Prefabricated board, manufacturing method, stacking method and construction method of prefabricated board
By setting concrete concrete components on prefabricated slabs to improve their strength, the problems of chaos and inefficiency on the construction site are solved, construction without the support of the lower bracket is achieved, and construction efficiency and seismic resistance of the overlapping floor slabs are improved.
Patent Information
- Application Number
- CN202010284449.0
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2020-04-10
- Publication Date
- 2024-11-12
- Estimated Expiration
- 2040-04-10
AI Technical Summary
During the construction process, existing prefabricated plates cause chaos on the construction site, inefficient construction efficiency and large formwork losses. It is necessary to build a full bracket under the prefabricated plate to support it, and the strength of the prefabricated plates is not enough to reduce the demand for the bracket.
Concrete components made of concrete materials are arranged on the prefabricated plate at parallel intervals, partly fixed in the plate body, and the other part protrudes from the upper surface, increasing the strength of the prefabricated plate so that the stressed edge can be placed on the load-bearing wall to support it. , omit the steps of building and dismantling the bracket below.
The strength of prefabricated plates is improved, the chaos and formwork losses at the construction site are reduced, the construction efficiency is improved, the steps of building and dismantling formwork and brackets are avoided, and the seismic resistance of the overlapping floor slabs is enhanced.
Smart Images

Figure CN111456318B_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the field of building technology, and in particular to a prefabricated board, a manufacturing method, a stacking method and a construction method of the prefabricated board. Background Art
[0002] Precast panels are the floor panels used in early 20th century buildings. They are modules or panels used in construction projects. They are called precast panels because they are produced and processed in prefabrication yards to form concrete prefabricated parts, and then transported to the construction site for installation.
[0003] When making prefabricated panels, first use wooden boards to nail a hollow model, distribute steel bars in the hollow part of the model, and then pour concrete. After the concrete solidifies, knock off the wooden boards, and what remains is the prefabricated panel. Prefabricated panels have many uses in construction, such as the cement panels covering the ditches beside the highway and the cement panels used as insulation layers on the roof.
[0004] In the process of force bearing and force transmission of precast panels, the ratio of the long side dimension to the short side dimension of the precast panels determines the force bearing condition of the precast panels, thus precast panels are divided into one-way panels and two-way panels. Among them, one-way panels refer to precast panels supported on both sides, that is, the load is mainly transmitted through the bending (and shearing) action in the length direction or width direction of the precast panels.
[0005] When manufacturing existing precast panels, the steel mesh layer is first set in the mold, and then one end of the truss bar is fixedly connected to the steel mesh layer, and then concrete is poured. The upper and lower surfaces of the concrete-cast steel mesh layer are formed to form a precast panel, wherein the part of the truss bar close to the steel mesh layer is located inside the precast panel, and the part of the truss bar away from the steel mesh layer is located outside the precast panel. During construction, the precast panels are supported by the load-bearing walls to splice the entire floor slab, and wooden molds are built around the spliced precast panels. Then, concrete is poured on the top surface of the precast panels to form a cast-in-place concrete layer. The cast-in-place concrete layer wraps the part of the truss bar located outside the precast panel. The truss bar is used to connect the precast panels and the cast-in-place layer to form a composite floor slab.
[0006] However, during the construction process, the above-mentioned precast panels are firstly spliced with the load-bearing walls as supports for the entire floor slabs, and then the cast-in-place concrete layer is poured on top of the precast panels. Since the load-bearing walls can only support the two ends of the precast panels, and there is no support in the middle of the precast panels, it is necessary to provide full support under the precast panels, that is, the formwork supports are densely arranged at certain intervals to support the precast panels, and then wooden formworks are built around the spliced precast panels, and concrete is poured in the wooden formworks as a whole to form a cast-in-place concrete layer. After the cast-in-place concrete layer reaches the required strength, the formwork supports are removed. The formwork and supports need to be built before construction, causing chaos on the construction site; and the formwork supports need to be removed after the construction is completed, resulting in low construction efficiency and high formwork consumption. Summary of the invention
[0007] The prefabricated board, the manufacturing method of the prefabricated board and the construction method provided in the embodiments of the present invention are used to solve the problems of chaotic construction site, low construction efficiency and large template consumption during the construction of existing prefabricated boards.
[0008] In order to achieve the above object, the embodiment of the present invention adopts the following scheme:
[0009] In the first aspect, an embodiment of the present invention provides a precast panel, which is a one-way panel, comprising: a precast panel body; a plurality of concrete components, each of which is a long strip structure, and the plurality of concrete components are arranged in parallel and at intervals on the precast panel body, the length direction of each concrete component is perpendicular or parallel to the length direction of the precast panel body, a part of the concrete component is fixed in the precast panel body, and another part of the concrete component protrudes from the upper surface of the precast panel body.
[0010] The concrete components in the precast panels provided in the embodiments of the present invention are made of concrete materials. Compared with the truss bars made of steel bar materials in the prior art, the strength of the concrete components is relatively high, so that the strength of the precast panels is improved. Therefore, at the subsequent construction site, it is only necessary to place the load-bearing edges of the above-mentioned precast panels (the two side edges on the precast panel body that are perpendicular to the length direction of the concrete components) on the load-bearing wall, thereby eliminating the need to set a mold bracket under the precast panel to support the precast panel, omitting the steps of building the formwork and the bracket, and dismantling the formwork and the bracket, thereby solving the problems of chaotic construction site, low construction efficiency, and high formwork consumption.
[0011] In some embodiments of the present invention, the concrete member is provided with an elongated hole, the opening direction of the elongated hole is perpendicular to the length direction of the concrete member, and the bottom surface of the elongated hole is flush with the upper surface of the precast board body.
[0012] In some embodiments of the present invention, the prefabricated panel further comprises a hanging member, a portion of which is located in the prefabricated panel body, and another portion of which extends to the outside of the upper surface of the prefabricated panel body.
[0013] In some embodiments of the present invention, it also includes: a steel mesh layer, which is arranged parallel to the upper surface of the precast panel body and located inside the precast panel body, and the concrete component is arranged on the steel mesh layer, wherein the hanging part includes: a fixing part, which is fixedly connected to the steel mesh layer; and a hanging part, which is fixedly connected to the fixing part, and a side of the hanging part away from the fixing part extends to the outside of the upper surface of the precast panel body.
[0014] In some embodiments of the present invention, a height H1 of the concrete component within the prefabricated panel body satisfies: (3 / 10)H≤H1≤(1 / 2)H, wherein H is the total height of the concrete component.
[0015] In some embodiments of the present invention, there are a plurality of the elongated holes, and the plurality of the elongated holes are arranged at intervals along the length direction of the concrete component.
[0016] In some embodiments of the present invention, if the length direction of the concrete component is parallel to the length direction of the precast panel body, the short side of the precast panel is the stress-bearing side, and the distance L between the central axes of two adjacent concrete components is jc The value range is: 200mm~500mm.
[0017] In some embodiments of the present invention, if the length direction of the concrete component is perpendicular to the length direction of the precast panel body, the long side of the precast panel is the force-bearing side, and the distance L between the central axes of two adjacent concrete components is jd The value range is: 200mm~600mm.
[0018] In some embodiments of the present invention, the plurality of concrete components include a plurality of first concrete components, and the distance L between the end of the first concrete component and the side of the precast plate close to the concrete component is d The value range is 100mm~300mm.
[0019] In some embodiments of the present invention, the plurality of concrete components further include a plurality of second concrete components, and one of the second concrete components is disposed between two adjacent first concrete components.
[0020] In the second aspect, an embodiment of the present invention further provides a method for manufacturing a precast panel, comprising placing a steel mesh layer in a hollow mold; fixing one side of a hanging member on the steel mesh layer, and placing a plurality of concrete components in parallel and at intervals on the steel mesh layer, with the length directions of the plurality of concrete components being parallel or perpendicular to the side panels of the hollow mold; pouring concrete in the hollow mold; and demolding the concrete after it solidifies to obtain the precast panel.
[0021] When the precast panels in the present invention are manufactured, concrete components are placed above the steel mesh layer, and the length directions of the multiple concrete components are parallel or perpendicular to the side panels of the hollow mold, that is, the length directions of the concrete components are perpendicular or parallel to the length directions of the precast panels manufactured by the hollow mold. Furthermore, the above-mentioned concrete components are made of concrete (concrete) materials, and since a part of the concrete components are located in the precast panels, the strength of the precast panels made by the concrete components is higher than that of the precast panels made by truss bars. At the subsequent construction site, it is only necessary to place the stress-bearing edges (the two side edges on the precast panels that are perpendicular to the length directions of the concrete components) of the precast panels manufactured by the above-mentioned manufacturing method on the load-bearing wall, and there is no need to support the mold and the bracket under the precast panels, thereby omitting the steps of building the template and the bracket, and dismantling the template and the bracket, thereby solving the problems of chaotic construction site, low construction efficiency, and large template consumption.
[0022] In a third aspect, an embodiment of the present invention further provides a method for stacking prefabricated panels, comprising the following steps: a plurality of prefabricated panels are placed vertically and stacked laterally on supporting shelves in sequence.
[0023] The prefabricated board stacking method provided in the embodiment of the present invention can avoid the problem of cracking that easily occurs when the prefabricated boards are stacked horizontally, and can save the area required for stacking the prefabricated boards by stacking the prefabricated boards vertically, thereby improving the utilization rate of the stacking site.
[0024] In a fourth aspect, an embodiment of the present invention further provides a method for constructing precast panels, comprising the following steps: placing two side edges of a plurality of precast panels that are perpendicular to the length direction of concrete components on the load-bearing walls of a building for splicing; building a fixed mold around the spliced plurality of precast panels; pouring concrete into the mold to form a cast-in-place concrete layer; and after the concrete solidifies, demolding to obtain a composite floor slab.
[0025] During the construction of the precast panels provided by the embodiment of the present invention, the precast panels are first hoisted and placed at the designated position of the load-bearing wall, and the two sides of the multiple precast panels perpendicular to the length direction of the concrete components are directly placed on the load-bearing wall of the building, and each floor slab is spliced, and wooden molds are built around the spliced precast panels. Since the precast panels with concrete components are of high strength, there is no need to provide full support under the precast panels, and concrete can be poured as a whole on the top surface of the spliced precast panels to form a cast-in-place concrete layer, thereby omitting the steps of building the formwork and the bracket, and removing the formwork and the bracket, thereby solving the problems of chaos on the construction site, low construction efficiency, and large formwork consumption. Finally, after the concrete solidifies, the composite floor slab can be obtained by demoulding.
[0026] In some embodiments of the present invention, before the step of pouring concrete into the mold, it also includes: placing a plurality of support negative reinforcements respectively on two precast panels overlapped and oppositely arranged on the same load-bearing wall, and each of the support negative reinforcements is located between two adjacent concrete components on the precast panel.
[0027] In some embodiments of the present invention, if there is a gap between adjacent prefabricated panels in the direction perpendicular to the load-bearing wall among the plurality of prefabricated panels that have been spliced, before the step of pouring concrete into the mold, it also includes: performing hanging mold construction on the gap between adjacent prefabricated panels in the direction perpendicular to the load-bearing wall. BRIEF DESCRIPTION OF THE DRAWINGS
[0028] Figure 1 is a three-dimensional structural diagram of a prefabricated panel in an embodiment of the present invention;
[0029] Figure 2 It is a structural schematic diagram of a concrete component in an embodiment of the present invention;
[0030] Figure 3 is a schematic structural diagram of a prefabricated panel in an embodiment of the present invention;
[0031] Figure 4 for Figure 3 Structural diagram of the AA section;
[0032] Figure 5 for Figure 4 Enlarged view of the middle P part;
[0033] Figure 6 for Figure 3 Structural diagram of the middle BB section;
[0034] Figure 7 for Figure 1 A top view of the precast panel in FIG.
[0035] Figure 8 for Figure 7 Structural diagram of the CC section;
[0036] Fig. 9 for Figure 7 Schematic diagram of the structure of the EE section;
[0037] Fig.10 for Figure 7 Schematic diagram of the structure of the FF section;
[0038] Fig.11 for Figure 7 Structural diagram of the middle DD section;
[0039] Fig.12 A structural schematic diagram of another placement method of a concrete structure in an embodiment of the present invention;
[0040] Fig.13 for Fig.12 Schematic diagram of the structure of the GG section;
[0041] Fig.14 for Fig.12 Schematic diagram of the structure of the HH section;
[0042] Fig.15 This is a schematic diagram of stacking prefabricated panels in an embodiment of the present invention;
[0043] Fig.16 This is a schematic diagram of transporting prefabricated panels in an embodiment of the present invention;
[0044] Fig.17 It is a schematic diagram of the hoisting of the prefabricated panels in the embodiment of the present invention;
[0045] Fig.18 It is a structural schematic diagram of a prefabricated plate provided with support negative reinforcement above the prefabricated plate in an embodiment of the present invention;
[0046] Fig.19 for Fig.18 Schematic diagram of the structure of the LL section;
[0047] Fig. 20 It is a schematic diagram of the structure of the negative reinforcement of the support in an embodiment of the present invention;
[0048] Fig.21 This is one of the structural schematic diagrams of the prefabricated panels after splicing in an embodiment of the present invention;
[0049] Fig. 22 This is the second structural schematic diagram of the prefabricated panels after splicing in an embodiment of the present invention.
[0050] Reference numerals:
[0051] 1-precast board body; 2-concrete component; 21-long hole; 22-first concrete component; 23-second concrete component; 3-hanging part; 31-fixing part; 32-hanging part; 33-bending part; 4-steel mesh layer; 5-L-shaped support shelf; 51-rib; 6-transport shelf; 7-support negative reinforcement; 110-cast-in-place concrete layer; 200-load-bearing wall. DETAILED DESCRIPTION
[0052] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0053] In the description of the present invention, it should be understood that the terms "center", "up", "down", "front", "back", "left", "right", "vertical", "horizontal", "top", "bottom", "inside", "outside", etc., indicating the orientation or position relationship are based on the orientation or position relationship shown in the drawings, and are only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as a limitation on the present invention.
[0054] The terms "first" and "second" are used for descriptive purposes only and should not be understood as indicating or implying relative importance or implicitly indicating the number of the indicated technical features. Thus, a feature defined as "first" or "second" may explicitly or implicitly include one or more of the features. In the description of the present invention, unless otherwise specified, "plurality" means two or more.
[0055] In the description of the present invention, it should be noted that, unless otherwise clearly specified and limited, the terms "installed", "connected", and "connected" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a direct connection, or an indirect connection through an intermediate medium, or it can be the internal communication of two components. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.
[0056] Reference Figure 1-2The precast panel provided in the embodiment of the present invention is a one-way panel, and the precast panel comprises: a precast panel body 1; a plurality of concrete components 2, the concrete components 2 are long strip structures, and the plurality of concrete components 2 are arranged in parallel and spaced relation on the precast panel body 1, and the length direction of each concrete component 2 is perpendicular or parallel to the length direction of the precast panel body 1, a part of the concrete component 2 is fixed in the precast panel body 1, and another part of the concrete component 2 protrudes from the upper surface of the precast panel body 1.
[0057] The concrete component 2 in the precast panel provided in the embodiment of the present invention is made of concrete material. Compared with the truss bars made of steel bar material in the prior art, the strength of the concrete component 2 is relatively high, so that the strength of the precast panel is improved. Therefore, at the subsequent construction site, it is only necessary to place the load-bearing edges of the above-mentioned precast panel (the two side edges on the precast panel body 1 that are perpendicular to the length direction of the concrete component 2) on the load-bearing wall, so there is no need to set a mold bracket under the precast panel to support the precast panel, and the steps of building the formwork and the bracket, and dismantling the formwork and the bracket are omitted, thereby solving the problems of chaos on the construction site, low construction efficiency, and high formwork consumption.
[0058] In some embodiments of the present invention, a long hole 21 is opened on the concrete member 2, and the opening direction of the long hole 21 is perpendicular to the length direction of the concrete member 2, and the bottom surface of the long hole 21 is flush with the upper surface of the prefabricated board body 1. Figure 1 and Figure 2 During the construction process, after the precast panels with the concrete components 2 are spliced, concrete is poured on the upper surface of the precast panels to form a cast-in-place concrete layer, which is connected to the precast panel body 1 through the concrete components 2. The long holes 21 opened on the concrete components 2 can increase the bite force between the cast-in-place concrete layer and the precast panel body 1, thereby improving the seismic performance of the composite floor slab made of the precast panels.
[0059] In some embodiments of the present invention, the above-mentioned prefabricated board further includes: a hanging member 3, a part of which is located in the prefabricated board body 1, and another part of which extends to the outside of the upper surface of the prefabricated board body 1. The other end of the hanging member 3 in the embodiment of the present invention extends to the outside of the upper surface of the prefabricated board body 1, or the other end of the hanging member 3 is extended to the outside of the side surface of the prefabricated board body 1. Compared with the latter solution, the connecting member in the former solution extends upward, and there is no need to open a corresponding avoidance portion in the mold for making the prefabricated board, which is convenient for the manufacture of the mold, and at the same time, it is convenient to remove the prefabricated board from the mold for making the prefabricated board through the hanging member 3 to achieve the demoulding effect.
[0060] In addition, when the prefabricated panels provided by the embodiment of the present invention are transported from a prefabrication plant to a construction site, the hanging member 3 can be used to hang the prefabricated panels on a sling, thereby facilitating the hoisting and transportation of the prefabricated panels.
[0061] In some embodiments of the present invention, the above-mentioned prefabricated panel further includes: a steel mesh layer 4, the steel mesh layer 4 is arranged parallel to the upper surface of the prefabricated panel body 1 and is located in the prefabricated panel body 1, and the concrete component 2 is arranged on the steel mesh layer 4, wherein the hanging member 3 includes: a fixing portion 31, the fixing portion 31 is fixedly connected to the steel mesh layer 4; a hanging portion 32, the hanging portion 32 is fixedly connected to the fixing portion 31, and the side of the hanging portion 32 away from the fixing portion 31 extends to the outside of the upper surface of the prefabricated panel body 1, such as Figure 1 , Figure 3 , Figure 4 and Figure 5 Compared with the solution of directly placing the hanging member 3 in the mold and fixing it in the precast panel body 1 through the solidification of concrete, the solution provided by the embodiment of the present invention fixes the fixing portion 31 on the hanging member 3 on the steel mesh layer 4, which can prevent the hanging member 3 from falling off during the hoisting process, making the connection between the hanging member 3 and the precast panel body 1 safer and more reliable.
[0062] Based on the above embodiment, the fixing portion 31 is arranged in parallel with the steel mesh layer 4, so that the concrete component 2 can be placed on the fixing portion 31 and the steel mesh layer 4 at the same time. Figure 5 shown.
[0063] The above-mentioned hanging part 3 is made of metal material, and the metal material is deformed by an external tool to form a roughly "L"-shaped hanging part 3. The arc transition between the above-mentioned fixing part 31 and the hanging part 32 further forms a bending part 33, which can prevent the hanging part 32 made of metal material from breaking at the bending part 33.
[0064] In some embodiments of the present invention, the height H1 of the concrete component 2 in the precast panel body 1 satisfies: (3 / 10)H≤H1≤(1 / 2)H, where H is the total height of the concrete component 2. Figure 5 If the height H1 of the concrete component 2 in the precast panel body 1 is less than (3 / 10)H, the depth of the concrete component 2 embedded in the precast panel body 1 is too shallow, which is not conducive to improving the strength of the precast panel; if the height H1 of the concrete component 2 in the precast panel body 1 is greater than (1 / 2)H, that is, the distance between the steel mesh layer 4 and the lower surface of the precast panel body 1 is too close, and the distance between the steel mesh layer 4 and the upper surface of the precast panel body 1 is too far, the force in the thickness direction of the precast panel body 1 is uneven, which is not conducive to ensuring the force performance of the precast panel.
[0065] In some embodiments of the present invention, the steel mesh layer 4 does not have reinforcement at the plate end of the prefabricated plate body 1. Figure 3 shown.
[0066] The reinforcement at the end of the prefabricated panels in the prior art makes the operation of the prefabricated panels complicated and time-consuming during the construction process. At the same time, due to the different sizes of the prefabricated panels, it is necessary to embed steel bars at different positions of the prefabricated panels according to the force requirements of the prefabricated panels, which results in the need to open holes on the mold at positions corresponding to the embedded steel bars of the prefabricated panels during the prefabrication process. The mold with holes can only be used to produce prefabricated panels of corresponding sizes, resulting in low mold reuse rate, increased mold cost, and long mold design and processing cycle. However, the present invention does not need to open avoidance holes on the mold to allow the steel bars to extend out of the prefabricated panel manufacturing mold, thereby reducing the mold manufacturing cost, as well as the mold design and manufacturing cycle, and increasing the mold reuse rate.
[0067] In some embodiments of the present invention, in order to further increase the bite force between the precast panel body 1 and the cast-in-place concrete layer, and thus increase the seismic performance of the composite floor slab made of the precast panels, so that the precast panels 100 after splicing can achieve the same effect as cast-in-place, there are multiple strip holes 21, and the multiple strip holes 21 are arranged at intervals along the length direction of the concrete member 2, such as Figure 2 shown.
[0068] Reference Figure 6 In some embodiments of the present invention, the distance L between the central axes of two adjacent long holes 21 is k equal, thereby making the stress conditions of various regions in the prefabricated panel 100 more uniform.
[0069] In some embodiments of the present invention, the distance L between the central axes of two adjacent long holes 21 is k The value range is: 400mm~800mm. If the distance between two adjacent long holes 21 is too large, it is not conducive to improving the seismic performance of the composite floor made of the above-mentioned prefabricated panels. If the distance between two adjacent long holes 21 is too large, a large number of molds are required during the production of the concrete component 2, and the production efficiency of the concrete component 2 is relatively low.
[0070] In some embodiments of the present invention, if the length direction of the concrete component 2 is parallel to the length direction of the precast panel body 1, the short side of the precast panel body 1 is the stress side, and the distance L between the central axes of two adjacent concrete components 2 is jc The value range is: 200mm~500mm. If the above spacing is set too small, the number of concrete components 2 is large, which leads to an increase in the weight of the precast panel, making it difficult to transport and hoist the precast panel. At the same time, if the above spacing is set too large, the stress performance of the precast panel and the appropriate strength of the precast panel cannot be guaranteed. Figure 7 to Figure 11 shown.
[0071] Similarly, if the length direction of the concrete component 2 is perpendicular to the length direction of the precast panel body 1, the long side of the precast panel 100 is the stress-bearing side, and the distance L between the central axes of two adjacent concrete components 2 is jd The value range is: 200mm~600mm, such as Fig.12 shown.
[0072] In some embodiments of the present invention, the plurality of concrete components 2 include a plurality of first concrete components 22, and the spacing L between the end of the first concrete component 22 and the side of the precast panel body 1 close to the concrete component 2 is d The value range is 100mm~300mm, such as Figure 7 and Fig. 9 As shown. Since there are manufacturing errors in the concrete component 2 and the precast panel body 1, if the lengths of the two are equal, the size of the concrete component 2 may be too large and cannot be placed in the precast panel production mold. Therefore, a suitable spacing L is made between the end of the concrete component 2 and the side of the precast panel near the end. d On the basis of ensuring that the concrete component 2 can be placed in the manufacturing mold of the precast panel, the stress-bearing performance of the precast panel can also be guaranteed.
[0073] In order to further enhance the strength of the prefabricated panel 100, the plurality of concrete components 2 further include a plurality of second concrete components 23, and a second concrete component 23 is provided between each of two adjacent first concrete components 22. Figure 7 shown.
[0074] In some embodiments of the present invention, the length L1 of the first concrete member 22 is: L1 = L-(2×L d ),like Fig. 9 As shown; the length L2 of the second concrete member 23 satisfies: (1 / 3)L≤L2≤(1 / 2)L, such as Fig.10 The length of the second concrete component 23 is shorter than that of the first concrete component 22. If the length of the second concrete component 23 is too short, it cannot play a role in strengthening the strength of the precast panel 100. If the length of the second concrete component 23 is too long, the weight of the precast panel will be too heavy during the precast stage, making it difficult to transport and hoist the precast panel.
[0075] Of course, the length of the second concrete component 23 may be equal to the length of the first concrete component 22 .
[0076] It should be noted that: refer to Figure 7 , Fig. 9 and Fig.10 If the short side of the prefabricated panel body 1 is placed on the load-bearing wall 200, the short side of the prefabricated panel body 1 will be the load-bearing side. Figure 12 to Figure 14If the long side of the precast panel body 1 is placed on the load-bearing wall 200, the long side of the precast panel body 1 is the load-bearing side. The length direction of the concrete component 2 is perpendicular to the load-bearing side of the precast panel body 1. The load-bearing wall 200 can also be a load-bearing beam.
[0077] The above-mentioned spacing will be described in detail below in conjunction with specific embodiments.
[0078] Reference Figure 7 and Fig.11 The length direction of the concrete component 2 in the embodiment of the present invention is parallel to the length direction of the precast panel body 1, that is, the short side of the precast panel body 1 is the force-bearing side, that is, the force-bearing direction of the precast panel body 1 is the length direction of the precast panel body 1 (i.e. Figure 7 The non-stress direction of the precast panel body 1 is the width direction of the precast panel body 1 (i.e. Figure 7 At this time, the distance L between two adjacent first concrete components 22 is jc1 is 500 mm, and a second concrete component 23 is provided in the middle position between two adjacent first concrete components 22. The spacing L between the first concrete component 22 and the second concrete component 23 adjacent to the first concrete component 22 is jc2 It is 250mm, that is, the distance between two adjacent concrete components 2 is 250mm.
[0079] Reference Fig.12 , the length direction of the concrete component 2 in the embodiment of the present invention is perpendicular to the length direction of the precast panel body 1, then the long side of the precast panel body 1 is the force-bearing side, that is, the force-bearing direction of the precast panel body 1 is the width direction of the precast panel body 1 (that is, Fig.12 The non-stress direction of the prefabricated panel body 1 is the length direction of the prefabricated panel body 1 (i.e. Fig.12 Since the span of the force-bearing side of the precast panel body 1 is short, the distance between two adjacent concrete components 2 can be set slightly farther, so that the distance L between two adjacent concrete components 2 is jd It is 600mm.
[0080] In some embodiments of the present invention, the side surfaces and the upper surface of the above-mentioned precast panel are rough surfaces, wherein the concave-convex depth of the rough surface is not less than 4 mm, thereby increasing the bite force between the precast panel body 1 and the cast-in-place concrete layer.
[0081] In some embodiments of the present invention, if the length direction of the concrete component 2 is consistent with the length direction of the precast panel body 1, the concrete component 2 is placed in the center along the length direction of the precast panel body 1, that is, the distance between the left end of the concrete component 2 and the left side of the precast panel body 1 is equal to the distance between the right end of the concrete component 2 and the right side of the precast panel body 1. Figure 7 and Fig. 9 shown.
[0082] Similarly, if the length direction of the concrete component 2 is consistent with the width direction of the precast panel body 1, the concrete component 2 is placed in the center along the width direction of the precast panel body 1, such as Fig.12 shown.
[0083] An embodiment of the present invention also provides a method for manufacturing a precast panel, comprising the following steps: placing a steel mesh layer in a hollow mold; fixing one side of a hanging piece on the steel mesh layer, and placing a plurality of concrete components in parallel and at intervals on the steel mesh layer, with the length directions of the plurality of concrete components being parallel or perpendicular to the side plates of the hollow mold; pouring concrete in the hollow mold; and after the concrete solidifies, demoulding to obtain a precast panel.
[0084] When the precast panels in the embodiments of the present invention are manufactured, concrete components are placed above the steel mesh layer, and the length directions of the multiple concrete components are parallel or perpendicular to the side panels of the hollow mold, that is, the length directions of the concrete components are perpendicular or parallel to the length directions of the precast panels manufactured by the hollow mold. Furthermore, the above-mentioned concrete components are made of concrete (concrete) materials, and since a part of the concrete components is located in the precast panels, the strength of the precast panels made by the concrete components is higher than that of the precast panels made by truss bars. At the subsequent construction site, it is only necessary to place the load-bearing edges of the precast panels made by the above-mentioned manufacturing method (the two side edges on the precast panel body that are perpendicular to the length directions of the concrete components) on the load-bearing wall, and there is no need to support the mold and the bracket under the precast panel, thereby omitting the steps of building the template and the bracket, and dismantling the template and the bracket, thereby solving the problems of chaotic construction site, low construction efficiency, and large template consumption.
[0085] The embodiment of the present invention further provides a method for stacking prefabricated panels, comprising the following steps: a plurality of prefabricated panels are placed vertically and stacked laterally on supporting shelves in sequence.
[0086] The method for stacking prefabricated panels provided in the embodiment of the present invention can avoid the problem of cracking that easily occurs when the prefabricated panels are stacked horizontally, and by stacking the prefabricated panels vertically, it can also save the area required for stacking the prefabricated panels, thereby improving the utilization rate of the stacking site.
[0087] Reference Fig.15 In the stacking process of the prefabricated panels 100 of the present invention, an L-shaped support shelf 5 for stacking the prefabricated panels 100 is first placed on a horizontal ground, the L-shaped support shelf 5 comprising ribs 51, the ribs 51 are arranged obliquely and are fixedly connected to two side portions of the L-shaped shelf, and then the lower surface of the prefabricated panels 100 is placed against a side of the L-shaped support shelf 5 away from the ribs 51, and the prefabricated panels 100 are stacked along the stacking direction (i.e. Fig.15The prefabricated panels 100 are stacked one by one in the direction indicated by the arrow in the middle (in the direction indicated by the arrow in the middle) to achieve vertical stacking of the prefabricated panels 100, thereby greatly saving the ground area occupied by the prefabricated panels 100 when stacked, and avoiding the problem of the prefabricated panels 100 being prone to cracking when stacked horizontally, and the above stacking method is easy to implement.
[0088] In order to make the stacking of the prefabricated panels 100 safer and more reliable, the height of the L-shaped support shelf 5 used to support one side of the prefabricated panels 100 is greater than half of the total height of the prefabricated panels 100 when placed vertically. Fig.15 The vertical distance between the top and bottom ends of the vertical portion of the L-shaped support shelf 5, the total height of the prefabricated panel 100 when placed vertically is the length of the long side of the prefabricated panel 100 when placed horizontally.
[0089] The present invention also provides a method for transporting prefabricated panels 100. Since the ends of the prefabricated panels 100 do not have ribs, the prefabricated panels 100 can be transported vertically. During the transportation of the prefabricated panels 100, a transport rack 6 for transporting the prefabricated panels 100 is first provided at the bottom of the truck, and then the prefabricated panels 100 are vertically placed in the transport rack 6 to achieve vertical transportation of the prefabricated panels 100, thereby avoiding the problem of the prefabricated panels 100 being prone to cracking when placed horizontally. In addition, since the prefabricated panels 100 cannot usually exceed six layers when placed horizontally, the transportation efficiency of the prefabricated panels 100 is low. If the prefabricated panels 100 are placed vertically, the area occupied by the prefabricated panels 100 at the bottom of the truck will be greatly reduced, so that the truck can load more prefabricated panels 100 at one time, thereby improving the transportation efficiency of the prefabricated panels 100. Fig.16 shown.
[0090] The present invention also provides a method for hoisting a prefabricated panel 100. In the embodiment of the present invention, there are multiple hanging members 3, and the multiple hanging members 3 are all arranged on the upper surface of the prefabricated panel body 1 and arranged close to the long side of the prefabricated panel 100. The above arrangement enables the prefabricated panel 100 to be hoisted by the long side during the hoisting process through the hoist 300, and the short side of the prefabricated panel 100 is suspended in the air, thereby realizing the vertical hoisting of the prefabricated panel, so that multiple prefabricated panels 100 can be hoisted at the same time, and there will be no collision between the multiple prefabricated panels 100, such as Figure 1 and Fig.17 shown.
[0091] Furthermore, in order to ensure that the force on the hanging parts 3 on the prefabricated board body 1 is relatively uniform during the lifting process of the prefabricated board 100, two hanging parts 3 are provided near the long side of the prefabricated board body 1, and the two hanging parts 3 are symmetrically distributed relative to the midline of the long side of the prefabricated board body 1.
[0092] The embodiment of the present invention also provides a construction method of a precast panel, comprising the following steps: placing two sides of a plurality of precast panels perpendicular to the length direction of the concrete component 2 on the load-bearing wall 200 of the building for splicing; building a fixed mold around the spliced plurality of precast panels; pouring concrete into the mold to form a cast-in-place concrete layer 110; after the concrete solidifies, demoulding, and obtaining a composite floor slab, such as Figures 18 to 20 shown.
[0093] In some embodiments of the present invention, the ratio between the thickness of the composite floor slab (i.e., the sum of the thickness of the precast panel 100 and the thickness of the cast-in-place concrete layer) and the span of the precast panel 100 (i.e., the length of the precast panel 100) is (1 / 30) to (1 / 35), so as to ensure that the precast panel 100 has better stress-bearing performance.
[0094] During the construction of the precast panels provided by the embodiment of the present invention, the precast panels are first hoisted and placed at the designated position of the load-bearing wall 200, and the two sides of the multiple precast panels 100 that are perpendicular to the length direction of the concrete component 2 are directly placed on the load-bearing wall 200 of the building, and each floor slab is spliced, and wooden molds are built around the spliced precast panels 100. Since the precast panels 100 provided with the concrete component 2 have a high strength, there is no need to fully support the bottom of the precast panels 100, and concrete can be poured as a whole on the top surface of the spliced precast panels 100 to form a cast-in-place concrete layer 110, thereby omitting the steps of building the formwork and the bracket, and removing the formwork and the bracket, thereby solving the problems of chaos at the construction site, low construction efficiency, and large formwork consumption. Finally, after the concrete solidifies, the demoulding is performed to obtain the composite floor slab.
[0095] In some embodiments of the present invention, before the step of pouring concrete into the mold, it also includes: placing multiple support negative reinforcements 7 on two precast panels 100 that are overlapped on the same load-bearing wall 200 and are arranged opposite to each other, and each support negative reinforcement 7 is located between two adjacent concrete components 2 on the precast panel 100. The support negative reinforcement 7 can connect the cast-in-place concrete layer 110 above the two precast panels 100 that are overlapped on the same load-bearing wall 200 and are arranged opposite to each other, so that the force on the cast-in-place concrete layer 110 is more uniform, thereby improving the force performance of the cast-in-place concrete layer 110, and thereby improving the force performance of the composite floor slab.
[0096] In some embodiments of the present invention, before the step of pouring concrete into the mold, it also includes: inserting the wire conduit into the long hole 21 of the concrete component 2 located above the precast panel body 1, and the long hole 21 is also conducive to the insertion of the wire conduit.
[0097] If the long sides of two adjacent prefabricated panel bodies 1 are fitted together, Fig.21For example, if the width of the house roof is 3.0 meters, and the width of the precast panel body 1 is 1.5 meters, two precast panel bodies 1 are laid on the house roof, and the long sides of the adjacent precast panel bodies 1 are attached to each other. At this time, a fixed mold is directly built around the spliced multiple precast panels 100; concrete is poured into the mold to form a cast-in-place concrete layer 110; after the concrete solidifies, the mold is removed to obtain the composite floor slab.
[0098] If there is a gap between the long sides of two adjacent prefabricated panel bodies 1 after splicing, such as Fig. 22 For example, if the width of the house roof is 3.2 meters, and the width of the precast panel body 1 is 1.5 meters, and two precast panel bodies 1 are laid on the house roof, there is a gap of 0.2 meters between the long sides of the adjacent precast panel bodies 1. At this time, the cast-in-place concrete layer 110 needs to be poured in the gap so that the long sides of the adjacent precast panel bodies 1 fit each other.
[0099] Therefore, if there is a gap between the sides of adjacent precast panels 100 in the spliced multiple precast panels 100 (that is, the precast panel bodies 1 mentioned above) in a direction perpendicular to the load-bearing wall 200, before the step of pouring concrete into the mold, it also includes: performing hanging mold construction on the gap between the sides of adjacent precast panels 100 in the multiple precast panels 100 in a direction perpendicular to the load-bearing wall 200. Since the amount of concrete pouring required at the above-mentioned gap is relatively small, hanging mold construction is adopted at the gap without setting a bracket under the gap, which is low in cost.
[0100] In some embodiments of the present invention, the above-mentioned steel mesh layer 4 and the support negative reinforcement 7 are both integral structures. Therefore, there is no need for reinforcement workers to tie the steel bars to form a steel mesh layer in the prefabrication plant and the construction site, thereby avoiding chaos in the prefabrication plant and the construction site, and at the same time improving the production efficiency of the prefabricated panel 100 and the production efficiency of the composite floor slab, thereby improving the construction efficiency of the house.
[0101] The above-mentioned steel mesh layer 4 and the support negative reinforcement 7 can be made into corresponding specifications by a steel bar manufacturer, and then transported to a prefabrication plant or a construction site for direct use.
[0102] In some embodiments of the present invention, the thickness of the steel mesh layer 4 and the support negative reinforcement 7 is greater than or equal to 15 mm to ensure the stress-bearing performance of the prefabricated panel 100 and the composite floor slab made of the prefabricated panel 100.
[0103] In the description of this specification, specific features, structures, materials or characteristics may be combined in an appropriate manner in any one or more embodiments or examples.
[0104] The above is only a specific embodiment of the present invention, but the protection scope of the present invention is not limited thereto. Any person skilled in the art can easily think of changes or substitutions within the technical scope disclosed by the present invention, which should be included in the protection scope of the present invention. Therefore, the protection scope of the present invention should be based on the protection scope of the claims.
Claims
1. A prefabricated panel, characterized in that: The prefabricated panel is a one-way panel, and the prefabricated panel comprises: Prefabricated panel body; A plurality of concrete components, each of which is a long strip structure, is arranged in parallel and at intervals on the precast panel body, the length direction of each concrete component is perpendicular or parallel to the length direction of the precast panel body, a part of the concrete component is fixed in the precast panel body, and another part of the concrete component protrudes from the upper surface of the precast panel body; The height H1 of the concrete component within the precast panel body satisfies: (3 / 10)H≤H1≤(1 / 2)H, where H is the total height of the concrete component; The plurality of concrete components include a plurality of first concrete components and a plurality of second concrete components. A second concrete component is provided between two adjacent first concrete components. The length L1 of the first concrete component is: L1 = L-(2×L d ), the length L2 of the second concrete component satisfies: (1 / 3)L≤L2≤(1 / 2)L, where L is the length of the precast panel body, L d L is the distance between the end of the first concrete component and the side of the precast panel body close to the first concrete component; d The value range is 100mm~300mm.
2. The prefabricated panel according to claim 1, characterized in that: The concrete component is provided with a long hole, the opening direction of the long hole is perpendicular to the length direction of the concrete component, and the bottom surface of the long hole is flush with the upper surface of the prefabricated board body.
3. The prefabricated panel according to claim 1 or 2, characterized in that: Also includes: A hanging member, a part of which is located in the prefabricated panel body, and another part of which extends to the outside of the upper surface of the prefabricated panel body.
4. The prefabricated panel according to claim 3, characterized in that: Also includes: A steel mesh layer, the steel mesh layer is arranged parallel to the upper surface of the precast panel body and is located in the precast panel body, the concrete component is arranged on the steel mesh layer, wherein the hanging member comprises: A fixing portion, the fixing portion being fixedly connected to the steel mesh layer; A hanging portion, wherein the hanging portion is fixedly connected to the fixing portion, and a side of the hanging portion away from the fixing portion extends to the outside of the upper surface of the prefabricated board body.
5. The prefabricated panel according to claim 4, characterized in that: The steel mesh layer has no reinforcement at the plate ends of the prefabricated plate body.
6. The prefabricated panel according to claim 2, characterized in that: There are a plurality of the elongated holes, and the plurality of the elongated holes are arranged at intervals along the length direction of the concrete component.
7. The prefabricated panel according to claim 1, characterized in that: If the length direction of the concrete component is parallel to the length direction of the precast panel body, the short side of the precast panel is the stress side, and the distance L between the central axes of two adjacent concrete components is jc The value range is: 200mm~500mm.
8. The prefabricated panel according to claim 1, characterized in that: If the length direction of the concrete component is perpendicular to the length direction of the precast panel body, the long side of the precast panel is the load-bearing side, and the distance L between the central axes of two adjacent concrete components is jd The value range is: 200mm~600mm.
9. A method for manufacturing a prefabricated panel according to any one of claims 1 to 8, characterized in that: The following steps are involved: Place the steel mesh layer in the hollow mold; Fixing one side of the hanging piece on the steel mesh layer, and placing a plurality of concrete components on the steel mesh layer in parallel and at intervals, with the length directions of the plurality of concrete components being parallel or perpendicular to the side plates of the hollow mold; pouring concrete into the hollow mold; After the concrete solidifies, the mold is removed to obtain the prefabricated board.
10. A method for stacking prefabricated panels according to any one of claims 1 to 8, characterized in that: The following steps are involved: Multiple prefabricated panels are placed vertically and stacked horizontally on the supporting shelves.
11. A construction method for a prefabricated panel according to any one of claims 1 to 8, characterized in that: The following steps are involved: Place two sides of the multiple prefabricated panels that are perpendicular to the length direction of the concrete components on the load-bearing walls of the building for splicing; Building a fixed mold around the assembled prefabricated panels; pouring concrete into the mold to form a cast-in-place concrete layer; After the concrete solidifies, demoulding is performed to obtain a composite floor slab.
12. The construction method of the prefabricated panel according to claim 11, characterized in that: Before the step of pouring concrete into the mold, the method further comprises: A plurality of support negative reinforcements are respectively placed on two prefabricated panels overlapped on the same load-bearing wall and arranged opposite to each other, and each of the support negative reinforcements is located between two adjacent concrete components on the prefabricated panel.
13. The construction method of prefabricated panels according to claim 11, characterized in that: If there is a gap between the sides of adjacent prefabricated panels in the direction perpendicular to the load-bearing wall, before the step of pouring concrete into the mold, the method further includes: A hanging formwork construction is performed on the gaps between the sides of the adjacent prefabricated panels in the direction perpendicular to the load-bearing wall.