Large-size special-shaped bearing platform construction system for complex riverbed
By using technical means such as cofferdam, operating platform, stable support and detachable steel bar tying frame in water-based bearing construction, the concrete cracking problem caused by temperature difference in water-based bearing construction is solved, and the support formwork and steel bars are realized The efficiency and safety of binding ensure the stability and structural performance of concrete pouring.
Patent Information
- Application Number
- CN202420752026.0
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-04-12
- Publication Date
- 2024-12-03
- Estimated Expiration
- 2034-04-12
AI Technical Summary
In bridge projects, the temperature difference caused by concrete pouring during the construction of the water-based bearing platform leads to concrete cracking and affects structural performance. Especially in the construction of large-volume special-shaped bearing platform of complex riverbeds, the technical problems of formwork support, steel bar binding and temperature control. Need to be solved urgently.
Using cofferdam, operating platform, stable bracket, detachable steel bar binding tire frame and mobile platform casting platform, combined with fixed steel molds, cooling water pipes and temperature sensors, formwork support, steel bar binding and temperature are achieved through steel sheet piles and guide rails. Control to ensure the stability and safety of concrete pouring.
It effectively solves the problem of supporting the formwork, improves the accuracy and efficiency of steel bars, ensures the safety of concrete pouring, and avoids the negative impact of concrete hydration heat through the cooling system, and improves the service performance of the structure.
Smart Images

Figure CN222100932U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the field of underwater pedestal construction, in particular to a large-volume special-shaped pedestal construction system for a complex riverbed. Background Art
[0002] In bridge engineering, the cap is an important part of the bridge structure, which plays the role of connecting the pile foundation and the pier and transferring the load on the pier. In actual construction, the cap is often large in size (up to 2000m 3 ), and the construction is carried out in the form of on-site pouring. The important problem faced by large-volume concrete construction is that cement hydration during concrete pouring causes a large temperature difference between the inner and outer surfaces of the concrete, which can easily lead to concrete cracking, thereby affecting the service performance of concrete components and structures. In view of the complex shape and large volume of the underwater pedestal, it is urgent to innovate a construction system for large-volume special-shaped pedestals in complex riverbeds to solve technical problems such as large-volume special-shaped pedestal formwork support, in-situ steel bar binding, and temperature control. Utility Model Content
[0003] The utility model aims to overcome the deficiencies in the prior art and provide a large-volume special-shaped bearing platform construction system for a complex riverbed.
[0004] This complex riverbed large-volume special-shaped foundation construction system includes a cofferdam, an operating platform, a stabilizing bracket, a detachable steel bar binding frame and a mobile foundation casting platform; steel sheet piles are arranged on the inner side of the cofferdam, and there is a pile foundation inside the cofferdam. The operating platform is fixed on the pile foundation through a corbel bracket, and a concrete cushion layer is cast on the operating platform; the stabilizing bracket is used to cut off the pile head of the pile foundation;
[0005] The formwork of the cap includes a fixed steel formwork, which is set on the concrete cushion layer. The steel sheet pile supports the fixed steel formwork outside the cap through the steel profile. There are two fixed steel forms inside the cap, and the gap between the two fixed steel forms inside the cap forms a post-casting strip.
[0006] The detachable steel bar tying frame is installed at the designed position of the pedestal and is used to tie the pedestal steel frame. Cooling water pipes and temperature sensors are installed on the pedestal steel frame. The cooling water pipes are connected to the steel casing circulation cooling system outside the pedestal. Guide rails are set on the steel sheet piles on both sides of the cofferdam, and the mobile pedestal casting platform is moved in a directed manner along the guide rails through pulleys.
[0007] Preferably, a corbel bracket is welded on the upper part of the pile foundation, an I-beam is supported on the upper part of the corbel bracket to form a support system, and an operating platform is arranged on the upper part of the support system.
[0008] Preferably, there are also a hanging basket and a lifting device; a stabilizing bracket is arranged on a concrete cushion layer outside the pile head to be cut; oblique connecting rods are arranged at the four corners of the stabilizing bracket, arc supports are welded at the ends of the oblique connecting rods, and the stabilizing bracket clamps and stabilizes the pile head by means of the arc supports; after the pile head is cut off, a cut pile head is formed, and the cut pile head is placed in a hanging basket, and a lifting lug is welded on the upper part of the hanging basket, and the lifting lug is connected to the lifting device by a steel wire rope.
[0009] Preferably, the steel sheet piles are provided with corbel brackets facing the shaping steel formwork, and steel sections are welded on the corbel brackets, with the two sides of the steel sections respectively pressing against the outside of the steel sheet piles and the outside of the shaping steel formwork; corbel brackets are welded at intervals on both sides of the supporting steel frame, and vertical steel plates are provided at the ends of the corbel brackets, which are supported on the shaping steel formwork on both sides of the post-casting strip.
[0010] Preferably, the detachable steel bar binding tire frame includes a first tire frame and a second tire frame, the first tire frame and the second tire frame are symmetrically arranged on both sides of the base, and the first tire frame and the second tire frame are connected as a whole through a longitudinal tooth plate; the first tire frame and the second tire frame both include a triangular support, a bottom transverse tooth plate, a top transverse tooth plate and a vertical support rod; the bottom transverse tooth plate and the top transverse tooth plate are provided with tooth grooves for the longitudinal steel bar binding and positioning of the base; the longitudinal tooth plate is provided with tooth grooves for the transverse steel bar binding and positioning of the base; reserved holes are provided at both ends of the bottom transverse tooth plate and the top transverse tooth plate, and two vertical support rods are respectively inserted into the reserved holes to fix the bottom transverse tooth plate and the top transverse tooth plate up and down, and the triangular support is arranged on the outside of the two vertical support rods.
[0011] Preferably, the cooling water pipe is tied to the steel frame of the cap, and the cooling water pipe is arranged in a serpentine shape along the direction of the cap; the steel casing circulating cooling system includes an inlet steel casing, an outlet steel casing, a water distributor and a connecting pipe, and the inlet steel casing and the outlet steel casing are connected by a connecting pipe; the cooling water flows into the cooling water pipe through the water distributor, and the cooling water pipe flows back to the steel casing circulating cooling system through the return pipe.
[0012] Preferably, inner supports and surrounding purlins are provided in the steel sheet piles above the concrete cushion layer, and corbel brackets are provided on the inner sides of the steel sheet piles below the inner supports and the surrounding purlins. The movable cap casting platform includes a casting platform plate, pulleys, guide rails and cross beams; the guide rails are placed on the upper part of the steel sheet pile corbel brackets, pulleys are provided at the bottom of both ends of the cross beams, and the pulleys move in a directional manner along the guide rails; the casting platform plate is connected to the cross beams through vertical hangers, the upper ends of the vertical hangers are fixed above the cross beams with high-strength bolts, and the lower ends of the vertical hangers are fixed below the casting platform plate with high-strength bolts.
[0013] The beneficial effects of the utility model are:
[0014] 1) The utility model arranges a stable bracket on the concrete cushion layer outside the pile head, thereby ensuring the stability of the pile head removal and lifting.
[0015] 2) The utility model uses a shaped steel mold as the template of the foundation and solves the problem of supporting the foundation template by reserving a post-casting strip.
[0016] 3) The utility model provides a detachable steel bar binding frame in the cap casting area, which can perform in-situ binding, thereby improving the in-situ binding accuracy and efficiency of the cap steel bar skeleton.
[0017] 4) The utility model provides a movable cap casting platform under the cofferdam purlin and the inner support, which solves the problem of casting the cap concrete inside the cofferdam and ensures the safety of casting.
[0018] 5) The utility model arranges temperature sensors on the steel frame of the foundation to monitor the temperature changes inside the foundation in real time after pouring, and circulates water through cooling pipes to cool down, effectively avoiding the negative impact of the hydration heat of large-volume concrete. BRIEF DESCRIPTION OF THE DRAWINGS
[0019] Figure 1 This is a schematic diagram of the pile head stabilization operation platform;
[0020] Figure 2 yes Figure 1 A magnified image of area A;
[0021] Figure 3 is a schematic diagram of a stable support structure;
[0022] Figure 4 It is the BB cross-section;
[0023] Figure 5 This is a schematic diagram of the pile head being lifted off;
[0024] Figure 6 yes Figure 5 Enlarged view of area C in the middle;
[0025] Figure 7 This is a schematic diagram of the construction of the foundation template;
[0026] Figure 8 yes Figure 7 Enlarged view of area D in the middle;
[0027] Fig. 9 This is the overall schematic diagram of the detachable steel bar binding frame of the foundation;
[0028] Fig.10 This is a schematic diagram of the steel bar binding frame structure;
[0029] Fig.11 This is a schematic diagram of the intelligent temperature control of the platform;
[0030] Fig.12 It is a schematic diagram of cooling water pipe arrangement;
[0031] Fig.13It is a schematic diagram of a movable cap casting platform;
[0032] Fig.14 yes Fig.13 Enlarged view of area E.
[0033] In the figure: 1-pile foundation; 2-pile head; 3-cut pile head; 4-stable support; 5-operating platform; 6-I-beam; 7-corbel support; 8-concrete cushion; 9-oblique connecting rod; 10-arc support; 11-hanging basket; 12-lifting equipment; 13-lifting lug; 14-wire rope; 15-steel; 16-support steel frame; 17-shaped steel mold; 18-steel sheet pile; 19-vertical steel plate; 20-first tire frame; 21-longitudinal tooth plate; 22-second tire frame; 23- Triangular support; 24-bottom horizontal tooth plate; 25-top horizontal tooth plate; 26-tooth groove; 27-vertical support rod; 28-water inlet steel casing; 29-water outlet steel casing; 30-connecting pipe; 31-water distributor; 32-cap steel frame; 33-post-casting strip; 34-cooling water pipe; 35-temperature sensor; 36-high-strength bolt; 37-vertical hanger; 38-casting platform plate; 39-pulley; 40-guide rail; 41-inner support; 42-purlin; 43-crossbeam. DETAILED DESCRIPTION
[0034] The utility model is further described below in conjunction with the embodiments. The description of the following embodiments is only used to help understand the utility model. It should be pointed out that for ordinary people in this technical field, the utility model can also be modified in some ways without departing from the principle of the utility model, and these improvements and modifications also fall within the scope of protection of the claims of the utility model.
[0035] As an example, Figures 1 to 14 As shown, this complex riverbed large-volume special-shaped foundation construction system includes a cofferdam, an operating platform 5, a stable support 4, a detachable steel bar binding frame and a movable foundation casting platform; Figure 2 As shown, a steel sheet pile 18 is provided inside the cofferdam, a pile foundation 1 is provided inside the cofferdam, a corbel bracket 7 is welded on the upper part of the pile foundation 1, an operating platform 5 is fixed on the pile foundation 1 through the corbel bracket 7, and a concrete cushion layer 8 is poured on the operating platform 5;
[0036] like Figure 1 , Figures 3 to 6As shown, the stabilizing bracket 4 is used to cut off the pile head 2 of the pile foundation 1; there are also a hanging basket 11 and a lifting device 12; the stabilizing bracket 4 is arranged on the concrete cushion layer 8 outside the pile head 2 to be cut; the stabilizing bracket 4 is provided with oblique connecting rods 9 at the four corners, and arc supports 10 are welded at the ends of the oblique connecting rods 9, and the stabilizing bracket 4 uses the arc supports 10 to clamp and stabilize the pile head 2; after the pile head 2 is cut off, a cut pile head 3 is formed, and the cut pile head 3 is placed in the hanging basket 11, and a lifting lug 13 is welded on the upper part of the hanging basket 11, and the lifting lug 13 is connected to the lifting device 12 through a wire rope 14.
[0037] like Figure 7 As shown, the formwork of the pedestal includes a shaped steel formwork 17, which is arranged on the concrete cushion layer 8, and the steel sheet piles 18 support the shaped steel formwork 17 on the outside of the pedestal through the steel sections 15. The steel sheet piles 18 are provided with corbel brackets 7 facing the shaped steel formwork 17, and the steel sections 15 are welded on the corbel brackets 7. The two sides of the steel sections 15 are respectively pressed against the outside of the steel sheet piles 18 and the outside of the shaped steel formwork 17.
[0038] like Figure 8 As shown, two shaping steel molds 17 are also provided in the pedestal, and the gap between the two shaping steel molds 17 in the pedestal forms a post-casting strip 33; a supporting steel frame 16 is placed in the post-casting strip 33, and corbel brackets 7 are welded at intervals on both sides of the supporting steel frame 16, and vertical steel plates 19 are provided at the ends of the corbel brackets 7, and the vertical steel plates 19 are supported on the shaping steel molds 17 on both sides of the post-casting strip 33.
[0039] like Fig. 9 and Fig.10 As shown, the detachable steel bar binding frame is arranged at the design position of the pedestal, and is used for binding the steel frame 32 of the pedestal. The detachable steel bar binding frame includes a first frame 20 and a second frame 22, and the first frame 20 and the second frame 22 are symmetrically arranged on both sides of the pedestal, and the first frame 20 and the second frame 22 are connected as a whole through a longitudinal tooth plate 21; the first frame 20 and the second frame 22 both include a triangular support 23, a bottom transverse tooth plate 24, a top transverse tooth plate 25 and a vertical support rod 27; the bottom transverse tooth plate 24 and the top transverse tooth plate 25 are provided with tooth grooves 26 for binding and positioning the longitudinal steel bars of the pedestal; the longitudinal tooth plate 21 is provided with tooth grooves 26 for binding and positioning the transverse steel bars of the pedestal; reserved holes are provided at both ends of the bottom transverse tooth plate 24 and the top transverse tooth plate 25, and two vertical support rods 27 are respectively inserted into the reserved holes to fix the bottom transverse tooth plate 24 and the top transverse tooth plate 25 up and down, and the triangular support 23 is provided on the outside of the two vertical support rods 27.
[0040] like Fig.11 and Fig.12As shown, a cooling water pipe 34 and a temperature sensor 35 are installed on the cap steel frame 32. The cooling water pipe 34 is tied to the cap steel frame 32, and the cooling water pipe 34 is arranged in a serpentine shape along the cap. The cooling water pipe 34 is connected to a steel casing circulation cooling system outside the cap. The steel casing circulation cooling system includes an inlet steel casing 28, an outlet steel casing 29, a water distributor 31 and a connecting pipe 30. The inlet steel casing 28 and the outlet steel casing 29 are connected by a connecting pipe 30. The cooling water flows into the cooling water pipe 34 through the water distributor 31, and the cooling water pipe 34 flows back to the steel casing circulation cooling system through the reflux pipe.
[0041] like Fig.13 and Fig.14 As shown, the steel sheet piles 18 above the concrete cushion layer 8 are provided with inner supports 41 and purlins 42, and the inner sides of the steel sheet piles 18 on both sides of the cofferdam below the inner supports 41 and purlins 42 are provided with corbel brackets 7, and the movable cap casting platform includes a casting platform plate 38, pulleys 39, guide rails 40 and cross beams 43; the guide rails 40 are placed on the upper part of the corbel brackets 7 of the steel sheet piles 18, and pulleys 39 are provided at the bottom of both ends of the cross beam 43, and the pulleys 39 move in a directional manner along the guide rails 40; the casting platform plate 38 is connected to the cross beam 43 through a vertical hanger 37, and the upper end of the vertical hanger 37 is fixed with a high-strength bolt 36 above the cross beam 43, and the lower end of the vertical hanger 37 is fixed with a high-strength bolt 36 below the casting platform plate 38.
Claims
1. A complex riverbed large-volume special-shaped foundation construction system, characterized in that: It includes a cofferdam, an operating platform, a stabilizing bracket, a detachable steel bar binding frame and a movable cap casting platform; steel sheet piles are arranged inside the cofferdam, a pile foundation exists inside the cofferdam, the operating platform is fixed on the pile foundation through a corbel bracket, and a concrete cushion layer is cast on the operating platform; the stabilizing bracket is used to cut off the pile head of the pile foundation; The formwork of the cap includes a fixed steel formwork, which is set on the concrete cushion layer. The steel sheet pile supports the fixed steel formwork outside the cap through the steel profile. There are two fixed steel forms inside the cap, and the gap between the two fixed steel forms inside the cap forms a post-casting strip. The detachable steel bar tying frame is installed at the designed position of the pedestal and is used to tie the pedestal steel frame. Cooling water pipes and temperature sensors are installed on the pedestal steel frame. The cooling water pipes are connected to the steel casing circulation cooling system outside the pedestal. Guide rails are set on the steel sheet piles on both sides of the cofferdam, and the mobile pedestal casting platform is moved in a directed manner along the guide rails through pulleys.
2. The complex riverbed large-volume special-shaped foundation construction system according to claim 1 is characterized in that: A corbel bracket is welded on the upper part of the pile foundation, and an I-beam is supported on the upper part of the corbel bracket to form a supporting system, and an operating platform is arranged on the upper part of the supporting system.
3. The complex riverbed large-volume special-shaped foundation construction system according to claim 1 is characterized in that: There are also hanging baskets and lifting equipment; a stable support is arranged on a concrete cushion outside the pile head that needs to be cut; oblique connecting rods are arranged at the four corners of the stable support, arc supports are welded at the ends of the oblique connecting rods, and the stable support clamps and stabilizes the pile head by means of the arc supports; after the pile head is cut off, a cut pile head is formed, and the cut pile head is placed in a hanging basket, and a lifting lug is welded on the upper part of the hanging basket, and the lifting lug is connected to the lifting equipment by a steel wire rope.
4. The complex riverbed large-volume special-shaped platform construction system according to claim 1 is characterized in that: The steel sheet piles are provided with corbel brackets facing the shaping steel formwork, and steel sections are welded on the corbel brackets. The two sides of the steel sections are respectively pressed against the outside of the steel sheet piles and the outside of the shaping steel formwork; corbel brackets are welded at intervals on both sides of the supporting steel frame, and vertical steel plates are arranged at the ends of the corbel brackets, which are supported on the shaping steel formwork on both sides of the post-casting strip.
5. The complex riverbed large-volume special-shaped platform construction system according to claim 1 is characterized in that: The detachable steel bar binding tire frame includes a first tire frame and a second tire frame, the first tire frame and the second tire frame are symmetrically arranged on both sides of the support platform, and the first tire frame and the second tire frame are connected as a whole through a longitudinal tooth plate; the first tire frame and the second tire frame both include a triangular support, a bottom transverse tooth plate, a top transverse tooth plate and a vertical support rod; the bottom transverse tooth plate and the top transverse tooth plate are provided with tooth grooves for the longitudinal steel bar binding and positioning of the support platform; the longitudinal tooth plate is provided with tooth grooves for the transverse steel bar binding and positioning of the support platform; reserved holes are provided at both ends of the bottom transverse tooth plate and the top transverse tooth plate, and two vertical support rods are respectively inserted into the reserved holes to fix the bottom transverse tooth plate and the top transverse tooth plate up and down, and the triangular support is arranged on the outside of the two vertical support rods.
6. The complex riverbed large-volume special-shaped platform construction system according to claim 1 is characterized in that: The cooling water pipe is tied to the steel frame of the cap and arranged in a serpentine shape along the direction of the cap; the steel casing circulating cooling system includes an inlet steel casing, an outlet steel casing, a water distributor and a connecting pipe, and the inlet steel casing and the outlet steel casing are connected by a connecting pipe; the cooling water flows into the cooling water pipe through the water distributor, and the cooling water pipe flows back to the steel casing circulating cooling system through the return pipe.
7. The complex riverbed large-volume special-shaped foundation construction system according to claim 1 is characterized in that: Inner supports and surrounding purlins are arranged in the steel sheet piles above the concrete cushion layer, and corbel brackets are arranged on the inner sides of the steel sheet piles below the inner supports and the surrounding purlins. The movable cap casting platform includes a casting platform plate, pulleys, guide rails and cross beams; the guide rails are placed on the upper part of the steel sheet pile corbel brackets, pulleys are arranged at the bottom of both ends of the cross beams, and the pulleys move in a directional manner along the guide rails; the casting platform plate is connected to the cross beams through vertical hangers, the upper ends of the vertical hangers are fixed above the cross beams with high-strength bolts, and the lower ends of the vertical hangers are fixed below the casting platform plate with high-strength bolts.