Infill wall combined anti-cracking structure and construction method
By adopting a combined crack-resistant structure and simplified construction methods in the frame-filled wall, hexagonal bricks and micro-expanded concrete are used to solve the crack-resistant problem of the frame-filled wall under the action of earthquakes, and the seismic performance and construction efficiency are improved.
Patent Information
- Application Number
- CN201911392651.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2019-12-30
- Publication Date
- 2024-12-06
- Estimated Expiration
- 2039-12-30
AI Technical Summary
Existing frame-filled walls are prone to cracking and collapse under the action of earthquakes, mainly due to insufficient shear strength and deformation capacity and complex construction process, which leads to a great impact on the overall stiffness of the structure, making it difficult to accurately consider the rigidity of the partition wall, causing damage to the main structure.
The combined crack-resistant structure is adopted, including upper floor beams, frame columns, lower floor beams, floor structure bricks, horse teeth joints, spring beams, fill wall structural columns and tie beams, and the mold is built through welding and embedded parts. Hexagonal bricks and micro-expanded concrete filling are used to increase tensile resistance, and nesting mode is used in structural column formwork to simplify construction steps.
Effectively prevent the occurrence of cracks in the building, simplify the construction process, save materials and manpower, improve the crack resistance and economic benefits of the filling wall, and enhance the seismic resistance of the structure.
Smart Images

Figure CN111101617B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to a filling wall structure, in particular to a filling wall combined anti-cracking structure and a construction method. Background Art
[0002] With the rapid development of my country's social economy, the proportion of high-rise buildings in urban construction has continued to increase. In the design of high-rise buildings, the frame is the main body, supplemented by the application of infill walls. Since such buildings take load and other factors into consideration when designing, the infill wall material is mainly lightweight blocks. However, after the construction of masonry and painting, the infill wall of this frame structure generally has vertical, horizontal, and oblique cracks of varying degrees due to various reasons, which directly affects the use and appearance of the house. Especially when it rains heavily, the outer wall will leak and affect the use function. At present, frame infill walls are mostly built with some small hollow blocks or porous bricks, and are connected to the main structure by a certain number of reinforcement bars. However, this structure has certain defects. From the perspective of structural stress performance, due to the problem of masonry quality, the overall performance of the infill wall is poor. Under the action of an earthquake, the infill wall is prone to sliding damage to the masonry mortar layer. In the prior art, reinforced concrete frame structure is a lateral force resisting structure widely used in buildings such as hotels, schools, and office buildings. Frame infill walls are the enclosing walls and partition walls of frame structure houses, and are generally non-load-bearing walls. In the investigation of the damage caused by the 5.12 Wenchuan earthquake, we found that the damage to the frame structure was relatively serious, a large part of which was due to the influence of the arrangement of the infill wall on the overall stiffness of the structure, that is, the infill wall and the main structure collided with each other during the earthquake, and the influence of the partition wall stiffness could not be accurately considered in the design calculation, resulting in damage to the frame main structure. At present, the application of frame structures in my country is quite extensive, so the reinforcement of frame infill walls is particularly important. It is found from macroscopic earthquake damage and experimental research that the cracking and collapse of the frame-filled wall under earthquake action are mainly due to the insufficient shear strength and deformation capacity of the frame-filled wall. The present invention proposes a new solution to the above problems. Summary of the invention
[0003] The purpose of the present invention is to overcome the deficiencies in the prior art and provide a combined anti-cracking structure of a filling wall and a construction method.
[0004] The combined anti-cracking structure of the filling wall comprises an upper floor beam, a frame column, a lower floor beam, building structure brickwork, a tie beam, a tooth joint, a spring beam, a casting mold for a filling wall structural column, and a casting mold for a filling wall tie beam; the upper floor beam and the lower floor beam are located at the upper and lower floors of the structure, the frame column stands on both sides between the upper floor beam and the lower floor beam, the building structure brickwork is arranged in a structural frame surrounded by the upper floor beam, the lower floor beam and the frame column; a tooth joint is left between the frame column and the building structure brickwork, and a tie beam is left on the upper part of the tooth joint; a spring beam is arranged on the top of the building structure brickwork; a reinforcing wire mesh is arranged at the part where the frame column and the building structure brickwork are released, and a dog tooth brick is arranged between the building structure brickwork and the upper floor beam;
[0005] The infill wall tie beam casting mold includes frame columns, upper floor beams, upper trusses, lower trusses, I-beams, connecting wood blocks, formwork brackets, side formwork brackets, side formwork bracket nuts and bolts, and embedded parts; the I-beams are located between the upper floor beams and the upper trusses and are connected by welding; the lower trusses are connected to the embedded parts; the formwork brackets are connected and fixed between the upper and lower trusses by connecting wood blocks, and the side formwork brackets are erected between the upper trusses and the lower trusses and are connected and fixed by the side formwork bracket nuts and bolts;
[0006] The infill wall structural column casting mold includes building structure brickwork, structural column formwork, exposed steel bars, stirrups, formwork fixing frames, formwork support frames, structural column formwork fixing bolts, structural column formwork fixing nuts and bottom structural bricks; the bottom of the building structure brickwork is laid with bottom structural bricks; the structural column formwork is arranged on one side of the building structure brickwork, and exposed steel bars and stirrups are arranged in the structural column formwork; formwork fixing frames are arranged at equal intervals outside the structural column formwork, and the formwork fixing frames are reinforced by formwork support frames, and the formwork support frames pass through the formwork fixing frames and are fixed; the formwork fixing frame and the structural column formwork are fixed by structural column formwork fixing bolts and structural column formwork fixing nuts.
[0007] As a preferred embodiment: the building structure brickwork is built into a hexagonal structure, the angle between the lower oblique side of the hexagon and the horizontal is not less than 75 degrees, the angle between the upper oblique side of the hexagon and the horizontal is not less than 75 degrees, and an opening window is left in the middle of the building structure brickwork; the micro-expansive concrete is filled in the gap between the building structure brickwork and the structural frame; the tooth joints are distributed in a tooth shape, and the upper part of the tooth joints that contacts the building structure brickwork is provided with a tooth joint wire grille, one end of the tooth joint wire grille is connected to the frame column, and the other end penetrates into the building structure brickwork; the lower end of the tie beam is provided with a tie beam wire grille at the part that contacts the tooth joint, and the length of the tie beam wire grille penetrating into the building structure brickwork is greater than the tooth joint wire grille.
[0008] As a preferred embodiment: the side I-beams are arranged on the inner side of the frame columns, the stiffening ribs are also arranged on the inner side of the frame columns, and the side I-beams and the stiffening ribs are in the same vertical line; the internal transverse trusses and the internal vertical trusses are respectively arranged on the two sides of the brickwork of the building structure, namely the front and back sides, and the internal transverse trusses are reinforced by connecting blocks.
[0009] As a preferred embodiment: a hole is reserved in the upper floor beam, one end of the spring is inserted into the hole and reinforced by an expansion bolt nut; the other end of the spring is inserted into the spring beam, and a spring beam wire grille is arranged between the spring beam and the brickwork of the building structure.
[0010] Preferably: the upper truss is connected and fixed to the frame column by an upper fixing screw, an upper fixing bolt and an upper fixing nut, the upper fixing nut penetrates into the frame column, the upper fixing bolt is arranged on the upper truss, and the upper fixing nut is connected and fixed together with the upper fixing bolt by the upper fixing screw; the lower truss is connected and fixed to the frame column by embedded parts, the embedded parts include plywood, embedded bolts, lower fixing rods, fixing frames, embedded bolts and embedded nuts, the embedded bolts are embedded in the frame column, the plywood is laid on the surface of the frame column, the fixing frame is connected to the plywood by welding, the embedded bolts penetrate into the embedded bolts, the embedded nuts are connected to the embedded bolts, the lower fixing rods are fixed in the embedded bolts and connected to the lower truss.
[0011] Preferably, the structural column template includes reserved holes, a front template, a middle template, a rear template and fixed columns. The front template, the middle template and the rear template are connected and fixed by welding. The upper parts of the middle template and the rear template are provided with reserved holes, and the lower parts of the middle template and the rear template are provided with fixed columns.
[0012] As a preferred embodiment: the fixed columns are fixed to the middle formwork and the lower part of the rear formwork through expansion bolt holes and expansion bolts; the structural column formwork is spliced in sections on one side of the building structure brickwork, and the splicing parts are connected by fixed columns and reserved holes.
[0013] The construction method of the infill wall combined anti-cracking structure includes the following construction steps:
[0014] 1) When the upper floor beams, frame columns and lower floor beams are cast, tooth joints are arranged on both sides of the frame columns in a toothed distribution, and tooth joint steel wire grilles are set at the corresponding positions of the frame columns on both sides;
[0015] 2) Then build the tie beam template; arrange the embedded parts: embed the embedded bolts in the frame column, then lay the plywood on the surface of the frame column, connect the fixing frame and the plywood by welding, insert the embedded bolts into the embedded bolts, connect the embedded bolts with the embedded nuts, fix the lower fixing rods in the embedded bolts, and prepare to connect with the lower trusses;
[0016] 3) Weld the I-beam to the upper floor beam and connect it to the upper truss. The upper truss is connected to the frame column through the upper fixing screw rod, upper fixing bolt and upper fixing nut to fix the upper truss. After fixing the upper and lower trusses, start to set up the internal structure of the formwork, arrange the formwork support and side formwork support, the formwork support is fixed by connecting wooden blocks, the side formwork support is fixed by the side formwork support nut bolt, and finally install the side formwork;
[0017] 4) Pre-set holes in the upper floor beams; fix one end of the spring to the upper floor beams through expansion bolts and nuts, connect the other end of the spring to the spring beam and arrange the spring beam wire grid, then set the tie beam and tie beam wire grid, and then fill with micro-expansive concrete; then lay the bottom structural bricks, and on the basis of the bottom structural bricks, use the building structure bricks to build the building into a hexagon, and reserve the positions of the opening windows and structural columns at the corresponding positions of the building;
[0018] 5) Arrange exposed steel bars and stirrups at one end of the building structure brickwork and on the basis of the position of the structural column. After the steel bars are arranged, start to set up the structural column formwork; first prefabricate the structural column formwork: weld the front formwork, middle formwork and rear formwork, preset reserved holes on the upper part of the middle formwork and rear formwork, arrange fixed columns at the lower part of the middle formwork and rear formwork, reserve expansion bolt holes on the fixed columns and the lower part of the formwork, and use expansion bolts to connect and fix;
[0019] 6) Build the structural column formwork: The structural column formwork adopts the nesting mode, and is nested in sections; after the nesting of the structural column formwork is completed, the formwork fixing frames are arranged at equal intervals on the outside of the structural column formwork, and the formwork fixing frames are reinforced by the formwork support frames, and the formwork support frames pass through the formwork fixing frames and are fixed; the part where the formwork fixing frame contacts the structural column formwork is reinforced by the structural column formwork fixing nuts and structural column formwork fixing bolts;
[0020] 7) Cast structural columns, arrange the side I-beams on the inner side of the frame columns, and the stiffening ribs are also arranged on the inner side of the frame columns, both of which are in the same vertical line; the internal transverse trusses and internal vertical trusses are arranged on both sides of the brickwork of the building structure, namely the front and back, and the internal transverse trusses are reinforced by connecting blocks; complete the construction of the combined anti-cracking structure of the infill wall.
[0021] The beneficial effects of the present invention are:
[0022] 1. The present invention adopts a hexagonal building structure and fills the pores with micro-expansive concrete. The hexagon has good ductility, and after being filled with micro-expansive concrete, the building provides a certain tensile resistance, which can well prevent the occurrence of cracks in the building.
[0023] 2. The tie beam of the present invention adopts a semi-suspended formwork construction, which saves a lot of construction materials compared to building the formwork from the ground, and the construction steps are simple and convenient, saving manpower and material resources, and having good economic and technical benefits.
[0024] 3. The casting mold for the filling wall structural column of the present invention is erected in a nested mode, which is not only convenient to erect but also simple in structure. The mold can be prefabricated or erected on site, saving manpower and material resources and having good technical and economic benefits. BRIEF DESCRIPTION OF THE DRAWINGS
[0025] Figure 1 It is the overall schematic diagram of the combined anti-cracking structure of the filling wall;
[0026] Figure 2 It is a schematic diagram of the upper floor beam and spring fixing device;
[0027] Figure 3 This is a schematic diagram of the steel wire mesh structure and dogtooth bricks that reinforce the interior of the frame column;
[0028] Figure 4 This is the overall front view of the mold for pouring the tie beam of the filling wall;
[0029] Figure 5 It is a schematic diagram of the embedded parts of the casting mold for the filling wall tie beam;
[0030] Figure 6 It is a schematic diagram of the overall side view of the casting mold for the infill wall tie beam;
[0031] Figure 7 This is the overall schematic diagram of the casting mold for the infill wall structural column;
[0032] Figure 8 It is a schematic diagram of the structural column template structure;
[0033] Fig. 9 It is a schematic diagram of the fixed column connection at the bottom of the structural column formwork;
[0034] Fig.10 It is a schematic diagram of the reinforcement structure of the combined anti-cracking structure of the filling wall.
[0035] Explanation of the reference numerals: 1-upper floor beam; 2-frame column; 3-lower floor beam; 4-opening window; 5-building structure brickwork; 6-tie beam; 7-tie beam wire grille; 8-horse tooth joint; 9-horse tooth joint wire grille; 10-micro-expansion concrete; 11-spring beam; 12-spring beam wire grille; 13-spring; 14-expansion bolt nut; 15-dog tooth brick; 16-reinforcement wire mesh; 17-I-beam; 18-lower truss; 19-formwork support; 20-connecting wood block; 21-side formwork support; 22-upper truss; 23-side formwork support nut bolt; 24-upper fixing bolt; 25-upper fixing screw; 26-upper fixing nut; 27-embedded part; 28-clamp Plate; 29-embedded bolts; 30-lower fixing rod; 31-fixing frame; 32-embedded bolts; 33-embedded nuts; 34-side formwork; 35-side I-beam; 36-stiffening ribs; 37-internal transverse trusses; 38-internal vertical trusses; 39-connecting blocks; 40-structural column formwork; 41-exposed steel bars; 42-hoops; 43-bottom structural bricks; 44-formwork fixing frame; 45-formwork support frame; 46-structural column formwork fixing nuts; 47-structural column formwork fixing bolts; 48-reserved holes; 49-front formwork; 50-middle formwork; 51-rear formwork; 52-fixed columns; 53-expansion bolt holes; 54-expansion bolts. DETAILED DESCRIPTION
[0036] The present invention is further described below in conjunction with embodiments. The description of the following embodiments is only used to help understand the present invention. It should be noted that for those of ordinary skill in the art, without departing from the principles of the present invention, several improvements and modifications may be made to the present invention, and these improvements and modifications also fall within the scope of protection of the claims of the present invention.
[0037] according to Figure 1 As shown, when the upper floor beams 1, frame columns 2, and lower floor beams 3 (the upper floor beams 1 and lower floor beams 3 are located on the upper and lower floors of the structure and are the originally existing structures) are cast, tooth joints 8 are arranged. The tooth joints 8 are arranged on both sides of the frame columns 2 in a tooth-like distribution, and tooth joint wire grilles 9 are set at corresponding positions of the frame columns 2 on both sides.
[0038] according to Figure 4 , Figure 5 , Figure 6 As shown, the tie beam template is built. The embedded parts 27 are arranged: the embedded bolts 29 are embedded in the frame column 2, and then the plywood 28 is laid on the surface of the frame column 2, the fixing frame 31 is connected with the plywood 28 by welding, the embedded bolts 32 are inserted into the embedded bolts 29, the embedded bolts 32 are connected with the embedded nuts 33, the lower fixing rods 30 are fixed in the embedded bolts 32, and are ready to be connected with the lower trusses 18.
[0039] according to Figure 4 , Figure 5 , Figure 6 As shown, the I-beam 17 is welded to the upper floor beam 1 and connected to the upper truss 22. The upper truss 22 is connected to the frame column 2 through the upper fixing bolts 24, the upper fixing nuts 26, and the upper fixing screws 25 to fix the upper truss 22. After fixing the upper and lower trusses, the internal structure of the formwork is set up, and the formwork bracket 19 and the side formwork bracket 21 are arranged. The formwork bracket 19 is fixed by connecting the wooden blocks 20, and the side formwork bracket 21 is fixed by the side formwork bracket nut bolts 23, and provides a certain vertical support force, and finally the side formwork 34 is installed.
[0040] according to Figure 1 , Figure 2 As shown, holes are pre-set in the upper floor beam 1 to facilitate the next construction step. The spring 13 is fixed to the upper floor beam 1 through the expansion bolt nut 14, the spring 13 is connected to the spring beam 11 and the spring beam wire grid 12 is arranged, the tie beam 6 and the tie beam wire grid 7 are set, and then the micro-expansive concrete 10 is filled. Then the bottom structure bricks 43 are laid to ensure stability. On the basis of the bottom structure bricks 43, the building structure bricks 5 are used to build the building into a hexagon, and the positions of the opening windows 4 and structural columns are reserved at the corresponding positions of the building.
[0041] according to Figure 7 , Figure 8 and Fig. 9 As shown, exposed steel bars 41 and stirrups 42 are arranged on one end of the building structure brickwork 5 and the position of the structural column. After the steel bars are arranged, the structural column formwork 40 can be set up. Prefabricated structural column formwork 40: the front formwork 49, the middle formwork 50 and the rear formwork 51 are welded, the upper part of the middle formwork 50 and the rear formwork 51 is preset with reserved holes 48, the lower part of the middle formwork 50 and the rear formwork 51 is arranged with fixed columns 52, the fixed columns 52 and the lower part of the formwork are reserved with expansion bolt holes 53, and are connected and fixed with expansion bolts 54.
[0042] according to Figure 7 As shown, the structural column template 40 is built: the structural column template 40 is nested in sections. After the nesting of the structural column template 40 is completed, a circle of template fixing frames 44 are arranged every half meter on the outside of the structural column template 40, and the template fixing frames 44 are reinforced by template support frames 45, which pass through the template fixing frames 44 and are fixed. The part of the template fixing frame 44 that contacts the structural column template 40 is reinforced by the structural column template fixing nut 46 and the structural column template fixing bolt 47.
[0043] according to Fig.10As shown, the structural column is cast, the side I-beam 35 is arranged inside the frame column 2, and the stiffening rib 36 is also arranged inside the frame 2, and the two are in the same vertical line. The internal transverse truss 37 and the internal vertical truss 38 are arranged on both sides of the building structure brickwork 5, namely the front and back, and the internal transverse truss 37 is reinforced by the connecting block 39. In this way, the infill wall combined crack-resistant structure is completed.
Claims
1. A combined anti-cracking structure of a filling wall, characterized by: The invention comprises an upper floor beam (1), a frame column (2), a lower floor beam (3), a building structure brickwork (5), a tie beam (6), a tooth joint (8), a spring beam (11), a casting mold for a filling wall structural column, and a casting mold for a filling wall tie beam; the upper floor beam (1) and the lower floor beam (3) are located on the upper and lower floors of the structure, the frame column (2) stands on both sides between the upper floor beam (1) and the lower floor beam (3), and the building structure brickwork (5) is arranged on the upper floor beam ( 1), in a structural frame formed by the lower floor beam (3) and the frame column (2); a tooth joint (8) is left between the frame column (2) and the building structure brickwork (5), and a tie beam (6) is left on the upper part of the tooth joint (8); a spring beam (11) is provided on the top of the building structure brickwork (5); a reinforcing steel wire mesh (16) is provided at the part where the frame column (2) and the building structure brickwork (5) are released, and a dog tooth brick (15) is provided between the building structure brickwork (5) and the upper floor beam (1); The infill wall tie beam casting mold comprises a frame column (2), an upper floor beam (1), an upper truss (22), a lower truss (18), an I-beam (17), a connecting wood block (20), a formwork support (19), a side form support (21), a side form support nut bolt (23) and an embedded part (27); the I-beam (17) is located between the upper floor beam (1) and the upper truss (22) and is connected by welding; the lower truss (18) is connected to the embedded part (27); the formwork support (19) is connected and fixed between the upper and lower trusses by connecting wood blocks (20); the side form support (21) is erected between the upper truss (22) and the lower truss (18) and is connected and fixed by the side form support nut bolt (23); The infill wall structural column casting mold comprises a building structure brickwork (5), a structural column formwork (40), exposed steel bars (41), stirrups (42), a formwork fixing frame (44), a formwork support frame (45), structural column formwork fixing bolts (47), structural column formwork fixing nuts (46) and bottom structural bricks (43); the bottom of the building structure brickwork (5) is laid with bottom structural bricks (43); the structural column formwork (40) is arranged on one side of the building structure brickwork (5), and exposed steel bars (41) and stirrups (42) are arranged inside the structural column formwork (40); formwork fixing frames (44) are arranged at equal intervals outside the structural column formwork (40), and the formwork fixing frames (44) are reinforced by formwork support frames (45), and the formwork support frames (45) pass through the formwork fixing frames (44) and are fixed; the formwork fixing frames (44) and the structural column formwork (4 0) is fixed by structural column template fixing bolts (47) and structural column template fixing nuts (46); a hole is reserved in the upper floor beam (1), one end of the spring (13) penetrates into the hole and is reinforced by the expansion bolt nut (14); the other end of the spring (13) penetrates into the spring beam (11), and a spring beam wire grid (12) is arranged between the spring beam (11) and the building structure brickwork (5); the structural column template (40) includes a reserved hole (48), a front template (49), a middle template (50), a rear template (51) and a fixing column (52), the front template (49), the middle template (50) and the rear template (51) are fixed by welding, the upper part of the middle template (50) and the rear template (51) are both provided with a reserved hole (48), and the lower part of the middle template (50) and the rear template (51) are provided with a fixing column (52).
2. The infill wall combined anti-cracking structure according to claim 1 is characterized in that: The building structure brickwork (5) is laid into a hexagonal structure, the angle between the lower oblique side of the hexagon and the horizontal is not less than 75 degrees, the angle between the upper oblique side of the hexagon and the horizontal is not less than 75 degrees, and an opening window (4) is left in the middle of the building structure brickwork (5); the micro-expansive concrete (10) is filled in the gap between the building structure brickwork (5) and the structural frame; the tooth joints (8) are distributed in a toothed shape, and the portion of the upper portion of the tooth joints (8) that contacts the building structure brickwork (5) is provided with a tooth joint steel wire grille (9), one end of the tooth joint steel wire grille (9) is connected to the frame column (2), and the other end penetrates into the building structure brickwork (5); the portion of the lower end of the tie beam (6) that contacts the tooth joint (8) is provided with a tie beam steel wire grille (7), and the length of the tie beam steel wire grille (7) penetrating into the building structure brickwork (5) is greater than the tooth joint steel wire grille (9).
3. The infill wall combined anti-cracking structure according to claim 1 is characterized in that: The side I-beam (35) is arranged on the inner side of the frame column (2), and the stiffening rib (36) is also arranged on the inner side of the frame column (2). The side I-beam (35) and the stiffening rib (36) are located on the same vertical line. The internal transverse truss (37) and the internal vertical truss (38) are respectively arranged on the two sides of the building structure brickwork (5), namely the front side and the back side. The internal transverse truss (37) is reinforced by a connecting block (39).
4. The infill wall combined anti-cracking structure according to claim 1, characterized in that: The upper truss (22) is connected and fixed to the frame column (2) via an upper fixing bolt (24), an upper fixing screw rod (25) and an upper fixing nut (26); the upper fixing nut (26) penetrates into the frame column (2); the upper fixing bolt (24) is arranged on the upper truss (22); the upper fixing nut (26) and the upper fixing bolt (24) are connected and fixed together via the upper fixing screw rod (25); the lower truss (18) is connected and fixed to the frame column (2) via an embedded part (27); the embedded part (27) includes a clamping plate (28). , embedded bolts (29), a lower fixing rod (30), a fixing frame (31), embedded bolts (32) and embedded nuts (33), wherein the embedded bolts (29) are embedded in the frame column (2), a plywood (28) is laid on the surface of the frame column (2), the fixing frame (31) is connected to the plywood (28) by welding, the embedded bolts (32) penetrate into the embedded bolts (29), the embedded nuts (33) are connected to the embedded bolts (29), and the lower fixing rod (30) is fixed in the embedded bolts (32) and connected to the lower truss (18).
5. The infill wall combined anti-cracking structure according to claim 1 is characterized in that: The fixing column (52) is fixed to the lower part of the middle template (50) and the rear template (51) through the expansion bolt holes (53) and the expansion bolts (54); the structural column template (40) is spliced in sections on one side of the building structure brickwork (5), and the splicing part is connected by the fixing column (52) and the reserved hole (48).
6. A construction method of the infill wall combined anti-cracking structure according to claim 1, characterized in that: The construction steps include: 1) When the upper floor beam (1), the frame column (2), and the lower floor beam (3) are all cast, tooth joints (8) are arranged, the tooth joints (8) are arranged on both sides of the frame column (2) in a toothed distribution, and tooth joint steel wire grilles (9) are arranged at corresponding positions of the frame columns (2) on both sides; 2) Then, the tie beam template is constructed; the embedded parts (27) are arranged: the embedded bolts (29) are embedded in the frame column (2), and then the plywood (28) is laid on the surface of the frame column (2), the fixing frame (31) and the plywood (28) are connected by welding, the embedded bolts (32) are inserted into the embedded bolts (29), the embedded bolts (32) are connected to the embedded nuts (33), the lower fixing rods (30) are fixed in the embedded bolts (32), and are prepared to be connected to the lower trusses (18); 3) Welding the I-beam (17) to the upper floor beam (1) and connecting them to the upper truss (22), the upper truss (22) is connected to the frame column (2) through the upper fixing bolts (24), the upper fixing nuts (26) and the upper fixing screws (25) to fix the upper truss (22); after fixing the upper and lower trusses, start to set up the internal structure of the formwork, arrange the formwork support (19) and the side formwork support (21), the formwork support (19) is fixed by connecting the wooden blocks (20), and the side formwork support (21) is fixed by the side formwork support nut bolts (23), and finally install the side formwork (34); 4) Pre-arranging holes in the upper floor beam (1); fixing one end of the spring (13) to the upper floor beam (1) through an expansion bolt nut (14); connecting the other end of the spring (13) to the spring beam (11) and arranging the spring beam wire grid (12); then arranging the tie beam (6) and the tie beam wire grid (7); and then filling the micro-expansive concrete (10); then laying the bottom structure bricks (43); and on the basis of the bottom structure bricks (43), using the building structure bricks (5) to lay the building into a hexagon, and reserving the positions of the opening windows (4) and the structural columns at the corresponding positions of the building; 5) Arrange exposed steel bars (41) and stirrups (42) at one end of the building structure brickwork (5) and at the location of the structural column. After the steel bars are arranged, start to set up the structural column formwork (40); first prefabricate the structural column formwork (40): weld the front formwork (49), the middle formwork (50) and the rear formwork (51), pre-set reserved holes (48) on the upper parts of the middle formwork (50) and the rear formwork (51), arrange fixed columns (52) on the lower parts of the middle formwork (50) and the rear formwork (51), reserve expansion bolt holes (53) between the fixed columns (52) and the lower part of the formwork, and use expansion bolts (54) to connect and fix; 6) Building the structural column formwork (40): The structural column formwork (40) is nested in sections in a nested manner; after the nesting of the structural column formwork (40) is completed, formwork fixing frames (44) are arranged at equal intervals outside the structural column formwork (40), and the formwork fixing frames (44) are reinforced by formwork support frames (45), and the formwork support frames (45) pass through the formwork fixing frames (44) and are fixed; the portion where the formwork fixing frames (44) contact the structural column formwork (40) is reinforced by structural column formwork fixing nuts (46) and structural column formwork fixing bolts (47); 7) Casting structural columns, side I-beams (35) are arranged on the inner side of the frame columns (2), and stiffening ribs (36) are also arranged on the inner side of the frame columns (2), and the two are in the same vertical line; internal transverse trusses (37) and internal vertical trusses (38) are arranged on both sides of the building structure brickwork (5), namely the front and back sides, and the internal transverse trusses (37) are reinforced by connecting blocks (39); and the construction of the infill wall combined anti-cracking structure is completed.
Citation Information
Patent Citations
Assembly type frame beam structure based on 3D printing
CN106193282A
Lower multi-layer assembly type heat insulation and energy saving building
CN106836468A
Combined anti-crack structure of infilled wall
CN212224301U
Fully-assembled prestress concrete frame Anti-seismic energy dissipation member system and construction method
WO2019056716A1