Urban rail side passage construction support device and use method

Through the modularly designed urban rail side channel construction support device, the combined structure of inner sliding sleeve and outer sleeve is used to solve the problems of low construction efficiency and major safety hazards in the existing technology, and achieve fast and flexible rail support , reduce labor intensity and material loss, and improve construction safety and efficiency.

CN111304981BActive Publication Date: 2024-11-12SHANGHAI CIVIL ENG GRP CO LTD OF CREC +1
View PDF 6 Cites 0 Cited by

Patent Information

Application Number
CN202010179992.4
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2020-03-16
Publication Date
2024-11-12
Estimated Expiration
2040-03-16

AI Technical Summary

Technical Problem

In the existing urban rail construction, the temporary transition method has problems such as low construction efficiency, high labor intensity, serious material loss and great safety hazards. Especially in the construction of underground shield section liaison channel, temporary support structures need to be frequently set up and demolished. , resulting in limited construction progress.

Method used

A modular urban rail side channel construction support device is designed, including an inner sliding sleeve assembly and an outer sleeve assembly. Through the combined structure of supporting the lead screw and transmission shaft head, flexible support and height adjustment of the rail is achieved. Ability to be quickly installed and disassembled without external power supply, suitable for cantilever hoisting and flatbed transport.

Benefits of technology

It improves construction efficiency, reduces labor intensity and material loss, simplifies the installation and disassembly of support devices, reduces labor costs, and improves construction safety.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN111304981B_ABST
    Figure CN111304981B_ABST
Patent Text Reader

Abstract

The present invention relates to the field of track construction technology, specifically, a construction support device for a side channel of an urban track and a method of use, comprising an inner sleeve assembly and an outer sleeve assembly, the two ends of the outer sleeve assembly are respectively sleeved on the outer sides of the inner ends of the two inner sleeve assemblies, and the transmission screws of the two inner sleeve assemblies are respectively provided with a second transmission bevel gear meshing with the first transmission bevel gear at one end thereof close to the first transmission bevel gear. The construction support device for a side channel of an urban track provided by the present invention has a simple and feasible combined structure, is easy to install and disassemble, adopts a modular design, is small in size, is easy to install, and can effectively improve construction efficiency; each component is finalized and processed and can be reused as a turnover material, saving construction materials; the support device can be hoisted by a small cantilever crane, which can greatly reduce labor intensity; an adjustable structure is adopted, which is convenient for adjusting the state of the support device, convenient for transportation, and saving labor costs; it does not need to rely on an external power supply when in use, and has high applicability.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of track construction, and in particular to a construction support device for a city trackside passage and a use method thereof. Background Art

[0002] In the domestic subway track laying construction, in the 25m section before and after the construction of the underground shield section connecting channel is not completed or the settlement is not stable, it is necessary to use a temporary transition method for construction, mainly using temporary piers and steel to set up temporary transition rails. When the structural settlement is stable and meets the requirements, the temporary transition rails are removed, the roadbed is cleaned, re-measured, and the line is adjusted before the overall roadbed construction of the section is carried out.

[0003] (1) The temporary transition is carried out by using a temporary supporting pier. A temporary supporting pier needs to be cast under each short rail sleeper, and a screw is supported laterally. One end of the screw is against the waist of the rail outside the rail, and the other end is against the side wall. The screw spacing is 5m (increased in curved sections), and the rail is connected to the rail with a gauge tie rod in the track center on the same section as the screw. The casting and removal of the pier consumes a lot of labor and building materials, and the construction efficiency is low.

[0004] (2) Temporary transition is carried out by using steel transition method. It is necessary to set steel of appropriate length every 1.5 meters. The support and transportation process of steel is completed entirely by manual labor, which is labor-intensive and has low construction efficiency. In addition, due to the small space, the steel needs to be cut before it can be removed during the disassembly process, resulting in serious material loss. In addition, there is no support device in the middle part of the steel. When the rail car passes, the middle part of the steel is easily deformed, causing a major safety hazard.

[0005] The problem of supporting the side channel in subway track construction is the key point that restricts the progress of the entire construction. In order to ensure the progress of the construction, the project requires not only a large amount of funds and human resources, but also outstanding safety hazards. The existing temporary support construction of the rail connection channel has the disadvantages of low efficiency, high labor input, low degree of mechanization, high labor cost, and serious material loss. Therefore, a modular and mechanized construction equipment with high support construction efficiency is developed; a scattered side channel support construction equipment that does not rely on external power supply operation. The development and application of the side channel support construction equipment will have a significant impact on the existing track construction methods. Summary of the invention

[0006] The purpose of the present invention is to solve the deficiencies of the prior art and to provide a construction support device for a city rail side passage and a method of use thereof, which adopts a modular structure, helps to improve construction efficiency, reduce labor intensity, and save construction costs.

[0007] In order to achieve the above-mentioned purpose, a construction support device for a side channel of an urban rail is designed, comprising: an inner sleeve assembly, a first supporting screw is connected to the inner sleeve assembly, and the height of the inner sleeve assembly can be changed by rotating the first supporting screw, a supporting portion is provided at the outer end of the inner sleeve assembly, and a transmission screw is connected to the inner end of the inner sleeve assembly; and an outer sleeve assembly, a cavity is provided in the outer sleeve assembly, and a transmission shaft head is connected to one side of the outer sleeve assembly, the outer end of the transmission shaft head is located outside the outer sleeve assembly to be connected to a driving mechanism, the inner end of the transmission shaft head is provided with a first transmission bevel gear located in the cavity of the outer sleeve assembly, and the upper side of the outer sleeve assembly is also symmetrically provided with an accommodating groove for clamping a rail; the two ends of the outer sleeve assembly are respectively sleeved on the outer sides of the inner ends of the two inner sleeve assemblies, and the ends of the transmission screws of the two inner sleeve assemblies close to the first transmission bevel gear are respectively provided with second transmission bevel gears meshing with the first transmission bevel gear.

[0008] Preferably, the inner sleeve assembly comprises an inner sleeve square tube, an end plate is provided at one end of the inner sleeve square tube farther from the outer sleeve assembly to serve as a supporting portion, a nut baffle is provided at one end of the inner sleeve square tube closer to the outer sleeve assembly, a transmission nut is provided on the nut baffle, and the transmission nut is matched and connected with the transmission screw.

[0009] Preferably, support holes are provided on the upper and lower sides of the inner sliding sleeve square tube correspondingly, and a filament nut is provided in the support hole, and the filament nut is used to cooperate with the first support screw.

[0010] Preferably, the outer end surface of the supporting portion is an inclined surface or an arc surface.

[0011] Preferably, the outer sleeve assembly includes an outer sleeve square tube, and a connecting hole is provided on the front side or rear side of the middle part of the outer sleeve square tube for the transmission shaft head to extend into the outer sleeve square tube, and a retaining ring is provided at the connecting hole to limit the inner end of the transmission shaft head to the inner side of the retaining ring.

[0012] Preferably, an opening is provided on the upper side of the middle portion of the outer sleeve square tube, and an upper cover plate is detachably connected to the opening.

[0013] Preferably, a screw positioning plate is symmetrically provided in the middle of the outer sleeve square tube, a through hole is provided in the middle of the screw positioning plate for the transmission screw to pass through, and a thrust bearing is provided between the transmission screw and the outer sleeve square tube.

[0014] Preferably, the outer sleeve assembly is connected with a second supporting screw, and the height of the outer sleeve assembly can be changed by rotating the second supporting screw.

[0015] The present invention also relates to a method for using the urban rail side channel construction support device. After the rails are laid in place, one end of the rails is connected to the main rail, and a track-lifting machine is used for temporary support in the middle. At this time, the rails are supported by the urban rail side channel construction support device, including the following steps:

[0016] Step a. Hoist the supporting device below the rail and rotate the supporting device to make it vertically cross the rail so that the lower bottom surface of the rail fits tightly in the accommodating groove.

[0017] Step b. Lift the rail to the reference elevation by means of the first supporting screw and the second supporting screw.

[0018] Step c. by rotating the transmission shaft head, the abutment portion at the outer end of the inner sleeve assembly is closely fitted to the pipe wall.

[0019] Preferably, the construction support device is transported by a flatbed truck, and the construction support device is hoisted by a cantilever crane mounted on the flatbed truck.

[0020] Advantageous Effects of the Invention

[0021] The advantages of the urban rail side channel construction support device provided by the present invention include but are not limited to: compared with the prior art, the urban rail side channel construction support device provided by the present invention has a simple and feasible combined structure, is easy to install and disassemble, adopts a modular design, is small in size, is easy to install, and can effectively improve construction efficiency; each component can be processed and reused as a circulating material, saving construction materials; the support device can be hoisted by a small cantilever crane, which can greatly reduce labor intensity; an adjustable structure is adopted to facilitate adjustment of the state of the support device, facilitate transportation, and save labor costs; it does not need to rely on an external power supply when in use, and has high applicability. BRIEF DESCRIPTION OF THE DRAWINGS

[0022] Figure 1 It is a schematic structural diagram of a bypass channel support device in one embodiment.

[0023] Figure 2 It is a schematic structural diagram of an inner sliding sleeve assembly in one embodiment.

[0024] Figure 3a It is a schematic structural diagram of an outer sleeve assembly in one embodiment.

[0025] Figure 3b yes Figure 3a AA section view.

[0026] Figure 4 It is a schematic diagram of a transmission structure part in one implementation.

[0027] Figure 5 It is a construction schematic diagram in one implementation mode.

[0028] In the figure: 1-1. Inner sleeve assembly 1-2. First supporting screw 1-3. Outer sleeve assembly 1-4. Second supporting screw 1-5. Transmission assembly 2-1. Inner sleeve square tube 2-2. End plate 2-3. Long nut 2-4. Support hole 2-5. Nut baffle 2-6. Transmission nut 3-1. Outer sleeve square tube 3-2. Positioning plate 3-3. Lifting ring 3-4. Upper cover plate 3-5. Nut 3-6. Cover plate bolt 3-7. Retaining ring 3-8. Retaining ring bolt 3-9. Side strip plate 3-10. Screw positioning plate 3-11. Thrust bearing 3-12. Block 4-1. Screw 4-2. Second transmission bevel gear 4-3. First transmission bevel gear 4-4. Transmission shaft head 5-1. Shield tube wall 5-2. Bypass channel support device 5-3. Mainline track bed 5-4. Small cantilever crane 5-5. Rail car flatbed. DETAILED DESCRIPTION

[0029] The present invention is further described below in conjunction with the accompanying drawings, and the structure and principle of the device and method are very clear to people in the field. It should be understood that the specific embodiments described herein are only used to explain the present invention and are not used to limit the present invention.

[0030] See also Figure 1 The present embodiment provides a construction support device for a passageway beside an urban rail, which includes an inner sleeve assembly and an outer sleeve assembly, wherein the inner sleeve assembly is cooperatively connected with a first supporting screw, and the height of the inner sleeve assembly can be changed by rotating the first supporting screw, and the outer end of the inner sleeve assembly is provided with a supporting portion and the inner end of the inner sleeve assembly is cooperatively connected with a transmission screw; a cavity is provided in the outer sleeve assembly, and a transmission shaft head is connected to one side of the outer sleeve assembly, the outer end of the transmission shaft head is located outside the outer sleeve assembly to be connected to the driving mechanism, the inner end of the transmission shaft head is provided with a first transmission bevel gear located in the cavity of the outer sleeve assembly, and the upper side of the outer sleeve assembly is also symmetrically provided with a receiving groove for clamping the rail.

[0031] The two ends of the outer sleeve assembly are respectively sleeved on the outer sides of the inner ends of the two inner sleeve assemblies, and the ends of the transmission screws of the two inner sleeve assemblies close to the first transmission bevel gear are respectively provided with second transmission bevel gears meshing with the first transmission bevel gears.

[0032] Combination Figure 2, the inner sleeve assembly may include an inner sleeve square tube, an end plate, a long nut, a support hole, a nut baffle, and a transmission nut. Each support device has two sets of inner sleeve assemblies, which are respectively driven to extend and retract to both sides by a transmission screw on both sides of the outer sleeve assembly. An end plate is welded to the end of the inner sleeve square tube far from the outer sleeve assembly as a supporting part, and a nut baffle is welded to the end close to the outer sleeve assembly. An opening is provided on the nut baffle and a transmission nut is welded at the opening. The transmission nut is threadedly matched with the transmission screw to achieve a matching connection. At the same time, the upper and lower sides of the inner sleeve square tube are correspondingly provided with support holes, and a long nut is welded in the support hole. The long nut is threadedly matched with the first support screw to achieve a matching connection. In a preferred embodiment, the outer end face of the supporting part is an inclined surface or an arc surface so as to be supported on the shield tube wall, for example, an inclined surface that gradually tilts outward from bottom to top.

[0033] Combination Figure 3a and Figure 3b The outer sleeve assembly may include an outer sleeve square tube, a positioning plate, a lifting ring, an upper cover plate, a nut, a cover plate bolt, a retaining ring, a retaining ring positioning bolt, a side strip plate, a lead screw positioning plate, a thrust bearing, a stopper, etc. Two positioning plates are symmetrically welded on the upper side of the outer sleeve square tube, so that a symmetrical accommodating groove is formed on the upper side of the outer sleeve square tube to play the role of positioning the rail. A connecting hole is provided on the front or rear side of the middle part of the outer sleeve square tube for the transmission shaft head to extend into the outer sleeve square tube, and a retaining ring is provided at the connecting hole. The retaining ring is a semicircular structure for positioning the transmission shaft head. It is spliced ​​by two semicircular retaining rings and connected to the outside of the connecting hole by bolts. Two annular extension sections are provided at intervals at the inner end of the transmission shaft head. After the inner end extends into the outer sleeve square tube through the connecting hole, the two annular extension sections are respectively located on the inner and outer sides of the connecting hole. The retaining ring is connected to the outside of the connecting hole to limit the inner end of the transmission shaft head to the inner side of the retaining ring, and a rotating bearing can also be provided between the retaining ring and the transmission shaft head to further ensure the limiting of the rotating shaft head.

[0034] In a preferred embodiment, a lifting ring can be welded on the upper side of the outer tube square tube, and the lifting ring is a lifting device provided for easy handling. In addition, an opening is provided on the upper side of the middle part of the outer tube square tube, and an upper cover plate is detachably connected to the opening by bolts to facilitate the inspection of transmission component failures, and a side strip plate is welded inside the outer tube square tube to position the upper cover plate in the vertical position, and blocks welded on the outer tube square tube are provided on both sides of the opening, and the upper cover plate is detachably connected to the block by bolts, thereby realizing a detachable connection with the outer tube square tube; a lead screw positioning plate is also welded symmetrically in the middle part of the outer tube square tube, and a through hole is provided in the middle part of the lead screw positioning plate for the transmission lead screw to pass through, so as to play the role of positioning the transmission lead screw, and a thrust bearing can be provided between the transmission lead screw and the outer tube square tube to reduce lateral friction. In addition, the outer tube assembly can also be connected with a second support lead screw in the same way as the inner sleeve assembly, and the height of the outer tube assembly can be changed by rotating the second support lead screw, and the diameter of the second support lead screw can be smaller than the diameter of the first support lead screw.

[0035] Combination Figure 4 The transmission screw, the first transmission bevel gear, the second transmission bevel gear, and the transmission shaft head form a transmission assembly. The first transmission bevel gear is driven to rotate by rotating the transmission shaft head, and then the first transmission bevel gear drives the second transmission bevel gear to rotate. The second transmission bevel gear drives two transmission screws symmetrically arranged on the left and right to rotate. The transmission nut is installed at the inner end of the inner sleeve structure, and the inner sleeve assembly is driven to extend and retract to both ends by the rotation of the transmission screw. The first transmission bevel gear is a small gear, and the second transmission bevel gear is a large gear, so that a larger transmission ratio can be obtained.

[0036] In a preferred embodiment, the first support screw and the second support screw of the support device adopt trapezoidal threads, and the ends adopt an external hexagonal structure. The screw rod can be easily rotated by a wrench to adjust the height of the support device. The internal transmission structure is to facilitate the adjustment of the inner sleeves at both ends to extend and retract to both sides, which can save time for manual adjustment of the bracket, so the transmission screw also adopts an external hexagonal structure.

[0037] Combination Figure 5 As shown, this embodiment modularizes the support device, uses the existing construction vehicle as a transportation platform, and the cantilever is mounted on the transportation flatbed. The support device is safely and quickly delivered to the construction work surface by a small cantilever crane. The height of the support device reaches the reference elevation of the rail through the first support screw and the second support screw, and the rail is placed in the accommodating groove. The transmission shaft head is rotated to drive the inner sleeve assembly to extend to both sides. When the end plates on both sides are tightly fitted with the pipe wall, the support is completed.

[0038] Example 1: Construction steps of the bypass support device

[0039] 1. The support device is loaded on a rail flatbed car and transported to the construction site.

[0040] 2. The rails are laid out in place, one end of the rail is connected to the main line rail, and a track-lifting machine is used to temporarily support the middle.

[0041] 3. Use the cantilever crane mounted on the flatbed truck to lift the support device under the rail.

[0042] 4. Rotate the support device so that it intersects the rail vertically, so that the lower surface of the rail fits tightly inside the baffle.

[0043] 5. Insert the first support screw and the second support screw and lift the rail to the reference elevation.

[0044] 6. By rotating the transmission shaft head, the abutment portion at the outer end of the inner sleeve assembly is closely fitted to the pipe wall.

[0045] 7. Release the lifting ring of the jib crane and fix the rails.

[0046] 8. The rail car flatbed moves forward and enters the next support process

[0047] Example 2: Disassembly steps of bypass channel support device

[0048] 1. The rail flatbed truck equipped with a cantilever crane travels to the construction site and backs up from one end for dismantling.

[0049] 2. Install the lifting ring.

[0050] 3. Rotate the drive shaft head to retract the inner sleeve assembly into the outer sleeve assembly.

[0051] 4. Remove the first support screw and the second support screw.

[0052] 5. Lift the support device onto the flatbed truck.

[0053] 6. Move the flatbed truck and proceed to the next disassembly process.

Claims

1. A construction support device for a city rail side passage, characterized in that include: An inner sleeve assembly, wherein the inner sleeve assembly is connected with a first supporting screw, and the height of the inner sleeve assembly can be changed by rotating the first supporting screw, and an abutting portion is provided at the outer end of the inner sleeve assembly and a transmission screw is connected with the inner end of the inner sleeve assembly; and An outer sleeve assembly, wherein a cavity is provided in the outer sleeve assembly, and a transmission shaft head is connected to one side of the outer sleeve assembly, the outer end of the transmission shaft head is located outside the outer sleeve assembly to be connected to the driving mechanism, and the inner end of the transmission shaft head is provided with a first transmission bevel gear located in the cavity of the outer sleeve assembly, and the upper side of the outer sleeve assembly is also symmetrically provided with a receiving groove for clamping the rail; The two ends of the outer sleeve assembly are respectively sleeved on the outer sides of the inner ends of the two inner sleeve assemblies, and the ends of the transmission screws of the two inner sleeve assemblies close to the first transmission bevel gear are respectively provided with second transmission bevel gears meshing with the first transmission bevel gears.

2. The urban rail side passage construction support device according to claim 1, characterized in that The inner sleeve assembly comprises an inner sleeve square tube, an end plate is provided at one end of the inner sleeve square tube which is farther from the outer sleeve assembly to serve as a supporting portion, a nut baffle is provided at one end of the inner sleeve square tube which is closer to the outer sleeve assembly, a transmission nut is provided on the nut baffle, and the transmission nut is matched and connected with the transmission lead screw.

3. A construction support device for a city rail side passage as claimed in claim 2, characterized in that Support holes are correspondingly arranged on the upper and lower sides of the inner sliding sleeve square tube, and a long filament nut is arranged in the support hole, and the long filament nut is used for matching and connecting with the first supporting lead screw.

4. The urban rail side passage construction support device according to claim 1, characterized in that The outer end surface of the supporting portion is an inclined surface or an arc surface.

5. The urban rail side passage construction support device according to claim 1, characterized in that The outer sleeve assembly comprises an outer sleeve square tube, a connecting hole is provided at the front or rear side of the middle part of the outer sleeve square tube for the transmission shaft head to extend into the outer sleeve square tube, and a retaining ring is provided at the connecting hole to limit the inner end of the transmission shaft head to the inner side of the retaining ring.

6. The urban rail side passage construction support device according to claim 5, characterized in that An opening is arranged on the upper side of the middle part of the outer sleeve square tube, and an upper cover plate is detachably connected to the opening.

7. The urban rail side passage construction support device according to claim 5, characterized in that A screw positioning plate is symmetrically arranged in the middle of the outer sleeve square tube, a through hole is arranged in the middle of the screw positioning plate for the transmission screw to pass through, and a thrust bearing is arranged between the transmission screw and the outer sleeve square tube.

8. The urban rail side passage construction support device according to claim 1, characterized in that The outer sleeve assembly is connected with a second supporting screw, and the height of the outer sleeve assembly can be changed by rotating the second supporting screw.

9. A method for using the urban rail side passage construction support device as claimed in claim 8, characterized in that After the rails are laid in place, one end of the rails is connected to the main rails and a track-lifting machine is used to temporarily support the rails in the middle. At this time, the rails are supported by the urban trackside channel construction support device, including the following steps: Step a. Lift the support device below the rail and rotate the support device to make it intersect the rail vertically so that the bottom surface of the rail fits tightly in the receiving groove; Step b. Lifting the rail to the reference elevation through the first support screw and the second support screw; Step c. by rotating the transmission shaft head, the abutment portion at the outer end of the inner sleeve assembly is closely fitted to the pipe wall.

10. The method for using the urban rail side passage construction support device according to claim 9, characterized in that The construction support device is transported by a flatbed truck, and the construction support device is hoisted by a cantilever crane mounted on the flatbed truck.

Citation Information

Patent Citations

  • Gauge supporting rod for ballastless track construction

    CN104674616A

  • Subway track-laying by-pass temporary transition device and construction method thereof

    CN110055835A

  • Temporary sleeper for tunnel shield construction

    CN202881780U

  • Rail skeleton supporting frame for metro rail mounting

    CN204491336U

  • Urban rail bypass channel construction supporting device

    CN212128692U