A facility for taking water from a rapid riverbed and its overall installation and construction method
By using technologies such as positioning steel pipe piles and drilling and explosion boats in rapid riverbeds, a steel truss platform was established, and the dry operation of water intake facilities was realized, which solved the construction safety and environmental protection problems in rapid riverbeds, and reduced construction costs and cycles.
Patent Information
- Application Number
- CN201910685711.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2019-07-28
- Publication Date
- 2024-11-05
- Estimated Expiration
- 2039-07-28
AI Technical Summary
The installation of water intake facilities in rapid riverbeds has problems such as high construction safety risks, difficulty in meeting environmental protection standards, long construction cycles and high construction costs. The existing technology is difficult to be applicable to rapid riverbed environments.
The steel truss platform is established by using the positioning steel pipe pile support system, deep hole blasting and drilling are carried out through drilling and explosion boats and pile driving boats, and the overall dry operation of the water intake head and water diversion pipe is achieved using hand-pulled hoists and hoisting equipment to reduce the water flow rate. And avoid underwater diving charges.
The safe, environmentally friendly and efficient installation of water intake facilities in rapid riverbeds has been achieved, which shortens the construction cycle and reduces costs, avoids underwater diving loading, and ensures the safety and environmental protection of the construction area.
Smart Images

Figure CN110295648B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the field of water intake facilities during the construction period of a waterworks or a pump house, and in particular to a water intake facility in a rapid riverbed and an overall installation construction method thereof. Background Art
[0002] Water intake facilities generally refer to water intake heads, water diversion pipes, and bell-shaped docking facilities at the junction of water intake heads and water diversion pipes. Their construction and installation have always been one of the most critical processes during the construction period of water plants. There are problems such as high construction safety risks, difficulty in meeting environmental protection standards, long construction periods, and high construction costs. In the prior art, the solutions adopted by those skilled in the art to solve the above technical problems are generally divided into two methods: wading operations and water-land conversion dry operations, which are used for the installation of water intake facilities. During wading operations, the floating sinking installation method is usually adopted. The pipeline is floated to the predetermined waters in sections, water is injected and sunk to the predetermined position, and ships and raft boats are used to assist in the implementation. The water-land conversion dry operation is relatively simple and clear, that is, the water flow is guided by burying pipes, diversion, etc., and then the water is pumped out by cofferdams, caissons, etc. to form dry land conditions for operation. However, the water-land conversion dry operation is suitable for shallow water, slow flow, and non-navigable working conditions. The premise of floating sinking installation during wading operations must be in sections, slow flow, and low navigation requirements.
[0003] For example, when installing water intake facilities in the Jinsha River (which belongs to the central navigation area of the Jinsha River Basin, the first-level water source, and the Chinese sturgeon protection area) at a distance of 20m to 80m from the shore, a water depth of 9m, and a flow rate of 6m / s, (specifically: two φ1420×14mm water diversion pipes (the underwater part of which is K0+000~K0+055) and a ship-shaped steel structure water intake head of 12.4m long, 3.6m wide, and 5.9m high (with a total weight of 36.9 tons)), and navigation conditions must be reserved, the safety risk of using the segmented floating cloud sinking installation method is huge. Therefore, it is a topic worthy of exploration and research to develop a new process and method suitable for the installation of water intake facilities in the rapids riverbed, and to take practical and effective measures in the rapids riverbed to solve the installation problems of water intake facilities in terms of construction period, cost-effectiveness, safety and quality control. Summary of the invention
[0004] The purpose of the present invention is to take effective measures in the rapid riverbed to reduce the water flow speed in the construction area, avoid underwater diving charge, and solve the installation problem of water intake facilities.
[0005] In order to solve the above technical problems, the present invention provides the following technical solutions:
[0006] The invention discloses a facility for taking water from a rapid riverbed, which is characterized in that it includes a water diversion pipe, a positioning steel pipe pile, a connecting beam parallel to the axis of the water diversion pipe, a pile cap, an I-beam crossbeam, a distribution beam, a steel panel, a column, a load-bearing beam, a water intake head, a water intake head flower rack, a water retaining facility, a crossbeam frame pipe, a railing, a sidewalk slab, a lifting ring weldment, a hand chain hoist, a canvas lifting sling, a roller, a water diversion pipe flower rack, and a connecting beam perpendicular to the axis of the water diversion pipe; the water diversion pipe includes a bell mouth and a straight section, and the water intake facility draws water from the center of the river for domestic and production water through a water intake pipeline, and is composed of a water intake head and a water diversion pipe; a water diversion pipe truss working platform and a bell mouth assembly working platform are established with the positioning steel pipe pile position as the support system, and on the truss level A construction passage is set up downstream of the platform for personnel to go up and down. An I-beam is installed on the top of every three rows of vertical positioning steel pipe piles. Two 10T hand winches are arranged on each I-beam to be used for binding and lifting pipes. With the positioning steel pipe piles as the support system, a 14m×5m steel truss platform is established as a welding and lifting work platform for the water intake head steel components. Two door-type brackets are set up on the platform in the longitudinal direction of the water flow direction of the water intake facility. The two door-type brackets are connected by load-bearing beams and flower racks to form a frame structure. Two 20T hand winches are arranged on each load-bearing beam to be used for lifting the water intake head by rings. The water intake facilities connected as a whole are lowered into the trough by using mooring cranes and hand winches to realize the dry operation of assembling the water intake head and connecting it with the water diversion pipe.
[0007] A method for overall installation and construction of a facility for taking water from a rapid riverbed, characterized in that it comprises the following steps:
[0008] (1): Use barges and drilling and blasting ships to construct double-row steel tube truss single-wall water retaining boards in a step-by-step manner using steel trusses and steel panels to reduce the water flow velocity in the construction area;
[0009] (2): Use a drilling and blasting ship to excavate the trench for the water intake facility by underwater deep hole blasting with a blasthole diameter of 90 mm, a hole depth of more than 5 m, micro-difference blasting between rows, and controlled single-stage explosive quantity;
[0010] (3): Use a pile-driving ship with a drilling rig to follow the pipe and drill and construct small-diameter steel pipe positioning piles using the "three-pipe two-drilling method". Arrange 5 rows and 6 rows of positioning steel pipe piles at the water intake head, with row spacing of 2.4m, 4.2m, 4.2m, and 2.4m, and row spacing of 0.9m; arrange 3 rows and 3 rows of positioning steel pipe piles at the bell mouth of the water diversion pipe in conjunction with the water intake head, with row spacing of 4.2m and row spacing of 2.0m; arrange 5 rows and 24 rows of positioning steel pipe piles at the straight section of the water diversion pipe, with row spacing of 1.2m, 2.1m, 0.6m, and 1.2m, and row spacing of 2.0m;
[0011] (4): A temporary wharf is set up on the downstream shore of the temporary water truss. A 500-horsepower motor boat and a pontoon are tied together for driving. The pontoon and floating crane are used as water transport platforms to transfer and hoist the steel truss platform components. The steel pipe positioning piles are used as the support system to build a 14m×5m steel truss platform as a welding and hoisting work platform for the water intake head steel components. Two gantry brackets are set on the platform in the longitudinal direction of the water flow direction of the water intake facility, and 6 20-ton hand hoists are configured for hoisting operations;
[0012] (5): Use pontoons and floating cranes with steel pipe positioning piles as the support system to build a water pipe truss working platform and a bell mouth assembly working platform. A construction channel for downstream facilities of the truss platform is provided for personnel to get on and off. A truss and operating platform are set up on the shore. An I-beam is installed on the top of each of the two rows of vertical steel pipe positioning piles. Two 10T hand chain hoists are arranged on each beam to be used for bundling and lifting the pipes.
[0013] (6): Use a hand winch to lift the water pipe and transport it from the river bank to the river in the direction of water head. Configure two winches to transport it to the designated location;
[0014] (7): Use the pontoon as a transport platform to transfer the water head components. Number the lifting parts before lifting. Use a 50T truck crane on the shore to lift the water head steel components in groups according to the numbers to the transport ship docked at the temporary wharf. The transport ship sails to the vicinity of the water head water working platform. Use a barge crane or floating crane to lift the water head steel components to the water head water working platform for assembly and splicing. After the components are transported to the platform, use the configured 20T hand winch for fine lifting;
[0015] (8): Use the barge crane and hand winch to move the water pipe, bell mouth and water intake head away from the water working platform, then remove the roller and transverse connecting components of the water pipe truss, and also remove the working platform steel plate and longitudinal and transverse connecting components of the water intake part. After there are no obstacles under the water intake head steel box, the connected water intake facilities are lowered into the trough at a uniform speed. After each lowering distance, the cross bar that hinders the lowering of the water pipe is removed, and the cross bar that has been removed on the upper part of the water pipe is immediately connected to ensure the structural stability of the bracket. Repeat until the trough is sunk into place and the water intake facility installation is completed.
[0016] Wherein: in the step (1), a double-row steel tube truss single-wall water retaining plate is set deep into the water at a position 8 to 10 m upstream of the water intake facility, and the end is set to be no less than 10 m longer than the water intake head, so as to reduce the water flow velocity in the water construction area of the water intake head and eliminate the safety hazard of the water retaining plate backflow to the water intake head construction, and an anchor is set to anchor the water retaining plate through a steel wire rope to share the impact force of the water flow, and the lower part converts the horizontal impact force of the water flow into bending torque and transmits it to the foundation through the support piles of the steel truss.
[0017] Wherein: the step (2) also includes: adopting the "three-tube and two-drill method" to follow up the steel pipe for charging and the drill bit of the drilling rig, so that the charging process is transferred from underwater to the surface, and the charging work can be completed by loading the charges sequentially from the top of the steel pipe on the ship, avoiding underwater diving charging. After detonation, wait for 15 minutes, and the safety officer and blaster will go to the blasting area to check and deal with the blind shot, and then use a dredger and an ultra-long arm excavator to carry out underwater slag cleaning, and then use underwater cameras and terrain scanners to cooperate with the inspection of the foundation trench to realize the acceptance of the foundation trench in the deep river.
[0018] Wherein: in the step (3): the steel pipe positioning pile is not less than 2.2m above the normal construction water level, and two hydraulic drilling rigs for geological exploration with eccentric drill bits are used to construct the steel pipe positioning pile. The steel pipe specification model is a seamless T40 steel pipe with a wall thickness of 8mm and a standard inner threaded casing for extension. The rock embedding depth is 2.5m to 3m, and C30 fine stone concrete is poured into the steel pipe to form a steel pipe concrete pile.
[0019] Wherein: in the step (5): a detachable movable crossbeam is installed on each row of steel pipe positioning piles to bear the weight of the pipeline and provide a working platform during pipeline transportation and docking; it plays a role of safety protection when the pipeline is lowered, and fine adjustment and measurement calibration are required every 50 cm of lowering. A roller is set on the middle crossbeam 0.5 m from the water surface for pipeline transportation. Between the two sections of the water diversion pipe, in order to prevent the steel pipe from flexible deformation, a clamp is added at the connection of the two sections of the steel pipe or an I-beam is welded to fix it before transportation into the river.
[0020] Wherein: in said step (8): before the overall sinking, make sinking positioning marks and scales, implement anti-collision and water rescue measures, prevent the water intake facilities from floating up with counterweights and set limit devices, reasonably arrange the lifting points and conduct trial lifting, check the performance of the lifting equipment, and have divers on duty.
[0021] The method further includes step (9): after sinking to the correct position, a diver goes to the bottom of the water to observe the water head and the contact between the water diversion pipe and the foundation trench. If there is a large gap under the pipe, the diver should fill it with C30 concrete blocks, then stack the formwork bags with concrete, and pour C30 underwater concrete to cover the pipe.
[0022] Wherein: in the step (9), the concrete in the underwater concrete pouring construction is mixed with an underwater non-dispersible concrete flocculant.
[0023] The method further includes step (10): after the underwater concrete reaches the designed strength, the steel truss platform and the water retaining plate are removed and the steel pipe positioning piles are cut off to restore the river channel.
[0024] The beneficial effects of the present invention are as follows: a facility for taking water from a rapid riverbed and an overall installation and construction method thereof are invented, effective measures are taken in the rapid riverbed to reduce the water flow velocity in the construction area, underwater diving charges are avoided, the overall installation and acceptance problems of the water intake facility are conveniently solved, and recycling can be achieved. BRIEF DESCRIPTION OF THE DRAWINGS
[0025] Figure 1 It is the basic plan view of the present invention
[0026] Figure 2 This is a cross-sectional view of the water intake head position of the present invention
[0027] Figure 3 It is a cross-sectional view of the water diversion pipe position of the present invention
[0028] Figure 4 This is a elevation view of the present invention
[0029] Figure 5 This is the connection method diagram of the top of the positioning steel pipe column of the present invention
[0030] Figure 6 It is a flow chart of the construction method of the present invention
[0031] In the figure: 1. Positioning steel pipe piles, 2. Parallel connecting beams, 3. Pile caps, 4. I-beam crossbeams, 5. Distribution beams, 6. Steel panels, 7. Columns, 8. Load-bearing beams, 9. Water intake flower racks, 10. Water intakes, 11. Water diversion pipes, 12. Riverbanks, 13. Water retaining facilities, 14. Crossbeam pipes, 15. Handrails, 16. Sidewalk slabs, 17. Lifting ring weldments, 18. Hand chain hoists, 19. Canvas lifting slings, 20. Rollers, 21. Water diversion pipe flower racks, 22. Vertical connecting beams. DETAILED DESCRIPTION
[0032] The technical solution of the present invention will be described clearly and completely below. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0033] A facility for taking water from a rapid riverbed, characterized in that it includes a water diversion pipe, a positioning steel pipe pile 1, a parallel connecting beam 2 parallel to the axis of the water diversion pipe, a pile cap 3, an I-beam crossbeam 4, a distribution beam 5, a steel panel 6, a column 7, a load-bearing beam 8, a water intake head 10, a water intake head flower rack 9, a water retaining facility 13, a crossbeam frame pipe 14, a railing 15, a sidewalk slab 16, a lifting ring weldment 17, a hand chain hoist 18, a canvas lifting sling 19, a roller 20, a water diversion pipe flower rack 21, and a vertical connecting beam 22 perpendicular to the axis of the water diversion pipe; the water diversion pipe includes a bell mouth and a straight line segment, and the water intake facility is a combination of a water intake head 10 and a water diversion pipe for drawing water from the center of a river for domestic and production water through a water intake pipeline; a positioning steel pipe pile 1 is used as a support system to establish a working plane of a water diversion pipe truss A work platform for assembling the platform and the trumpet mouth is provided, and a construction passage is set up downstream of the truss platform for personnel to go up and down. An I-beam beam 4 is installed on the top of every three rows of vertical positioning steel pipe piles 1. Two 10T hand winches are arranged on each I-beam beam to be used for binding and lifting pipes; with the positioning steel pipe piles as the support system, a 14m×5m steel truss platform is established as a welding and lifting work platform for the water intake head steel components. Two door-type brackets are arranged on the platform in the longitudinal direction of the water flow direction of the water intake facility. The two door-type brackets are connected by load-bearing beams 8 and flower racks to form a frame structure. Two 20T hand winches are arranged on each load-bearing beam to be used for lifting the water intake head by rings; the water intake facilities connected as a whole are lowered into the trough by mooring cranes and hand winches, so as to realize the dry operation of assembling the water intake head and connecting the water diversion pipe.
[0034] A pile-driving ship with a drilling rig was used to follow the pipe drilling and construct small-diameter steel pipe positioning piles using the "three-pipe and two-drill method". Five columns and six rows of positioning steel pipe piles were arranged at the water intake head, with column spacing of 2.4m, 4.2m, 4.2m, and 2.4m, and row spacing of 0.9m; three columns and three rows of positioning steel pipe piles were arranged at the bell mouth of the water diversion pipe in combination with the water intake head, with column spacing of 4.2m and row spacing of 2.0m; five columns and 24 rows were arranged in the straight section of the water diversion pipe, with column spacing of 1.2m, 2.1m, 0.6m, and 1.2m, and row spacing of 2.0m; the steel pipe specification model is D168mm, 8mm wall thickness seamless T40 steel pipe, which is connected with a standard inner threaded casing, with a rock embedded depth of 2.5m to 3m, and C30 fine stone concrete is pressure-filled in the steel pipe to form steel pipe concrete piles.
[0035] Wherein, the pile cap 3 is welded and fixed on the top of the positioning steel pipe pile to provide a welding fixation and force support surface for the main beam;
[0036] Wherein, the distribution beam 5 is welded and fixed to the upper part of the I-beam cross beam and is formed into a working platform for the water intake head through a steel panel;
[0037] The upright column 7, the load-bearing beam 8 and the flower stand (water intake head part) are welded together to form a frame structure for water intake head hoisting;
[0038] The load-bearing beam 8 is welded and fixed on the top of the positioning steel pipe pile 1, and forms a portal structure with the positioning steel pipe pile, serving as a load-bearing structure for lifting the water diversion pipe (the bell mouth and the straight section).
[0039] The positioning steel pipe piles are connected by connecting beams (parallel to the axis of the water diversion pipe), connecting beams (perpendicular to the axis of the water diversion pipe), and flower racks (part of the water diversion pipe) to form a frame structure to enhance structural stability;
[0040] The water diversion pipe (the bell mouth and the straight section) is lifted by a hand chain hoist through a canvas lifting sling in a bottom-covering binding manner. The upper hook of the hand chain hoist is hooked on the lifting ring weldment, and the bearing force is transmitted to the foundation through the portal truss.
[0041] The lifting ring weldment 17 is welded and fixed to the lower edge of the load-bearing beam 8 .
[0042] The steel components of the water intake head 10 are welded and hoisted by hand winches and mooring cranes.
[0043] Among them, railings and sidewalk slabs are used to provide construction passages for personnel to go up and down the downstream facilities of the truss platform.
[0044] It also includes installing a detachable movable crossbeam on each row of steel pipe positioning piles, which bears the weight of the pipeline and provides a working platform during pipeline transportation and docking; it plays a role in safety protection when the pipeline is lowered, and fine-tuning and measurement calibration are required every 50cm of lowering; a roller is installed on the middle beam 0.5m from the water surface for pipeline transportation; between the two sections of water diversion pipes, in order to prevent flexible deformation of the steel pipe, a clamp is added or an I-beam is welded at the connection of the two sections of the steel pipe before transportation into the river.
[0045] It also includes using a hand winch to lift the water pipe, transporting it from the river bank to the water head in the river, and configuring two winches to transport it to the designated location. It can realize the dry operation of assembling large water heads and connecting them to the water pipe, as well as the overall lowering of the water head and the water pipe in coordinated operation, which can speed up the realization of construction period goals and reduce safety risks.
[0046] The "three-tube and two-drill" method is a drilling method, including a guide tube, casing and drill rod, followed by drilling, and the drill bit is an eccentric drill. The operation process is: the ship is positioned, the guide tube is lowered first, and then the casing is lowered → according to the surface conditions of the rock, if it is relatively broken, the casing is first alloy drilled (the eccentric drill bit will be slightly enlarged by the pressure-bearing rotating drill bit to facilitate the casing to follow up) → After the alloy is drilled to the complete bedrock, the relevant drilling tools are lifted → the drill rod is lowered for impact rotary drilling to the designed bottom elevation → the hole depth is measured, if it is not deep enough, the above steps are repeated.
[0047] A method for overall installation and construction of a facility for taking water from a rapid riverbed, characterized in that it comprises the following steps:
[0048] (1): Use barges and drilling and blasting ships to construct double-row steel tube truss single-wall water retaining panels in a step-by-step manner using steel trusses and steel panels to reduce the water flow velocity in the construction area;
[0049] (2): Use a drilling and blasting ship to excavate the trench for the water intake facility by underwater deep hole blasting with a blasthole diameter of 90 mm, a hole depth of more than 5 m, micro-difference blasting between rows, and controlled single-stage explosive quantity;
[0050] (3): Use a pile-driving ship with a drilling rig to follow the pipe and drill and construct small-diameter steel pipe positioning piles using the "three-pipe two-drilling method". Arrange 5 rows and 6 rows of positioning steel pipe piles at the water intake head, with row spacing of 2.4m, 4.2m, 4.2m, and 2.4m, and row spacing of 0.9m; arrange 3 rows and 3 rows of positioning steel pipe piles at the bell mouth of the water diversion pipe in conjunction with the water intake head, with row spacing of 4.2m and row spacing of 2.0m; arrange 5 rows and 24 rows of positioning steel pipe piles at the straight section of the water diversion pipe, with row spacing of 1.2m, 2.1m, 0.6m, and 1.2m, and row spacing of 2.0m;
[0051] (4): A temporary wharf is set up on the downstream shore of the temporary water truss. A 500-horsepower motor boat and a pontoon are tied together for driving. The pontoon and floating crane are used as water transport platforms to transfer and hoist the steel truss platform components. The steel pipe positioning piles are used as the support system to build a 14m×5m steel truss platform as a welding and hoisting work platform for the water intake head steel components. Two gantry brackets are set on the platform in the longitudinal direction of the water flow direction of the water intake facility, and 6 20-ton hand hoists are configured for hoisting operations;
[0052] (5): Use pontoons and floating cranes with steel pipe positioning piles as the support system to build a water pipe truss working platform and a bell mouth assembly working platform. A construction channel for downstream facilities of the truss platform is provided for personnel to get on and off. A truss and operating platform are set up on the shore. An I-beam is installed on the top of each of the two rows of vertical steel pipe positioning piles. Two 10T hand chain hoists are arranged on each beam to be used for bundling and lifting the pipes.
[0053] (6): Use a hand winch to lift the water pipe and transport it from the river bank to the river in the direction of water head. Configure two winches to transport it to the designated location;
[0054] (7): Use the pontoon as a transport platform to transfer the water head components. Number the lifting parts before lifting. Use a 50T truck crane on the shore to lift the water head steel components in groups according to the numbers to the transport ship docked at the temporary wharf. The transport ship sails to the vicinity of the water head water working platform. Use a barge crane or floating crane to lift the water head steel components to the water head water working platform for assembly and splicing. After the components are transported to the platform, use the configured 20T hand winch for fine lifting;
[0055] (8): Use the barge crane and hand winch to move the water pipe, bell mouth and water intake head away from the water working platform, then remove the roller and transverse connecting components of the water pipe truss, and also remove the working platform steel plate and longitudinal and transverse connecting components of the water intake part. After there are no obstacles under the water intake head steel box, the connected water intake facilities are lowered into the trough at a uniform speed. After each lowering distance, the cross bar that hinders the lowering of the water pipe is removed, and the cross bar that has been removed on the upper part of the water pipe is immediately connected to ensure the structural stability of the bracket. Repeat until the trough is sunk into place and the water intake facility installation is completed.
[0056] Wherein: in the step (1), a double-row steel tube truss single-wall water retaining plate is set deep into the water at a position 8 to 10 m upstream of the water intake facility, and the end is set to be no less than 10 m longer than the water intake head, so as to reduce the water flow velocity in the water construction area of the water intake head and eliminate the safety hazard of the water retaining plate backflow to the water intake head construction, and an anchor is set to anchor the water retaining plate through a steel wire rope to share the impact force of the water flow, and the lower part converts the horizontal impact force of the water flow into bending torque and transmits it to the foundation through the support piles of the steel truss.
[0057] Wherein: the step (2) also includes: adopting the "three-tube and two-drill method" to follow up the steel pipe for charging and the drill bit of the drilling rig, so that the charging process is transferred from underwater to the surface, and the charging work can be completed by loading the charges sequentially from the top of the steel pipe on the ship, avoiding underwater diving charging. After detonation, wait for 15 minutes, and the safety officer and blaster will go to the blasting area to check and deal with the blind shot, and then use a dredger and an ultra-long arm excavator to carry out underwater slag cleaning, and then use underwater cameras and terrain scanners to cooperate with the inspection of the foundation trench to realize the acceptance of the foundation trench in the deep river.
[0058] Wherein: in the step (3): the steel pipe positioning pile is not less than 2.2m above the normal construction water level, and two hydraulic drilling rigs for geological exploration with eccentric drill bits are used to construct the steel pipe positioning pile. The steel pipe specification model is a seamless T40 steel pipe with a wall thickness of 8mm and a standard inner threaded casing for extension. The rock embedding depth is 2.5m to 3m, and C30 fine stone concrete is poured into the steel pipe to form a steel pipe concrete pile.
[0059] Wherein: in the step (5): a detachable movable crossbeam is installed on each row of steel pipe positioning piles to bear the weight of the pipeline and provide a working platform during pipeline transportation and docking; it plays a role of safety protection when the pipeline is lowered, and fine adjustment and measurement calibration are required every 50 cm of lowering. A roller is set on the middle crossbeam 0.5 m from the water surface for pipeline transportation. Between the two sections of the water diversion pipe, in order to prevent the steel pipe from flexible deformation, a clamp is added at the connection of the two sections of the steel pipe or an I-beam is welded to fix it before transportation into the river.
[0060] Wherein: in said step (8): before the overall sinking, make sinking positioning marks and scales, implement anti-collision and water rescue measures, prevent the water intake facilities from floating up with counterweights and set limit devices, reasonably arrange the lifting points and conduct trial lifting, check the performance of the lifting equipment, and have divers on duty.
[0061] The method further includes step (9): after sinking to the correct position, a diver goes to the bottom of the water to observe the water head and the contact between the water diversion pipe and the foundation trench. If there is a large gap under the pipe, the diver should fill it with C30 concrete blocks, then stack the formwork bags with concrete, and pour C30 underwater concrete to cover the pipe.
[0062] Wherein: in the step (9), the concrete in the underwater concrete pouring construction is mixed with an underwater non-dispersible concrete flocculant.
[0063] The method further includes step (10): after the underwater concrete reaches the designed strength, the steel truss platform and the water retaining plate are removed and the steel pipe positioning piles are cut off to restore the river channel.
[0064] Wherein, in said step (10), the truss platform above the water surface adopts a barge to provide an operating platform for gas cutting, and the underwater steel pipe positioning piles are cut by divers using a special underwater cutting strip.
[0065] The method also includes the step of recycling the steel truss members.
[0066] The present invention discloses an overall installation construction method for water intake facilities in a rapid riverbed. Effective measures are taken in the rapid riverbed to reduce the water flow velocity in the construction area, avoid underwater diving charge, conveniently solve the overall installation and acceptance problems of the water intake facilities, and realize recycling.
[0067] The above is only a specific embodiment of the present invention, but the protection scope of the present invention is not limited thereto. The above technical solution only reflects the preferred technical solution of the technical solution of the present invention. Any technician familiar with the technical field in the present invention can easily think of changes or substitutions within the technical scope disclosed by the present invention, which should be included in the protection scope of the present invention. Therefore, the protection scope of the present invention shall be based on the protection scope of the claims.
Claims
1. A method for installing and constructing a facility for taking water from a rapid riverbed, characterized in that: The steps include: (1): Use barges and drilling and blasting ships to construct double-row steel tube truss single-wall water retaining boards in a step-by-step manner using steel trusses and steel panels to reduce the water flow velocity in the construction area; (2): Use a drilling and blasting ship to excavate the trench for the water intake facility by underwater deep hole blasting with a blasthole diameter of 90 mm, a hole depth of more than 5 m, micro-difference blasting between rows, and controlled single-stage explosive quantity; (3): Use a pile-driving ship with a drilling rig to follow the pipe and drill and construct small-diameter steel pipe positioning piles using the "three-pipe two-drilling method". Five rows and six lines of positioning steel pipe piles are arranged at the water intake head, with row spacing of 2.4m, 4.2m, 4.2m, and 2.4m, and row spacing of 0.9m; three rows and three lines of positioning steel pipe piles are arranged at the bell mouth of the water diversion pipe in conjunction with the water intake head, with row spacing of 4.2m and row spacing of 2.0m; five rows and 24 lines of positioning steel pipe piles are arranged in the straight section of the water diversion pipe, with row spacing of 1.2m, 2.1m, 0.6m, and 1.2m, and row spacing of 2.0m; (4): A temporary wharf is set up on the downstream shore of the temporary water truss. A 500-horsepower motor boat and a pontoon are tied together for driving. The pontoon and floating crane are used as water transport platforms to transfer and hoist the steel truss platform components. The steel pipe positioning piles are used as the support system to build a 14m×5m steel truss platform as a welding and hoisting work platform for the water intake head steel components. Two gantry brackets are set on the platform in the longitudinal direction of the water flow direction of the water intake facility, and 6 20-ton hand hoists are configured for hoisting operations; (5): Use pontoons and floating cranes with steel pipe positioning piles as the support system to build a water pipe truss working platform and a bell mouth assembly working platform. A construction channel for downstream facilities of the truss platform is provided for personnel to get on and off. A truss and operating platform are set up on the shore. An I-beam is installed on the top of each of the two rows of vertical steel pipe positioning piles. Two 10T hand chain hoists are arranged on each beam to be used for bundling and lifting the pipes. (6): Use a hand winch to lift the water pipe and transport it from the river bank to the river in the direction of water head. Configure two winches to transport it to the designated location; (7): Use the pontoon as a transport platform to transfer the water head components. Number the lifting parts before lifting. Use a 50T truck crane on the shore to lift the water head steel components in groups according to the numbers to the transport ship docked at the temporary wharf. The transport ship sails to the vicinity of the water head water working platform. Use a barge crane or floating crane to lift the water head steel components to the water head water working platform for assembly and splicing. After the components are transported to the platform, use the configured 20T hand winch for fine lifting; (8): Use the barge crane and hand winch to move the water pipe, bell mouth and water intake head away from the water working platform, then remove the roller and transverse connecting components of the water pipe truss, and also remove the working platform steel plate and longitudinal and transverse connecting components of the water intake part, so that there are no obstacles under the water intake head steel box, and then lower the connected water intake facilities into the trough at a uniform speed. After each lowering distance, remove the cross bar that hinders the lowering of the water pipe, and immediately connect the cross bar that has been removed on the upper part of the water pipe to ensure the structural stability of the bracket. Repeat until the trough is in place and the water intake facilities are installed; In the step (1), a double-row steel tube truss single-wall water retaining plate is set deep into the water at a position 8 to 10 m upstream of the water intake facility, and the end is set to be no less than 10 m longer than the water intake head, so as to reduce the water flow velocity in the water construction area of the water intake head and eliminate the safety hazard of the water retaining plate backflow to the water intake head construction. An anchor is set to anchor the water retaining plate through a steel wire rope to share the impact force of the water flow. The lower part converts the horizontal impact force of the water flow into bending moment and torque through the support piles of the steel truss and transmits it to the foundation; The step (2) also includes: using the "three-tube and two-drill method" to follow up the steel pipe for charging and the drill bit of the drilling rig, so that the charging process is transferred from underwater to the surface, and the charging work can be completed by loading the charges sequentially from the top of the steel pipe on the ship, avoiding underwater diving charging, waiting for 15 minutes after detonation, and the safety officer and blaster will go to the blasting area to check and deal with the blind shot, and then use a dredger and an ultra-long arm excavator to clean the slag underwater, and then use an underwater camera and a terrain scanner to cooperate with the inspection of the foundation trench to realize the acceptance of the foundation trench in the deep river; The facilities for taking water from the rapid riverbed include a water diversion pipe, a positioning steel pipe pile, a connecting beam parallel to the axis of the water diversion pipe, a pile cap, an I-beam crossbeam, a distribution beam, a steel panel, a column, a load-bearing beam, a water intake head, a water intake head flower rack, a water retaining facility, a crossbeam frame pipe, a railing, a sidewalk slab, a lifting ring weldment, a hand chain hoist, a canvas lifting sling, a roller, a water diversion pipe flower rack, and a connecting beam perpendicular to the axis of the water diversion pipe; the water diversion pipe includes a bell mouth and a straight section, and the water intake facility is composed of a water intake head and a water diversion pipe for drawing water from the center of the river for domestic and production water through a water intake pipeline; a water diversion pipe truss working platform and a bell mouth assembly working platform are established with the positioning steel pipe pile position as the support system, and downstream of the truss platform A construction passage is set up for personnel to go up and down. An I-beam is installed on the top of every three rows of vertical positioning steel pipe piles. Two 10T hand winches are arranged on each I-beam to be used for binding and lifting pipes. With the positioning steel pipe piles as the support system, a 14m×5m steel truss platform is established as a welding and lifting work platform for the water intake head steel components. Two door-type brackets are set on the platform in the longitudinal direction of the water flow direction of the water intake facility. The two door-type brackets are connected by load-bearing beams and flower racks to form a frame structure. Two 20T hand winches are arranged on each load-bearing beam to be used for lifting the water intake head by rings. The water intake facilities connected as a whole are lowered into the trough by mooring cranes and hand winches to realize the dry operation of assembling the water intake head and connecting it with the water diversion pipe.
2. The method for overall installation and construction of a facility for taking water from a rapid riverbed according to claim 1, characterized in that: In the step (3), the steel pipe positioning piles are at least 2.2 m above the normal construction water level. Two hydraulic drilling rigs for geological exploration with eccentric drill bits are used to construct the steel pipe positioning piles. The steel pipe specification model is a seamless T40 steel pipe with a wall thickness of 8 mm and a standard inner threaded casing for extension. The rock embedding depth is 2.5 m to 3 m. C30 fine stone concrete is poured into the steel pipe to form a steel pipe concrete pile.
3. The method for overall installation and construction of a facility for taking water from a rapid riverbed according to claim 1, characterized in that: In the step (5), a detachable movable crossbeam is installed on each row of steel pipe positioning piles to bear the weight of the pipe and provide a working platform during pipeline transportation and docking; it plays a role of safety protection when the pipe is lowered, and fine adjustment and measurement calibration are required every 50 cm of lowering. A roller is set on the middle crossbeam 0.5 m from the water surface for pipeline transportation. Between the two sections of the water diversion pipe, in order to prevent the steel pipe from being flexibly deformed, a clamp is added at the connection of the two sections of the steel pipe or an I-beam is welded to fix it before transportation into the river.
4. The method for overall installation and construction of a facility for taking water from a rapid riverbed according to claim 1, characterized in that: In the step (8), before the overall sinking, sinking positioning marks and scales are made, anti-collision and water rescue measures are implemented, counterweights are used to prevent the water intake facilities from floating up, and limit devices are set, the lifting points are reasonably arranged and tested, the performance of the lifting equipment is checked, and divers are in place.
5. The method for overall installation and construction of a facility for taking water from a rapid riverbed according to claim 1, characterized in that: The method also includes step (9): after sinking to the correct position, a diver goes to the bottom of the water to observe the water head and the contact between the water pipe and the foundation trench. If there is a large gap under the pipe, the diver should fill it with C30 concrete blocks to level it, then stack the formwork bags with concrete, and pour C30 underwater concrete to cover the pipe.
6. The method for overall installation and construction of a facility for taking water from a rapid riverbed according to claim 5, characterized in that: In the step (9), the concrete in the underwater concrete pouring construction is mixed with an underwater non-dispersible concrete flocculant.
7. The method for overall installation and construction of a facility for taking water from a rapid riverbed according to claim 1, characterized in that: The method further includes step (10): after the underwater concrete reaches the designed strength, the steel truss platform and the water retaining plate are removed and the steel pipe positioning piles are cut off to restore the river channel.