A temporary roof for a reactor building with an umbrella-shaped foldable opening and closing type
Through the temporary ceiling design of the umbrella-shaped folding open-close reactor factory, the use of three-dimensional steel brackets, steel cables, membrane materials and motor systems, the existing ceiling efficiency and insufficient structure are solved, and high reliability and convenient operation are achieved , meets the progress and safety needs of the project construction.
Patent Information
- Application Number
- CN201910527205.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2019-06-18
- Publication Date
- 2024-11-01
- Estimated Expiration
- 2039-06-18
AI Technical Summary
The temporary ceiling of the existing reactor factory has low opening and closing efficiency, insufficient structural strength, short service life, and complex installation and disassembly processes, interferes with the hoisting of the internal housing facilities, and is unable to achieve fully automated operations, which increases the risk of high-altitude operations.
Adopt the umbrella-shaped folding open-close temporary ceiling design, including three-dimensional steel brackets, steel cables, membrane materials, motors and support devices. The expansion and closing of membrane materials are realized through an automated motor system, combined with automatic locking devices and auxiliary facilities to achieve rapid , safely turn on and off.
It improves the reliability of the roof and the convenience of maintenance, meets the construction progress and safety requirements of the project, reduces the danger of high-altitude operations, and realizes fully automated operation and longer service cycles.
Smart Images

Figure CN110219409B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to a simulation verification platform, in particular to an umbrella-shaped folding and retractable temporary roof cover for a reactor plant. Background Art
[0002] Since the third-generation nuclear power technology represented by AP1000 adopted the open-top construction method, equipment and bulk materials are hoisted in sequence before the reactor building completes the structural capping, which has changed the traditional construction and installation boundaries.
[0003] On the one hand, the open-top construction method is conducive to the parallel development of civil engineering and installation operations, shortening the construction period. On the other hand, the open-top construction method exposes the reactor building directly to the atmospheric environment during construction, making it more susceptible to the effects of rain, snow and typhoons.
[0004] Installing a temporary cover for the nuclear island is a temporary measure to address the impacts caused by environmental changes. However, the current temporary cover has many problems such as low opening and closing efficiency, insufficient structural strength and short service life. It is impossible to fully utilize the temporary cover while meeting the requirements of project construction progress and safety. Moreover, the structure is relatively complex, and the installation and disassembly process is difficult. It seriously interferes with the lifting of facilities inside the shell during use.
[0005] In addition, it brings many inconveniences to the installation and use of the ring crane, and it is impossible to achieve fully automated operation, which is labor-intensive and time-consuming, and greatly increases the risk of high-altitude operations.
[0006] Therefore, there is a particular need for an umbrella-shaped folding and retractable temporary roof for a reactor building to solve the above-mentioned existing problems. Summary of the invention
[0007] The object of the present invention is to provide an umbrella-shaped folding and retractable temporary roof cover for a reactor building, which aims to overcome the deficiencies of the prior art and has high reliability and is convenient for inspection and maintenance.
[0008] The technical problem solved by the present invention can be achieved by adopting the following technical solutions:
[0009] A temporary roof for an umbrella-shaped folding and retractable reactor building, characterized in that it comprises a three-dimensional steel support, a plurality of steel cables, a membrane material, a motor and a supporting device; the three-dimensional steel support is arranged on the top of a nuclear island containment, the non-combining end of the three-dimensional steel support is fixed on the shell of the nuclear island containment, the combining end of the three-dimensional steel support is arranged on the upper end of the top of the nuclear island containment, the supporting device is arranged on the nuclear island containment, a motor track is laid on the supporting device, the motor runs on the motor track, one end of the steel cable is fixed to the combining end of the three-dimensional steel support, the other end of the steel cable is fixed to the motor, and the membrane material is laid on the steel cable.
[0010] In one embodiment of the present invention, the three-dimensional steel support is divided into three supports, the plane angle between the supports is 120°, and the height of the combined end of the three-dimensional steel support from the top plane of the nuclear island containment is 5-15m.
[0011] In one embodiment of the present invention, a rotating shaft is provided at the combined end of the three-dimensional steel support, and one end of the steel cable is fixed on the rotating shaft.
[0012] In one embodiment of the present invention, the number of the steel cables is 3-48, the lengths are uniform, and the cables can simultaneously unfold, gather and tension the membrane material.
[0013] In one embodiment of the present invention, the membrane material includes but is not limited to PTFE membrane material, glass fiber PVC architectural membrane material, glass fiber silicone resin architectural membrane material, glass fiber synthetic rubber architectural membrane material and ETFE membrane material.
[0014] In one embodiment of the present invention, the membrane material is provided with folds along the direction of the steel cables, a fold is provided at the junction of each steel cable and the membrane material, and a fold is also provided between every two steel cables.
[0015] In one embodiment of the present invention, the steel cables are fixed to different motors by steel cable anchors, and the number of the motors is greater than one and not greater than the number of the steel cables.
[0016] In one embodiment of the present invention, automatic locking devices are provided at both ends of the joint after the membrane material is unfolded. The automatic locking devices are arranged along the direction of the steel cables through automatic locking device fixing rods and are arranged on two steel cables that are close to each other when unfolded.
[0017] In one embodiment of the present invention, auxiliary facilities are provided on the top of the joint end of the three-dimensional steel support, and the auxiliary facilities include but are not limited to snow melting equipment, lightning rods, maintenance passages and ventilation equipment.
[0018] Compared with the prior art, the umbrella-shaped folding and retractable temporary roof cover for a reactor building of the present invention adopts a shape similar to an umbrella and can be automatically opened or closed by folding; when opened, it can meet the requirements of the reactor building for lighting, ventilation or hoisting, etc.; when closed, it can meet the requirements for wind protection, rain protection and snow protection; the use process has high reliability and is convenient for inspection and maintenance, thereby achieving the purpose of the present invention.
[0019] The features of the present invention can be clearly understood by referring to the drawings and the following detailed description of the preferred embodiments. BRIEF DESCRIPTION OF THE DRAWINGS
[0020] Figure 1 It is a structural schematic diagram of the reactor building containment of the present invention;
[0021] Figure 2 It is a three-dimensional schematic diagram of the temporary top cover of the present invention in a closed state;
[0022] Figure 3 It is a three-dimensional schematic diagram of the temporary cover of the present invention when it is in an open state;
[0023] Figure 4 It is a top view schematic diagram of the temporary top cover of the present invention in a closed state;
[0024] Figure 5 It is a top view schematic diagram of the temporary top cover of the present invention in an open state;
[0025] Figure 6 It is a schematic structural diagram of the temporary top cover rotating shaft of the present invention. DETAILED DESCRIPTION
[0026] In order to make the technical means, creative features, objectives and effects achieved by the present invention easy to understand, the present invention is further explained below with reference to specific diagrams.
[0027] Example
[0028] like Figures 1 to 6 As shown, the umbrella-shaped folding and retractable temporary roof cover of the reactor building of the present invention includes a three-dimensional steel bracket 3 located on the top of the nuclear island containment 1 for supporting; a plurality of steel cables 4 for unfolding, folding and stretching the membrane material 7; the membrane material 7 stretched by the steel cables 4; a motor 10 for stretching and running the steel cables 4; a motor track 5 for maintaining the running direction of the motor 10; a plurality of automatic locking devices 8 and automatic locking device fixing rods 6; a rotating shaft 9; a supporting device 2 and auxiliary facilities 11 for realizing the operation of the roof.
[0029] The three-dimensional steel bracket 3 is located at the top of the nuclear island containment and is divided into three brackets with a plane angle of 120°. The non-bonded end of the three-dimensional steel bracket 3 is fixed on the shell of the nuclear island containment 1, and the bonded end of the three-dimensional steel bracket 3 is 5-15m high from the top plane of the nuclear island containment 1.
[0030] A rotating shaft 9 is provided at the joint end of the three-dimensional steel support 3 , and the rotating shaft 9 plays the role of stretching and rotating the steel cable 4 .
[0031] One end of the steel cable 4 is pulled on the rotating shaft 9, and the other end of the steel cable 4 is fixed to the motor 10 to achieve tensioning at both ends. The number of steel cables 4 is between 3 and 48, and the length is consistent, and they play the role of simultaneously unfolding, retracting and tensioning the membrane material 7.
[0032] The types of membrane materials 7 include PTFE membrane materials, glass fiber PVC architectural membrane materials, glass fiber silicone resin architectural membrane materials, glass fiber synthetic rubber architectural membrane materials, ETFE membrane materials and other types of special membrane materials.
[0033] The membrane material 7 is provided with folds 12 along the direction of the steel cables 4, a fold 12 is provided at the junction of each steel cable 4 and the membrane material 7, and a fold 12 is also provided between every two steel cables 4. The folds 12 must be specially processed so as to meet the requirements of strength and service life during repeated expansion and contraction.
[0034] The steel cables 4 are all fixed to different motors 10 through steel cable anchors. The number of motors 10 may be less than the number of steel cables 4. The number of motors 10 is greater than 1, and driven wheel locks can be used at other positions. The motors 10 control the stretching, unfolding and retracting of the steel cables 4 and the membrane material 7.
[0035] The motor 10 has an internal brake device to control the operation of the motor 10. The motor 10 runs on a motor track 5, which is laid on the support device 2.
[0036] After the membrane material 7 is unfolded, the two ends of the joint are installed with automatic locking devices 8, which play the role of automatic combination, so that the entire roof remains in the unfolded state. The automatic locking device 8 is installed on the automatic locking device fixing rod 6, which is arranged along the direction of the steel cable 4 and arranged on two steel cables 4 that are close to each other when unfolded.
[0037] After the membrane material 7 and the steel cable 4 are gathered by the motor 10, they are fixed under one of the steel supports of the three-dimensional steel support 3. The auxiliary facilities 11 include snow melting equipment, lightning rods, maintenance passages, ventilation equipment, and the like.
[0038] When the weather changes and precautions need to be taken, at the beginning, the two motors 10 at the outermost end of the closure are the first to pull the steel cables 4 to slide symmetrically along the motor track 5 at the same time. After the two motors 10 slide a certain distance, the two adjacent motors 10 begin to slide in the same way, and the remaining motors 10 slide and run in the same way, and the running distance of the motors 10 is controlled by the brake device of the motor 10. During the whole process, one end of the steel cables 4 connected to the rotating shaft 9 also slides at the same time until all the steel cables 4 and the entire membrane material 7 are fully unfolded. After all are unfolded, the two motors 10 at the outermost end are in contact, and the automatic locking device 8 is started to achieve automatic locking.
[0039] When the weather conditions are good, when the folding begins, the automatic locking device 8 opens, and the two motors 10 at the locking position slide in opposite directions along the motor track 5 at the same time, and the remaining motors 10 slide and operate in the same way. During the whole process, one end of the steel cable 4 connected to the rotating shaft 9 also slides at the same time until all the steel cables 4 and the entire membrane material 7 are completely folded, and then all the membrane materials 7, the steel cables 4 and the motors 10 are fixed under one of the steel supports of the three-dimensional steel support 3 through the braking device of the motor 10.
[0040] When installing the ring crane, only one or all of the three-dimensional steel brackets 3 need to be removed, and then the ring crane is installed. After the ring crane is installed, the removed part is installed to restore the function of the roof. The whole process uses the same crane.
[0041] In order to ensure the safe operation of the entire temporary roof and improve the construction environment inside the reactor building, some auxiliary facilities 11 need to be installed, including snow melting equipment, lightning rods, maintenance passages, ventilation equipment, etc.
[0042] The above shows and describes the basic principles and main features of the present invention and the advantages of the present invention. Those skilled in the art should understand that the present invention is not limited to the above embodiments, and the above embodiments and descriptions are only for explaining the principles of the present invention. Without departing from the spirit and scope of the present invention, the present invention may have various changes and improvements, which fall within the scope of the present invention to be protected, and the scope of the present invention to be protected is defined by the attached claims and their equivalents.
Claims
1. An umbrella-shaped foldable temporary roof for a reactor building, characterized in that: It includes a three-dimensional steel support, a plurality of steel cables, a membrane material tensioned by the steel cables, a motor and a supporting device; the three-dimensional steel support is arranged on the top of the nuclear island containment, the non-joined end of the three-dimensional steel support is fixed on the shell of the nuclear island containment, the joined end of the three-dimensional steel support is arranged on the upper end of the top of the nuclear island containment, the supporting device is arranged on the nuclear island containment, a motor track is laid on the supporting device, the motor runs on the motor track, one end of the steel cable is fixed on the joined end of the three-dimensional steel support, the other end of the steel cable is fixed to the motor, and the membrane material is laid on the steel cable; The three-dimensional steel bracket is divided into three brackets, the plane angle between the brackets is 120°, and the height of the combined end of the three-dimensional steel bracket from the top plane of the nuclear island containment is 5-15m; A rotating shaft is provided at the combined end of the three-dimensional steel bracket, and one end of the steel cable is fixed on the rotating shaft; After the membrane material is unfolded, both ends of the joint are provided with automatic locking devices, which are arranged along the direction of the steel cable through the automatic locking device fixing rod and are arranged on the two steel cables that are close to each other when unfolded; When closing, the two motors at the outermost ends first pull the steel cables to slide symmetrically along the motor track at the same time. After the two motors slide one end distance, the two adjacent motors begin to slide in the same way, and the remaining motors slide and run in the same way, and the motor's running distance is controlled by the motor's brake device. During the whole process, one end of the steel cable connected to the rotating shaft also slides at the same time until all the steel cables and the entire membrane material are fully unfolded. After all are unfolded, the two motors at the outermost ends contact and start the automatic locking device to achieve automatic locking; When the folding starts, the automatic locking device opens, and the two motors at the lock slide in opposite directions along the motor track at the same time, and the remaining motors slide and operate in the same way. During the whole process, one end of the steel cable connected to the rotating shaft also slides at the same time until all the steel cables and the entire membrane material are fully folded, and then the brake device of the motor is used to fix all the membrane materials, steel cables and motors under one of the three-dimensional steel brackets; The membrane material is provided with folds along the direction of the steel cables, a fold is provided at the junction of each steel cable and the membrane material, and a fold is also provided between every two steel cables; The membrane materials include PTFE membrane materials, glass fiber PVC architectural membrane materials, glass fiber silicone resin architectural membrane materials, glass fiber synthetic rubber architectural membrane materials, and ETFE membrane materials.
2. The umbrella-shaped foldable reactor building temporary roof as claimed in claim 1, characterized in that: The number of the steel cables is 3-48 and the lengths are the same.
3. The umbrella-shaped foldable reactor building temporary roof as claimed in claim 1, characterized in that: The steel cables are fixed to different motors through steel cable anchors, and the number of the motors is greater than one and not greater than the number of the steel cables.
4. The umbrella-shaped foldable reactor building temporary roof as claimed in claim 1, characterized in that: Auxiliary facilities are arranged on the top of the combined end of the three-dimensional steel support, and the auxiliary facilities include snow melting equipment, lightning rod, maintenance passage and ventilation equipment.