Underpass subway support structure and manufacturing method thereof
By setting up a subway underpass support structure under the existing subway station and using pipe curtain walls and frozen pipes to form a waterproof curtain, the construction difficulties of new subway structures in high-water-level soft soil areas were solved, and a safe and economical connection and deformation control of the new and old structures were achieved.
Patent Information
- Application Number
- CN201910817867.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2019-08-30
- Publication Date
- 2024-11-29
- Estimated Expiration
- 2039-08-30
AI Technical Summary
When constructing a new subway structure beneath an existing subway station in a high-water-level soft soil area, there is a risk of sudden pressure water inrush, which makes construction difficult, affects the deformation and normal operation of the existing subway station, and the force transmission between the old and new structures is unclear, affecting safety and construction costs.
The project adopts an underpass support structure, including working shafts, support frames, and connectors. It combines pipe curtain walls with frozen pipes to form two waterproof curtains. The support frame runs through the existing subway station and is equipped with anti-buoyancy devices to control deformation and reduce the frozen volume.
Effectively control the risk of sudden surge of pressurized water, reduce the amount of frozen material, reduce construction complexity and cost, ensure clear force transmission between new and old structures, reduce the deformation impact on existing subway stations, and improve construction safety and schedule.
Smart Images

Figure CN110608047B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the field of construction engineering, and in particular to a support structure for underpass subway and a manufacturing method thereof. Background Art
[0002] In the process of urban development, the subway has played a vital role with its large passenger capacity, high speed and punctuality. With the increasing intensity of subway construction in recent years, subway lines have gradually become a network, and the number of transfer stations has increased. However, due to the long interval between planning rounds of subway construction, some subway stations in the early batches could not determine whether there were long-term transfer stations during the preliminary design process, or the specific location of the transfer stations was uncertain, so they could not be reserved in the structure. This is mainly manifested in: the diameter of the first station enclosure structure (such as underground continuous walls or bored pile steel bars) is large, the spacing between steel bars is small, and the shield machine cannot cut, thus affecting the implementation of the later subway structure. With the further deepening of subway construction in large and medium-sized cities, the problems caused by such situations have become more obvious.
[0003] Passing under such operating subway stations involves controlling the engineering risks of the underground excavation method itself and controlling the deformation of the operating station above. Especially in soft soil areas with high water levels, the following difficulties will be faced:
[0004] 1. The newly built underground excavation structure needs to be located at a deeper position below the existing station, which poses a risk of sudden surge of pressurized water, making the project impossible to implement. In addition, once underground water and soil surge in, it will inevitably cause a large deformation of the subway station operating above, and have an adverse impact on surrounding buildings, roads, and pipelines.
[0005] 2. The deformation control requirements of the subway station above are extremely high, and it must not affect normal operations. If the design and construction measures are not in place, it will cause uneven settlement of the structure of the operating station above, and even cause large deformation, threatening operational safety.
[0006] 3. The stress safety design of the new and old structures in the permanent use stage is complex. The new structure should be able to bear the vertical load of the existing structure, and there should be a safe and reliable force transmission path between the two to ensure the stability of the top support under the bottom plate of the existing structure.
[0007] 4. Building new structures under existing subway stations often requires removing the existing subway station’s ground walls and pile foundations, which weakens the existing subway station’s anti-floating bearing capacity.
[0008] At present, for soft soil areas with high water levels, new subway structures are built under operating subway stations without reserved conditions for future shield tunneling. In practice, the construction is difficult and the frozen volume is large. The anti-floating structure in the existing subway station is easily damaged during the construction process, increasing the deformation risk of the existing subway station, which in turn affects the normal operation of the existing subway station. Summary of the invention
[0009] In order to build a new station under an existing subway station, it is necessary to solve the problems of pressurized water inrush and large frozen soil construction volume encountered during underground excavation, and at the same time control the deformation of the existing station above, so that the force transmission between the new and old structures is clear and effective, and there is no impact on the operation of the existing station. It is necessary to provide a support structure for underpass subway and its manufacturing method.
[0010] A support structure for underpasses in a subway, comprising a working shaft, the working shaft extending vertically underground along both sides of an existing subway station; a support frame, the support frame being arranged below the existing subway station and connected to the working shaft, the support frame constituting a passage underpassing the subway, comprising a tube curtain wall; a connecting piece, the connecting piece connecting the supporting frame, the working shaft and the existing subway station, and being used to prevent the existing subway station from deforming.
[0011] Furthermore, the cross section of the tube curtain wall includes a closed structure composed of a plurality of pipes connected side by side, and the channel is arranged along the inside of the tube curtain wall.
[0012] Furthermore, the pipeline that can be drilled manually is arranged through the pile foundation below the existing subway station.
[0013] Furthermore, a stiffening plate is arranged inside the pipeline.
[0014] Furthermore, the support frame includes a first waterproof layer formed by grouting grout, and the first waterproof layer is used to fill the gaps between the multiple pipelines connected side by side.
[0015] Furthermore, freezing pipes are arranged inside the plurality of pipelines connected in parallel, and the freezing pipes are used to freeze the soil layer around the pipelines and form a second waterproof layer of the support frame.
[0016] Furthermore, the support frame also includes a plurality of inner lining layers, which are arranged in the tube curtain wall and penetrate the existing subway station, and the passage is arranged inside the inner lining layers.
[0017] Furthermore, the working shaft comprises a plate wall structure on one side close to the existing subway station, and the existing subway station comprises ground wall structures on both sides, and the support frame passes through the plate wall structure and the ground wall structure.
[0018] Furthermore, the connecting member includes an upper connecting member and a lower connecting member, and the upper connecting member and the lower connecting member respectively connect the support frame and the plate wall structure and the ground wall structure located above and below the support frame, so that the underpass subway support structure and the existing subway station are combined into one.
[0019] Furthermore, the connecting member also includes an anti-floating device, which is arranged on the plate wall structure and the ground wall structure to prevent deformation of the integrated structure.
[0020] The technical solution provided by this application not only meets the demand for building a new subway station under an existing subway station, but can also be applied to building a new structure under an existing underground frame structure. The underpass subway support structure provided by this application has a large pipe curtain support rigidity, a strong bearing capacity for the upper station, and is more favorable for the deformation control of the upper station. It can also reduce the vertical clearance between the new structure and the existing station, thereby reducing the burial depth of the new station and saving construction costs; secondly, the pipe curtain wall and the freezing pipe are combined, the pipe curtain is used as a supporting structure, and the freezing curtain and the pipe curtain lock together form two water-stopping curtains. Under the condition of ensuring water stoppage, the frozen volume is greatly reduced, and the deformation effect of frost heave and thaw settlement on the existing subway station can be better controlled. In addition, new stations and working wells are set up on both sides of the existing subway station. Considering the high risk of dark excavation projects in high-water strata, once a dangerous situation occurs, such as a sudden surge of pressurized water, measures can be taken from the opposite side to remedy it, such as adding freezing holes from the opposite side to freeze, to ensure the stability of water and soil under the existing subway station. Finally, the new subway station is built close to the existing subway station, and the section of the underground excavation only needs to meet the train passing limit. The volume of the underground excavation is small, and the impact on the safety, construction period, and existing stations of the underground excavation construction is relatively small.
[0021] Furthermore, a method for manufacturing a support structure for underpass subway is provided, comprising the following steps:
[0022] Excavating working shafts along both sides of the existing subway station, wherein the working shafts extend vertically underground;
[0023] A support frame connected to the working shaft is arranged below the existing subway station, and the support frame forms a passage passing under the subway, including a tube curtain wall;
[0024] The working shaft, the existing subway station and the support frame are connected via connecting pieces.
[0025] Furthermore, the support frame construction method comprises the following steps:
[0026] Connect multiple pipes side by side to form a pipe curtain wall with a closed cross-section structure;
[0027] Injecting grouting grout along the gaps between the plurality of pipelines connected in parallel to form a first waterproof layer;
[0028] A freezing pipe is arranged in the pipeline to freeze the soil layer around the pipeline to form a second waterproof layer;
[0029] A plurality of inner lining layers are arranged along the tube curtain wall, and the plurality of inner lining layers penetrate the existing subway station and form the passage passing under the subway station.
[0030] Furthermore, anti-floating devices are arranged on the existing subway station and the working shaft.
[0031] The various specific structures of the present application and their functions and effects will be further described in detail below in conjunction with the accompanying drawings. BRIEF DESCRIPTION OF THE DRAWINGS
[0032] Figure 1 This is a schematic diagram of the working well structure of Example 1 of the present application;
[0033] Figure 2 This is a working position diagram of the support frame of Example 1 of the present application;
[0034] Figure 3 This is a side view of the tube curtain wall of Example 1 of the present application;
[0035] Figure 4 This is a partial enlarged view of the tube curtain wall 3-1 of Example 1 of the present application;
[0036] Figure 5 This is a front view of the underpass subway support structure of Example 1 of the present application;
[0037] Figure 6 A side view of the underpass subway support structure of Example 1 of the present application;
[0038] Figure 7 This is a manufacturing flow chart of the underpass subway support structure of Example 1 of the present application;
[0039] Figure 8 This is a manufacturing flow chart of the support frame of Example 1 of the present application;
[0040] Fig. 9 This is a side view of the underpass subway support structure of Example 2 of the present application. DETAILED DESCRIPTION
[0041] The technical solutions in the embodiments of the present application will be further described clearly and completely below in conjunction with the accompanying drawings. However, it should be noted that the following embodiments are only some preferred embodiments in the present application and do not involve all embodiments covered by the technical solutions of the present application.
[0042] It should be noted that, in the description of this application, when an element is referred to as being "fixed to" another element, it may be directly on the other element or there may be a central element. When an element is considered to be "connected to" another element, it may be directly connected to the other element or there may be a central element at the same time.
[0043] Unless otherwise defined, all technical and scientific terms used herein have the same meaning as those generally understood by those skilled in the art of the present invention. The terms used herein in the specification of the present invention are only for the purpose of describing specific embodiments and are not intended to limit the present invention. The term "and / or" used herein includes any and all combinations of one or more related listed items.
[0044] Figure 1 What is shown is a schematic diagram of the working shaft structure of Example 1 of the present application. Ground wall structures 11 are arranged on both sides of the existing subway station 1, a working shaft 2 is excavated along both sides of the existing subway station 1, and the internal enclosure structure of the working shaft 2 is reinforced. A plate wall structure 21 is arranged on the side of the working shaft 2 close to the existing subway station 1. Preferably, the plate wall structure 21 is close to the ground wall structure 11. On the one hand, the working shaft 2 provides a construction environment for constructing an underpass subway. At the same time, after the completion of the later construction, the working shaft 2 can be transformed into a platform of a newly built subway station. Therefore, the working shaft 2 is arranged close to the existing subway station 1, and the two are subsequently connected, which can not only make the new and old subway stations closely combined, but also greatly save construction costs.
[0045] Figure 2 The figure shows the support frame workstation diagram of Example 1 of the present application. The support frame 3 is arranged below the existing subway station 1 and connects the working shafts 2 on both sides. The support frame 3 forms a passage of the newly built subway station, including a tube curtain wall 31. Furthermore, the support frame 3 penetrates the plate wall structure 21 and the ground wall structure 11.
[0046] Figure 3 The figure shows a side view of the tube curtain wall of Example 1 of the present application. The tube curtain wall 31 is arranged below the floor 12 of the existing subway station 1. Its cross section includes a closed structure composed of a plurality of pipes 311 connected in parallel. The passage of the newly built subway is arranged inside the closed structure. The pipes 311 constituting the tube curtain wall 31 are preferably steel pipes, which have a special structure. The adjacent pipes 311 are provided with matching lock buckles 112 and lock heads 113. Figure 4 The enlarged partial view of the tube curtain wall 3-1 of the embodiment 1 of the present application is shown. In addition, by arranging a stiffening plate inside the pipeline 311, the strength of the pipeline 311 is increased, and the supporting strength of the tube curtain wall 31 is improved.
[0047] With the pipe curtain wall 31 of this structure, the size of the pipe 311 is selected according to the design plan, and the pipe 311 is pushed into the underground soil layer through the working wells 2 on both sides to form an interconnected pipe curtain wall 31. Further, after the construction of the pipe curtain wall 31 is completed, the gap between adjacent pipes 311 is filled with grout to form a first waterproof layer 312. After the first waterproof layer 312 solidifies, the soil layer outside the pipe curtain wall 31 is frozen through the freezing pipe in the pipe 311, specifically forming a soil layer with a thickness of 1 meter that can be frozen, thereby forming a second waterproof layer 313 of the pipe curtain wall 31.
[0048] It should be noted that Figure 3 The cross-section of the tube curtain wall 31 shown is a rectangular structure, but other types of structures, such as circular, elliptical, etc., can be constructed into a passage under the subway according to actual needs, which are all permitted by this application. Technicians in this field can design a suitable structure of the tube curtain wall 31 according to engineering needs.
[0049] In addition, when the pipeline 311 is pushed into the underground soil layer from the working well 2, if there are no obstacles, a longer pipeline 311, such as a through pipe, can be selected; but when obstacles are encountered, they can be pushed in from the working wells 2 on both sides, and the obstacles are set between two adjacent sections of the pipeline 311. At the same time, in order to make the pipeline 311 have better strength, preferably, a stiffening plate is set in the pipeline 311 to enhance its support strength.
[0050] Figure 5 The figure shows the front view of the support structure for the subway underpass of Example 1 of the present application. Working shafts 2 are excavated on both sides of the existing subway station 1. A support frame 3 is set below the existing subway station 1. The support frame 3 is connected to the working shaft 2 and includes a tube curtain wall 31, a first waterproof layer 312, a second waterproof layer 313, an inner lining layer 32, and a passage 33. When the support frame 3 passes through the existing subway station 1, it is necessary to destroy the enclosure and support structure below the existing subway station 1, especially the ground wall structure 11 on both sides thereof, and the plate wall structure 21 of the working shaft 2. The ground wall structure 11 is not only used to support the existing subway station 1, but also can play an anti-floating role to prevent the existing subway station 1 from floating and deforming due to the pressure of groundwater. After the ground wall structure 11 is destroyed, in order to prevent the existing subway station 1 from floating or sinking and deforming, the ground wall structure 11, the plate wall structure 21 and the support frame 3 located above and below the support frame 3 are connected together through the upper connecting member 34 and the lower connecting member 35, respectively, so that the newly built subway station and the existing subway station are combined into an integrated structure. Finally, the anti-floating device 36 is installed on the top and the middle of the ground wall structure 11 and the plate wall structure 21 to prevent the existing subway station ground wall structure 11 from losing anti-buoyancy due to the opening of the lower part, causing the structure to float or sink and other deformations.
[0051] It should be noted that although the waterproof layer involved in the above technical solution includes a first waterproof layer 312 and a second waterproof layer 313, it does not mean that the present application is limited to two waterproof layers. Instead, it is planned from an economic perspective. Technical personnel in this field can add waterproof layers of appropriate thickness and quantity according to actual needs and in combination with the technical solution mentioned in this application.
[0052] By adopting the technical solution provided in this application, a new subway station can be set up just below the existing subway station 1. The excavation depth requirement for the working shaft 2 is low, the overall structure is compact, and the construction cost is economical. This overcomes the problems of other technical solutions that require a large amount of excavation and complex construction when building a new subway station, while reducing the impact on the operation of the existing subway station 1.
[0053] Figure 6 What is shown is a side view of the support structure for underpass of the subway of Example 1 of the present application. Multiple lining layers are arranged inside the tube curtain wall 31 to further enhance the support for the newly built subway station. The lining layer 32 is arranged close to the inner wall of the tube curtain wall 31 to form a relatively complete and smooth plane. It should be noted that the thickness or quantity of the lining layer 32 can be designed according to the actual engineering needs. A channel 33 is arranged close to the inner lining layer 32. The channel 33 can be transported to the construction site after being manufactured in the factory in advance, and the channel 33 can be pushed in through the working shaft 2 on one side to form a channel under the subway. It can also be cast on site. Compared with the traditional mining excavation method, the channel 33 manufactured in advance can greatly save engineering time and excavation workload. At the same time, it has a more uniform force surface and a better bearing effect. Therefore, technicians in this field can perform the most optimized design according to engineering needs.
[0054] Figure 7 The flowchart of the manufacturing method of the underpass subway support structure of Example 1 of the present application is shown, which includes the following steps:
[0055] S11: excavating working shafts along both sides of the existing subway station, wherein the working shafts extend vertically underground;
[0056] S12: a support frame connected to the working shaft is arranged below the existing subway station, wherein the support frame forms a passage passing under the subway, including a tube curtain wall;
[0057] S13: Connecting the working shaft, the existing subway station and the support frame via connecting parts.
[0058] A working pit is excavated on each side of the existing subway station, and the enclosure structure of the working pit is as close to the enclosure structure of the existing subway station as possible, so that the overall structure is compact and the construction volume is small. The two working pits excavated successively are back-built with slab walls and other structures to reinforce their internal supports. After the internal structure of the working pit is completed, part of the ground wall structure or enclosure piles of the existing subway station is chiseled out, and the support frame is pushed from one working pit to the opposite working pit.
[0059] Figure 8 The figure shows a manufacturing flow chart of the support frame of Example 1 of the present application, which includes the following steps:
[0060] S21: connecting multiple pipes side by side to form a pipe curtain wall with a closed cross-section;
[0061] S22: injecting grout along the gaps between the plurality of pipes connected in parallel to form a first waterproof layer;
[0062] S23: a freezing pipe is arranged in the pipeline to freeze the soil layer around the pipeline to form a second waterproof layer;
[0063] S24: A plurality of inner lining layers are arranged along the tube curtain wall, and the plurality of inner lining layers penetrate the existing subway station and form the passage passing under the subway.
[0064] The pipe curtain wall is composed of multiple pipes connected side by side. The pipe curtain wall is pushed forward from one working well to the opposite working well. Its cross section is a closed structure. The inner diameter of the pipe must meet the size requirements of the subsequent dark excavation structure. Anti-friction lubricant is applied to the lock buckle of the pipe curtain joint, and grouting is performed to form the first waterproof layer. A freezing pipe is left inside the pipeline. After the pipe curtain is completed, the soil layer around the pipeline is frozen to form the second waterproof layer. Multiple lining layers are set along the inside of the pipe curtain wall. Multiple lining layers pass through the existing subway station and form a passage under the subway. Finally, anti-floating devices are set on the existing subway station and working well to prevent the existing subway station from floating or sinking due to construction below.
[0065] Fig. 9 What is shown is a side view of the tube curtain wall of Example 2 of the present application, wherein a load-bearing pile foundation 13 is arranged under the existing subway station 1. Since the pile foundation 13 has a certain rigidity, the pipeline 311 cannot be directly penetrated. Therefore, when a new subway station is built under the bottom plate 12 of the existing subway station 1, when the tube curtain wall 31 is set, the pile foundation 13 needs to be manually chiseled out at the place where the tube curtain wall 31 penetrates the pile foundation 13. Therefore, the pipeline 311 arranged at this work station should have a cavity for workers to chisel through, such as a large-diameter pipeline 311.
[0066] The adoption of the technical solution provided by this application not only meets the demand for building new subway stations under existing subway stations, but can also be applied to the construction of new structures under existing underground frame structures. The underpass subway support structure provided by this application has large pipe curtain support rigidity, strong bearing capacity for the upper station, and is more favorable for the deformation control of the upper station. It can also reduce the vertical clearance between the new structure and the existing station, thereby reducing the burial depth of the new station and saving construction costs; secondly, a combination of pipe curtain wall and frozen pipe is adopted, with the pipe curtain as the supporting structure, and the frozen curtain and the pipe curtain lock together form two water-stopping curtains. Under the condition of ensuring water-stopping, the frozen volume is greatly reduced, which can better control the deformation effect of frost heave and thaw settlement on the existing subway station.
[0067] In addition, new stations and working pits are set up on both sides of the existing subway station. Considering the high risk of underground excavation in high-water strata, once a dangerous situation occurs, such as sudden surge of pressurized water, measures can be taken from the opposite side to remedy it, such as adding freezing holes from the opposite side to freeze the soil and water below the existing subway station to ensure the stability of the water and soil under the existing subway station. Finally, the new subway station is built close to the existing subway station, and the underground excavation section only needs to meet the train passing limit. The underground excavation volume is small, which has little impact on the safety and construction period of underground excavation construction, as well as the impact on the existing station.
[0068] The technical features of the above-described embodiments may be arbitrarily combined. To make the description concise, not all possible combinations of the technical features in the above-described embodiments are described. However, as long as there is no contradiction in the combination of these technical features, they should be considered to be within the scope of this specification.
[0069] The above-mentioned embodiments only express several implementation methods of the present invention, and the descriptions thereof are relatively specific and detailed, but they cannot be understood as limiting the scope of the invention patent. It should be pointed out that, for ordinary technicians in this field, several variations and improvements can be made without departing from the concept of the present invention, and these all belong to the protection scope of the present invention. Therefore, the protection scope of the patent of the present invention shall be subject to the attached claims.
Claims
1. A support structure for underpasses, characterized in that: include: A working shaft, the working shaft extending vertically underground along both sides of the existing subway station; A support frame, the support frame is arranged below the existing subway station and connected to the working shaft, the support frame constitutes a passage passing under the subway, including a tube curtain wall; the working shaft comprises a plate wall structure on the side close to the existing subway station, and the two sides of the existing subway station comprise a ground wall structure, and the support frame penetrates the plate wall structure and the ground wall structure; the cross section of the tube curtain wall comprises a closed structure composed of a plurality of pipes connected in parallel, and the passage is arranged along the inside of the tube curtain wall; the support frame comprises a first waterproof layer composed of grouting grout, and the first waterproof layer is used to fill the gaps between the plurality of pipes connected in parallel; freezing pipes are arranged inside the plurality of pipes connected in parallel, and the freezing pipes are used to freeze the soil layer around the pipes and constitute a second waterproof layer of the support frame; A connecting member, the connecting member includes an upper connecting member and a lower connecting member, the upper connecting member and the lower connecting member are respectively connected to the support frame and the plate wall structure and the ground wall structure located above and below the support frame, so that the underpass subway support structure and the existing subway station are combined into one, forming an integrated structure for preventing the existing subway station from deforming; The connecting member also includes an anti-floating device, which is arranged on the plate wall structure and the ground wall structure to prevent deformation of the integrated structure.
2. The underpass subway support structure according to claim 1 is characterized in that: The pipeline that can be drilled manually is arranged at the pile foundation below the existing subway station.
3. The underpass subway support structure according to claim 1 is characterized in that: A stiffening plate is arranged inside the pipeline.
4. The underpass subway support structure according to claim 1 is characterized in that: The support frame further comprises a plurality of inner lining layers, which are arranged in the tube curtain wall and penetrate the existing subway station, and the passage is arranged inside the inner lining layers.
5. A method for manufacturing a support structure for underpasses according to any one of claims 1 to 4, characterized in that: The following steps are involved: Excavating working shafts along both sides of the existing subway station, wherein the working shafts extend vertically underground; A support frame connected to the working shaft is arranged below the existing subway station, and the support frame forms a passage passing under the subway, including a tube curtain wall; The working shaft, the existing subway station and the support frame are connected via connecting pieces.
6. The method for manufacturing a support structure for underpass subway according to claim 5, characterized in that: The support frame construction method comprises the following steps: Connect multiple pipes side by side to form a pipe curtain wall with a closed cross-section structure; Injecting grouting grout along the gaps between the plurality of pipelines connected in parallel to form a first waterproof layer; A freezing pipe is arranged in the pipeline to freeze the soil layer around the pipeline to form a second waterproof layer; A plurality of inner lining layers are arranged along the tube curtain wall, and the plurality of inner lining layers penetrate the existing subway station and form the passage passing under the subway station.
7. The method for manufacturing a support structure for underpass subway according to claim 6, characterized in that: Anti-floating devices are arranged on the existing subway station and the working shaft.
Citation Information
Patent Citations
Method for horizontal dynamic controlled-freezing water stopping between pipe roofs
CN104088652A
Large-section and small clear spacing dark excavation construction method through combined supporting of MJS construction method and pipe curtain method
CN107620600A
Underneath pass subway supporting structure
CN211008655U