Steel tube concrete arch bridge and construction method

Through the fixed bracket system and other innovative construction technologies, the problem of difficulty in installing the arch foot formwork and docking accuracy of the arch ribs in the construction of steel pipe concrete arch bridges has been solved, the construction efficiency and stability have been improved, and economic and safety have been improved.

CN108660903BActive Publication Date: 2024-12-06ANHUI HIGHWAY ENG CORP
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN201810636205.7
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2018-06-20
Publication Date
2024-12-06
Estimated Expiration
2038-06-20

AI Technical Summary

Technical Problem

During the construction process, there are problems such as difficulty in installing and fixing the arch foot formwork, difficulty in ensuring the docking accuracy of the arch rib of the steel pipe, difficulty in controlling structural stability, large labor investment, poor economy and poor safety. The traditional construction methods are cumbersome and difficult to organize. .

Method used

Adopt a combination of pre-pressure technology for reaction pre-pressure of the bottom beam of anchoring bag water injection pressure heavy pre-pressure technology, attached fixed fixed fast disassembly articulated opening and closing steel mold , , boom installation platform truss slide rail mobile construction platform and tie cable lossless traction and line laying system, through these technical means, improve the stability and efficiency of arch rib installation and simplify the construction process.

Benefits of technology

It improves the stability and docking accuracy of steel pipe arch rib installation, saves construction period and cost, improves the degree of construction mechanization, and ensures the accuracy of structural dimensions and construction safety.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN108660903B_ABST
    Figure CN108660903B_ABST
Patent Text Reader

Abstract

The present invention relates to a steel tube concrete arch bridge, comprising side arch ribs, main arch ribs, hangers, tie rods and bridge pier structures; the side span structure comprises side arch supports, side span cast-in-place reinforced concrete arch ribs, cast-in-place side arch end beams, side span cast-in-place inter-rib beams, cast-in-place side arch rib tie beams, cast-in-place side columns, flexible prestressed tie rods and cast-in-place bridge decks; the middle span structure comprises arch seats, middle span steel tube concrete arch ribs, main arch hollow inter-rib beams, prefabricated hollow longitudinal beams, flexible prestressed tie rods, tie rod steel plate boxes, truss-type permanent upper wind support, K-shaped permanent middle wind support, temporary wind support, arch foot embedded section, inner steel strand bundle extruded cable hanger and outer steel strand bundle extruded cable hanger. The present invention has the beneficial effects that the steel tube arch rib fixing bracket provided by the present invention improves the stability of the steel tube arch rib installation construction operation and effectively ensures the docking accuracy.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to a steel tube concrete arch bridge and a construction method, belongs to the field of bridge engineering, and is suitable for the construction of a Feiyan type steel tube concrete arch bridge. Background Art

[0002] The construction of long-span bridges requires the use of high-strength, lightweight and easy-to-construct engineering materials, and hopes that the structure has good ductility and recovery performance. The use of steel tube concrete composite materials in arch bridges can greatly reduce the deadweight of the bridge and can also greatly improve the structural dynamic performance. The arch ribs of steel tube concrete arch bridges are mainly compressed components, and their stability has always been a concern for bridge engineers. The lateral stiffness of large-span arch bridges is generally small, and large displacements under wind loads may affect the normal operation of the bridge structure and even cause structural damage, causing certain safety hazards. Although large-span concrete arch bridges can use hollow arch rib components, their cross-sectional dimensions make the wind-blocking area large, and the wind loads they receive can still have a great impact on lateral stability. Transverse wind bracing can ensure that the rib arches of steel tube concrete do not suffer local instability before the overall instability, which is an important guarantee for lateral stability. The arrangement of transverse braces directly affects the stability of steel tube concrete arch bridges and is one of the factors that must be considered in design. However, too many cross braces are unreasonable from the perspective of design and construction. They will also make the space above the arch look messy and complicated, weakening the beauty of the arch bridge.

[0003] The horizontal thrust of the flying swallow tie arch bridge under the action of dead load is mainly balanced by the tie rods, while the thrust at the arch foot caused by temperature load and live load is mainly offset by the foundation. The flying swallow tie arch bridge is usually arranged as an upper bearing type in the side span and a middle bearing type in the main span. A reasonable structural form is generally that the side span adopts a material with a large load concentration (such as reinforced concrete) and a small span-rise ratio (the smaller the span-rise ratio, the greater the horizontal component of the axial pressure in the arch). This form is easy to balance the thrust generated by the main arch rib at the arch foot and is more economical. The lower bearing part of the flying swallow tie arch bridge is usually a suspension system, which has a large flexibility and affects the comfort of the vehicle. The overall stiffness of the bridge deck system can be improved by extending the length of the upper bearing bridge deck system, thereby reducing the deformation of the main beam in the operating state and weakening the vibration of the bridge deck. The longitudinal stiffness can also be improved by setting inclined hangers. The lateral stiffness of the Feiyan tie-arch bridge can be ensured by a certain number of transverse braces, or it can be set up as a basket arch bridge to indirectly increase the lateral stiffness of the bridge by the lateral inclination of the hangers.

[0004] During the construction of steel tube concrete arch bridges, it is often difficult to install and fix the arch foot formwork. During the construction of steel tube concrete arch bridges, it is often difficult to ensure the accuracy of the steel tube arch rib docking, it is difficult to control the structural stability during the construction process, the labor input during the installation of the steel tube arch rib is large, the economy is poor, and the safety during the construction process is poor. The conventional steel tube concrete arch bridge tie rod system and hanger construction method cannot meet the construction requirements, and the traditional drop frame technology construction steps are cumbersome and difficult to organize. Summary of the invention

[0005] The purpose of the present invention is to overcome the deficiencies in the prior art and provide a steel tube concrete arch bridge and a construction method.

[0006] The steel tube concrete arch bridge comprises side arch ribs, main arch ribs, hangers, tie rods and bridge pier structures; the side span structure comprises side arch supports, side span cast-in-place reinforced concrete arch ribs, cast-in-place side arch end beams, side span cast-in-place inter-rib cross beams, cast-in-place side arch rib tie beams, cast-in-place side columns, flexible prestressed tie rods and cast-in-place bridge decks; the middle span structure comprises arch seats, middle span steel tube concrete arch ribs, main arch hollow inter-rib cross beams, prefabricated hollow longitudinal beams, flexible prestressed tie rods, tie rod steel plate boxes, truss-type permanent upper wind bracing, K-shaped permanent middle wind bracing, temporary wind bracing, arch foot embedded sections, inner steel strand whole bundle extruded cable hangers and outer steel strand whole bundle extruded cable hangers;

[0007] The cast-in-place side arch rib tie beam is arranged between the two side span cast-in-place reinforced concrete arch ribs; the cast-in-place side columns are arranged above the side span cast-in-place reinforced concrete arch ribs and arch seats to support the T-shaped prestressed cross beams; the embedded section of the arch foot is connected to the arch seat through the concrete wrapped outside the arch foot, and the arch seat is arranged above the pedestal of the main span; the cross beam between the hollow ribs of the main arch is arranged between the two middle span steel tube concrete arch ribs; the upper parts of the inner steel strand whole bundle extruded cable hanger and the outer steel strand whole bundle extruded cable hanger are connected to the middle span steel tube concrete arch rib, and the lower parts of the inner steel strand whole bundle extruded cable hanger and the outer steel strand whole bundle extruded cable hanger are connected to the hanger cross beam; the truss-type permanent upper wind brace, K-shaped permanent middle wind brace and temporary wind brace are arranged between the two middle span steel tube concrete arch ribs.

[0008] As a preferred embodiment, the cast-in-place side arch end cross beam is arranged above the end of the cast-in-place reinforced concrete arch rib of the side span, and the cast-in-place inter-rib cross beam of the side span is arranged above the cast-in-place reinforced concrete arch rib of the side span.

[0009] Preferably, the flexible prestressed tie rods are arranged through the tie rod steel plate box, and their ends are anchored to the top of the cast-in-situ reinforced concrete arch ribs of the side spans.

[0010] As a preferred embodiment, the pedestal is arranged above the pile foundation, columns are arranged above the pedestal of the side span, and side arch supports are arranged above the columns.

[0011] As a preferred embodiment, one end of the side span cast-in-place reinforced concrete arch rib is connected to the arch seat, and the other end is placed on the side arch support.

[0012] Preferably, one end of the arch seat is connected to the cast-in-situ reinforced concrete arch rib of the side span, and the other end is provided with an arch foot embedded section, and the middle span steel tube concrete arch rib is consolidated with the arch foot embedded section through the arch foot outer concrete.

[0013] Preferably, the upper tensioning ends of the inner steel strand whole bundle extruded cable hanger and the outer steel strand whole bundle extruded cable hanger are connected to the mid-span steel tube concrete arch rib through the hanger anchor head holes, and the lower fixed section is connected to the hanger crossbeam through the hanger end embedded parts.

[0014] As a preferred embodiment, the mid-span steel tube concrete arch rib installation section includes an upstream arch rib and a K-shaped permanent wind brace, with a temporary wind brace added at the front.

[0015] As a preferred embodiment, the supports of the middle span steel tube concrete arch rib and the side span cast-in-place reinforced concrete arch rib adopt a standardized support system.

[0016] The construction method of the steel tube concrete arch bridge comprises the following steps:

[0017] 1) Construction preparation: organize relevant personnel to review drawings, then conduct technical briefings on key processes, check materials and equipment, formulate test plans, establish a construction measurement control network, and further understand and implement on-site construction safety measures;

[0018] 2) Construction of pile foundation and piers: construct the foundation of side arch and main arch, pour pile foundation and piers, then pour arch seat at the pier of main arch, pour columns on the pier of side arch, pour side arch support above the columns, and when pouring the cap and arch seat of main pier, embed the steel pipe of arch rib arch foot, local pressure-bearing steel plate of arch foot, and embedded parts of arch foot wrapped with concrete steel bars, etc. When pouring the cap and arch seat of main pier, install the bracket on the cap in advance and install the empty steel pipe of arch foot of main arch;

[0019] 3) Processing of main arch ribs: The arch ring of the middle span steel tube concrete arch rib adopts dumbbell-shaped steel tube concrete, and the arch ribs are prefabricated in sections in the factory;

[0020] 4) Set up the integral fixed bracket of the arch foot: connect the integral fixed bracket through the embedded steel plate, set the fixed steel plate and positioning bolts on the positioning frame to locate and weld the shear nail welding position;

[0021] 5) Arch foot construction: The arch seat is set above the main span pedestal, the arch foot embedded section is installed, the arch foot and tie beam steel bars are tied, and the arch foot outer concrete construction adopts the outer concrete attachment fixed stereotyped fast installation and fast disassembly hinged opening and closing steel formwork casting technology, pour the arch foot outer concrete for fixing, vibrate and compact, and perform maintenance;

[0022] 6) Erection of arch rib support: Before erecting the support, the foundation of the support shall be reinforced and stabilized, and corresponding drainage facilities shall be set up around the support foundation. The support construction of the middle span steel tube concrete arch rib and the side span cast-in-place reinforced concrete arch rib shall adopt a standardized support system;

[0023] 7) Install the flexible support net: level the height-adjustable curved lattice steel support plate, and then place the flexible support net on the height-adjustable curved lattice steel support plate;

[0024] 8) Support loading preloading: The support preloading of the middle span concrete-filled steel tube arch rib and the side span cast-in-place reinforced concrete arch rib adopts the combined preloading technology of the assembled step anchor cable frame anchor bottom beam reaction preloading and the bag water injection weight preloading;

[0025] 9) Monitoring support deformation: Measure the vertical elastic deformation of the standardized support system, and take into account the pre-arching caused by the sinking deformation of the temporary support during construction when the arch rib is erected;

[0026] 10) Arch rib support unloading: After setting the pre-arch, unload the standardized support system;

[0027] 11) Erection of the main beam of the triangular area: Erection of the main beam of the triangular area on the standardized support system, and casting of the hollow inter-rib cross beam of the main arch;

[0028] 12) Tie rod installation system erection: The flexible prestressed tie rod construction adopts the tie rod cable non-destructive traction and pay-off system, rolls the finished tie rod cable drum, erects the fixed drum frame, places the finished tie rod cable drum on the drum frame bottom plate, erects the cable bracket, installs the vertical guide groove with roller, leads out the traction wire rope, starts the winch, keeps a uniform speed during the traction process, leaves enough working length after traction is in place, adjusts the guide wheel frame elevation to meet the design, and installs the tie rod anchor head: finally, installs the prestressed tie rod anchor end;

[0029] 13) Erection of arch rib construction support system: The middle span steel tube concrete arch rib and the side span cast-in-place reinforced concrete arch rib are finalized by using a temporary reinforcement technology combining a separate hinged reinforcement steel plate and a standardized integral arc-shaped reinforcement channel steel. A standardized support system is erected for the middle span steel tube concrete arch rib, and the upper part of the standardized support system is fixed by reinforcing steel pipes and reinforced support steel plates;

[0030] 14) Casting of side span structure: Install side span arch rib formwork, end beam formwork, and inter-rib beam formwork on the standardized support system, and tie the steel bars; then cast the side span cast-in-place reinforced concrete arch ribs, side span cast-in-place inter-rib beams, and cast-in-place side arch rib tie beams, cast side arch rib concrete, and cast end beam concrete. After reaching the design strength of more than 90%, tension the end beam prestressed steel strands, and cast the cast-in-place side columns on the side span cast-in-place reinforced concrete arch ribs;

[0031] 15) Installation of steel pipes for the main arch ribs in the middle span: hoist in sections, connect the empty steel pipe sections with temporary bolts, and close the empty steel pipes; avoid wind bracing, cross beams and hangers between the hollow ribs of the main arch at the steel pipe sections; weld the joints between the sections after adjusting the arch axis; weld or bolt the exhaust holes on the arch top; install truss-type permanent upper wind bracing, K-shaped permanent middle wind bracing, and temporary wind bracing;

[0032] 16) Procedure for pumping concrete for the main arch ribs of the middle span: The arch rib concrete is poured once, and the upper, middle and lower cavities are poured independently. The pouring order is the lower chord, the upper chord and the middle slab. Concrete is pumped from the arch feet on both sides to the arch top at the same time. When the concrete is pumped to the arch top on both sides, continue pumping until the scheduling steel pipe is filled with concrete. When the concrete strength reaches the requirement, remove the exhaust pipe and seal the hole with the same steel plate for welding.

[0033] 17) Side arch closing: Close the side span cast-in-place reinforced concrete arch ribs. After the side arch ribs have been cured for 7-10 days, pour the arch foot closing joint concrete; symmetrically cast the cast-in-place side arch rib tie beams;

[0034] 18) Symmetrically cast the hollow inter-rib cross beams of the main arch, cast the cast-in-place side columns of the side arch, and install the main arch columns; hoist the T-shaped prestressed cross beams, hoist the side arch end cross beams on one side of the side span, and install the side span longitudinal beams; install the precast bridge deck of the side span, and cast the cast-in-place bridge deck of the side span;

[0035] 19) Erection of the boom construction platform: The construction platform includes the construction platform bottom plate, laying of the slide rails, laying of the bottom plate slide rail grooves, and erection of the platform trusses;

[0036] 20) Tie rod tensioning: Install longitudinal flexible prestressed tie rod cables, install side span prestressed tie rod support frames and tie rod steel plate boxes, tension the inner and outer tie rods respectively, and use symmetrical, graded, and cyclic tensioning for tie rod tensioning;

[0037] 21) Remove the main arch ring support in the middle span of the navigation hole, and retain the support below the main arch rib intercostal beam;

[0038] 22) Installation of mid-span hangers: The construction of the arch rib hangers of the mid-span steel tube concrete arch rib adopts a mobile construction platform with fixed slide rails attached to the arch rib. The prefabricated hanger beams of the mid-span are installed symmetrically from the mid-span and arch foot to the 1 / 4 of the arch rib, and the side beams on one side of the main span are installed; prefabricated hollow longitudinal beams are installed; tie rod steel plate boxes are installed; the installation of the prefabricated hanger beams of the mid-span is carried out according to the installation elevation of the bottom of the beam after considering the pre-arch in the construction diagram of the arch rib hangers of the mid-span; after all the prefabricated beams are installed, the length or force of all the hanger cables are re-adjusted in accordance with the above-mentioned installation elevation of the bottom of the beam;

[0039] 23) Tensioning and anchoring of the hanger rod: tension and anchor the inner hanger rod and the outer hanger rod respectively; the upper tensioning ends of the inner steel strand bundle extruded cable hanger rod and the outer steel strand bundle extruded cable hanger rod are connected to the middle span steel tube concrete arch rib through the hanger rod anchor head hole, and the lower fixed section is connected to the hanger rod cross beam through the hanger rod end embedded parts;

[0040] 24) Remove all remaining supports, install the prefabricated bridge deck of the main span, and cast the cast-in-place bridge deck of the main span;

[0041] 25) Cast the bridge deck and anti-collision guardrails evenly and symmetrically across the three spans of the entire bridge, and install expansion joints;

[0042] 26) After the completion of the entire bridge, the cable tension of all inner steel strand bundle extruded cable hangers, outer steel strand bundle extruded cable hangers and flexible prestressed tie anchor cables shall be measured. The initial tensioning cable force of the hangers shall be appropriately adjusted based on the analysis results of the design elevation control of the beams during construction. The error between the measured cable force and the designed cable force of the tie cable shall not exceed 8%, otherwise corresponding cable adjustments shall be made.

[0043] The beneficial effects of the present invention are:

[0044] 1. The steel tube arch rib fixing bracket of the present invention improves the stability of the steel tube arch rib installation construction work and effectively ensures the docking accuracy.

[0045] 2. The construction method of the assembled step anchor cable frame anchoring bottom beam reaction preloading combined with bag water injection weight preloading reduces an unnecessary construction procedure, saves construction time, and can effectively save costs.

[0046] 3. The attached, fixed, and standardized quick-detachable hinged opening and closing steel formwork involved in the present invention improves the installation and construction speed of the arch foot formwork and effectively ensures the structural dimensions.

[0047] 4. The boom installation platform truss of the present invention adopts a standardized slide rail mobile construction platform, which greatly improves the boom construction efficiency and greatly improves the degree of construction mechanization.

[0048] 5. The tie rod installation in the present invention effectively avoids possible damage to the tie rod during the installation process through the tie rod cable lossless traction and release system, ensures the integrity of the tie rod construction, and effectively reduces frictional resistance. BRIEF DESCRIPTION OF THE DRAWINGS

[0049] Figure 1 It is a detailed elevation drawing of a concrete-filled steel tube arch bridge;

[0050] Figure 2 It is the plan view of the arch rib structure;

[0051] Figure 3 It is the cross section of the main arch rib hanger beam;

[0052] Figure 4 It is the cross section of the main arch rib intercostal beam and side beam;

[0053] Figure 5 It is the cross section of the side arch rib column beam;

[0054] Figure 6 It is the cross section of the side arch end beam;

[0055] Figure 7 It is the plan view of the bridge deck system;

[0056] Figure 8 It is a schematic diagram of a standardized support system;

[0057] Fig. 9 This is the structural diagram of the concrete-encased arch foot of a steel tube concrete arch bridge;

[0058] Fig.10 This is the structural diagram of the shear stud welding positioning frame;

[0059] Fig.11 This is the structural diagram of the finalized fixture for the arch rib of a steel tube concrete arch bridge;

[0060] Fig.12 This is the installation structure diagram of the external prestressed tie rod of the steel tube concrete;

[0061] Fig.13 It is a diagram of a replaceable lock tie rod anchor;

[0062] Fig.14 This is the structural diagram of the arch rib hanger of the steel tube concrete arch bridge;

[0063] Fig.15 It is a cross-sectional view of the exhaust hole and the feed hole.

[0064] Explanation of the reference numerals: 1-pile foundation, 2-cap, 3-arch seat, 4-side arch support, 5-column, 6-middle span steel tube concrete arch rib, 7-side span cast-in-place reinforced concrete arch rib, 8-cast-in-place side arch end beam, 9-side span cast-in-place inter-rib beam, 10-cast-in-place side arch rib tie beam, 11-cast-in-place side column, 12-T-shaped prestressed beam, 13-main arch hollow inter-rib beam, 14-precast hollow longitudinal beam, 15-laying corbel, 16-precast bridge deck, 17-cast-in-place bridge deck, 18-flexible prestressed tie rod, 19-inner steel strand bundle extruded cable hanger, 20-outer steel strand bundle extruded cable hanger, 21-hanger anchor head hole, 22-upper tensioning end, 23-lower fixed section, 24-hanger end embedded part, 25-chord steel pipe , 26-middle slab, 27-self-compacting concrete, 28-feed hole, 29-exhaust hole, 30-exhaust pipe, 31-arch foot embedded section, 32-arch foot outer concrete, 33-arch foot local pressure-bearing steel plate, 34-shear nail, 35-interchangeable lock tie anchor, 36-tie support frame, 37-tie steel plate box, 38-truss type permanent upwind support, 39-K-shaped permanent wind support, 40-temporary wind support, 41-standardized support system, 42-arch rib standardization reinforcement channel steel frame, 43-side cross beam, 44-suspender cross beam, 45-outer side arch rib, 46-inner side arch rib, 47-column support, 48-left and right auxiliary inner arch ribs share the lower foundation, 49-inner prestressed tie rod, 50-outer prestressed tie rod, 51-side cross beam Beam support, 52-sidewalk, 53-non-motorized vehicle lane, 54-motorized vehicle lane, 55-anti-collision guardrail, 56-outer main arch rib, 57-inner main arch rib, 58-prefabricated slab blocks, 59-foundation treatment piles, 60-shallow solidified cement soil slab, 61-assembled step anchor frame anchor bottom beam, 62-anchor embedded section, 63-main arch rib arch foot steel pipe, 64-reserved anchor hole, 65-frame bracket bottom plate, 66-pier fixed plate embedded parts, 67-unit L-shaped steel plate frame, 68-elevation adjustable arc lattice steel support plate, 69-flexible support net, 70-bag, 71-side end plate, 72-easy-to-detach partition plate, 73-reaction preload anchor cable, 74-pier embedded anchor cable reaction end, 75-pressure steel mesh, 76-shear steel Plate, 77-L-shaped limit plate, 78, end plate with holes, 79, comb-shaped integral fixing bolts, 80-anti-crack steel mesh, 81-arc guard plate, 82-integral fixed bracket, 83-embedded steel plate, 84-shaped steel plate, 85-shear nail welding positioning frame, 86-positioning bolt, 87-reinforced steel pipe shelving steel pipe, 88-reinforced support steel plate, 89-jack limit shelving cavity, 90-bracket cross brace, 91-jack, 92-reinforced rib plate, 93-arch rib fixed steel plate, 94-steel pipe arch rib fixed bracket, 95-fastening ear plate, 96-arc integral channel steel, 97-adjustable long screw for tensioning, 98-temporary connection plate for arch rib tensioning, 98-steel pipe arch rib joint, 99-continuous stress tester, 100-steel pipe arch rib,101-ear plate fastening bolts, 102-adjustable steel plate top plate, 103-adjustable bolt group, 104-adjustable steel plate base, 105-adjustable steel plate bracket, 106-hinge shaft, 107-tie rod finished cable drum, 108-fixed drum frame, 109-drum frame bottom plate, 110-vertical guide groove with roller, 111-symmetrical winch, 112-cable with buckle shoulder pole beam, 113-cable bracket, 114-tie rod cable, 115-tie rod with transition arc support Splitter, 116-traction steel wire rope, 117-anchor plate fixing rib, 118-sealing device, 119-erection fixing steel plate, 120-anchor bolt, 121-compression device, 122-protective cover, 123-support cylinder, 124-filling mortar, 125-embedded pipe, 126-shock absorption device, 127-slide rail, 128-construction platform bottom plate, 129-bottom plate slide rail groove, 130-embedded pull brake, 131-platform truss. DETAILED DESCRIPTION

[0065] The present invention is further described below in conjunction with embodiments. The description of the following embodiments is only used to help understand the present invention. It should be noted that for those of ordinary skill in the art, without departing from the principles of the present invention, several improvements and modifications may be made to the present invention, and these improvements and modifications also fall within the scope of protection of the claims of the present invention.

[0066] like Figures 1 to 15As shown, the steel tube concrete arch bridge comprises: side arch ribs, main arch ribs, hangers, tie rods and bridge pier structures; the side span structure comprises side arch supports 4, side span cast-in-place reinforced concrete arch ribs 7, cast-in-place side arch end beams 8, side span cast-in-place inter-rib beams 9, cast-in-place side arch rib tie beams 10, cast-in-place side columns 11, flexible prestressed tie rods 18 and cast-in-place bridge decks 17; the middle span structure comprises arch seats 3, middle span steel tube concrete arch ribs 6, main arch hollow inter-rib beams 13, prefabricated hollow longitudinal beams 14, flexible prestressed tie rods 18, tie rod steel plate boxes 37, truss-type permanent upper wind braces 38, K-shaped permanent middle wind braces 39, temporary wind braces 40, arch foot embedded sections 31, inner steel strand bundle extruded cable hangers 19 and outer steel strand bundle extruded cable hangers 20; the cast-in-place side arch rib tie beams 10 are arranged at two The side span is between cast-in-place reinforced concrete arch ribs 7; the cast-in-place side columns 11 are arranged above the side span cast-in-place reinforced concrete arch ribs 7 and the arch seat 3 to support the T-shaped prestressed cross beam 12; the arch foot embedded section 31 is connected to the arch seat 3 through the arch foot outer concrete 32, and the arch seat 3 is arranged above the pedestal 2 of the main span; the main arch hollow rib inter-rib cross beam 13 is arranged between the two middle span steel tube concrete arch ribs 6; the upper parts of the inner steel strand bundle extruded cable hanger 19 and the outer steel strand bundle extruded cable hanger 20 are connected to the middle span steel tube concrete arch rib 6, and the lower parts of the inner steel strand bundle extruded cable hanger 19 and the outer steel strand bundle extruded cable hanger 20 are connected to the hanger cross beam 44; the truss type permanent upper wind brace 38, the K-shaped permanent wind brace 39, and the temporary wind brace 40 are arranged between the two middle span steel tube concrete arch ribs 6.

[0067] The cast-in-place side arch end cross beam 8 is arranged above the end of the side span cast-in-place reinforced concrete arch rib 7, and the side span cast-in-place inter-rib cross beam 9 is arranged above the side span cast-in-place reinforced concrete arch rib 7. The flexible prestressed tie rod 18 is arranged through the tie rod steel plate box 37, and its end is anchored to the top of the side span cast-in-place reinforced concrete arch rib 7. The pedestal 2 is arranged above the pile foundation 1, and a column 5 is arranged above the pedestal 2 of the side span, and a side arch support 4 is arranged above the column 5. One end of the side span cast-in-place reinforced concrete arch rib 7 is connected to the arch seat 3, and the other end is placed on the side arch support 4. One end of the arch seat 3 is connected to the side span cast-in-place reinforced concrete arch rib 7, and the other end is provided with an arch foot embedded section 31, and the middle span steel tube concrete arch rib 6 is consolidated with the arch foot embedded section 31 through the arch foot outer concrete 32. The upper tensioning ends 22 of the inner steel strand bundle extruded cable hanger 19 and the outer steel strand bundle extruded cable hanger 20 are connected to the middle span steel tube concrete arch rib 6 through the hanger anchor hole 21, and the lower fixed section 23 is connected to the hanger cross beam 44 through the hanger end embedded part 24. The installation section of the middle span steel tube concrete arch rib 6 includes an upstream arch rib and a K-shaped permanent wind brace 39, and a temporary wind brace 40 is added in front of it. The brackets of the middle span steel tube concrete arch rib 6 and the side span cast-in-place reinforced concrete arch rib 7 adopt a standardized bracket system 41.

[0068] The construction method of the steel tube concrete arch bridge comprises the following steps:

[0069] 1) Construction preparation: organize relevant personnel to review drawings, then conduct technical briefings on key processes, check materials and equipment, formulate test plans, establish a construction measurement control network, and further understand and implement on-site construction safety measures;

[0070] 2) Construction of pile foundation and pier: construct the foundation of side arch and main arch, pour pile foundation 1 and pier 2, then pour arch seat 3 at pier 2 of main arch, pour column 5 on pier 2 of side arch, pour side arch support 4 above column 5, when pouring cap 2 and arch seat 3 of main pier, pre-embed arch rib arch foot steel pipe, arch foot local pressure bearing steel plate 33, arch foot outer concrete steel bar pre-embedded parts and other pre-embedded parts, when pouring cap 2 and arch seat 3 of main pier, pre-install cap 2 upper bracket and install main arch arch foot empty steel pipe;

[0071] 3) Processing of main arch ribs: The arch ring of the middle span steel tube concrete arch rib 6 adopts dumbbell-shaped steel tube concrete, and the arch ribs are prefabricated in sections in the factory;

[0072] 4) Setting up the integral fixing bracket of the arch foot: connecting the integral fixing bracket 82 through the embedded steel plate 33, and setting the shaping steel plate 84 and the positioning bolt 86 on the positioning frame 85 to position and weld the welding position of the shear nail 34;

[0073] 5) Arch foot construction: The arch seat 3 is set above the pedestal 2 of the main span, the arch foot embedded section 31 is installed, the arch foot and tie beam steel bars are tied, and the arch foot outer concrete 32 is constructed by using the outer concrete attachment fixed stereotyped fast assembly and fast disassembly hinged opening and closing steel formwork casting technology, the arch foot outer concrete 32 is cast for fixing, and vibrated to make it dense, and maintenance is carried out in time;

[0074] 6) Erection of arch rib support: Before erection of the support, the foundation of the support is reinforced and stabilized, and corresponding drainage facilities are set around the support foundation. The support construction of the middle span steel tube concrete arch rib 6 and the side span cast-in-place reinforced concrete arch rib 7 adopts a standardized support system 41;

[0075] 7) Installing the flexible support net: leveling the height-adjustable curved lattice steel support plate 68, and then placing the flexible support net 69 on the height-adjustable curved lattice steel support plate 68;

[0076] 8) Support loading preloading: The support preloading of the middle span steel tube concrete arch rib 6 and the side span cast-in-place reinforced concrete arch rib 7 adopts the preloading technology of the combined reaction force preloading of the assembled step anchor cable frame anchor bottom beam and the water injection weight preloading of the bag;

[0077] 9) Monitoring support deformation: Measure the vertical elastic deformation of the standardized support system 41. When the arch rib is erected, the pre-arching caused by the sinking deformation of the temporary support during construction should be considered and included;

[0078] 10) Arch rib support unloading: after setting the pre-arch, the standardized support system 41 is unloaded;

[0079] 11) Erection of the triangular area main beam: Erection of the triangular area main beam on the standardized support system 41, and casting of the main arch hollow inter-rib cross beam 13;

[0080] 12) Tie rod installation system erection: The flexible prestressed tie rod 18 is constructed using a tie rod cable non-destructive traction and pay-off system, the finished tie rod cable drum 107 is rolled, the fixed drum frame 108 is erected, the finished tie rod cable drum 107 is placed on the drum frame bottom plate 109, the cable bracket 113 is erected, the vertical guide groove 110 with rollers is installed, the traction wire rope 116 is led out, and the winch 111 is started. The traction process speed should not be too fast and should be kept at a uniform speed. After traction is in place, sufficient working length is left, the guide wheel frame elevation is adjusted to meet the design, and the tie rod anchor head is installed: finally, the prestressed tie rod anchor end is installed;

[0081] 13) Erection of arch rib construction support system: The middle span steel tube concrete arch rib 6 and the side span cast-in-place reinforced concrete arch rib 7 are shaped by using a temporary reinforcement technology combining a separated hinged reinforcement steel plate and a standardized integral arc-shaped reinforcement channel steel. The middle span steel tube concrete arch rib 6 is erected with a standardized support system 41, and the upper part of the standardized support system 41 is fixed by reinforcing steel pipes 87 and reinforcing support steel plates 88;

[0082] 14) Casting the side span structure: Install the side span arch rib formwork, end beam formwork, and inter-rib beam formwork on the standardized support system 41, and tie the steel bars (pay attention to the setting of embedded parts); then cast the side span cast-in-place reinforced concrete arch rib 7, the side span cast-in-place inter-rib beam 9, the cast-in-place side arch rib tie beam 10, cast the side arch rib concrete, cast the end beam concrete, and after reaching the design strength of more than 90%, tension the end beam prestressed steel strand, and cast the cast-in-place side column 11 on the side span cast-in-place reinforced concrete arch rib 7;

[0083] 15) Install the steel pipes of the main arch ribs in the middle span: hoist in sections, connect the empty steel pipe sections with temporary bolts, and close the empty steel pipes; avoid the wind braces, the cross beams 13 between the hollow ribs of the main arch, and the hangers at the steel pipe sections; after adjusting the arch axis, weld the joints between the sections; weld or bolt the arch top exhaust holes 29; install the truss-type permanent upper wind brace 38, K-shaped permanent middle wind brace 39, and temporary wind brace 40;

[0084] 16) Procedure for pumping concrete for the main arch rib of the middle span: the arch rib concrete is poured once, and the upper, middle and lower cavities are poured independently, and the pouring order is the lower chord, the upper chord, and the middle slab 26; concrete is pumped from the arch feet on both sides to the arch top at the same time; when the concrete is pumped to the arch top on both sides, continue pumping until the scheduling steel pipe is full of concrete; insert a vibrating rod to vibrate for two minutes, and when the concrete strength reaches the requirement, remove the exhaust pipe 30, and seal the hole with the same steel plate for welding;

[0085] 17) Closing of side arches: Closing the cast-in-situ reinforced concrete arch ribs 7 of the side spans. After the side arch ribs have been cured for 7-10 days, pouring the arch foot closing joint concrete (closing the arch foot); symmetrically pouring the cast-in-situ side arch rib tie beams 11;

[0086] 18) Symmetrically cast the main arch hollow inter-rib cross beam 13, cast the cast-in-place side column 11 of the side arch, and install the main arch column; hoist the T-shaped prestressed cross beam 12, hoist the side arch end cross beam 8 on one side of the side span, and install the side span section longitudinal beam; install the side span section precast bridge deck 17, and cast the side span section cast-in-place bridge deck 17;

[0087] 19) Erection of the boom construction platform: The construction platform includes a construction platform bottom plate 128, laying of slide rails 127, laying of bottom plate slide rail grooves 129, and erection of the platform truss 131;

[0088] 20) Tie rod tensioning: Install the longitudinal flexible prestressed tie rod 18 cable, install the side span prestressed tie rod support frame 36 and the tie rod steel plate box 37, and tension the inner and outer tie rods respectively. The tie rod tensioning adopts symmetrical, graded and cyclic tensioning;

[0089] 21) Remove the main arch ring support in the middle span of the navigation hole, and retain the support below the main arch rib intercostal beam;

[0090] 22) Installation of mid-span hangers: The arch rib hangers of the mid-span concrete-filled steel tube arch rib 6 are constructed using a mobile construction platform with attached arch rib fixed slide rails. The mid-span prefabricated hanger cross beams 44 are installed symmetrically from the mid-span and arch foot to the 1 / 4 of the arch rib, and the side cross beams 43 on one side of the main span are installed; the prefabricated hollow longitudinal beams 14 are installed; the tie steel plate box 37 is installed; the installation of the mid-span prefabricated hanger cross beams 44 is carried out according to the installation elevation of the bottom of the beam after the pre-arch is considered in the mid-span arch rib hanger structure diagram; after all the prefabricated cross beams are installed in place, the length or force of all the hanger cables are re-adjusted in accordance with the above-mentioned installation elevation of the bottom of the beam;

[0091] 23) Tension anchoring of the suspender rod: tension anchoring is performed on the inner suspender rod and the outer suspender rod respectively; the upper tensioning ends 22 of the inner steel strand bundle extruded cable suspender rod 19 and the outer steel strand bundle extruded cable suspender rod 20 are connected to the middle span steel tube concrete arch rib 6 through the suspender rod anchor head hole 21, and the lower fixed section 23 is connected to the suspender rod cross beam 44 through the suspender rod end embedded part 24;

[0092] 24) Remove all remaining brackets, install the main span prefabricated bridge deck 17, and cast the main span cast-in-place bridge deck 16;

[0093] 25) Cast the bridge deck and anti-collision guardrail 55 evenly and symmetrically for the three spans of the whole bridge, and install the expansion joints;

[0094] 26) After the completion of the whole bridge, the cable tension of all inner steel strand bundle extruded cable hangers 19, outer steel strand bundle extruded cable hangers 20 and flexible prestressed tie rods 18 anchor cables shall be measured. The initial tensioning force of the hangers shall be appropriately adjusted in combination with the analysis results of the design elevation control of the beams during construction. The error between the measured cable tension of the tie rods and the designed cable tension shall not exceed 8%, otherwise corresponding cable adjustments shall be made.

Claims

1. A construction method for a steel tube concrete arch bridge, It is characterized in that The steel tube concrete arch bridge comprises a side arch rib, a main arch rib, a hanger, a tie rod and a bridge pier structure; the side span structure comprises a side arch support (4), a side span cast-in-place reinforced concrete arch rib (7), a cast-in-place side arch end beam (8), a side span cast-in-place inter-rib beam (9), a cast-in-place side arch rib tie beam (10), a cast-in-place side column (11), a flexible prestressed tie rod (18) and a cast-in-place bridge deck (17); the middle span structure comprises an arch seat (3), a middle span steel tube concrete arch rib (6), a main arch hollow inter-rib beam (13), a prefabricated hollow longitudinal beam (14), a flexible prestressed tie rod (18), a tie rod steel plate box (37), a truss-type permanent upper wind brace (38), a K-shaped permanent middle wind brace (39), a temporary wind brace (40), an arch foot embedded section (31), an inner steel strand bundle extruded cable hanger rod (19) and an outer steel strand bundle extruded cable hanger rod (20); The cast-in-place side arch rib tie beam (10) is arranged between two side span cast-in-place reinforced concrete arch ribs (7); the cast-in-place side column (11) is arranged above the side span cast-in-place reinforced concrete arch rib (7) and the arch seat (3) to support the T-shaped prestressed cross beam (12); the arch foot embedded section (31) is connected to the arch seat (3) through the arch foot outer concrete (32), and the arch seat (3) is arranged above the pedestal (2) of the main span; the main arch hollow rib inter-rib cross beam (13) is arranged between the two middle span steel tube concrete arch ribs (6 ); the upper parts of the inner steel strand bundle extruded cable hanger (19) and the outer steel strand bundle extruded cable hanger (20) are connected to the middle span steel tube concrete arch rib (6), and the lower parts of the inner steel strand bundle extruded cable hanger (19) and the outer steel strand bundle extruded cable hanger (20) are connected to the hanger crossbeam (44); the truss-type permanent upper wind brace (38), the K-shaped permanent middle wind brace (39), and the temporary wind brace (40) are arranged between the two middle span steel tube concrete arch ribs (6); The construction method of the steel tube concrete arch bridge comprises the following steps: 1) Construction preparation: organize relevant personnel to review drawings, then conduct technical briefings on key processes, check materials and equipment, formulate test plans, establish a construction measurement control network, and further understand and implement on-site construction safety measures; 2) Construction of pile foundation and pier: construct the foundation of the side arch and the main arch, cast the pile foundation (1) and the pedestal (2), then cast the arch seat (3) at the pedestal (2) of the main arch, cast the column (5) on the pedestal (2) of the side arch, cast the side arch support (4) above the column (5), and when casting the pedestal (2) and the arch seat (3) of the main pier, embed the arch rib arch foot steel pipe, the arch foot local pressure bearing steel plate (33), the arch foot outer concrete steel bar embedded parts and other embedded parts, and when casting the pedestal (2) and the arch seat (3) of the main pier, pre-install the pedestal (2) upper bracket and install the main arch arch foot hollow steel pipe; 3) Processing of main arch ribs: The arch ring of the middle span steel tube concrete arch rib (6) adopts dumbbell-shaped steel tube concrete, and the arch rib is prefabricated in sections in the factory; 4) Erecting the integral fixing bracket of the arch foot: connecting the integral fixing bracket (82) through the embedded steel plate (83), setting the fixed steel plate (84) and the positioning bolt (86) on the positioning frame (85) to locate and weld the welding position of the shear stud (34); 5) Arch foot construction: The arch seat (3) is set above the main span pedestal (2), the arch foot embedded section (31) is installed, the arch foot and tie beam steel bars are tied, and the arch foot outer concrete (32) is constructed by using the outer concrete attachment fixed fixed and standardized fast assembly and fast disassembly hinged opening and closing steel formwork casting technology, the arch foot outer concrete (32) is cast for fixing, and then vibrated and compacted, and then maintained; 6) Erection of arch rib support: Before erecting the support, the foundation of the support is reinforced and stabilized, and corresponding drainage facilities are set up around the support foundation. The support construction of the middle span steel tube concrete arch rib (6) and the side span cast-in-place reinforced concrete arch rib (7) adopts a standardized support system (41); 7) Installing the flexible support net: leveling the height-adjustable curved lattice steel support plate (68), and then placing the flexible support net (69) on the height-adjustable curved lattice steel support plate (68); 8) Support loading preloading: The support preloading of the middle span steel tube concrete arch rib (6) and the side span cast-in-place reinforced concrete arch rib (7) adopts the combined preloading technology of the assembled step anchor cable frame anchor bottom beam reaction preloading and the bag water injection weight preloading; 9) Monitoring support deformation: Measure the vertical elastic deformation of the standardized support system (41), and take into account the pre-arching caused by the sinking deformation of the temporary support during construction when the arch rib is erected; 10) Arch rib support unloading: After setting the pre-arch, the standardized support system (41) is unloaded; 11) Erection of the triangular area main beam: Erection of the triangular area main beam on the standardized support system (41), and casting of the main arch hollow inter-rib cross beam (13); 12) Tie rod installation system erection: The flexible prestressed tie rod (18) is constructed using a tie rod cable non-destructive traction and pay-off system, the finished tie rod cable drum (107) is rolled, a fixed drum frame (108) is erected, the finished tie rod cable drum (107) is placed on the drum frame bottom plate (109), a cable bracket (113) is erected, a vertical guide groove with rollers (110) is installed, the traction wire rope (116) is led out, and the winch (111) is started. The traction process is kept at a constant speed. After the traction is in place, a sufficient working length is reserved, the guide wheel frame elevation is adjusted to meet the design, and the tie rod anchor head is installed: Finally, the prestressed tie rod anchor end is installed; 13) Erection of arch rib construction support system: The middle span steel tube concrete arch rib (6) and the side span cast-in-place reinforced concrete arch rib (7) are shaped by using a temporary reinforcement technology combining a separate hinged reinforcement steel plate and a standardized integral arc-shaped reinforcement channel steel. A standardized support system (41) is erected for the middle span steel tube concrete arch rib (6), and the upper part of the standardized support system (41) is fixed by reinforcing steel pipe shelving steel pipes (87) and reinforcing support steel plates (88); 14) Casting the side span structure: Install the side span arch rib formwork, end cross beam formwork, and inter-rib cross beam formwork on the standardized support system (41), and tie the steel bars; then cast the side span cast-in-place reinforced concrete arch rib (7), the side span cast-in-place inter-rib cross beam (9), and the cast-in-place side arch rib tie beam (10); cast the side arch rib concrete, cast the end cross beam concrete, and after reaching a design strength of more than 90%, tension the end cross beam prestressed steel strands; and cast the cast-in-place side columns (11) on the side span cast-in-place reinforced concrete arch rib (7); 15) Install the steel pipes for the main arch ribs in the middle span: hoist in sections, connect the empty steel pipe sections with temporary bolts, and close the empty steel pipes; avoid the wind braces, the cross beams (13) between the hollow ribs of the main arch, and the hangers at the steel pipe sections; after adjusting the arch axis, weld the joints between the sections; weld or bolt the arch top exhaust holes (29); install the truss-type permanent upper wind brace (38), K-shaped permanent middle wind brace (39), and temporary wind brace (40); 16) Procedure for pumping concrete for the main arch rib of the middle span: the arch rib concrete is poured once, and the three cavities of upper, middle and lower are poured independently, in the order of lower chord, upper chord, and middle tie plate (26); concrete is pumped from the arch feet on both sides to the arch top at the same time; when the concrete is pumped to the arch top on both sides, continue pumping until the scheduling steel pipe is full of concrete; when the concrete strength reaches the requirement, remove the exhaust pipe (30) and seal the hole with the same steel plate and weld it; 17) Closing of side arches: Closing the side span cast-in-place reinforced concrete arch ribs (7). After the side arch ribs have been cured for 7-10 days, pouring the arch foot closing joint concrete; symmetrically pouring the cast-in-place side arch rib tie beams (10); 18) Symmetrically cast the hollow inter-rib cross beams (13) of the main arch, cast the cast-in-place side columns (11) of the side arch, and install the main arch columns; hoist the T-shaped prestressed cross beams (12), hoist the side arch end cross beams (8) on one side of the side span, and install the side span longitudinal beams; install the side span precast bridge deck (17), and cast the cast-in-place bridge deck (17) of the side span; 19) Setting up a boom construction platform: The construction platform includes a construction platform bottom plate (128), laying of slide rails (127), laying of bottom plate slide rail grooves (129), and setting up of a platform truss (131); 20) Tie rod tensioning: Install the longitudinal flexible prestressed tie rod (18) cable, install the side span prestressed tie rod support frame (36) and the tie rod steel plate box (37), and tension the inner and outer tie rods respectively. The tie rod tensioning adopts symmetrical, graded and cyclic tensioning; 21) Remove the main arch ring support in the middle span of the navigation hole, and retain the support below the main arch rib intercostal beam; 22) Installation of mid-span hangers: The arch rib hangers of the mid-span steel tube concrete arch rib (6) are constructed by using a mobile construction platform with an attached arch rib fixed slide rail. The mid-span prefabricated hanger beams (44) are installed symmetrically from the mid-span and arch foot to the 1 / 4 direction of the arch rib, and the side beams (43) on one side of the main span are installed; the prefabricated hollow longitudinal beams (14) are installed; the tie steel plate box (37) is installed; the installation of the mid-span prefabricated hanger beams (44) is carried out according to the beam bottom installation elevation after considering the pre-arch in the mid-span arch rib hanger structure diagram; after all the prefabricated beams are installed, the length or force of all the hanger cables are re-adjusted in accordance with the above beam bottom installation elevation; 23) Suspension anchoring: the inner and outer suspension rods are tensioned and anchored respectively; the upper tensioning ends (22) of the inner steel strand bundle extruded cable suspension rod (19) and the outer steel strand bundle extruded cable suspension rod (20) are connected to the middle span steel tube concrete arch rib (6) through the suspension rod anchor head hole (21), and the lower fixed section (23) is connected to the suspension rod cross beam (44) through the suspension rod end embedded part (24); 24) Remove all remaining supports, install the precast bridge deck (17) of the main span, and cast the cast-in-place bridge deck (16) of the main span; 25) Cast the bridge deck and anti-collision guardrail (55) evenly and symmetrically over the three spans of the whole bridge, and install the expansion joints; 26) After the whole bridge is completed, the cable tension of all inner steel strand bundle extruded cable hangers (19), outer steel strand bundle extruded cable hangers (20) and flexible prestressed tie rods (18) is measured. The initial tensioning cable force of the hangers is appropriately adjusted in combination with the analysis results of the design elevation control of the cross beam during construction. The error between the measured cable force and the designed cable force of the tie rod tensioning force is not more than 8%, otherwise the cable is adjusted accordingly.

2. The construction method of the steel tube concrete arch bridge according to claim 1, Features: The cast-in-place side arch end cross beam (8) is arranged above the end of the side span cast-in-place reinforced concrete arch rib (7), and the side span cast-in-place inter-rib cross beam (9) is arranged above the side span cast-in-place reinforced concrete arch rib (7).

3. The construction method of the steel tube concrete arch bridge according to claim 1, Features: The flexible prestressed tie rod (18) is arranged to pass through the tie rod steel plate box (37), and its end is anchored to the top of the cast-in-place reinforced concrete arch rib (7) of the side span.

4. The construction method of the steel tube concrete arch bridge according to claim 1, Features: The capping platform (2) is arranged above the pile foundation (1), a column (5) is arranged above the capping platform (2) of the side span, and a side arch support (4) is arranged above the column (5).

5. The construction method of the steel tube concrete arch bridge according to claim 1, Features: One end of the side span cast-in-place reinforced concrete arch rib (7) is connected to the arch seat (3), and the other end is placed on the side arch support (4).

6. The construction method of the steel tube concrete arch bridge according to claim 1, Features: One end of the arch seat (3) is connected to the side span cast-in-place reinforced concrete arch rib (7), and the other end is provided with an arch foot embedded section (31). The middle span steel tube concrete arch rib (6) is consolidated with the arch foot embedded section (31) through the arch foot outer concrete (32).

7. The construction method of the steel tube concrete arch bridge according to claim 1, Features: The upper tensioning ends (22) of the inner steel strand bundle extruded cable hanger (19) and the outer steel strand bundle extruded cable hanger (20) are connected to the mid-span steel tube concrete arch rib (6) through the hanger anchor head holes (21), and the lower fixed sections (23) are connected to the hanger crossbeam (44) through the hanger end embedded parts (24).

8. The construction method of the steel tube concrete arch bridge according to claim 1, Features: The mid-span concrete-filled steel tube arch rib (6) installation segment comprises an upstream arch rib and a K-shaped permanent wind brace (39), the front of which is provided with a temporary wind brace (40).

9. The construction method of the steel tube concrete arch bridge according to claim 1, Features: The supports of the middle span steel tube concrete arch rib (6) and the side span cast-in-place reinforced concrete arch rib (7) adopt a standardized support system (41).