Existing building heat preservation renewal system based on near-zero energy consumption

By installing wave mesh skeletons and insulation layers on existing buildings, the problems of low assembly efficiency and high construction costs in the existing technology are solved, structural strengthening and functional renewal are achieved, assembly speed and efficiency are improved, and construction is reduced Cost and ash pollution meet the needs of urban renewal.

CN222295816UActive Publication Date: 2025-01-03LIANGGU CONSTR ENG (SHANGHAI) CO LTD
View PDF 0 Cites 1 Cited by

Patent Information

Application Number
CN202421652143.6
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-07-12
Publication Date
2025-01-03
Estimated Expiration
2034-07-12

AI Technical Summary

Technical Problem

When existing buildings undergo thermal insulation and energy-saving transformation, it is difficult to improve assembly efficiency and save construction costs, while simultaneously achieving structural strengthening and functional renewal.

Method used

Adopt an existing building insulation and renewal system based on near zero energy consumption. By installing a wave mesh skeleton and insulation layer on the existing wall, the insulation wall will be updated after formation. The assembly process is accelerated by prefabricated molding and on-site molding, and through Special U-shaped plug buckles simplify construction.

Benefits of technology

It improves assembly speed and efficiency, enhances structural strength, reduces construction costs and ash pollution, facilitates pipeline layout and line transformation, and meets the infrastructure needs of urban renewal.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222295816U_ABST
    Figure CN222295816U_ABST
Patent Text Reader

Abstract

The utility model provides an existing building heat preservation renewal system based on near-zero energy consumption, which belongs to the field of near-zero energy consumption buildings and comprises an existing wall body and a back renewal heat preservation wall body. The post-renewal heat preservation wall serves as a renewal structure of an existing wall and aims at improving the structural wall and the heat preservation function of the existing wall. The existing wall body is formed on an existing building, and the existing wall body is defined as a wall body needing heat preservation and renewal. The post-renewal heat preservation wall body comprises a wave net framework and a heat preservation layer, the wave net framework can be fixed to an existing wall body in an assembled mode, and the heat preservation layer is attached to the wave net framework. The wave net framework and the heat preservation layer in the post-renewal heat preservation wall body are attached to the existing wall body after being integrally formed in a factory. Or after the wave net framework is fixed to the existing wall body, the heat preservation layer is attached to the wave net framework.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model belongs to the field of nearly zero energy consumption buildings, and in particular relates to an existing building thermal insulation renewal system based on nearly zero energy consumption. Background Art

[0002] Near-zero energy buildings can make the indoor environment more suitable for people's life and residence through energy-saving design and efficient operation, while significantly reducing energy consumption intensity, so that the energy-saving effect of buildings in hot summers and warm winters and hot summers and cold winters can reach more than 75%, and the energy saving of public buildings can reach more than 60%.

[0003] The wall insulation of existing buildings is one of the measures to achieve near-zero energy consumption for building energy conservation. At present, the early residential or office buildings built in China do not have insulation functions. Carrying out insulation and energy-saving renovation for these existing buildings that have been built for a long time is one of the ways to achieve the goals of urban renewal and building energy conservation and emission reduction.

[0004] Installing an insulation system on existing buildings (existing buildings are interpreted as buildings that are above ground and whose main structure is not to be continued and put into use) can achieve insulation upgrades and structural reinforcement. However, the problem in the field of prefabricated buildings is how to achieve structural reinforcement and functional updates while improving assembly efficiency and saving construction costs. This is a technical problem that needs to be solved urgently in this field.

[0005] Therefore, the utility model arises as the times require. Utility Model Content

[0006] The purpose of the utility model is to provide an existing building renewal system that has high assembly efficiency and can achieve structural reinforcement and functional renewal;

[0007] To achieve this goal, the utility model first provides an existing building insulation renewal system based on near-zero energy consumption, which is characterized by comprising:

[0008] Existing walls, the existing walls are formed on existing buildings, and the existing walls are defined as walls that need to be insulated and updated;

[0009] The post-updated thermal insulation wall comprises:

[0010] A wave net frame, wherein the wave net frame can be assembled and fixed to the existing wall;

[0011] A heat-insulating layer, the heat-insulating layer being attached to the corrugated mesh skeleton;

[0012] The corrugated mesh frame and the insulation layer in the later-updated insulation wall are attached to the existing wall after being integrally formed in the factory; or, after the corrugated mesh frame is fixed to the existing wall, the insulation layer is attached to the corrugated mesh frame.

[0013] Preferably, the insulation layer is insulation concrete, and the insulation concrete is attached to and formed on the wave mesh frame to be integrally formed into the post-renovation insulation wall.

[0014] Preferably, the insulation layer includes an insulation board and an insulation molding material, the wave mesh frame is installed on one side of the insulation board, the wave mesh frame and the insulation board are fixed to the existing wall, the wave mesh frame is located on the side of the insulation board away from the existing wall, and the insulation molding material is spray-molded on the wave mesh frame.

[0015] Preferably, the trough position of the wave mesh skeleton is fixed to the insulation board through a fixing piece; the fixing piece is a U-shaped buckle, the insertion part of the U-shaped buckle is a barbed structure, and the U-shaped buckle fixes the wave mesh skeleton to the insulation board through the mesh holes of the wave mesh skeleton.

[0016] Preferably, the post-renovation thermal insulation wall further includes embedded reinforcement bars; the embedded reinforcement bars are arranged in a height direction of the post-renovation thermal insulation wall, and the embedded reinforcement bars extend to the end of the post-renovation thermal insulation wall and are embedded in the main structure of the building.

[0017] Preferably, it further comprises a mounting support, wherein the mounting support is mounted on the main building structure, and the embedded reinforcement is fixed to the mounting support.

[0018] Preferably, it also includes a plaster layer, and the plaster layer is coated on the outside of the post-renovation thermal insulation wall.

[0019] The technical effects of the above technical solution of the utility model come from one or more of the following combinations:

[0020] This solution is implemented on existing walls to update the insulation wall. Specifically, the wave mesh frame and the insulation layer are prefabricated or installed on site, which greatly improves the assembly speed and efficiency. The wave mesh frame plays a role in structural reinforcement, and the insulation layer plays a role in insulation update. The existing buildings can meet the needs of urban renewal infrastructure and better meet the needs of life.

[0021] The crests and troughs of the wave mesh skeleton form cavity areas, which facilitate pipeline layout and line reconstruction in old communities. There is no need to perform grooving or other construction on the existing wall structure, which can save labor and reduce dust pollution.

[0022] Through the special U-shaped buckle, which includes a barbed structure, the insulation board and the corrugated mesh frame can be easily assembled, and the construction is easy, simple and convenient. BRIEF DESCRIPTION OF THE DRAWINGS

[0023] Figure 1A first structural top view of the utility model is expressed.

[0024] Figure 2 A first structural stereoscopic display diagram of the utility model is expressed.

[0025] Figure 3 A second structural top view of the utility model is expressed.

[0026] Figure 4 A second structural stereoscopic display diagram of the utility model is expressed.

[0027] Figure 5 The schematic diagram of the exterior wall installation of the utility model is expressed.

[0028] Figure 6 The schematic diagram of the structure of the U-shaped buckle in the utility model is expressed.

[0029] Figure 7 Two structural schematic diagrams of the insulation board in the utility model are expressed. DETAILED DESCRIPTION

[0030] The following description is given to enable those skilled in the art to implement and use the utility model and incorporate it into specific application contexts. Various modifications, as well as various uses in different applications will be readily apparent to those skilled in the art, and the general principles defined herein are applicable to a wide range of embodiments. Thus, the utility model is not limited to the embodiments given herein, but should be granted the broadest scope consistent with the principles and novel features disclosed herein.

[0031] In the following detailed description, many specific details are set forth to provide a more thorough understanding of the present invention. However, it is apparent to those skilled in the art that the practice of the present invention need not be limited to these specific details. In other words, well-known structures and devices are shown in block diagram form without detailed display to avoid obscuring the present invention.

[0032] The reader is reminded of all documents and literature filed simultaneously with this specification and open to public inspection, and the contents of all such documents and literature are incorporated herein by reference. Unless otherwise directly stated, all features disclosed in this specification (including any attached claims, abstracts and drawings) can be replaced by alternative features for achieving the same, equivalent or similar purposes. Therefore, unless otherwise explicitly stated, each feature disclosed is only an example of a group of equivalent or similar features.

[0033] Note that, where used, the symbols left, right, front, back, top, bottom, forward, reverse, clockwise and counterclockwise are used only for convenience and do not imply any specific fixed direction. In fact, they are used to reflect the relative position and / or direction between the various parts of the object. In addition, the terms "first" and "second" are used only for descriptive purposes and should not be understood as indicating or implying relative importance.

[0034] In the description of the present invention, it should be noted that, unless otherwise clearly specified and limited, the terms "installation", "connection" and "connection" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection; it can be a direct connection, or it can be indirectly connected through an intermediate medium, or it can be the internal communication of two components. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.

[0035] Note that, in the case of use, further, preferably, further and more preferably are simple beginnings for explaining another embodiment based on the previous embodiment, and the content of further, preferably, further or more preferably followed by the above embodiment is combined with the previous embodiment as a complete composition of another embodiment. Several further, preferably, further or more preferably settings followed by the same embodiment can be arbitrarily combined to form another embodiment.

[0036] The present invention is described in detail below in conjunction with the accompanying drawings and specific embodiments. Note that the aspects described below in conjunction with the accompanying drawings and specific embodiments are only exemplary and should not be construed as limiting the scope of protection of the present invention.

[0037] It should be noted that the corrugated mesh skeleton 22 in the drawings of this embodiment is a metal mesh plate with fine mesh holes, so it can be sprayed with slurry. In order to clearly show the overall structure, the drawings do not show the details of the mesh holes, but those skilled in the art should be able to know that the aperture of the mesh holes is not limited, as long as it can be sprayed with slurry.

[0038] See also Figure 1~Figure 5, this embodiment provides an existing building insulation renewal system based on near-zero energy consumption, including an existing wall 1 and a post-renewal insulation wall 2; wherein the post-renewal insulation wall 2 is a renewal structure of the existing wall 1, and is intended to improve the structural strength and insulation function of the existing wall 1. Specifically, the existing wall 1 is formed on an existing building, and the existing wall 1 is defined as a wall that needs insulation renewal; the post-renewal insulation wall 2 includes a wave mesh frame 22 and an insulation layer, and the wave mesh frame 22 can be assembled and fixed to the existing wall 1, and the insulation layer is attached to the wave mesh frame 22. The wave mesh frame 22 and the insulation layer in the post-renewal insulation wall 2 are attached to the existing wall 1 after being integrally formed in the factory; or, after the wave mesh frame 22 is fixed to the existing wall 1, the insulation layer is attached to the wave mesh frame 22.

[0039] In the implementation, "existing buildings" are interpreted as: buildings that are above ground and whose main structures are no longer to be built and put into use. This embodiment has a wide range of applications and can be used as an urban renewal project for existing buildings. "Existing walls" are existing walls of existing buildings.

[0040] First, see Figure 1 and Figure 2 The later-updated thermal insulation wall 2 can be integrally formed in the factory, and then transported to the construction site and screwed into the existing wall 1 by self-tapping screws 23 for assembly and installation. Specifically, the thermal insulation layer of the later-updated thermal insulation wall 2 is thermal insulation concrete 24A, and the thermal insulation concrete 24A is attached to and formed on the wave mesh frame 22 to form the later-updated thermal insulation wall 2 as a whole.

[0041] Furthermore, the precast concrete slab is formed by pressing on the formwork platform with the corrugated mesh skeleton 22 as the structural carrier, and the post-updated thermal insulation wall 2 can be formed. If the pipeline layout needs to be updated, the wiring pipeline can be buried during prefabrication. It should be noted that the thermal insulation concrete 24A is a common building material, which is a concrete material formed by adding a foaming agent to a slurry made of cement-based cementitious materials, aggregates, admixtures, additives and water. This embodiment is not limited here, and it can be selected in time according to the progress of existing technology or the expected development of materials science.

[0042] After the later-updated thermal insulation wall 2 is formed, holes or grooves can be punched or slotted to plant the rebars 3. The positions of the rebars 3 are arranged according to the height direction of the later-updated thermal insulation wall 2. The rebars 3 extend to the ends of the later-updated thermal insulation wall 2 and are planted in the main structure of the building. Specifically, the main structure of the building is generally implemented as a structural beam of an existing building.

[0043] See also Figure 3 and Figure 4 As another implementation of this embodiment, the later updated thermal insulation wall 2 can also be formed as a prefabricated structure in an integrated manner in a factory and constructed and formed on site.

[0044] Specifically, in the present embodiment, the insulation layer includes an insulation board 21 and an insulation molding material 24, the wave mesh skeleton 22 is installed on one side of the insulation board 21, the wave mesh skeleton 22 and the insulation board 21 are fixed to the existing wall 1, the wave mesh skeleton 22 is located on the side of the insulation board 21 away from the existing wall 1, and the insulation molding material 24 is spray-molded on the wave mesh skeleton 22. The spraying of the insulation molding material 24 forms a protective layer of 0.8~1.2cm to prevent the structure of the steel bars and the wave mesh skeleton 22 from being exposed. Preferably, the insulation molding material 24 is an insulation paste, insulation mortar or foam insulation material. When using foam insulation material, a template can be supported on one side of the wave mesh skeleton 22, and the foam insulation material can be filled between the insulation board 21 and the template, and the template can be removed after molding.

[0045] The insulation board 21 is made of organic polymer material, preferably XPS material, which has certain structural strength and insulation function. In addition, shallow grooves can be opened on the insulation board 21 for wiring, which is convenient for the layout of pipelines (water pipes, wires and other water and electricity structure wiring) of the wall.

[0046] For further information, see Figure 7 The insulation board 21 can be a vacuum insulation panel for building (internationally referred to as VIP panel, vacuum insulation panels for building-ings). Figure 7 As can be seen from the structure (a), the insulation board 21 can be spliced ​​by multiple vacuum insulation boards for construction at the stepped opening, where the stepped opening is a dense structure, which can be used as a nailing point for self-tapping screws 23 to be nailed into the existing wall 1 for assembly and installation; or Figure 7 As can be seen from the structure (b), the insulation board skeleton 210 is formed of foam material, and the building vacuum insulation panel is embedded in the skeleton 210 to form the insulation board as a whole.

[0047] The prefabricated structure is a combination of an insulation board 21 and a wave mesh frame 22, wherein the wave trough position of the wave mesh frame 22 is fixed to the insulation board 21 by a fixing member. Figure 6 The fixing piece is a U-shaped buckle 25, the insertion part of the U-shaped buckle 25 is a barb structure, and the U-shaped buckle 25 fixes the corrugated mesh frame 22 to the insulation board 21 through the mesh of the corrugated mesh frame 22. The number of U-shaped buckles 25 is not limited, mainly to achieve stable assembly and fixation of the two. Similarly, the prefabricated structure is also fixed by nailing the self-tapping screws 23 into the existing wall 1.

[0048] Similarly, holes or grooves can be punched in the insulation molding material 24 layer to plant the reinforcement 3, and the position of the reinforcement 3 is arranged according to the height direction of the later updated insulation wall 2, and the reinforcement 3 extends to the end of the later updated insulation wall 2 and is planted in the main structure of the building. Specifically, the main structure of the building is generally implemented as a structural beam of an existing building.

[0049] See also Figure 5 When the later-updated thermal insulation wall 2 of this embodiment is installed on the outer wall of the existing wall 1, this embodiment further includes a mounting support 5, which is installed on the main structure of the building, and the anchor bar 3 is fixed to the mounting support 5. The mounting support 5 can be a mounting bracket, which is intended to provide an installation fulcrum for fixing the anchor bar 3, thereby assisting the stability of the later-updated thermal insulation wall 2 when used as an outer wall.

[0050] It should be noted that after the later-updated thermal insulation wall 2 is formed, plastering is required to form a plastering layer 4, and the plastering layer 4 is coated on the later-updated thermal insulation wall 2 to form a neater appearance.

[0051] Beneficial effects of this embodiment:

[0052] This solution is implemented on the existing wall 1 to update the insulation wall 2; specifically, the wave mesh frame 22 and the insulation layer are prefabricated or installed on site, which greatly improves the assembly speed and efficiency; and the wave mesh frame 22 plays a role in structural reinforcement, and the insulation layer plays a role in insulation update; so that the existing buildings can meet the needs of urban renewal infrastructure and better meet the needs of life.

[0053] The crests and troughs of the wave mesh skeleton 22 form a cavity area, which is convenient for pipeline layout and line reconstruction in old communities. There is no need to perform construction such as grooving on the structure of the existing wall 1, which can save labor and reduce dust pollution.

[0054] Through the specially made U-shaped buckle 25, which includes a barbed structure, the insulation board 21 and the corrugated mesh frame 22 can be easily assembled, and the construction is convenient, simple and convenient.

[0055] Furthermore, the utility model is described in detail above in conjunction with the embodiments of the drawings, and a person skilled in the art can make various variations of the utility model according to the above description. Therefore, certain details in the embodiments should not constitute a limitation of the utility model, and the scope of protection of the utility model shall be defined by the scope of the attached claims.

Claims

1. The existing building insulation renewal system based on near-zero energy consumption is characterized by: include: Existing walls, the existing walls are formed on existing buildings, and the existing walls are defined as walls that need to be insulated and updated; The post-updated thermal insulation wall comprises: A wave net frame, the wave net frame can be assembled and fixed to the existing wall; A heat-insulating layer, the heat-insulating layer being attached to the corrugated mesh skeleton; The corrugated mesh frame and the insulation layer in the later-updated insulation wall are attached to the existing wall after being integrally formed in the factory; or, after the corrugated mesh frame is fixed to the existing wall, the insulation layer is attached to the corrugated mesh frame.

2. The existing building insulation renewal system based on near-zero energy consumption as claimed in claim 1 is characterized by: The thermal insulation layer is thermal insulation concrete, and the thermal insulation concrete is attached and formed on the wave mesh frame to be integrally formed into the post-renewal thermal insulation wall.

3. The existing building insulation renewal system based on near-zero energy consumption as claimed in claim 1 is characterized by: The insulation layer includes an insulation board and an insulation molding material. The wave mesh frame is installed on one side of the insulation board. The wave mesh frame and the insulation board are fixed to the existing wall. The wave mesh frame is located on the side of the insulation board away from the existing wall. The insulation molding material is spray-molded on the wave mesh frame.

4. The existing building insulation renewal system based on near-zero energy consumption as claimed in claim 3 is characterized by: The trough position of the wave mesh frame is fixed to the insulation board through a fixing piece; the fixing piece is a U-shaped buckle, the insertion part of the U-shaped buckle is a barbed structure, and the U-shaped buckle fixes the wave mesh frame to the insulation board through the mesh of the wave mesh frame.

5. The existing building insulation renewal system based on near-zero energy consumption according to any one of claims 1 to 4, characterized in that: The post-updated thermal insulation wall also includes embedded reinforcement bars; the embedded reinforcement bars are arranged in the height direction of the post-updated thermal insulation wall, and the embedded reinforcement bars extend to the end of the post-updated thermal insulation wall and are embedded in the main structure of the building.

6. The existing building insulation renewal system based on near-zero energy consumption as claimed in claim 5 is characterized by: It also includes a mounting support, which is mounted on the main building structure, and the embedded reinforcement is fixed to the mounting support.

7. The existing building insulation renewal system based on near-zero energy consumption as claimed in claim 1 is characterized by: It also includes a plaster layer, which is coated on the rear-renovation thermal insulation wall.

Citation Information

Cited By

  • Existing building heat preservation updating system and method based on near-zero energy consumption

    CN118461951A