube bundle installation assembly 4-5, multiple gravity heat pipes 4-2 can be installed in a tube bundle, which improves the working efficiency of the geothermal well heat extraction operation of the utility model.

[0035] Through the above arrangement, a plurality of gravity heat pipes 4 - 2 coaxially sealed and butted together form a whole long gravity heat pipe, in which the evaporation section is located in the heat exchange inner tube 7 , and the condensation section is located in the medium heat exchange structure.

[0036] Working principle:

[0037] The geothermal water enters the water storage chamber 3 from the lower port of the well pipe 5, and the geothermal water in the water storage chamber 3 is pumped into the upper water pipe 2 under the action of the water pump body 1. Under the action of the water pump body 1, the geothermal water entering the upper water pipe 2 flows upward into the heat exchange inner pipe 7, and flows upward along the heat exchange inner pipe 7. During the flow process, the heat pipe heat exchange device 4 in the heat exchange inner pipe 7 can extract the heat in the geothermal water and release the absorbed heat to the medium heat exchange structure, that is, the working medium evaporation section in the long gravity heat pipe composed of multiple gravity heat pipes 4-2 absorbs heat to form steam, and the steam rises along the pipeline of the heat pipe to the condensation section. The liquid working medium after heat release and condensation flows back to the evaporation section along the pipe walls on both sides under the action of gravity, and the cycle repeats to achieve heat transfer. The geothermal water that completes the heat exchange flows out from the upper end of the heat exchange inner pipe 7 and flows into the return water chamber 10, and flows out through a number of through holes opened on the well pipe 5 and connected to the return water chamber 10, so as to achieve the recharging of the geothermal water;

[0038] After the long gravity heat pipe composed of multiple gravity heat pipes 4-2 in the heat pipe heat exchange device 4 absorbs the heat in the geothermal water, it releases the heat into the medium inner tube 12 in the medium heat exchange structure. The working medium in the medium inner tube 12 absorbs the heat to form steam and flows along the medium inner tube 12 to the medium outlet 17, and then flows into the heat pump unit 19 through the medium outlet 17 for heat exchange, and then transmits the heat to the user 20 for utilization. The working medium after heat exchange in the heat pump unit 19 flows toward the medium return port 16, and flows into the return channel 13 through the medium return port 16, and flows into the medium inner tube 12 at the lower end of the return channel 13, and the heat is transferred by repeating the cycle.

Claims

1. A geothermal heat extraction system based on gravity heat pipes, characterized by: The invention comprises a wellhead cover plate (15) arranged at the wellhead position of the upper end of the well pipe (5), a medium heat exchange structure is installed through the wellhead cover plate (15), a medium return port (16) and a medium outlet (17) are connected to the medium heat exchange structure, and an above-ground user is installed between the medium return port (16) and the medium outlet (17); the invention also comprises a heat exchange inner tube (7) arranged in the well pipe (5) and located below the medium heat exchange structure and having a clearance fit therewith, a heat pipe heat exchange device (4) is arranged in the inner cavity of the heat exchange inner tube (7), and the upper end of the heat pipe heat exchange device (4) extends to the inner cavity of the medium heat exchange structure; the lower end of the heat exchange inner tube (7) is connected to the upper water pipe (2), and the lower end of the upper water pipe (2) is installed with a water intake pump body (1); A sealing member support (6) is installed between the hot inner tube (7) and the well pipe (5), dividing the inner cavity of the well pipe (5) into a return water chamber (10) located at the top and a water storage chamber (3) located at the bottom; a plurality of through holes communicating with the return water chamber (10) are opened on the well pipe (5); the heat pipe heat exchange device (4) comprises a plurality of tube bundle installation assemblies (4-5) connected by flanges, a plurality of butt-joint sleeves (4-6) are installed between two adjacent tube bundle installation assemblies (4-5), a plurality of gravity heat pipes (4-2) are inserted in each tube bundle installation assembly (4-5), and a sealing butt joint assembly (4-4) is installed between the butt joint sleeves (4-6) for sealingly connecting the two butt joint gravity heat pipes (4-2).

2. The geothermal heat extraction system based on gravity heat pipe according to claim 1, characterized in that: The tube bundle installation assembly (4-5) comprises two sets of installation flanges (4-5-1) arranged opposite to each other, and a plurality of sets of water-permeable pipe sleeves (4-5-2) distributed in a circumferential direction are connected between the two sets of installation flanges (4-5-1); each water-permeable pipe sleeve (4-5-2) is provided with a plurality of water-permeable holes (4-3).

3. The geothermal heat extraction system based on gravity heat pipe according to claim 2, characterized in that: The sealing docking assembly (4-4) comprises two sets of sealing sleeves (4-4-1) that are butt-connected, each sealing sleeve (4-4-1) being a semicircular cylindrical structure; and also comprises a clamping ring (4-4-2) sleeved on the ends of the two butt-connected gravity heat pipes (4-2), each clamping ring (4-4-2) being respectively clamped with an annular groove provided on the inner wall of each sealing sleeve (4-4-1), and a clamping sealing gasket (4-4-3) being provided between the clamping ring (4-4-2) and the annular groove.

4. The geothermal heat extraction system based on gravity heat pipe according to claim 3 is characterized in that: The butt joint side surfaces of each sealing sleeve (4-4-1) are provided with a plugging protrusion (4-4-4) and a plugging groove (4-4-5) pluggably matched with the plugging protrusion (4-4-4), and also include a butt joint sealing ring (4-4-6) provided between the butt joint surfaces of the two sets of sealing sleeves (4-4-1).

5. The geothermal heat extraction system based on gravity heat pipe according to claim 4, characterized in that: The heat pipe heat exchange device (4) also includes a plurality of fins (4-1) installed on the upper end of the gravity heat pipe (4-2).

6. The geothermal heat extraction system based on gravity heat pipe according to claim 1, characterized in that: The medium heat exchange structure comprises a medium outer tube (11) penetrating a wellhead cover plate (15), a sealing top plate (14) fixedly connected to the top of the medium outer tube (11), and a medium inner tube (12) arranged in the inner cavity of the medium outer tube (11) and fixedly connected to the sealing top plate (14), a channel for heat exchange medium to flow is arranged between the lower end of the medium inner tube (12) and the bottom surface of the medium outer tube (11); the outer peripheral wall of the medium inner tube (12) and the inner peripheral wall of the medium outer tube (11) form a reflux channel (13) for circulating the heat exchange medium; a medium reflux port (16) is connected to the reflux channel (13), and a medium outlet (17) is connected to the inner cavity of the medium inner tube (12).

7. The geothermal heat extraction system based on gravity heat pipe according to claim 1, characterized in that: The ground user includes a heat pump unit (19), a user (20) and a circulating water pump (18).

8. The geothermal heat extraction system based on gravity heat pipe according to claim 6, characterized in that: A thermal insulation layer (8) is provided on the outer walls of the heat exchange inner tube (7) and the medium outer tube (11).