Assembled support and hanger for integrated pipelines in subway stations and construction method thereof
By using prefabricated supports and hangers, centralized fixed pipelines and decorative ceiling booms in subway stations, the problems of porous civil structures and large space occupation are solved, saving space and improving installation efficiency.
Patent Information
- Application Number
- CN201910098683.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2019-01-31
- Publication Date
- 2024-10-01
- Estimated Expiration
- 2039-01-31
AI Technical Summary
When the subway station equipment system pipeline booms and decoration ceiling booms are installed independently, the civil concrete wall panels or beams become riddled with holes and occupy a large space, failing to effectively reduce the number of poles and save space.
The integrated pipeline assembly type support and hanger of the subway station is used, including cross arm beams, lateral fixed arms, fixed columns and diagonal braces. It is customized and processed in the factory and assembled on site to achieve centralized fixation of pipelines and decoration ceiling booms, reducing the need for civil engineering work. Structural punching and space occupation.
It greatly reduces secondary drilling damage to civil structures, saves pipeline installation space, improves installation efficiency, reduces costs, and avoids the risk of displacement during earthquakes through reasonable layout.
Smart Images

Figure CN109755907B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of metro engineering electromechanical installation, and in particular to an assembled support and hanger bracket for integrated pipelines of a metro station and a construction method thereof. Background Art
[0002] There are many types of pipelines in subway station equipment systems, and there are tens of thousands of hangers for independent installation of each pipeline and fixed hangers for station decoration ceilings. When all hangers need to be fixed by drilling holes on the civil engineering concrete wall panels or beams, the civil engineering concrete wall panels or beams become riddled with holes, and the independent installation of each pipeline requires a large installation space.
[0003] At present, although there are some different forms of assembled combined supports and hangers, they are still arranged in a classified manner. The pipeline supports and hangers are still organically combined with the decoration ceiling hangers, and the pipelines are either stacked up and down, occupying a large height space, or arranged in a flat row, adding fixed vertical poles connected to the civil concrete wall panels or beams. The problem of reducing the number of vertical poles and saving space has not been completely solved. Summary of the invention
[0004] The purpose of the present invention is to provide an assembled support and hanger bracket for integrated pipelines in a subway station and a construction method thereof, which can be customized and processed in the factory and can solve the problem of a large number of connection and fixing points between pipeline hangers of equipment systems in subway stations, decoration ceiling hangers and civil concrete wall panels or beams, and can effectively save pipeline installation space.
[0005] The technical solution adopted by the present invention is:
[0006] The assembled support and hanger for integrated pipelines in subway stations is characterized by:
[0007] The assembled support and hanger is installed below the bottom surface of the structural plate between the two side walls or beams in the subway station, and includes a crossbeam, a lateral fixed arm, a fixed column and a diagonal brace;
[0008] The cross beam is arranged horizontally between the wall panels on both sides, the two ends of the cross beam are fixedly connected with vertical lateral fixed arms, the upper middle of the cross beam is fixedly connected with a vertical fixed column, and the middle of the cross beam is also fixedly connected with at least one diagonal brace;
[0009] The lower part of the lateral fixed arm, the bottom end of the fixed column and the bottom end of the diagonal brace are all fixedly connected to the crossbeam;
[0010] The outer side of the lateral fixed arm is fixedly installed on the wall or the side of the beam, and the top of the fixed column and the diagonal brace is fixedly installed on the beam body;
[0011] The various components are prefabricated into finished components in a factory and assembled and fixed into a whole on the installation site.
[0012] A vertical pipeline support column is fixedly connected above the cross arm beam, and at least one set of pipeline support cross arms is connected between the pipeline support column and the lateral fixed arm or the fixed column.
[0013] Pipeline positioning pieces or pipe clamps are arranged on the cross arm beam or the cross arm of the pipeline support.
[0014] A pipeline hanger is arranged on the cross arm or the bottom surface of the cross arm beam of the pipeline support.
[0015] A decorative ceiling hanger is arranged on the bottom surface of the crossbeam.
[0016] The cross beam, lateral fixed arm, fixed column, pipeline support column and pipeline support cross beam are single or double C-shaped channel steel or I-beam.
[0017] The construction method of the assembled support and hanger for the integrated pipeline of the subway station is characterized by:
[0018] The following steps are involved:
[0019] A. According to the pipeline installation layout drawings and the components of the assembled supports and hangers determined by BIM layout, the fixed positions of the first group of assembled supports and hangers to be installed on the wall panels are determined by on-site inspection and layout, and the lateral fixed arms are installed in sequence by drilling holes on the wall panels; then the cross arm is connected to the lateral fixed arm and installed, and then the cross arm is detected and adjusted along the pipeline installation direction to accurately fix the height of the cross arm on the lateral fixed arm, and the height of the cross arm is locked after ensuring that there is no collision or conflict in the overall pipeline space; then the fixed position of the fixed column on the beam body is located, and the top of the fixed column is installed and tightened on the beam body, and then the bottom end of the fixed column is connected and tightened with the cross arm, and finally the fixed diagonal brace is connected in this order; then the maximum pipeline width space to be installed in multiple layers is detected and adjusted longitudinally, and the precise positioning of the pipeline support column on the cross arm is locked after ensuring that there is no collision or conflict in the overall pipeline space, and finally the cross arm of the fixed pipeline support is connected in this order;
[0020] B. According to the process of step A, sequentially construct and install the assembled supports and hangers described in each subsequent group;
[0021] C. After completing step B, start to install the pipeline or cable tray in sections on the installed assembled support and hanger, and check in time according to the pipeline installation layout drawing and the on-site space to ensure that it does not affect the subsequent laying and installation of other pipelines, and then use pipeline positioning pieces or pipe clamps to fasten or directly lock them;
[0022] D. Follow the process of step C to install each pipeline or cable tray in sequence until all pipelines and cable trays are installed;
[0023] E. According to the decoration ceiling design or layout detailed drawings and the actual position of the crossbeam of the assembled support and hanger that has been completed on site, locate and check the accurate position of the decoration ceiling hanger, and install and fix and lock the decoration ceiling hanger after confirming that it is correct;
[0024] F. After completing step E, start installing and connecting the decorative ceiling keels in sequence, and then install the decorative ceiling.
[0025] The present invention has the following advantages:
[0026] (1) The pipelines of various equipment systems of the subway station are centrally arranged on the prefabricated support and hanger brackets. At the same time, the hangers of the subway station decoration ceiling are directly fixed on the cross beams of the prefabricated support and hanger brackets, which greatly reduces the number of hangers directly fixed on the civil engineering concrete wall panels or beams and the secondary drilling damage to the civil engineering structure.
[0027] (2) In a limited space, through the organic combination of parallel arrangement and stacking, the spatial layout is rationally planned, the pipeline installation space is saved, and the maximum advantage of the assembled support and hanger is brought into play.
[0028] (3) By connecting and fixing the lateral fixed arms, diagonal braces and civil engineering concrete wall panels or beams, it is possible to prevent the assembled support and hanger system from undergoing large lateral or longitudinal horizontal displacements when an earthquake occurs.
[0029] (4) BIM technology can be used to lay out and cut materials, and the factory can customize the processing, reducing material waste and overcoming the difficulties of on-site processing and production.
[0030] (5) Through reasonable process steps and construction methods, the overall construction and installation are unified to avoid pipeline dismantling or rework, improve installation efficiency and reduce installation costs. BRIEF DESCRIPTION OF THE DRAWINGS
[0031] Figure 1 It is a front view of the present invention.
[0032] Figure 2 It is a top view of the present invention.
[0033] Figure 3 It is a construction step diagram of the present invention.
[0034] In the figure, 1-cross beam, 2-lateral fixed arm, 3-fixed column, 4-diagonal brace, 5-pipeline support column, 6-pipeline support cross arm, 7-connecting piece, 8-fastener, 91-decoration ceiling hanger, 92-pipeline hanger, 10-pipe clamp, 11-pipeline positioning piece, 12-civil construction concrete wall panel or beam. DETAILED DESCRIPTION
[0035] The present invention is described in detail below in conjunction with specific implementation modes.
[0036] The present invention relates to an assembled support and hanger structure for integrated pipelines of a subway station. Through BIM technology, material cutting and factory customization are carried out, and finally all components only need to be assembled at the construction and installation site.
[0037] The assembled support and hanger is installed below the bottom surface of the structural plate between the two side walls or beams in the subway station, and includes a crossbeam 1, a lateral fixed arm 2, a fixed column 3 and a diagonal brace 4. The crossbeam 1 is arranged horizontally between the two side walls or beams, and the two ends of the crossbeam 1 are fixedly connected with vertical lateral fixed arms 2, and the upper middle part of the crossbeam 1 is fixedly connected with a vertical fixed column 3. The middle part of the crossbeam 1 is also fixedly connected with at least one diagonal brace 4, which can prevent the assembled support and hanger system from undergoing a large longitudinal horizontal displacement when an earthquake occurs. The lower part of the lateral fixed arm 2, the bottom end of the fixed column 3 and the bottom end of the diagonal brace 4 are all fixedly connected to the crossbeam 1. The outer side of the lateral fixed arm 2 is directly fixedly installed on the side wall plate or beam, which can prevent the assembled support and hanger system from undergoing a large lateral horizontal displacement when an earthquake occurs. The top ends of the fixed column 3 and the diagonal brace 4 are fixedly installed to the bottom surface of the beam or structural plate.
[0038] Each component is prefabricated into a finished component in the factory and assembled and fixed into a whole at the installation site. Only the top of the lateral fixed arm 2 and the top of the fixed column 3 and the top of the diagonal brace 4 are directly fixed to the civil concrete wall slab or beam 12 through the connecting piece 7 and the fastener 8 respectively. The remaining components are connected and fixed to each other through the connecting piece 7 and the fastener 8.
[0039] The lower part of the lateral fixed arm 2, the bottom end of the fixed column 3 and the bottom end of the diagonal brace 4 are all connected and fixed to each other through the connector 7 and the fastener 8, and are not connected and fixed to the civil concrete wall slab or beam 12. The connector is a small part that connects the components to each other, and the fastener is a bolt.
[0040] At least one vertical pipeline support column 5 is fixedly connected to the cross arm beam 1 via a connector 7 and a fastener 8, and at least one set of pipeline support cross arms 6 is fixedly connected between the pipeline support column 5 and the lateral fixed arm 2 or the fixed column 3 via a connector 7 and a fastener 8. A pipeline positioning member 11 or a pipe clamp 10 is provided on the cross arm beam 1 or the pipeline support cross arm 6.
[0041] The pipeline support cross arm 6 or the bottom surface of the cross arm beam 1 is provided with a pipeline hanger 92. The bottom surface of the cross arm beam 1 is provided with a decoration ceiling hanger 91.
[0042] The decoration ceiling hanger 91 is directly connected and fixed to the lower side of the crossbeam 1 through the connector 7 and the fastener 8. The pipeline hanger 92 and the pipe clamp 10 are respectively connected and fixed to the crossbeam 1 or the pipeline support crossbeam 6 through the connector 7 and the fastener 8. The pipeline positioning member 11 is connected to the crossbeam 1 or the pipeline support crossbeam 6 through the fastener 8 to prevent the pipeline from moving horizontally to the left and right.
[0043] The crossbeam 1, lateral fixed arm 2, fixed column 3, pipeline support column 5 and pipeline support crossbeam 6 are single or double C-shaped channel steel or I-beam, so that the connecting part 7 can be flexibly moved and adjusted in relative position thereon to meet the needs of fine-tuning the positioning position of the on-site pipeline installation.
[0044] Due to the different civil engineering space conditions of the specific station and the specifications and quantity of pipelines in each equipment system, the crossbeam 1, lateral fixed arm 2, fixed column 3, diagonal brace 4, pipeline support column 5, pipeline support crossbeam 6, etc. need to be subjected to BIM technology three-dimensional modeling and collision inspection, force calculation and analysis, specification selection, material generation, layout and cutting according to the specific pipeline comprehensive design or layout deepening drawings, and then customized processing in the factory. Except for the above-mentioned components, other components (including connectors 7, fasteners 8, decoration ceiling hangers 91, pipeline hangers 92, pipe clamps 10, pipeline locators 11, etc.) can be directly selected for finished product specifications.
[0045] The construction method of the above-mentioned subway station integrated pipeline assembled support and hanger comprises the following steps:
[0046] A. According to the pipeline installation layout drawings and the components of the assembled supports and hangers determined by BIM layout, the fixed positions of the first group of assembled supports and hangers to be installed on the wall panels are determined by on-site inspection and layout, and the lateral fixed arms 2 are installed on the wall panels in sequence; then the cross arm 1 is connected to the lateral fixed arm 2 and installed, and then the cross arm 1 is precisely fixed on the lateral fixed arm 2 along the pipeline installation direction, and then the height of the cross arm 1 is locked after ensuring that there is no collision or conflict in the overall pipeline space; then the fixed position of the fixed column 3 on the beam body is located, and the top of the fixed column 3 is installed and tightened on the beam body, and then the bottom end of the fixed column 3 is connected and tightened with the cross arm 1, and finally the fixed diagonal brace 4 is connected in this order; then the maximum pipeline width space to be installed in multiple layers is longitudinally detected and adjusted to precisely position the pipeline support column 5 on the cross arm 1, and the pipeline support column 5 is locked after ensuring that there is no collision or conflict in the overall pipeline space, and finally the fixed pipeline support cross arm 6 is connected in this order;
[0047] B. According to the process of step A, sequentially construct and install the assembled supports and hangers described in each subsequent group;
[0048] C. After completing step B, start to piece together the pipelines or cable trays on the installed assembled support and hanger in sections, and check in time according to the pipeline installation layout drawing and the on-site space to ensure that it does not affect the subsequent laying and installation of other pipelines, and then use pipeline positioning pieces 11 or pipe clamps 10 to fasten or directly lock them;
[0049] D. Follow the process of step C to install each pipeline or cable tray in sequence until all pipelines and cable trays are installed;
[0050] E. According to the decoration ceiling design or layout deepening drawing and the actual position of the cross arm beam 1 of the assembled support and hanger that has been completed on site, locate and check the accurate position of the decoration ceiling hanger 91, and install and fix and lock the decoration ceiling hanger 91 after confirming that it is correct;
[0051] F. After completing step E, start installing and connecting the decorative ceiling keels in sequence, and then install the decorative ceiling.
[0052] The content of the present invention is not limited to the embodiments listed, and any equivalent changes made to the technical solution of the present invention by ordinary technicians in this field after reading the description of the present invention are covered by the claims of the present invention.
Claims
1. The construction method of the assembled support and hanger for the integrated pipeline of the subway station is characterized by: The following steps are involved: A. According to the pipeline installation layout drawing and the components of the assembled support and hanger determined by BIM layout, the fixed positions of the first group of assembled support and hanger to be installed on the wall panel are determined by on-site inspection and layout, and the lateral fixed arms (2) are installed by drilling holes on the wall panel in sequence; then the cross arm (1) is connected to the lateral fixed arm (2) and installed, and then the cross arm (1) is longitudinally detected and adjusted along the pipeline installation direction. The height of the cross arm (1) is locked after ensuring that there is no collision or conflict in the overall pipeline space; Then locate the fixed position of the fixed column (3) on the beam body, and drill holes on the beam body to install and tighten the top of the fixed column (3), then connect and tighten the bottom end of the fixed column (3) to the crossbeam (1), and finally connect the fixed diagonal brace (4) in this order; then longitudinally detect and adjust the precise positioning of the pipeline support column (5) on the crossbeam (1) according to the maximum pipeline width space to be installed in multiple layers, ensure that there is no collision or conflict in the overall pipeline space, and then lock the pipeline support column (5), and finally connect the fixed pipeline support crossbeam (6) in this order; B. According to the process of step A, sequentially construct and install the assembled supports and hangers described in each subsequent group; C. After completing step B, start to install the pipeline or cable tray in sections on the installed assembled support and hanger, and check in time according to the pipeline installation layout drawing and the on-site space to ensure that it does not affect the subsequent laying and installation of other pipelines, and then use pipeline positioning pieces (11) or pipe clamps (10) to fasten or directly lock them; D. Follow the process of step C to install each pipeline or cable tray in sequence until all pipelines and cable trays are installed; E. According to the decoration ceiling design or layout detailed drawing and the actual position of the crossbeam (1) of the assembled support and hanger that has been constructed on site, locate and check the accurate position of the decoration ceiling hanger (91), and after confirming that it is correct, install and fix and lock the decoration ceiling hanger (91); F. After completing step E, start to install and connect the decoration ceiling keels in sequence, and install the decoration ceiling; The subway station integrated pipeline assembly-type support and hanger constructed according to the construction method is installed below the beam body between the wall panels on both sides of the subway station, and comprises a crossbeam (1), a lateral fixed arm (2), a fixed column (3) and a diagonal brace (4); The cross beam (1) is arranged horizontally between the wall panels on both sides. Vertical lateral fixed arms (2) are fixedly connected to the upper parts of both ends of the cross beam (1). A vertical fixed column (3) is fixedly connected to the upper part of the middle of the cross beam (1). Front and rear symmetrical diagonal braces (4) are also fixedly connected to the upper part of the middle of the cross beam (1). The bottom ends of the lateral fixed arms (2), the fixed columns (3) and the diagonal braces (4) are all fixedly connected to the crossbeam (1), and the components are prefabricated in a factory and connected into a whole; The outer side of the lateral fixing arm (2) is fixedly mounted to the wall panel, and the top ends of the fixing columns (3) and the diagonal braces (4) are fixedly mounted to the beam body.
2. The construction method of the subway station integrated pipeline assembly support and hanger according to claim 1 is characterized by: A vertical pipeline support column (5) is fixedly connected above the cross arm beam (1), and a pipeline support cross arm (6) is connected between the pipeline support column (5) and the lateral fixed arm (2) or the fixed column (3).
3. The construction method of the subway station integrated pipeline assembly support and hanger according to claim 2 is characterized by: A pipeline positioning piece (11) or a pipe clamp (10) is provided on the cross arm beam (1) or the pipeline support cross arm (6).
4. The construction method of the subway station integrated pipeline assembly support and hanger according to claim 2 is characterized by: A pipeline hanger rod (92) is provided on the bottom surface of the pipeline support cross arm (6).
5. The construction method of the subway station integrated pipeline assembly support and hanger according to claim 1 is characterized by: A decoration ceiling hanging rod (91) is arranged on the bottom surface of the cross arm beam (1).
6. The construction method of the subway station integrated pipeline assembly support and hanger according to claim 2 is characterized by: The cross arm beam (1), the lateral fixed arm (2), the fixed column (3), the pipeline support column (5) and the pipeline support cross arm (6) are single or double C-shaped channel steel or I-shaped steel.