Secondary lining trolley for preventing arch from falling out and construction method for preventing arch from falling out
By using a second lining trolley and construction method to prevent vault deflation in tunnel construction, and using monitors and liftable detection devices, the safety hazards of vault secondary lining are solved, and the vault grouting is realized Accurate control significantly reduces the empty discharge rate and construction risks.
Patent Information
- Application Number
- CN201910142919.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2019-02-26
- Publication Date
- 2024-11-22
- Estimated Expiration
- 2039-02-26
AI Technical Summary
During tunnel construction, the safety hazards of the secondary lining of the vault is leaked out during pouring, resulting in loosening and deformation of the surrounding rock, and may even cause blocks or partial collapse of the tunnel. It is difficult for the existing technology to effectively prevent and monitor such situations. .
A two-lined trolley and construction method are designed to prevent vaulting from being disembarked. By using a monitor to issue a warning when the vault poured concrete reaches a designated position, the required grouting time is calculated based on the grouting speed and vault curve. , set corresponding parameters to prevent the vault from being dissipated and too much grouting, and use lifting detection devices and monitor systems to achieve this goal.
It effectively prevents the vault deflation and excessive grouting, significantly reduces the vault deflation rate, thereby improving construction safety and quality, reducing construction funds and speeding up progress.
Smart Images

Figure CN109736848B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the field of tunnel construction, and in particular to a secondary lining trolley for preventing a vault from falling out and a construction method for preventing a vault from falling out. Background Art
[0002] At present, the linings of highway tunnels in my country are all designed as composite linings. Under normal circumstances, the secondary linings of the surrounding rock of grade II and III bear 30% of the surrounding rock relaxation load, and the secondary linings of the surrounding rock of grade IV and V bear 50% of the surrounding rock relaxation load. When designing the structural analysis and calculation, it is considered that the backfill behind the composite lining is dense and the surrounding rock behind the lining can provide radial elastic resistance. Therefore, whether it is the back of the arch secondary lining is empty or the back of the side wall secondary lining is empty, the stress form of the secondary lining structure is changed, the local stress of the secondary lining is increased, and it causes great safety hazards to the project. The safety hazard of the back of the arch secondary lining is even greater. When the secondary lining arch is empty, since the arch is positive bending moment, that is, the upper edge of the arch is tensile, the upper edge of the arch is not equipped with stress steel bars according to conventional reinforcement, which will cause the upper edge of the arch to be tensile and crack, resulting in water leakage and corrosion of steel bars, and then the secondary village masonry concrete is damaged. On the other hand, if the secondary lining vault is hollowed out during pouring, the surrounding rock will lose its due protection and support at the very beginning, which may further loosen and deform the surrounding rock, leading to instability and damage of the surrounding rock. In severe cases, it may even cause the tunnel to fall off and partially collapse. In summary, the phenomenon of hollowing out of the top of the secondary lining must be prevented. The hollowing out of the secondary lining vault during pouring is generally caused by the way the secondary lining is poured. The secondary lining is poured from bottom to top, one ring at a time. When pouring to the vault, it is completely unknown whether the vault is completely filled with concrete.
[0003] Therefore, in order to solve the above problems, a secondary lining trolley and a construction method for preventing the vault from falling out are needed. The monitor can issue an alarm by forming a passage when the vault pouring concrete reaches the designated position. The grouting time required after the concrete reaches the designated position can be calculated through the grouting speed and the vault curve. The corresponding parameters are set so that the monitor will give a prompt to stop the vault grouting at the corresponding time to prevent the vault from falling out and excessive grouting of the vault. Summary of the invention
[0004] In view of this, the purpose of the present invention is to overcome the defects in the prior art and provide a second lining trolley and a construction method for preventing the vault from becoming hollow. The monitor can issue an alarm when the vault pouring concrete reaches the specified position by relying on the concrete to form a passage. The grouting time required after the concrete reaches the specified position is calculated through the grouting speed and the vault curve. The corresponding parameters are set so that the monitor gives a prompt to stop the vault grouting at the corresponding time to prevent the vault from becoming hollow and excessive vault grouting.
[0005] The secondary lining trolley for preventing the vault from falling out provided by the present invention comprises a secondary lining trolley main body and a liftable detection device arranged in the middle of the secondary lining trolley main body; the liftable detection device comprises a detection assembly, a turbine screw elevator and a motor; the detection assembly comprises a sleeve coaxially arranged on the top of the screw of the turbine screw elevator, a first conductor and a second conductor independently arranged on the top of the inner wall of the sleeve and exposed from the sleeve, and a monitor whose positive and negative poles are electrically connected to the first conductor and the second conductor respectively; the motor drives the turbine screw elevator to make the sleeve slide in the vertical direction to realize the extension or retraction of the sleeve to the trolley template on the top of the secondary lining trolley main body; the first conductor and the second conductor are insulated from each other.
[0006] Furthermore, the monitor includes a buzzer, a warning red light and a warning green light which are respectively connected in series with the power supply on the secondary lining trolley, and the warning red light is also connected in series with a controller.
[0007] Furthermore, the monitor is installed in a protection box, and the protection box is fixed on the secondary lining trolley at a distance of 1.2-1.5m from the ground through a box bracket.
[0008] Furthermore, the first conductor and the second conductor are symmetrical along the axis of the sleeve.
[0009] Furthermore, the first conductor and the second conductor are covered with rubber sleeves, and the rubber sleeves are clamped in the holes on the inner wall of the sleeve.
[0010] Furthermore, the top grouting holes of the second lining trolley body are arranged on both sides of the bottom of the top trolley template, and the height difference between the top grouting holes and the highest point of the top trolley template is 0.5-1.0m.
[0011] The beneficial effects of the present invention are as follows: the second lining trolley for preventing the vault from being hollowed out disclosed by the present invention can issue an alarm by means of a monitor when the vault pouring concrete reaches a designated position by means of a passage formed by the concrete, and can calculate the grouting time required after the concrete reaches the designated position by means of the grouting speed and the vault curve, and can set corresponding parameters so that the monitor can give a prompt to stop the vault grouting at a corresponding time, thereby preventing the vault from being hollowed out and excessive grouting of the vault, and the liftable detection device can be recycled without affecting the quality of the vault.
[0012] The present invention also provides a construction method for preventing the vault from falling out, and the construction method for preventing the vault from falling out comprises the following steps:
[0013] Step 1: Construction preparation;
[0014] Step 2: Overall installation of the secondary lining trolley;
[0015] Step 3: Grouting is performed on the arch walls on both sides of the tunnel, and at the same time, the motor is started to drive the turbine screw lift to lift the casing to the designated position;
[0016] Step 4: Vault grouting and filling: When pouring the vault concrete, if the buzzer of the monitor sounds and the warning green light comes on, it means that the concrete has reached the designated position;
[0017] Step 5: Start the motor to drive the turbine screw lift to retract the casing into the trolley template on the top of the secondary lining trolley body;
[0018] Step 6: The warning red light comes on and the concrete vault grouting is stopped;
[0019] Step 7: Demould and move the trolley.
[0020] The beneficial effects of the present invention are as follows: the present invention discloses a construction method for preventing the vault from being hollowed out. During the vault grouting, a buzzer sounds and a green warning light is emitted through the monitor of the second lining trolley when the concrete reaches a designated position, and then the liftable detection device is retracted, and the vault grouting is stopped when the red warning light of the monitor is on, so as to prevent the vault from being hollowed out and excessive vault grouting. BRIEF DESCRIPTION OF THE DRAWINGS
[0021] The present invention will be further described below in conjunction with the accompanying drawings and embodiments:
[0022] Figure 1 It is a structural schematic diagram of the present invention;
[0023] Figure 2 It is a structural schematic diagram of the present invention;
[0024] Figure 3 It is a construction flow chart of the present invention. DETAILED DESCRIPTION
[0025] like Figure 1 and Figure 2As shown, the second lining trolley for preventing the vault from being emptied in this embodiment includes a second lining trolley body 1 and a liftable detection device arranged in the middle of the second lining trolley body 1; the liftable detection device includes a detection assembly 2, a turbine screw lift 3 and a motor 4; the detection assembly 2 includes a sleeve 21 coaxially arranged at the top of the screw of the turbine screw lift 3, a first conductor 22 and a second conductor 23 independently arranged at the top of the inner wall of the sleeve 21 and exposed from the sleeve 21, and a monitor whose positive and negative poles are electrically connected to the first conductor 22 and the second conductor 23 respectively; the motor 4 drives the turbine screw lift 3 to make the sleeve 21 slide in the vertical direction to realize that the sleeve 21 extends or retracts the top trolley template 11 of the second lining trolley body 1; the first conductor 22 and the second conductor 23 are insulated from each other. When the vault grouting reaches the position of the first conductor 22 and the second conductor 23, due to the conductivity of the concrete, the positive and negative poles of the monitor are connected, and the monitor works to issue a corresponding warning. The turbine screw lift 3 is driven by the motor 4, which can make the sleeve 21 slide in the vertical direction, so as to control the position of the first conductor 22 and the second conductor 23. The height of the first conductor 22 and the second conductor 23 can be changed according to different grouting equipment and different arch specifications. At the same time, the sleeve 21 can be retracted into the top trolley template 11 of the secondary lining trolley body 1 after the monitor alarm, which does not affect the arch pouring and can be recycled.
[0026] In this embodiment, the monitor includes a buzzer 24, a warning red light 25 and a warning green light 26 which are respectively connected in series with the power supply on the second lining trolley, and the warning red light 25 is also connected in series with a controller 27. The controller 27 is a delay controller, and a time relay can also be used. When the concrete reaches the specified position, the buzzer 24 sounds and the warning green light 26 lights up, reminding the staff to retract the casing 21 and prepare to stop the vault grouting. At this time, the controller 27 also starts timing, which is the value set by the staff according to the height of the first conductor 22 and the second conductor 23, the grouting speed and the vault curve. When the time is up, the warning red light 25 lights up to remind the staff to stop the vault grouting.
[0027] In this embodiment, the monitor is installed in a protective box 12, and the protective box 12 is fixed on the secondary lining trolley 1.2-1.5m above the ground through a box bracket. Since blasting and ballast removal by transport vehicles will generate a lot of dust, and the air humidity in the tunnel is relatively high, the monitor must be waterproof and dustproof to avoid equipment damage or internal short circuit.
[0028] In this embodiment, the first conductor 22 and the second conductor 23 are symmetrical along the axis of the sleeve 21, and are exposed on both sides of the sleeve 21 respectively to contact the outside world. The template needs to vibrate during grouting to avoid concrete voids. The first conductor 22 and the second conductor 23 are arranged on both sides along the sleeve 21 to avoid accidental formation of a passage due to concrete splashing caused by vibration during vault grouting to the greatest extent.
[0029] In this embodiment, the first conductor 22 and the second conductor 23 are covered with a rubber sleeve, and the rubber sleeve is clamped in the hole on the inner wall of the sleeve 21. The sleeve 21 itself is also conductive, and the first conductor 22 and the second conductor 23 need to be insulated from each other. The use of the rubber sleeve has good insulation effect, low cost and easy installation.
[0030] In this embodiment, the top grouting hole 13 of the second lining trolley body 1 is arranged on both sides of the bottom of the top trolley template 11, and the height difference between the top grouting hole 13 and the highest point of the top trolley template 11 is 0.5-1.0m. The top grouting hole 13 is generally designed at the highest point of the top trolley template 11, but in this embodiment, it is necessary to avoid concrete splashing onto the first conductor 22 and the second conductor 23 during grouting, so the top grouting hole 13 is designed on both sides, but considering the grouting pressure of the grouting equipment, the height difference between the top grouting hole 13 and the highest point of the top trolley template 11 cannot be too large, and the preferred value of the height difference is 0.7m. Of course, the use of grouting equipment with a larger delivery pressure can adopt a larger height difference.
[0031] like Figure 3 As shown, the present invention also provides a construction method for preventing the vault from falling out, and the construction method for preventing the vault from falling out comprises the following steps:
[0032] Step 1: Construction preparation.
[0033] Carry out laser measurement on the initial support section and deal with the support section that does not meet the requirements; when the surrounding rock grade changes, the grade of the lining section should also change accordingly, but it needs to be approved by the design unit. The lining in the area with poor surrounding rock should be extended 10m to the area with good surrounding rock; implement the tunnel secondary lining trolley access system, and the secondary lining trolley must be accepted before entering the site.
[0034] Step 2: Overall installation of the second lining trolley.
[0035] The body of the secondary lining trolley itself is a secondary lining platform for steel bar processing. Steel rails are laid under the trolley for easy walking. Auxiliary parts such as telescopic components, hydraulic system, electrical control system, etc. are installed. At the same time, some preparation work is also done for the subsequent pouring of concrete: raising the top form, opening the side form, checking the clearance, cleaning the formwork; installing the conveying pipeline, head plate, water stop strip and embedded parts; finally, cleaning the cabin, repairing the panel, reinforcing the trolley, applying the release agent, etc.
[0036] Step 3: Grouting is performed on the arch walls on both sides of the tunnel, and at the same time, the motor 4 is started to drive the turbine screw lift 3 to lift the casing 21 to the specified position.
[0037] Pour concrete into the side molds on both sides of the tunnel (the cloth hanging trolley has been installed with steel bars when laying the waterproof board, and the second lining only needs to pour concrete). Open a working window on the side mold for concrete pouring and tamping. The poured concrete should be poured directly into the warehouse as much as possible. A connecting hose should be installed at the end of the concrete delivery pipe to control the vertical distance between the pipe mouth and the pouring surface. The concrete must not flow directly to the waterproof board surface to the pouring position. The vertical distance should be controlled within 1.2m to prevent concrete segregation. Pour the concrete to 50cm below the working window. Before closing the working window, the concrete slurry residue and other debris near the window should be cleaned up, and the mold release agent should be applied and closed to prevent uneven patches or even leakage on the concrete surface of the window. The position of the casing 21 is determined according to the grouting speed and the arch curve. The position cannot be too high to avoid excessive grouting due to the failure to close the concrete grouting pipe immediately after the monitor prompts, and the position cannot be too low to cause the arch to be emptied;
[0038] Step 4: Vault grouting and filling; when pouring the vault concrete, if the buzzer 24 of the monitor sounds and the warning green light 26 lights up, it means that the concrete has reached the designated position;
[0039] The spacing between grouting holes should be no greater than 3m, and the number of reserved holes within each formwork trolley should be no less than 4. The arch grouting filling should be carried out after the lining concrete strength reaches 100%. The strength grade of the injected mortar should meet the design requirements, and the grouting pressure should be controlled within 0.1MPa.
[0040] Step 5: Start the motor 4 to drive the turbine screw lift 3 to retract the sleeve 21 into the top trolley template 11 of the secondary lining trolley body 1.
[0041] When the concrete reaches the designated position, the staff is prompted to start the motor 4 to drive the turbine screw lift 3, and pay attention to the warning red light 25, preparing to stop the concrete vault grouting.
[0042] Step 6: The warning red light 25 comes on and the concrete vault grouting is stopped.
[0043] The red warning light 25 turns on, indicating that the amount of grouting of the vault has reached the ideal value. At this time, stopping the grouting of the concrete vault can prevent the vault from being emptied and the vault from being over-grouted.
[0044] Step 7: Demould and move the trolley.
[0045] After testing, the vault voiding rate using this technical solution was reduced from the original 4% to 0.1%. It can be determined that the adoption of the above technical solution can significantly reduce the vault voiding phenomenon, reduce construction costs, speed up construction progress and improve construction quality.
[0046] Finally, it should be noted that the above embodiments are only used to illustrate the technical solution of the present invention rather than to limit it. Although the present invention has been described in detail with reference to the preferred embodiments, those skilled in the art should understand that the technical solution of the present invention can be modified or replaced by equivalents without departing from the purpose and scope of the technical solution of the present invention, which should be included in the scope of the claims of the present invention.
Claims
1. A secondary lining trolley for preventing the vault from falling out, characterized in that: It includes a secondary lining trolley body and a liftable detection device arranged in the middle of the secondary lining trolley body; the liftable detection device includes a detection component, a worm gear screw lift and a motor; the detection component includes a sleeve coaxially arranged on the top of the screw of the worm gear screw lift, a first conductor and a second conductor independently arranged on the top of the inner wall of the sleeve and exposed from the sleeve, and a monitor whose positive and negative poles are electrically connected to the first conductor and the second conductor respectively; the motor drives the worm gear screw lift to make the sleeve slide in the vertical direction to realize the extension or retraction of the sleeve to the top trolley template of the secondary lining trolley body; the first conductor and the second conductor are insulated from each other, and the first conductor and the second conductor are symmetrical along the axis of the sleeve, and the top grouting hole of the secondary lining trolley body is arranged on both sides of the bottom of the top trolley template, and the height difference between the top grouting hole and the highest point of the top trolley template is 0.5-1.0m.
2. The secondary lining trolley for preventing the vault from falling out according to claim 1 is characterized in that: The monitor comprises a buzzer, a warning red light and a warning green light which are respectively connected in series with the power supply on the secondary lining trolley, and the warning red light is also connected in series with a controller.
3. The secondary lining trolley for preventing the vault from falling out according to claim 1 is characterized in that: The monitor is installed in a protection box, and the protection box is fixed on the secondary lining trolley at a distance of 1.2-1.5m from the ground through a box bracket.
4. The secondary lining trolley for preventing the vault from falling out according to claim 1 is characterized in that: The first conductor and the second conductor are covered with rubber sleeves, and the rubber sleeves are clamped in the holes on the inner wall of the sleeve.
5. The secondary lining trolley for preventing the vault from falling out according to claim 2 is characterized in that: A construction method for preventing the vault from falling out is also provided, wherein the construction method for preventing the vault from falling out comprises the following steps: Step 1: Construction preparation; Step 2: Overall installation of the secondary lining trolley; Step 3: Grouting is performed on the arch walls on both sides of the tunnel, and at the same time, the motor is started to drive the worm screw elevator to lift the casing to the specified position; Step 4: Vault grouting and filling: When pouring the vault concrete, if the buzzer of the monitor sounds and the warning green light comes on, it means that the concrete has reached the designated position; Step 5: Start the motor to drive the worm screw lift to retract the casing into the trolley template on the top of the secondary lining trolley body; Step 6: The warning red light comes on and the concrete vault grouting is stopped; Step 7: Demould and move the trolley.