A prefabricated bridge expansion joint device and construction method thereof
The prefabricated anchor concrete blocks and comb-toothed plates of the prefabricated bridge expansion joint device are quickly installed, combined with the use of double-headed screws and micro-expanded slurry, and the problems of long construction time and cumbersome maintenance in the existing technology are solved, and the rapid and Economical bridge expansion joint device replacement and repair improves vehicle traffic comfort and bridge structural stability.
Patent Information
- Application Number
- CN201911346744.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2019-12-24
- Publication Date
- 2024-11-26
- Estimated Expiration
- 2039-12-24
AI Technical Summary
The existing bridge expansion joint device has a long construction time, a long closed traffic time, a cumbersome maintenance process and high cost, which affects vehicle traffic and bridge structure safety.
Using prefabricated bridge expansion joint devices, including prefabricated anchor concrete blocks and comb-toothed plates, rapid installation and adjustment through double-headed screws and plastic sleeves, flexible sinks and micro-expanded slurries ensure stability, simplifying construction processes and reducing Human equipment demand.
It shortens construction time, reduces the impact on traffic, reduces maintenance costs, improves the flatness of the bridge deck and driving comfort, and is suitable for the restoration and replacement of new and old bridges.
Smart Images

Figure CN110904832B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to a bridge expansion joint construction technology, in particular to an assembled bridge expansion joint device capable of quickly replacing comb plates. The invention also relates to a construction method of the expansion joint device. Background Art
[0002] When a bridge connects traffic roads, heavy traffic will cause the beam to deform. These deformations need to be released by appropriate devices, otherwise the structure of the beam itself will be destroyed. The device that releases the deformation of the bridge beam is the bridge expansion joint device. Therefore, the bridge expansion joint device is one of the most vulnerable components in the bridge structure, and its maintenance or replacement frequency is high. With the sharp increase in highway traffic, the speed and load of vehicles continue to increase, and people's requirements for driving comfort are getting higher and higher. However, due to problems such as damage to concrete in the anchoring area and fracture of expansion joints, driving comfort will be reduced, and serious accidents may even occur, and sometimes the bridge structure will be affected. Therefore, in the process of bridge design and construction, the design and construction of bridge expansion joints are receiving more and more attention.
[0003] At present, the commonly used bridge expansion joint devices adopt the method of on-site welding and on-site pouring of concrete in the anchoring area. The construction time is long and the traffic needs to be closed for a long time. Once the concrete in the anchoring area or the expansion device is damaged, the concrete in the anchoring area needs to be chiseled open and the fixed steel bars need to be cut for repair or replacement. In summary, the construction and maintenance of commonly used bridge expansion joint devices have the following defects: long construction time and long traffic closure time; the construction is too troublesome, cutting, cleaning and welding require a lot of manpower and equipment, and the cost is high.
[0004] As the many technical difficulties and social problems caused by damage to bridge expansion joints become increasingly prominent, how to target the damage characteristics of highway bridge expansion joints and complete the rapid replacement and repair of damaged bridge expansion joints while minimizing the impact on vehicle travel time is a technical challenge that bridge maintenance and management departments must face and urgently need to solve. Summary of the invention
[0005] The purpose of the present invention is to provide an assembled bridge expansion joint device with simple structure, reasonable design and convenient construction to address the problems existing in the existing bridge expansion joint devices. The present invention also provides a construction method of the device.
[0006] To achieve the above purpose, the present invention can adopt the following technical solutions:
[0007] The prefabricated bridge expansion joint device described in the present invention includes left and right anchoring concrete blocks respectively placed on the left and right beam body mounting grooves of the expansion joint, vertical through holes are reserved on the left and right anchoring concrete blocks, and fixing parts pre-embedded in the beam body pass through the vertical through holes to fix the left and right anchoring concrete blocks on the beam body mounting grooves; the left and right comb plates placed on the expansion joint are fixedly connected to the left and right anchoring concrete blocks through connecting parts pre-embedded in the left and right anchoring concrete blocks; a flexible water guide groove is arranged between the left and right anchoring concrete blocks at the upper part of the expansion joint, and the two ends of the water guide groove are respectively fixed on the side walls of the left and right anchoring concrete blocks.
[0008] A leveling mortar layer is poured on the upper surface of the beam installation groove located at the bottom of the left and right anchor concrete blocks, and a micro-expansion slurry is poured in the gap between the side walls of the left and right anchor concrete blocks and the side walls of the beam installation groove; rigid gaskets for leveling comb plates are arranged on the left and right anchor concrete blocks under the left and right comb plates.
[0009] The fixing part embedded in the beam body is a double-headed screw, the lower part of which is installed in the threaded hole of the mounting plate embedded in the beam body, and the upper part of which is screwed with an anti-loosening nut; an inner hexagonal groove for screwing the double-headed screw is provided on the upper end surface of the double-headed screw; the vertical through-holes located on the upper surfaces of the left and right anchoring concrete blocks are stepped structures, and the anti-loosening nuts are sunk in the vertical through-holes of the stepped structure.
[0010] The left and right comb plates are provided with stepped mounting holes, and the connecting parts embedded in the left and right anchor concrete blocks are double-headed screws. The bottom of the double-headed screw is installed in the threaded holes of the mounting plates embedded in the left and right anchor concrete blocks, and the upper part passes through the stepped mounting holes, on which anti-loosening nuts are screwed; an inner hexagonal groove for screwing the double-headed screw is provided on the upper end surface of the double-headed screw.
[0011] A plastic sleeve is installed on the double-headed screw at the concrete pouring position, the external thread of the plastic sleeve matches the threaded hole of the mounting plate, and the internal thread of the plastic sleeve matches the thread of the double-headed screw.
[0012] A mounting plate with threaded holes is welded to the positioning reinforcement.
[0013] The mounting plate with threaded holes is provided with a plurality of through holes with positioning and fixing functions at intervals.
[0014] The upper surfaces of the left and right anchoring concrete blocks are evenly provided with grooves, and inverted U-shaped lifting steel bars are pre-embedded in the grooves.
[0015] The construction method of a bridge expansion joint device described in the present invention comprises the following specific steps:
[0016] S1: Prefabricate the left and right anchor concrete blocks in the factory: open threaded holes and non-threaded through holes on the cut mounting plate, then screw a certain number of studs on the mounting plate, install plastic sleeves at the pre-embedded concrete ends at the bottom of the studs, and weld and fix the mounting plate to the positioning steel bars; reserve vertical through holes, then pour concrete according to the design requirements, and finally maintain according to the standards to the specified age;
[0017] S2: Embed stud screws in the left and right beams of the expansion joint: First, open threaded holes and non-threaded through holes on the cut mounting plate according to the design requirements, then screw a certain number of stud screws on the mounting plate, and install plastic sleeves at the embedded concrete ends at the bottom of the stud screws, and weld and fix the mounting plate to the positioning steel bars; pour concrete to the designed height, and finally maintain according to the standard to the specified age;
[0018] S3: pouring a leveling mortar layer to level the working surfaces of the left and right beam installation grooves;
[0019] S4: hoist the left and right anchor concrete blocks in place respectively, and pass the double-ended screws embedded in the left and right beam bodies through the vertical through holes reserved on the left and right anchor concrete blocks respectively, and adjust the upper end faces of the double-ended screws to an appropriate height by screwing the hexagonal grooves embedded in the upper end faces of the double-ended screws in the left and right beam bodies, and tighten them with anti-loosening nuts, and apply anti-fouling coating;
[0020] S5: Install the left and right comb plates: Place rigid gaskets according to the height of the asphalt pavement layer on the bridge deck; Install the comb plates by screwing the hexagonal grooves on the upper end faces of the stud screws embedded in the left and right anchor concrete blocks, adjusting the upper end faces of the stud screws to be slightly lower than the upper surface of the comb plates, tightening them with anti-loosening nuts, and applying anti-fouling coating;
[0021] S6: pouring micro-expansion grouting material into the gaps between the left and right anchor concrete blocks and the left and right beam bodies;
[0022] S7: Level the upper surfaces of the left and right anchor concrete blocks and the asphalt pavement layer of the bridge deck to complete the construction of the prefabricated bridge expansion joint device.
[0023] The advantages of the present invention are embodied in the following points:
[0024] 1. It can realize the accurate and batch prefabrication of anchor concrete blocks, the main components of the expansion joint device, in the factory. The installation on site only needs to be carried out according to the process flow. There is no need for tedious work such as steel bar welding and concrete cutting. The construction time is short, the impact on traffic is small, and less manpower and equipment are required during the construction process.
[0025] 2. This device can be used for the construction of bridge expansion joints, and can also be used for the repair of bridge expansion joints on built bridges, with strong adaptability;
[0026] 3. Each part of the device can be easily dismantled and replaced, which is more practical. During maintenance, only the damaged part needs to be replaced, and no comprehensive maintenance or replacement is required, which reduces the maintenance cost;
[0027] 4. During the installation and construction of the device, the height of the anchoring concrete block can be adjusted on site to be consistent with the height of the asphalt pavement layer of the bridge deck. The method is simple, improves the flatness of the bridge deck, and further improves the driving comfort. BRIEF DESCRIPTION OF THE DRAWINGS
[0028] Figure 1 It is a schematic diagram of the cross-sectional structure of the expansion joint device of the present invention.
[0029] Figure 2 yes Figure 1 Schematic diagram of the top view structure.
[0030] Figure 3 This is a structural diagram of the fixings / connectors embedded in the beam body / anchor concrete block.
[0031] Figure 4 yes Figure 3 Structural diagram of the mounting plate.
[0032] Figure 5 It is a structural diagram of the left anchored concrete block.
[0033] Figure 6 yes Figure 5 Schematic diagram of the top view structure.
[0034] Figure 7 It is a structural diagram of the pre-embedded installation groove of the left beam.
[0035] Figure 8 yes Figure 7 Schematic diagram of the top view structure. DETAILED DESCRIPTION
[0036] like Figure 1-2As shown, the assembled bridge expansion joint device of the present invention comprises a left anchor concrete block 102 placed on the installation groove of the left beam body 101 of the expansion joint and a right anchor concrete block 202 placed on the installation groove of the right beam body 201, respectively. Vertical through holes are reserved on the left anchor concrete block 102 and the right anchor concrete block 202, and the fixing parts embedded in the beam body pass through the vertical through holes to fix the left anchor concrete block 102 and the right anchor concrete block 202 on the installation grooves of the left beam body 101 and the right beam body 201; The left comb plate 103 and the right comb plate 203 placed on the expansion joint are respectively connected to the left and right anchor concrete blocks through the connectors pre-buried in the left anchor concrete block 102 and the right anchor concrete block 202; a flexible water guide groove 104 made of rubber material is arranged between the left anchor concrete block 102 and the right anchor concrete block 202 at the upper part of the expansion joint, and the two ends of the water guide groove 104 are respectively fixed to the side walls of the left anchor concrete block 102 and the right anchor concrete block 202 by screws; the left anchor concrete block is provided with a flexible water guide groove 104 made of rubber material between the left anchor concrete block 102 and the right anchor concrete block 202 ... The upper surfaces of the beam installation grooves at the bottom of the left and right anchoring concrete blocks 102 and 202 are respectively poured with leveling mortar layers 105 and 205 (the leveling mortar uses self-leveling fast-hardening mortar, which can level the working surface of the installation groove to ensure the accurate installation of the anchoring concrete blocks without voids and to achieve the construction strength requirements in a short time), and the gaps between the side walls of the left and right anchoring concrete blocks 102 and 202 and the corresponding side walls of the beam installation grooves are poured with micro-expansion slurries 106 and 206 (micro-expansion slurries). The material has good fluidity, which can meet the requirements of grouting or pressure grouting, and has micro-expansion performance, which can make a certain pre-compression stress between the anchor concrete block and the beam body, ensure that the connection is more stable, and prevent rainwater and debris from entering); rigid gaskets 107 and 207 for leveling the comb plates are arranged on the left anchor concrete block 102 and the right anchor concrete block 202 under the left comb plate 103 and the right comb plate 203 (so that the comb plate and the asphalt pavement layer on the bridge surface can reach the same height to ensure the comfort of vehicle driving).
[0037] The connectors embedded in the left anchor concrete block 102 and the right anchor concrete block 202 of the present invention can adopt the same structure as the fixing members embedded in the left beam body 101 and the right beam body 201. Figure 3 , Figure 4As shown, it includes a stud screw 1, the lower part of which is installed in the threaded hole of the mounting plate 2 (after installation, the upper part is screwed with an anti-loosening nut); an inner hexagonal groove for screwing the stud screw is provided on the upper end surface of the stud screw 1, which is used to adjust the relative position between the upper end surface of the stud screw 1 and the surrounding mounting body; a plastic sleeve 4 is installed on the stud screw 1 at the concrete pouring position, the external thread of the plastic sleeve 4 matches the threaded hole of the mounting plate 2, and the internal thread of the plastic sleeve 3 matches the thread of the stud screw 1, which can effectively protect the pre-buried stud screw 1 from being solidified by the concrete after pouring, and ensure that the stud screw 1 can be freely disassembled and assembled. The mounting plate 2 is made of a whole steel plate, which has good integrity and is easy to process. Most importantly, it can well ensure the position accuracy of each stud screw installed thereon. In addition to the threaded holes 5 for installing the stud screws 1, the mounting plate 2 is also provided with a large number of through holes 6 that do not affect its structural stability. Steel bars or concrete can pass through these through holes 6 for positioning and fixing the mounting plate 2. The processed mounting plate 2 is welded to the positioning steel bars 7.
[0038] The bridge constructed by the expansion joint device of the present invention can be a bridge under construction or a built bridge where the original expansion joint device is repaired. If the expansion joint device is used to construct and repair an existing bridge, it is necessary to embed fixing parts (stud screws, mounting plates, positioning steel bars, etc.) in the left beam body 101 and the right beam body 201.
[0039] When the bridge constructed by the present invention is a bridge under construction that requires construction of a bridge expansion device, the construction process is as follows:
[0040] S1: prefabricate the left anchor concrete block 102 and the right anchor concrete block 202 in the factory: open the threaded holes 5 and the non-threaded through holes 6 on the cut mounting plate 2 according to the design requirements, then screw a certain number of stud screws 1 on the mounting plate, and install the plastic sleeve 4 on the pre-embedded concrete end at the lower part of the stud screw 1, and weld and fix the mounting plate 2 on the positioning steel bar 7; in order to facilitate the hoisting during construction, the screw holes can be reserved, and the two ends of the inverted U-shaped steel bar can be welded (to form the hoisting steel bar), and the vertical through holes can be reserved, and then the concrete is poured according to the design requirements. Finally, it is cured to the specified age according to the standard. After the left anchor concrete block 102 is formed, the structure is as follows: Figure 5 , Figure 6 As shown;
[0041] S2: Embed stud screws in the left beam 101 and the right beam 201 of the expansion joint: The method is the same as S1. First, threaded holes 5 and non-threaded through holes 6 are opened on the cut mounting plate 2 according to the design requirements. Then, a certain number of stud screws 1 are screwed onto the mounting plate, and plastic sleeves 4 are installed at the embedded concrete ends of the stud screws 1. The mounting plate 2 is welded and fixed to the positioning steel bars 7. Concrete is poured to the designed height, and finally, it is cured to the specified age according to the standard. Figure 7, Figure 8 This is a schematic diagram of the structure after the left beam body is pre-embedded with double-headed screws;
[0042] S3: pouring leveling mortar layers 105 and 205 to level the working surfaces of the left and right beam installation grooves;
[0043] S4: hoist the left anchor concrete block 102 and the right anchor concrete block 202 into place respectively, and pass the double-headed screws embedded in the left beam body 101 and the right beam body 201 through the vertical through-holes reserved on the left and right anchor concrete blocks 102 and 202 respectively, and adjust the upper end surface of the double-headed screw 1 to an appropriate height through the hexagonal groove on the upper end surface of the double-headed screw 1, tighten it with an anti-loosening nut, and apply an anti-fouling coating; during actual construction, the vertical through-holes located on the upper surfaces of the left and right anchor concrete blocks 102 and 202 are stepped structures, and the anti-loosening nuts can be sunk into the vertical through-holes of the stepped structure;
[0044] S5: Install the left comb plate 103 and the right comb plate 203. The left comb plate 103 is placed across the expansion joint on the right anchor concrete block 202: Before construction, the required thickness of the rigid gaskets 107 and 207 is calculated according to the height of the bridge deck asphalt pavement layer 1001 (the rigid gaskets can be used in one or more stacks according to the height adjustment requirements). After they are placed, the comb plates are installed to ensure that the height of the upper surface of the comb plates is consistent with that of the bridge deck asphalt pavement layer 1001, thereby improving driving comfort; by screwing the hexagonal groove on the upper end surface of the stud screw 1 embedded in the left and right anchor concrete blocks 102 and 202, the upper end surface of the stud screw is adjusted to be slightly lower than the upper surface of the comb plate, and tightened with an anti-loosening nut, and coated with an anti-fouling coating;
[0045] S6: pouring micro-expansion grouting material 106, 206 into the gaps between the left and right anchor concrete blocks 102, 202 and the left and right beam bodies 101, 201;
[0046] S7: Use quick-hardening UHPC to level the upper surfaces of the left and right anchor concrete blocks 102, 202 and the bridge deck asphalt pavement layer 1001, completing the construction of the prefabricated bridge expansion joint device.
[0047] On the contrary, the comb plate can be quickly replaced or the assembled bridge expansion device can be disassembled and replaced, and a small part needs to be chiseled, such as the upper end of the double-headed screw covered with fast-hardening UHPC.
Claims
1. A construction method for a bridge expansion joint device, using the following assembled bridge expansion joint device: comprising left and right anchoring concrete blocks respectively placed on the left and right beam body mounting grooves of the expansion joint, vertical through holes are reserved on the left and right anchoring concrete blocks, stud screws pre-buried in the beam body pass through the vertical through holes, and the left and right anchoring concrete blocks are fixed on the beam body mounting grooves; left and right comb plates placed on the expansion joint are fixedly connected to the left and right anchoring concrete blocks through stud screws pre-buried in the left and right anchoring concrete blocks; a flexible water guide groove is arranged between the left and right anchoring concrete blocks at the upper part of the expansion joint, and the two ends of the water guide groove are respectively fixed on the side walls of the left and right anchoring concrete blocks; The specific construction steps include: S1: Prefabricate the left and right anchor concrete blocks in the factory: open threaded holes and non-threaded through holes on the cut mounting plate, then screw a certain number of studs on the mounting plate, install plastic sleeves at the pre-embedded concrete ends at the bottom of the studs, and weld and fix the mounting plate to the positioning steel bars; reserve vertical through holes, then pour concrete according to the design requirements, and finally maintain according to the standards to the specified age; S2: Embed stud screws in the left and right beams of the expansion joint: First, open threaded holes and non-threaded through holes on the cut mounting plate according to the design requirements, then screw a certain number of stud screws on the mounting plate, and install plastic sleeves at the embedded concrete ends at the bottom of the stud screws, and weld and fix the mounting plate to the positioning steel bars; pour concrete to the designed height, and finally maintain according to the standard to the specified age; S3: pouring a leveling mortar layer to level the working surfaces of the left and right beam installation grooves; S4: hoist the left and right anchor concrete blocks in place respectively, and pass the double-ended screws embedded in the left and right beam bodies through the vertical through holes reserved on the left and right anchor concrete blocks respectively, and adjust the upper end faces of the double-ended screws to an appropriate height by screwing the hexagonal grooves embedded in the upper end faces of the double-ended screws in the left and right beam bodies, and tighten them with anti-loosening nuts, and apply anti-fouling coating; S5: Install the left and right comb plates: Place rigid gaskets according to the height of the asphalt pavement layer on the bridge deck; Install the comb plates by screwing the hexagonal grooves on the upper end faces of the stud screws embedded in the left and right anchor concrete blocks, adjusting the upper end faces of the stud screws to be slightly lower than the upper surface of the comb plates, tightening them with anti-loosening nuts, and applying anti-fouling coating; S6: pouring micro-expansion grouting material into the gaps between the left and right anchor concrete blocks and the left and right beam bodies; S7: Level the upper surfaces of the left and right anchor concrete blocks and the asphalt pavement layer of the bridge deck to complete the construction of the prefabricated bridge expansion joint device.