One-time controlled blasting demolition method for elevator shaft outside dam body

The one-time controlled blasting method for elevator shafts addresses the inefficiencies and safety concerns of layered demolition by optimizing hole arrangement and detonation, achieving safe and efficient separation from the dam body.

CN111486759BActive Publication Date: 2024-12-03SINOHYDRO BUREAU 16 CO LTD
View PDF 5 Cites 0 Cited by

Patent Information

Application Number
CN202010440289.4
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2020-05-22
Publication Date
2024-12-03
Estimated Expiration
2040-05-22

AI Technical Summary

Technical Problem

The existing layered demolition method for elevator shafts outside a dam body is labor-intensive, time-consuming, and poses safety risks due to uncertain blasting impacts, leading to increased construction costs and delays, especially when dealing with reinforced concrete structures.

Method used

A one-time controlled blasting method for the elevator shaft, involving hole arrangement, charge calculation, and detonation network connection, using specific drilling and charging techniques to ensure efficient separation of the shaft from the dam body.

Benefits of technology

This method reduces manpower and material consumption, minimizes safety risks, and enhances efficiency by eliminating multiple drilling and cleaning steps, while ensuring controlled debris and shock wave management.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN111486759B_ABST
    Figure CN111486759B_ABST
Patent Text Reader

Abstract

A safe and efficient construction method for blasting and demolishing the elevator shaft outside the dam body, characterized by the one-time blasting and demolishing of the elevator shaft outside the dam body as a whole, and a blasting technology scheme consisting of hole layout technology, charging technology, and detonation network connection technology. Technical process: selection of blasthole diameter d → determination of drilling depth H1 → determination of single consumption K → initial determination of blasthole position → calculation of single hole charge Qn → determination of blockage length Ls → verification of row spacing between blastholes → blasthole charging → connection of detonation network. The present invention avoids multiple blasthole drilling operations, blasthole charging, and connection of blasting networks, thereby improving efficiency. Delay detonators are used as detonators in the holes, which can better utilize the kinetic energy generated by the blasting and achieve the best blasting effect. Drawing a blasting grid diagram can more accurately calculate the required amount of charge. Explosives are also arranged in the three outer walls, which is conducive to wall crushing and convenient for later slag removal and transportation.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the field of concrete blasting demolition, and is particularly suitable for controlled blasting demolition construction of an elevator shaft outside a dam body. Background Art

[0002] Demolition blasting technology is the main means of demolishing large buildings and plays an important role in social construction and economic development. Controlled demolition blasting technology refers to a blasting technology that uses certain technical means to control the flying debris, earthquake, air shock wave, smoke, noise and other public hazards caused by the explosion of explosives in the blasted object during the engineering blasting process. The requirements of controlled blasting are:

[0003] 1. Control the scope of blasting, destroy only the blasted parts, and keep the integrity of the rest of the parts;

[0004] 2. The direction of the building's collapse after blasting;

[0005] 3. Control the distance of flying debris generated during blasting;

[0006] 4. The intensity of air shock waves and noise.

[0007] During the demolition of a concrete gravity dam, the elevator shaft outside the dam body must be demolished first. The elevator shaft outside the dam body is higher than the ground and faces empty space on three sides. In addition, the concrete used in the elevator shaft is reinforced concrete with high strength. Currently, the elevator shaft outside the dam body is mostly demolished in layers, which has the following problems:

[0008] (1) It is necessary to carry out multiple blast hole drilling operations, blast hole charging and blast network connection and other construction processes. The more layers there are, the more manpower and material resources are consumed, the greater the safety risk, and it may cause delays in the construction period.

[0009] (2) After each layer of blasting is completed, the blasting surface needs to be cleaned before the next layer of blasting can be carried out. This adds the process of cleaning the blasting surface, which is time-consuming and labor-intensive, and increases the construction cost.

[0010] (3) The wall of the elevator shaft outside the dam body was built a long time ago and its strength cannot be controlled in advance. After the previous layer is demolished by blasting, the impact of the blasting shock on the next layer of concrete is uncertain, which is very likely to affect the integrity of the next layer of concrete, making it impossible to continue blasting the next layer. It has to be demolished by manual machinery, which will greatly increase the demolition time and the labor intensity of the workers. Summary of the invention

[0011] The purpose of the present invention is to overcome the defects of the existing layered demolition of the elevator shaft outside the dam body and to provide a safe and efficient one-time controlled blasting demolition method for the elevator shaft outside the dam body.

[0012] The technical solution adopted by the present invention is a one-time controlled blasting demolition method for the elevator shaft outside the dam body. The key point is that a one-time blasting demolition method is adopted for the entire elevator shaft outside the dam body, which is composed of three parts: a method for arranging holes and charging charges at the connection between the elevator shaft outside the dam body and the dam body; a method for arranging holes and charging charges on the wall of the elevator shaft outside the dam body; and a method for connecting the detonation network.

[0013] 1.1. Hole arrangement and charge charging method for the connection between the elevator shaft outside the dam body and the dam body:

[0014] 1.1.1 Selection of blasthole diameter: Use a drilling rig to drill vertical holes from top to bottom on the surface of the elevator shaft outside the dam body, with a hole diameter d of 75mm-100mm;

[0015] 1.1.2 Determination of drilling depth: The actual height of the elevator shaft outside the dam body is H (the distance from the dam surface to the bottom after the elevator room above the elevator shaft is mechanically dismantled). The blasthole is over-deep h. The blasthole drilling depth is determined to be H1=H+h. The blasthole is over-deep: h=(0.2-0.3)W, where W is the minimum resistance line;

[0016] 1.1.3 Determination of single hole consumption K: First determine the concrete strength grade and the corresponding rock type, then check the loosening charge K value corresponding to Table 2 "Unit Consumption K Value Table" in "Method for Determining Unit Consumption K Value at Blasting Site". The K value of the last row of blastholes should be 0.1kg / m greater than the K value of the previous row of blastholes. 3 -0.3kg / m 3 , in order to generate a greater blasting thrust than loosening blasting, and ultimately achieve the purpose of blasting separation of the elevator shaft and the dam body;

[0017] 1.1.4 Determine the position of blastholes: row spacing a, spacing b are initially determined: when the thickness D1 of the connection between the elevator shaft outside the dam body and the dam body is less than or equal to 1.5m, a single row of blastholes is arranged at the connection between the elevator shaft, and the distance between the center of the blasthole and the free side is row spacing a, a=(0.5-0.8)D1, the distance between the center of the blastholes on both sides and the free side on both sides is equal to row spacing a, after determining the two side holes, the blastholes in the middle are arranged at equal spacing b, b / a=1.0-1.3; when 1. When 5m<D1<3.5m, two rows of blastholes are arranged at the connection part of the blasthole elevator shaft. The distance between the center of the front row of blastholes and the free side is 1.2-1.5m, and the distance between the center of the blastholes on both sides and the free side is equal to the row distance a1. After the two side holes are determined, the blastholes in the middle are arranged at an equal interval b. When multiple rows of blastholes are arranged, b / a=1.5-2.0; the row distance a2 between the second row and the first row is 1.2-1.5m, and the second row is arranged in a vertical row with the first row;

[0018] 1.1.5 Calculation of single-hole charge Qn: Draw a blasting grid diagram. The blasting grid is a rectangle. The center line of a row of holes in a single-row blasthole is a straight side of the rectangle, and the center line of two adjacent holes is another straight side of the rectangle. The other two straight sides of the blastholes on both sides are the free surface, and the other two straight sides of the middle hole are the free surface and the center line of the other two adjacent holes. The grid diagram of the first row of holes in the double-row blastholes is the same as that of the single-row blastholes. The second row is in a straight line with the first row. The blasting grid is the same as the first row of holes with the center line of the second row and the first row being a straight side of the rectangle. The rectangular grid is the single-hole blasting volume V n The calculation basis of V n =S n *H, determine the single-hole blasting volume. In the actual construction process, the single-tube charge value is fixed, so calculate Q n When Q n / V n Close to K value, V n is the volume of the corresponding grid.

[0019] 1.1.6 Yellow mud is used as the blasthole plugging material. The plugging length is proportional to the blasthole diameter and inversely proportional to the unit consumption of explosives. Refer to the values ​​in Table 1 of "Calculation of blasthole plugging length" to loosen the blasthole plugging length L s The theoretical range is 1.5m-2.0m. If the calculated single hole charge length plus the plugging length is greater than H, the spacing a and b between blasting holes need to be reselected;

[0020] 1.2. Hole arrangement and charge method in the elevator shaft wall outside the dam body: The thickness of the elevator shaft wall is D2. If D2≤0.6m, no blast hole arrangement is considered. If 0.6m<D2≤2.5m, 1-2 blast holes are drilled in the center of the wall. If there are two blast holes, the two blast holes are distributed symmetrically with the center. The single hole blasting volume V n =D2 2 *H.

[0021] Calculate the charge Q per hole n When Q n / V n The maximum possible approach to K value; the drilling depth, drilling hole diameter, single consumption K value and plugging length are determined in the same way as above;

[0022] 1.3. Detonation network connection method: The detonation network uses a relatively economical and practical non-electric millisecond detonator detonation network, and the detonating cord is used for detonation. The detonating cord adopts a duplex connection (equivalent to a U-shaped connection). The method of connecting the detonation network is millisecond difference blasting between holes. One ms15-section detonator is installed at the bottom and top of the hole respectively (to prevent one of them from being damaged), with a delay of 880ms. The detonator leg line is led out and connected to the main line to the adjacent hole in the same section. The inter-hole mutual detonator uses ms2 section (both 2), with a delay of 25ms, and is detonated by a firing gun. The detonation order is: first detonate the explosives in the wall at the same time, and then detonate the explosives in the connection parts from right to left or from left to right. The blasting network connection is completed, and the maximum single-shot charge Q is calculated. n Must be less than Q S , Q S The maximum single-shot dose allowed.

[0023] The elevator shaft outside the dam body is rectangular, and the present invention divides it into two different blasting units: the connection between the elevator shaft outside the dam body and the dam body, and the wall of the elevator shaft outside the dam body (three sides). When the thickness of the elevator shaft wall is relatively thin, considering the drilling accuracy, the elevator shaft that is too high, and the possible perforation, etc., the present invention is only suitable for the demolition of elevator shafts with H≤20m. The present invention performs drilling, charging, and detonation at one time, and the time spent is short. There is no need to perform blast hole making operations and blasting surface cleaning multiple times, which is safe and efficient. The blasting force is spread out in all directions. At the connection between the elevator shaft outside the dam body and the dam body, the present invention calculates the single-hole charge Q n When calculating the charge Q per hole, the distance between the blast hole and the open side is used as the basis. When arranging holes in the elevator shaft wall outside the dam body, since the wall thickness is much smaller than the wall length, the charge Q per hole is calculated based on the distance between the blast hole and the open side. n The thickness of the wall is used as the basis.

[0024] Specific: Step 1.1.5 Single hole charge Q n The drawing of blasting grid diagram described in the calculation, when the thickness D1 of the connection between the elevator shaft outside the dam body and the dam body is less than or equal to 1.5m, a single row of blast holes is arranged at the connection between the elevator shaft, and the distance between the center of the blast hole and the free side is the row spacing a of (0.5-0.8)D1, and the distance between the center of the blast holes on both sides and the free sides is equal to the row spacing a. After the two side holes are determined, the blast holes in the middle are arranged at equal intervals b; when 1.5m<M<3.5m, two rows of blast holes are arranged at the connection between the blast hole elevator shaft, and the distance between the center of the front row of blast holes and the free side is the row spacing a1 of 1.2-1.5m, and the distance between the center of the blast holes on both sides and the free sides is equal to the row spacing a1. After the two side holes are determined, the blast holes in the middle are arranged at equal intervals b; the row spacing a2 between the second row and the first row is 1.2-1.5m, and the second row is distributed in a vertical row with the first row.

[0025] The blasthole diameter d of the present invention is 76 mm or 90 mm. From the perspective of blasting economic effect and charging construction, the larger the blasthole diameter, the more charging, the more single-hole blasting volume, the larger the blasthole diameter, the more convenient charging, and the less likely the hole is to be blocked. From the perspective of blasting effect, the smaller the blasthole diameter, the more evenly the explosive is distributed in the blasthole, and the better the blasting effect.

[0026] Determination of the unit consumption K: When there are multiple rows of blast holes at the connection between the elevator shaft outside the dam body and the dam body, the K value of the last row of blast holes should be 0.1kg / m greater than the K value of the previous row of blast holes. 3 -0.3kg / m 3 , in order to generate a greater blasting thrust than loosening blasting, and ultimately achieve the purpose of blasting separation of the elevator shaft and the dam body.

[0027] Blast hole tools: generally use hydraulic drill rigs or high air pressure drill rigs for drilling.

[0028] W is equal to the minimum value of the distance between the explosive and the free surface, that is, the minimum value of the hole spacing, row spacing and blockage.

[0029] The over-depth of the blasthole is calculated according to the empirical formula: h = (0.2-0.3)W, W is the minimum resistance line, and the coefficient for reinforced concrete takes a larger value, 0.3.

[0030] Hole arrangement and charge method in the wall of the elevator shaft outside the dam body: The wall of the elevator shaft is relatively thin, generally in the range of 0.6m-2.5m. If the wall thickness is less than 0.6m, it is not considered to arrange blastholes. Considering the impact of blasting debris on the surrounding buildings and the collision of the elevator shaft with the ground after falling, it is not necessary to loosen and blast the entire wall. Only 1 to 2 blastholes need to be arranged in the middle of each wall. The drilling depth, drilling diameter, single consumption K value and blocking length determine the connection between the elevator shaft outside the dam body and the dam body.

[0031] The advantages of the present invention are: it is a one-time blasting demolition of the entire elevator shaft outside the dam body, avoiding multiple blast hole making operations, blast hole charging and connecting blasting networks, and improving efficiency. There are usually newly built dams, factory buildings or other buildings behind the elevator shaft. The detonation sequence adopted by this technical solution is in the left and right direction rather than the front and back direction, which reduces the harm of blasting scattered objects. One ms15-section detonator is installed at the bottom and top of the hole, with a delay of 880ms. Two ms15-section detonators are installed to (prevent one of them from being damaged). The in-hole detonator uses ms2 sections (both 2), with a delay of 25ms, which can better utilize the kinetic energy generated by the blasting and achieve the best blasting effect. Drawing a blasting grid diagram can more accurately calculate the required amount of medicine. We also arranged explosives in the three outer walls. The blasting loosens the inside of the wall, and the elevator shaft will break into small pieces after falling, which is convenient for later slag removal and transportation. BRIEF DESCRIPTION OF THE DRAWINGS

[0032] Figure 1 This is the layout diagram of the blasting holes of the present invention.

[0033] Figure 2 The blasting charge structure diagram of the connection between the elevator shaft outside the dam body and the dam body

[0034] Figure 3 The structure diagram of the blasting charge inside the wall of the elevator shaft outside the dam body

[0035] Figure 4 The layout diagram of the blasting network for the elevator shaft outside the dam body

[0036] Among them: 1 the connection between the elevator shaft outside the dam body and the dam body, 2 the wall of the elevator shaft outside the dam body, 3 blast holes, 4 powder rolls, 5 detonating cords, 6 bamboo pieces, 7 detonating detonators, and 8 blocked blast holes. DETAILED DESCRIPTION

[0037] The present invention is described in detail below in conjunction with the drawings. The enumerated embodiments can enable those skilled in the art to better understand the present invention, but do not limit the present invention in any form.

[0038] Embodiment 1, as Figure 1 As shown, the size (in meters) of the elevator shaft outside the dam body is: the height is 16, the thickness of the connection part between the elevator shaft outside the dam body and the dam body is 2.28, the thickness of the three walls of the elevator shaft outside the dam body are 0.9, 1.5, and 1.5 respectively, and the size of the middle rectangular elevator shaft is: 5.05*6. To demolish it, the present invention performs a one-time blasting demolition of the elevator shaft outside the dam body as a whole, which is specifically composed of three parts: the hole arrangement and charging method of the connection part 1 between the elevator shaft outside the dam body and the dam body; the hole arrangement and charging method of the wall 2 of the elevator shaft outside the dam body; and the detonation network connection method:

[0039] 1.1. Hole arrangement and charge charging method for the connection between the elevator shaft outside the dam body and the dam body:

[0040] 1.1.1 Selection of blasthole diameter: Use a drilling rig to drill vertical holes from top to bottom on the surface of the elevator shaft outside the dam body, with a hole diameter d of 75mm-100mm. Select the size of the existing drill bit and use a hydraulic drilling rig to drill. The diameter d of the blasthole 3 of the present invention is selected to be 90mm;

[0041] 1.1.2 Drilling depth: The calculation formula for the blasthole drilling depth H1 is as follows:

[0042] H1=H+h (1)

[0043] Wherein H is the actual height of the elevator shaft outside the dam body, which generally refers to the distance from the dam surface to the bottom after the elevator room above the elevator shaft is dismantled mechanically. h is the over-depth of the blast hole, which is used to overcome the chassis resistance, make the blasted chassis relatively flat, and prevent the formation of the foundation. h = (0.2-0.3) W, and the coefficient for reinforced concrete is 0.3. W is equal to the minimum value of the distance from the explosive to the free surface, that is, the minimum value of the hole spacing, row spacing, and blockage. For Z-type holes, W = 0.45m-0.75m. In order to facilitate drilling operations, the h of Z-type holes in the present invention is uniformly taken as 0.1m, and that of T-type holes is W = 1.2m. In order to facilitate drilling operations, the h of T-type holes is taken as 0.3m.

[0044] 1.1.3 Determination of single hole charge consumption K: First determine the concrete strength grade and the corresponding rock type, then check the loosening charge K value corresponding to Table 2 "Unit charge consumption K value table" in "Method for determining unit charge consumption K value at blasting site" ("Method for determining unit charge consumption K value at blasting site" ("Highway" No. 10, 1965)). The strength grade of elevator shaft reinforced concrete is R28300D300, which is about Ⅸ for rock grade. The corresponding loosening charge K value in Table 2 "Unit charge consumption K value table" in "Method for determining unit charge consumption K value at blasting site" is 0.60kg / m 3 The left and right blasting effects are the best, and the unit charge consumption K of the T1 row of blast holes is 0.60kg / m 3 , the K value of T2 row blastholes should be 0.1kg / m greater than that of T1 row blastholes 3 -0.3kg / m 3 In order to generate a greater blasting thrust than loosening blasting and ultimately achieve the purpose of separating the elevator shaft from the dam body by blasting, the K value of the T2 row of blast holes is 0.8kg / m 3 ;

[0045] 1.1.4 When the thickness D1 of the connection between the elevator shaft outside the dam body and the dam body is less than or equal to 1.5m, a single row of blastholes is arranged at the connection between the elevator shaft, and the distance between the center of the blasthole and the side facing the sky is the row spacing a, a=(0.5-0.8)D1, and the distance between the center of the blastholes on both sides and the side facing the sky is equal to the row spacing a. After determining the two side holes, the blastholes in the middle are arranged at an equal spacing b, b / a=1.0-1.3; when 1.5m<D1<3.5m, two rows of blastholes are arranged at the connection between the blasthole elevator shaft, and the distance between the center of the front row of blastholes and the side facing the sky is a1 of 1.2-1. 5m, the distance between the center of the blastholes on both sides and the free sides on both sides is equal to the row spacing a1. After determining the two side holes, the blastholes in the middle are arranged at an equal spacing b. When multiple rows of blastholes are arranged, b / a=1.5-2.0; the row spacing a2 between the second row and the first row is 1.2-1.5m, and the second row is arranged in a vertical column with the first row; the thickness of D1 of the present invention is 2.28, the blasting holes are arranged in a rectangular form, and 2 rows are set. The blasting holes numbered T in the figure are the blasting holes at the connection between the elevator shaft outside the dam body and the dam body. The hole row spacing a is initially planned to be in the range of 1.1m-1.2m, with a total of 8 blasting holes. Since there are a large number of dowel bars at the connection between the elevator shaft outside the dam body and the dam body, the row spacing a is selected to be 1.2m, so that the second row of holes is located in the dam body, which is conducive to destroying the connecting steel bars and separating the elevator shaft from the dam body. Selection of row spacing: The overall width is 8.4 meters. The distance between the first holes on both sides, i.e. the 1st and 4th row holes in the figure and the empty edge is equal to the row spacing a, 1.2m. The remaining 2 blast holes are evenly distributed in the middle 6 meters, with a spacing b = 2m.

[0046] 1.1.5 Calculation of single-hole charge Qn: Draw a blasting grid diagram. The blasting grid is a rectangle. The center line of a row of holes in a single-row blasthole is a straight side of the rectangle, and the center line of two adjacent holes is another straight side of the rectangle. The other two straight sides of the blastholes on both sides are the free surface, and the other two straight sides of the middle hole are the free surface and the center line of the other two adjacent holes. The grid diagram of the first row of holes in the double-row blastholes is the same as that of the single-row blastholes. The second row is in a straight line with the first row. The blasting grid is the same as the first row of holes with the center line of the second row and the first row being a straight side of the rectangle. The rectangular grid is the single-hole blasting volume V n The calculation basis of V n =S n *H, calculate the single hole blasting volume Q n When Q n / V n Close to K value, V n is the volume of the corresponding grid. See Table 1 for specific data.

[0047] Hole arrangement and charge method in the elevator shaft wall 2 outside the dam body: The thickness of the elevator shaft wall is D2. If D2≤0.6m, no blast hole arrangement is considered. If 0.6m<D2≤2.5m, 1-2 blast holes are drilled in the center of the wall. If there are two blast holes, the two blast holes are distributed symmetrically with the center. The single hole blasting volume V n =D2 2 *H, calculate the single hole blasting volume Q n When Q n / V n The maximum possible approach to K value. The drilling depth, drilling diameter, unit consumption K value and plugging length are determined in the same way as above;

[0048] In this example, the thicknesses of the three walls of the elevator shaft outside the dam body are 0.9, 1.5, and 1.5 respectively. The size of the rectangular elevator shaft in the middle is: 5.05*6. The blasting holes numbered Z are the blasting holes in the walls of the elevator shaft. One to two blast holes are arranged in the middle of each wall, for a total of four.

[0049] like Figure 2 , 3 As shown in the figure, the charging structure diagram of the method scheme provided by the present invention. Since there are a large number of dowel bars at the connection between the elevator shaft outside the dam body and the dam body, the unit consumption of the blasting hole design of T2-1-4 row should be increased by 0.1kg / m3-0.3kg / m on the basis of T1-1-4 row. 3 In order to generate a greater blasting thrust than loosening blasting, the purpose of separating the elevator shaft from the dam body by blasting is finally achieved. The calculation formula for the charge amount of a single hole is as follows:

[0050] Explosive quantity per hole (kg) = K (kg / m 3 )*H(m)*V 单孔 (m 3 ) (2)

[0051] The blast hole charging conditions are shown in Table 1:

[0052] Table 1 Blasting hole charge situation

[0053] Hole No. Hole distance(m) Spacing(m) H(m) <![CDATA[Unit consumption (kg / m 3 )]]> Explosive quantity (kg) T1-1 1.2 2.2 16.0 0.60 25.5 T1-2 1.2 2.0 16.0 0.63 24.0 T1-3 1.2 2.0 16.0 0.63 24.0 T1-4 1.2 2.2 16.0 0.60 25.5 T2-1 1.2 2.2 16.0 0.78 33.0 T2-2 1.2 2.0 16.0 0.78 30.0 T2-3 1.2 2.0 16.0 0.78 30.0 T2-4 1.2 2.2 16.0 0.78 33.0 Z1-1 0.45 0.45 16.0 0.62 2 Z1-2 0.75 0.75 16.0 0.56 5 Z1-3 0.75 0.75 16.0 0.56 5 Z1-4 0.75 0.75 16.0 0.56 5

[0054] 1.1.6 Yellow mud is used as the blasthole plugging material. The plugging length is proportional to the blasthole diameter and inversely proportional to the unit consumption of explosives. Refer to "Calculation of blasthole plugging length" (Mining and Metallurgical Engineering, Vol. 19, No. 4, December 1999); the values ​​in Table 1 are loose blasthole plugging length L s The theoretical range is 1.5m-2.0m. If the calculated single hole charge length plus the plugging length is greater than H, the spacing a and b between blasting holes need to be reselected;

[0055] The explosives can be selected from φ60 (single tube explosive quantity 1.5kg, single tube length 46.5cm) and φ32 (single tube explosive quantity 0.2kg, single tube length 24.5cm) colloidal emulsion explosives 4, and uncoupled charge can reduce the initial explosion pressure, reduce the proportion of over-crushing and increase the throwing work. The blast hole at the connection between the elevator shaft and the dam body of the present invention is φ60. According to the maximum charge in the table above, the length of the explosive column is 22*0.465m=10.23m, plus the blocking length L s =2m is less than 16.0m, which meets the requirements. The blast holes on the three walls of the elevator shaft outside the dam body are made of φ32 colloidal emulsion explosives. They are all double-strand detonating cords 5, and the explosive rolls are tied with bamboo strips 6, with interval loading, and a ms15-section detonating detonator 7 is installed at the upper and lower parts of the blast holes. In order to make the explosives produce a good blasting effect, yellow mud is selected as the blocking material to block the blast holes, and the length Ls of the blast hole blocking 8 is 2m.

[0056] like Figure 4 As shown, the layout diagram of the detonation network in the method scheme provided by the present invention. The detonation network uses a relatively economical and practical non-electric millisecond detonator detonation network, and the detonating cord is detonated. The detonating cord adopts a duplex connection (equivalent to a U-shaped connection). The method of connecting the detonation network is millisecond difference blasting between holes. One ms15-section detonator is installed at the bottom and top of the hole respectively (to prevent one of them from being damaged), with a delay of 880ms. The detonator leg line is led out and connected to the main line to the adjacent hole in the same section. The inter-hole detonator uses ms2 section (both 2 pieces), with a delay of 25ms, and is detonated by a firing gun. The detonation sequence is: first detonate the explosives in the wall at the same time (after the firing gun is fired, Z1-1--Z1-4 detonate at the same time at 905ms), then detonate the explosives in the connection parts from right to left, and only detonate the explosives in two holes at the same time (T1-4 and T2-4 detonate at 930ms, T1-3 and T2-3 detonate at 955ms, T1-2 and T2-2 detonate at 980ms, and T1-1 and T2-1 detonate at 1005ms). The maximum single-shot charge Q1 of the detonation network is 63.0kg. The types of surrounding protected buildings include switch stations, factory buildings, hydropower stations and central control rooms, which are about 120m away from the blasting point. The minimum allowable vibration velocity is determined to be 0.5cm / s, and the maximum allowable single-shot charge Q is calculated. S =139kg, satisfying Q1<Q S .

Claims

1. A one-time controlled blasting demolition method for an elevator shaft outside a dam body, characterized in that a one-time blasting demolition method is adopted for the entire elevator shaft outside the dam body, which consists of three parts: a method for arranging holes and charging explosives at the connection between the elevator shaft outside the dam body and the dam body; a method for arranging holes and charging explosives on the wall of the elevator shaft outside the dam body; and a method for connecting the detonation network: 1.

1. Hole arrangement and charge charging method for the connection between the elevator shaft outside the dam body and the dam body: 1.1.1 Selection of blasthole diameter: Use a drilling rig to drill vertical holes from top to bottom on the surface of the elevator shaft outside the dam body, with a hole diameter d of 75mm-100mm; 1.1.2 Determination of drilling depth: The actual height of the elevator shaft outside the dam body is H, the distance from the dam surface to the bottom, the blasthole over-depth is h, and the blasthole drilling depth is determined to be H1=H+h, and the blasthole over-depth is: h=(0.2-0.3)W, W is the minimum resistance line; 1.1.3 Determination of single hole consumption K: First determine the concrete strength grade and the corresponding rock category, then check the loosening charge K value corresponding to Table 2 "Unit Consumption K Value Table" in "Method for Determining Unit Consumption K Value at Blasting Site". The K value of the last row of blastholes should be 0.1kg / m³-0.3kg / m³ greater than the K value of the previous row of blastholes, in order to generate a greater blasting thrust than loosening blasting, and ultimately achieve the purpose of separating the elevator shaft from the dam body by blasting; 1.1.4 Determine the location of the blastholes: row spacing a, spacing b is initially determined: when the thickness D1 of the connection between the elevator shaft outside the dam body and the dam body is less than or equal to 1.5m, a single row of blastholes is arranged at the connection between the elevator shaft, and the distance between the center of the blasthole and the open edge is row spacing a, a= (0.5-0.8 ) D1, the distance between the center of the blast holes on both sides and the free sides on both sides is equal to the row spacing a. After the two side holes are determined, the blast holes in the middle are arranged at an equal spacing b, b / a=1.0-1.3; when 1.5m<D1<3.5m, two rows of blast holes are arranged at the connection part of the blast hole elevator shaft, the distance between the center of the front row of blast holes and the free sides is a1 of 1.2-1.5m, the distance between the center of the blast holes on both sides and the free sides is equal to the row spacing a1, after the two side holes are determined, the blast holes in the middle are arranged at an equal spacing b, when multiple rows of blast holes are arranged, b / a=1.5-2.0; the row spacing a2 between the second row and the first row is 1.2-1.5m, and the second row is arranged in a vertical row with the first row; 1.1.5 Calculation of single-hole charge Qn: Draw a blasting grid diagram. The blasting grid is a rectangle. The center line of a row of holes in a single-row blasthole is a straight side of the rectangle, and the center line of two adjacent holes is another straight side of the rectangle. The other two straight sides of the blastholes on both sides are the free surface, and the other two straight sides of the middle hole are the free surface and the center line of the other two adjacent holes. The grid diagram of the first row of holes in the double-row blastholes is the same as that of the single-row blastholes. The second row is in a straight line with the first row. The blasting grid is the same as the first row of holes with the center line of the second row and the first row being a straight side of the rectangle. The rectangular grid is the single-hole blasting volume V n The calculation basis of V n =S n * H, determine the single-hole blasting volume. In the actual construction process, the single-tube charge value is fixed, so calculate Q n When Q n / V n Close to K value, V n is the volume of the corresponding grid; 1.1.6 Yellow mud is used as the blasthole plugging material. The plugging length is proportional to the blasthole diameter and inversely proportional to the unit consumption of explosives. Refer to the values ​​in Table 1 of "Calculation of blasthole plugging length" to loosen the blasthole plugging length L s The theoretical range is 1.5m-2.0m. If the calculated single hole charge length plus the plugging length is greater than H, the spacing a and b between blasting holes need to be reselected; 1.

2. Hole arrangement and charge method in the elevator shaft wall outside the dam body: The thickness of the elevator shaft wall is D2. If D2≤0.6m, no blast hole arrangement is considered. If 0.6m<D2≤2.5m, 1-2 blast holes are drilled in the center of the wall. If there are two blast holes, the two blast holes are distributed symmetrically with the center. The single hole blasting volume V n = D2 2 * H, calculate the charge Q per hole n When Q n / V n The maximum possible approach to K value; the drilling depth, drilling diameter, K value of single consumption and plugging length are determined in the same way as above; 1.

3. Detonation network connection method: The detonation network uses a relatively economical and practical non-electric millisecond detonator detonation network, and the detonating cord is detonated. The detonating cord adopts a duplex connection. The connection method of the detonation network is millisecond difference blasting between holes. One ms15-section detonator is installed at the bottom and top of the hole, with a delay of 880ms. The detonator foot line is led out and connected to the main line to the adjacent hole in the same section. The inter-hole direct detonator uses ms2 section, with a delay of 25ms. The detonation is initiated by a firing gun. The detonation sequence is: first detonate the explosives in the wall at the same time, and then detonate the explosives in the connection parts from right to left or from left to right. The blasting network connection is completed, and the maximum single-shot charge Q is calculated. n Must be less than Q S , Q S The maximum single-shot dose allowed.

2. The one-time controlled blasting demolition method for the elevator shaft outside the dam body according to claim 1 is characterized in that: Step 1.1.5 Single hole charge Q n The drawing of blasting grid diagram described in the calculation, when the thickness M of the connection between the elevator shaft outside the dam body and the dam body is less than or equal to 1.5m, a single row of blast holes is arranged at the connection between the elevator shaft, and the distance between the center of the blast hole and the free side is a row spacing a of 0.5-0.8M, and the distance between the center of the blast holes on both sides and the free side is equal to the row spacing a. After the two side holes are determined, the middle blast holes are arranged at equal intervals b; when 1.5m<M<3.5m, two rows of blast holes are arranged at the connection between the blast hole elevator shaft, and the distance between the center of the front row of blast holes and the free side is a row spacing a1 of 1.2-1.5m, and the distance between the center of the blast holes on both sides and the free side is equal to the row spacing a1. After the two side holes are determined, the middle blast holes are arranged at equal intervals b; the row spacing a2 between the second row and the first row is 1.2-1.5m, and the second row is distributed in a vertical row with the first row.

3. The one-time controlled blasting demolition method for the elevator shaft outside the dam body according to claim 1 is characterized in that: The bore diameter d is 76mm or 90mm.

4. The one-time controlled blasting demolition method for an elevator shaft outside a dam body according to claim 1 is characterized in that: When there are two rows of blast holes at the connection between the elevator shaft outside the dam body and the dam body, the K value of the last row of blast holes should be 0.1kg / m³-0.3kg / m greater than the K value of the front row of blast holes.

5. The one-time controlled blasting demolition method for the elevator shaft outside the dam body according to claim 1 is characterized in that: The drilling rig used is a hydraulic drilling rig or a high air pressure drilling rig.

6. The one-time controlled blasting demolition method for the elevator shaft outside the dam body according to claim 1 is characterized in that: W is equal to the minimum value of the distance from the explosive to the free surface, and is the minimum value of the hole spacing, row spacing and blocking length.

7. The one-time controlled blasting demolition method for the elevator shaft outside the dam body according to claim 1 is characterized in that: For reinforced concrete, the coefficient is 0.3, and the blasthole is too deep: h=0.3W.

Citation Information

Patent Citations

  • Initiation method of deep hole blasting for dismounting building

    CN101709939A

  • Building blasting demolition method

    CN110553560A

  • Urban deep foundation pit shallow layer loosening control blasting construction method

    CN111121575A

  • One-time blasting demolition device for elevator shaft outside dam body

    CN212227894U

  • Method of Explosive Demolition on the Buildings by useof Explosives

    KR1020020013618A