Bottom-supported pedestal for storing prefabricated bridge columns and method of using the same
By designing a bottom-bearing pedestal, using the drainage system of connecting pipes and water collection wells, and the support structure of rubber pads and wooden wedges, the problem of unsafe storage of prefabricated bridge columns in high columns and coastal areas has been solved, and safe and convenient storage has been achieved. Lifting and stable storage.
Patent Information
- Application Number
- CN201810478423.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2018-05-18
- Publication Date
- 2024-10-11
- Estimated Expiration
- 2038-05-18
AI Technical Summary
Existing storage technology for bridge prefabricated columns has problems such as unsafe storage, large area, and inconvenient operation in high columns and coastal areas. It is especially difficult to ensure safety and economy under strong wind conditions.
Design a bottom-supporting pedestal, including a base and a pedestal with multiple rows and columns. The pedestal is equipped with connecting pipes and water collection wells. The bottom of the pedestal is equipped with rubber pads and wooden wedges. It is lifted and stored vertically by a gantry crane. Install a drainage device at the bottom of the pedestal to prevent water accumulation.
It achieves safe and convenient storage of columns, prevents uneven settlement and resists large wind forces, and at the same time reduces the difficulty of foundation treatment and floor space.
Smart Images

Figure CN108468346B_ABST
Abstract
Description
Technical Field
[0001] The invention belongs to the technical field of large prefabricated component storage, and in particular relates to a bottom-supported pedestal for storing prefabricated bridge columns and a use method thereof. Background Art
[0002] The columns in prefabricated bridge components are generally stored vertically or horizontally. Horizontal storage occupies a large area and is limited by the site, while vertical storage occupies a small area and is less restricted. For high columns located in coastal areas, with strong winds and poor coastal foundations, a safe, economical and easy-to-operate beam storage method must be adopted. Summary of the invention
[0003] The present invention aims to overcome the defects in the above-mentioned prior art and provide a bottom-supported pedestal for storing prefabricated bridge columns which has a simple structure, is convenient to use and safe to store.
[0004] In order to achieve the above purpose, the technical solution adopted by the present invention is: a bottom-supported pedestal for storing prefabricated bridge columns, including a base, the base is provided with a plurality of grooves to form the pedestal, and the plurality of pedestals are arranged downwardly, and the active surface of the pedestal is located below the upper surface of the base; the plurality of pedestals are neatly arranged in multiple rows and columns, and each pedestal is provided with a connecting pipe, and the connecting pipe is located at the bottom of the pedestal; the connecting pipes on each pedestal are connected, and a water collection well is provided on the base, and the connecting pipe is connected to the water collection well.
[0005] As a preferred solution of the present invention, a plurality of pile foundations are provided below the base, and the pile foundations are located corresponding to the positions of the pedestal.
[0006] As a preferred solution of the present invention, the pedestals are located inside the base, and the thickness between adjacent pedestals forms the side walls of the pedestals.
[0007] As a preferred solution of the present invention, the side wall of the pedestal is vertically arranged, and a rubber strip is provided on the top of the side wall of the pedestal.
[0008] As a preferred solution of the present invention, a wooden wedge is further provided on the top of the side wall of the pedestal.
[0009] As a preferred solution of the present invention, the connecting pipes of the same row of pedestals are interconnected, and connecting pipes of several rows converge and flow into the water collection well.
[0010] The invention discloses a bottom-supported pedestal for storing prefabricated bridge columns and a method for using the same, comprising the following steps:
[0011] Step A: Spray the number and installation direction on the side of the column, arrange the pads on the side wall of the column, and set the rubber pad at the bottom of the column;
[0012] Step B: Drain the water on the pedestal into the water collection well through the connecting pipe to ensure that there is no water accumulation at the bottom of the pedestal;
[0013] Step C: Lift the column vertically by the gantry crane, and hoist the column onto the pedestal under the action of the gantry crane;
[0014] Step D: When the column needs to be used, lift the column to the use site using a gantry crane.
[0015] As a preferred solution of the present invention, the column is locked by a wooden wedge after being hoisted to the pedestal.
[0016] As a preferred solution of the present invention, a rubber strip is provided on the top of the side wall of the pedestal.
[0017] The beneficial effects of the present invention are as follows: compared with the prior art, the bottom-supported storage pedestal is located below the ground, and the components are convenient to lift. After the foundation is processed and supported, the safety of column storage can be ensured, while uneven settlement can be prevented and strong wind forces can be resisted. BRIEF DESCRIPTION OF THE DRAWINGS
[0018] Figure 1 It is a schematic diagram of the structure of the present invention;
[0019] Figure 2 It is a schematic diagram of the structure of the pedestal;
[0020] The reference numerals in the figure are: base 1, wooden wedge 2, pedestal 3, pile foundation 4, water collection well 5, connecting pipe 6, column 7. DETAILED DESCRIPTION
[0021] The embodiments of the present invention are described in detail below with reference to the accompanying drawings.
[0022] like Figure 1-2 As shown, a bottom-supported pedestal for storing prefabricated bridge columns includes a base 1, and the base 1 is provided with a groove to form a pedestal 3, and the pedestals 3 are all arranged downward, and the active surface of the pedestals 3 is located below the upper surface of the base 1; the pedestals 3 are neatly arranged in multiple rows and columns, and each pedestal 3 is provided with a connecting pipe 6, and the connecting pipe 6 is located at the bottom of the pedestal 3; the connecting pipes 6 on each pedestal 3 are connected, and a water collection well 5 is provided on the base 1, and the connecting pipe 6 is connected to the water collection well 5.
[0023] The base 1 and the pedestal 3 are both located below the ground, which is convenient for lifting the column 7. After the foundation is processed, a pile foundation 4 is added under the base 1 to make the base 1 and the pedestal 3 have better stability, thereby ensuring that the column 7 has better safety during storage, which can prevent uneven settlement and resist strong wind force.
[0024] The size of the pedestal 3 is designed according to the size of the column 7. The size of the pedestal 3 is slightly larger than that of the column 7 to facilitate the hoisting of the column 7. Fifteen pedestals 3 form a group of base 1. The pedestals 3 on the same base 1 have the same size, and the 15 pedestals 3 are arranged in 3 rows and 5 columns to facilitate the gantry crane to lift and place the column 7. At the same time, the columns 7 neatly arranged in 3 rows and 5 columns make the bottom-supported pedestal have better stability. PHC piles are used at the bottom of the pedestal 3 to make the pedestal 3 have better strength.
[0025] The pedestal 3 is located inside the base 1, and the thickness between adjacent pedestals 3 forms the side wall of the pedestal 3. The side wall is a reinforced concrete structure, and the side wall of the pedestal 3 is vertically arranged. A rubber strip is provided on the top of the side wall of the pedestal 3 to protect the hoisted column 7. A wooden wedge 2 is also provided on the top of the side wall of the pedestal 3. During the hoisting process of the column 7, the wooden wedge 2 guides and supports the column 7 to prevent the column 7 from colliding with the pedestal 3 during the hoisting process, thereby causing damage to the column 7 and the pedestal 3. At the same time, after the column 7 is placed on the pedestal 3, the wooden wedge 2 is in a triangular shape, which clamps the gap between the pedestal 3 and the column 7, and clamps the gap between the pedestal 3 and the column 7 by the gravity of the wooden wedge 2 itself, thereby realizing the positioning of the column 7 on the pedestal 3.
[0026] The connecting pipes 6 of the same row of pedestals 3 are interconnected, and the connecting pipes 6 of three rows converge and flow into the water collection well 5. Since the pedestal 3 is located below the ground and the base 1 needs to be built in a humid place such as the seaside, there will be water accumulation in the pedestal after high tide and rain, and the accumulated water will soak the columns 7, which will cause damage to the columns 7 to a certain extent. The connecting pipe 6 is located at the bottom of the pedestal 3, and the water in the pedestal 3 flows into the water collection well 5 through the connecting pipe 6, thereby ensuring that there is no water accumulation in the pedestal 3, making the storage environment of the columns 7 more suitable.
[0027] In actual use, the method of using this bottom-supported pedestal includes the following steps:
[0028] The number and installation direction are sprayed on the side of the column 7, and pads are arranged on the side walls of the column 7, and rubber pads are set at the bottom of the column 7; the water on the pedestal 3 is discharged into the water collection well 5 through the connecting pipe 6 to ensure that there is no water accumulation at the bottom of the pedestal 3; the column 7 is lifted vertically by the gantry crane, and the column 7 is lifted onto the pedestal 3 under the action of the gantry crane; when the column 7 needs to be used, the column 7 is lifted to the use site by the gantry crane.
[0029] The spray number and installation direction are used to ensure the accuracy of the column 7 during the lifting and placement process. The pads and rubber pads on the column 7 are used to prevent the column 7 from being damaged during the placement and lifting process. After the column 7 is lifted to the pedestal 3, it is locked by the wooden wedge 2. A rubber strip is provided on the top of the side wall of the pedestal 3.
[0030] A gantry crane is used to lift the prefabricated column 7 onto the storage pedestal 3. The prefabricated column 7 is vertically placed into the storage pedestal 3 and supported between the pedestal 3 and the column 7 by wooden wedges 2. The column is placed 1.1m into the pedestal. Rubber pads are used at the bottom of the column 7, and pads are set on the side walls. Rubber strips are provided at the corners of the storage pedestal 3 to protect the concrete structure of the column 7. A drainage device is provided on the storage pedestal 3. 15 pedestals form a group. 15 columns can be placed in one group. A water collection well 5 is provided in one group. A connecting pipe 6 is provided under each pedestal 3. Natural water can be discharged into the water collection well 5 through the connecting pipe 6, so as to recycle water and improve the storage quality of the prefabricated columns 7. The height of the prefabricated column 7 can reach 20m. The bearing capacity of the foundation is extremely important. PHC piles are used to prevent the settlement of the base 1.
[0031] The above description of the disclosed embodiments enables one skilled in the art to implement or use the present invention. Various modifications to these embodiments will be apparent to one skilled in the art, and the general principles defined herein may be implemented in other embodiments without departing from the spirit or scope of the present invention; therefore, the present invention will not be limited to the embodiments shown herein, but rather to the widest scope consistent with the principles and novel features disclosed herein.
[0032] Although this article uses the following terms more frequently: base 1, wooden wedge 2, pedestal 3, pile foundation 4, water collection well 5, connecting pipe 6, column 7, etc., it does not exclude the possibility of using other terms; these terms are used only to more conveniently describe and explain the essence of the present invention; interpreting them as any additional limitations is contrary to the spirit of the present invention.
Claims
1. A method for using a bottom-supported pedestal for storing prefabricated bridge columns, characterized in that: The invention comprises a base (1), wherein the base (1) is provided with a plurality of grooves to form a pedestal (3), wherein the plurality of pedestals (3) form a group of the base (1), wherein the plurality of pedestals (3) are all arranged downwardly, and the active surface of the pedestal (3) is located below the upper surface of the base (1); the plurality of pedestals (3) are neatly arranged in multiple rows and columns, and each pedestal (3) is provided with a connecting pipe (6), and the connecting pipe (6) is located at the bottom of the pedestal (3); the connecting pipes (6) on each pedestal (3) are connected, and a water collection well (5) is provided on the base (1), and the connecting pipe (6) is connected to the water collection well (5); the base (1) and the pedestal (3) are both located below the ground, and a plurality of pile foundations (4) are provided below the base (1), and the pile foundations (4) are located corresponding to the position of the pedestal (3); the pedestal (3) is located inside the base (1), and the thickness between adjacent pedestals (3) forms the side wall of the pedestal (3), and the following steps are also included: Step A: spray-paint the side of the column (7) with numbers and installation directions, arrange pads on the side walls of the column (7), and place rubber pads at the bottom of the column (7); Step B: drain the water on the pedestal (3) into the water collection well (5) through the connecting pipe (6), ensuring that there is no water accumulation at the bottom of the pedestal (3); Step C: vertically lifting the column (7) by means of a gantry crane, and lifting the column (7) onto the pedestal (3) by means of the gantry crane; Step D: When the column (7) needs to be used, the column (7) is hoisted to the use site by a gantry crane.
2. The method for using the bottom-supported pedestal for storing prefabricated bridge columns according to claim 1 is characterized in that: The upright column (7) is locked by means of a wooden wedge (2) after being hoisted to the pedestal (3).
3. The method for using the bottom-supported pedestal for storing prefabricated bridge columns according to claim 1 is characterized in that: A rubber strip is provided on the top of the side wall of the pedestal (3).
4. The method for using the bottom-supported pedestal for storing prefabricated bridge columns according to claim 1 is characterized in that: The side wall of the pedestal (3) is arranged vertically, and a rubber strip is provided on the top of the side wall of the pedestal (3).
5. The method for using the bottom-supported pedestal for storing prefabricated bridge columns according to claim 1 is characterized in that: A wooden wedge (2) is also provided on the top of the side wall of the pedestal (3).
6. The method for using the bottom-supported pedestal for storing prefabricated bridge columns according to claim 1, characterized in that: The connecting pipes (6) of the pedestals (3) in the same row are connected, and the connecting pipes (6) in several rows converge and flow into the water collection well (5).