A liquid nitrogen freezer with a partition plate on a freezing tube and a construction method
A freezing tube and freezer technology, which is used in infrastructure engineering, soil protection, construction, etc., can solve problems such as poor uniformity of frozen walls, inability to precisely control the development of frozen soil, and difficult control.
Patent Information
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Publication Date
- 2020-09-04
Smart Images

Figure 1 
Figure 2 
Figure 3
Abstract
Description
technical field
[0001] The patent of the present invention relates to a liquid nitrogen freezer with partitions on the freezing pipe and its construction method, especially suitable for the freezing pipe with partitions used in the construction of the rapid emergency freezing method to seal water and reinforce the frozen section of soil. Liquid nitrogen freezer and construction method. Background technique
[0002] The artificial freezing method uses artificial refrigeration technology to freeze the water in the formation, turn the natural rock and soil into frozen soil, increase its strength and stability, and isolate the connection between groundwater and underground engineering, so that construction can be carried out under the protection of the frozen wall. There are two commonly used construction methods, one is salt water freezing, and the other is liquid nitrogen freezing. Both methods have their own advantages and disadvantages. Liquid nitrogen quick freezing is ofte...
Examples
specific Embodiment
[0034] The first step is to measure the depth range of the bottom layer that needs to be frozen according to the needs of actual construction. According to the measurement situation, open spray holes 3 along the direction of the freezing pipe 1 where holes need to be opened, and do not open spray holes 3 at positions that do not need to be frozen. Five spring supports 10 are welded at the inner edge of the plate, and the upper and lower sides of the circular dividing plate 4 are welded with the freezing tubes 1 at both ends to form a joint between the dividing plate and the freezing tube 1 in the middle. According to the needs of freezing depth during construction, joints with partitions are welded at different positions of the freezing tube 1 to form liquid nitrogen freezing tubes 1 with different partition intervals;
[0035] In the second step, use the plugging 5 to block one end of the liquid supply pipe, and insert the liquid supply pipe along the spring support 10 on the ...