A photoelectric storage and charging integrated microgrid energy management system and method
Through the integrated microgrid energy management system of photo-storage and charging, the scheduling of energy storage units and public power grids is solved, and the problem of photovoltaic power generation changes and insufficient power supply at night is achieved, the stable operation of the microgrid and efficient utilization of resources are achieved, and the cost is reduced. , and extends the service life of the energy storage unit.
Patent Information
- Application Number
- CN202010473552.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2020-05-29
- Publication Date
- 2024-11-12
- Estimated Expiration
- 2040-05-29
AI Technical Summary
The dynamic changes in photovoltaic power generation in microgrids and the problems of energy instability and resource waste caused by nighttime inability to work increase the cost of use and difficult to manage challenges.
A integrated microgrid energy management system for optical storage and charging is designed, including power generation units, public grid units, energy storage units, load units and monitoring units. Through monitoring and scheduling, energy storage units are used to supplement insufficient power and upload interference. The power reaches the public grid and uses an emergency unit to provide power in the event of a failure.
It realizes the stable operation of the microgrid, improves the power utilization rate, reduces costs, and extends the service life of the energy storage unit, prevents faults and power outages.
Smart Images

Figure CN111525622B_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the field of microgrid technology, and in particular to a photovoltaic storage and charging integrated microgrid energy management system and method. Background Art
[0002] In recent years, microgrids have flourished due to their low construction cost, low operating loss, and no environmental pollution. Photovoltaic power generation is the most commonly used new energy source because of its convenient material acquisition and mature technology, and is widely used in microgrids. However, it is inevitable that environmental and time factors have a great impact on photovoltaic power generation. The amount of solar radiation is always changing dynamically, and the power of photovoltaic power generation also changes accordingly. At night, photovoltaic power generation cannot work properly due to lack of solar energy. To solve this problem, energy storage devices are often installed in microgrids, but this will increase the cost of using microgrids and make it difficult to manage and dispatch the energy in the entire microgrid, resulting in a waste of resources. Summary of the invention
[0003] The purpose of the present invention is to solve the problems existing in the above-mentioned prior art and to provide an integrated photovoltaic storage and charging microgrid energy management system and method, which can effectively ensure the stable operation of the entire microgrid, while improving the utilization rate of electric energy and reducing costs.
[0004] The objective of the present invention is achieved through the following technical solutions:
[0005] A photovoltaic storage and charging integrated microgrid energy management system, comprising:
[0006] The power generation unit generates electricity through solar photovoltaic and connects to the AC bus;
[0007] The public grid unit is used to connect the public grid to the microgrid for power supply, and to upload the excess power of the microgrid to the public grid;
[0008] An energy storage unit, used to store the electric energy generated by the power generation unit in the form of direct current;
[0009] A load unit, used to connect a load to the microgrid to consume electrical energy;
[0010] Supervisory control unit, used to monitor and control the devices in the microgrid.
[0011] The working principle of the present invention is as follows: the electric energy generated by the power generation unit is supplied to the microgrid. When the power generation unit is insufficient, the energy storage unit is used to compensate for the power supply. If the power supply of the energy storage unit is insufficient, the public power grid unit is used to supplement the power supply. When the power generation unit supplies excessive power, it is stored by the energy storage unit. When the energy storage unit is fully charged, the excess power is uploaded to the public power grid. The present invention has low requirements for the energy storage unit, so the cost of use is low. At the same time, it can reasonably use the public power grid for power dispatch, ensuring stable power supply of the microgrid while avoiding waste of power.
[0012] As a preferred embodiment of the present invention, the power generation unit includes a photovoltaic panel and a photovoltaic grid-connected inverter, and the photovoltaic panel is connected to the AC bus through the photovoltaic grid-connected inverter.
[0013] As a preferred embodiment of the present invention, the public grid unit includes a public grid and a distribution transformer, and the public grid is connected to the AC bus through the distribution transformer.
[0014] As a preferred embodiment of the present invention, the energy storage unit includes an energy storage inverter and an energy storage battery pack, and the energy storage battery pack is connected to the AC bus through the energy storage inverter.
[0015] As a preferred embodiment of the present invention, the load unit includes a DC load, a rectifier, an AC load and a transformer, the DC load is connected to the AC bus through the rectifier, and the AC load is connected to the AC bus through the transformer.
[0016] As a preferred embodiment of the present invention, the monitoring unit includes an acquisition control terminal and a human-computer interaction terminal, and the acquisition control terminal and the human-computer interaction terminal are connected to an AC bus through a switching power supply.
[0017] As a preferred embodiment of the present invention, the system further comprises:
[0018] Emergency unit, used to supply power in case of microgrid failure or power outage.
[0019] As a preferred embodiment of the present invention, the emergency unit includes a generator, a transformer, a super capacitor and a rectifier, the generator is connected to the AC bus through the transformer, the super capacitor is connected to the AC bus through the rectifier, and the super capacitor is connected to the generator.
[0020] As a preferred embodiment of the present invention, circuit breakers are provided between the power generation unit, the public grid unit, the energy storage unit, the load unit, the monitoring unit, the emergency unit and the AC bus, and the circuit breakers are connected to the monitoring unit.
[0021] The present invention also provides a method for managing energy in a microgrid with integrated photovoltaic storage and charging, using the above-mentioned microgrid energy management system with integrated photovoltaic storage and charging, the method comprising the following steps:
[0022] Step S1, the power generation unit generates electric energy to supply the load unit. If the power generation is excessive, it is determined whether the energy storage unit is full. If the energy storage unit is not full, step S2.1 is executed. If the energy storage unit is full, step S2.2 is executed. If the power generation cannot meet the consumption of the load unit, the power shortage of the load unit is calculated, and it is determined whether the current time is a peak period or an underestimated time. If it is a peak period, step S3.1 is executed. If it is an underestimated period, step S3.2 is executed.
[0023] Step S2.1, supplying the excess power of the power generation unit to the energy storage unit for charging and storage;
[0024] Step S2.2, uploading the excess power of the power generation unit to the public grid unit;
[0025] Step S3.1, determine whether the power shortage of the load unit is greater than the maximum output power of the energy storage unit. If so, execute step S3.2. If not, enable the energy storage unit to discharge to compensate for the power shortage of the load unit.
[0026] Step S3.2, connecting the public grid unit to the microgrid to compensate for the power shortage of the load unit, and determining whether the current discharge depth of the energy storage unit is less than the maximum discharge depth of the energy storage unit set by the system, if so, executing step S4;
[0027] Step S4: the public grid unit supplies power to the microgrid and charges the energy storage unit.
[0028] The advantages of the present invention are:
[0029] 1. Through reasonable power dispatching, the stable operation of the entire microgrid is effectively guaranteed, while the utilization rate of power is improved and the cost is reduced.
[0030] 2. Through reasonable and efficient energy management methods, the number of charge and discharge times of the energy storage unit is reduced, its service life is extended, and the economic benefits are improved.
[0031] 3. The setting of emergency unit can effectively prevent sudden failures or power outages to ensure the smooth operation of the microgrid. BRIEF DESCRIPTION OF THE DRAWINGS
[0032] Figure 1 This is a structural principle diagram of a photovoltaic storage and charging integrated microgrid energy management system of the present invention;
[0033] Figure 2 A communication bus topology diagram of a photovoltaic storage and charging integrated microgrid energy management system of the present invention;
[0034] Figure 3 The present invention is a flow chart of a method for energy management of a photovoltaic, storage and charging integrated microgrid. DETAILED DESCRIPTION
[0035] The present invention will be further described in detail below in conjunction with the accompanying drawings and specific implementation methods.
[0036] like Figure 1 As shown, a photovoltaic storage and charging integrated microgrid energy management system includes a power generation unit, a public grid unit, an emergency unit, an energy storage unit, a load unit, and a monitoring unit, each of which is connected to the AC bus through a circuit breaker.
[0037] The power generation unit includes a photovoltaic panel for converting solar energy into electrical energy and a photovoltaic grid-connected inverter for converting direct current into alternating current. The photovoltaic panel is connected to the AC bus through the photovoltaic grid-connected inverter and the circuit breaker. The power generation unit continuously transmits electrical energy to the entire microgrid.
[0038] The public grid unit includes a 10kV grid and a distribution transformer. The 10kV grid is connected to the AC busbar through a distribution transformer and a circuit breaker. When the power generation unit is not enough to support the power consumption of the microgrid during the off-peak period, or when the power generation unit and the energy storage unit are not enough to support the power consumption of the microgrid during the peak period, the public grid unit is connected to the microgrid to transmit electricity to the entire microgrid to compensate for the lack of power in the microgrid. If the power generation unit generates too much electricity and the energy storage unit is full, the excess electricity in the microgrid will be uploaded to the public grid unit.
[0039] The emergency unit includes a diesel generator, a transformer, a supercapacitor and a rectifier. The diesel generator is connected to the AC bus through a transformer and a circuit breaker, the supercapacitor is connected to the AC bus through a rectifier and a circuit breaker, and the supercapacitor is connected to the diesel generator. In the event of a microgrid failure or power outage, the microgrid needs a diesel generator to generate electricity. However, the diesel generator also needs a starting power supply to support it from starting to having full load capacity, which takes a long time. Most diesel generators use built-in batteries as starting power supplies. This traditional starting method will not only cause the built-in battery to be deeply discharged, seriously affecting the service life of the built-in battery, but also under low temperature conditions, it is difficult to start successfully due to the rapid decrease in the capacity of the built-in battery. By utilizing the fast discharge characteristics of supercapacitors, instantaneous starting power and starting torque are provided to meet the peak power requirements of diesel generators, which can not only effectively shorten the starting time of diesel generators, but also easily start diesel generators under low temperature conditions. Due to the natural consumption of supercapacitors, it is necessary to regularly charge and discharge the supercapacitors through rectifiers and circuit breakers to extend the service life of supercapacitors.
[0040] The energy storage unit includes an energy storage inverter and an energy storage battery pack. The energy storage battery pack is connected to the AC bus through the energy storage inverter and the circuit breaker. When the energy storage unit is charging, the energy storage inverter rectifies the AC power in the AC bus and stores the electric energy in the energy storage battery pack in the form of DC power. When the energy storage unit is discharging, the energy storage inverter first inverts the DC power released by the energy storage battery pack into AC power and then transmits it to the AC bus. The energy storage unit can effectively ensure the stable operation of the microgrid at all times and all weather, and has better economic benefits.
[0041] The load unit includes a transformer, an AC load, a rectifier, and a DC load. The AC load is connected to the AC bus through a transformer and a circuit breaker, and the DC load is connected to the AC bus through a rectifier and a circuit breaker. The load unit is used to consume electrical energy. The AC load can be a collection of multiple parallel AC loads, not just one AC load. The DC load can also be a collection of multiple parallel DC loads, not just one DC load.
[0042] The monitoring unit includes a switching power supply, a data acquisition control terminal and a human-computer interaction terminal. The data acquisition control terminal and the human-computer interaction terminal are connected to the AC bus through a switching power supply and a circuit breaker. Figure 2 As shown in the figure, the human-machine interaction terminal communicates with the acquisition control terminal through industrial Ethernet. The communication bus of the system is established by building a topological structure and using TCP / IP, MOUBUS, serial port and IEC104 communication methods. The devices in each unit transmit data to the monitoring unit via the communication bus, and the control instructions are sent from the monitoring unit to the corresponding device via the communication bus, thereby realizing system energy management and ensuring the real-time performance of the system. The main monitoring data include: the power generation power, voltage, and current of the photovoltaic panel, the voltage, battery temperature, battery SOC, and SOH of the supercapacitor battery, the power consumption of the AC load, the power consumption of the DC load, the alarm parameters of the energy storage inverter, the battery voltage, battery temperature, battery SOC, and SOH of the energy storage battery group, and the opening and closing status of each circuit breaker. The monitoring unit displays all data intuitively on the human-machine interaction terminal to facilitate the staff to operate.
[0043] like Figure 3 As shown, the present invention also provides a method for managing energy in a microgrid with integrated photovoltaic storage and charging, using the above-mentioned integrated photovoltaic storage and charging microgrid energy management system, the method comprising the following steps:
[0044] Step S1, the power generation unit generates electric energy to supply the load unit. If the power generation is excessive, it is determined whether the energy storage unit is full. If the energy storage unit is not full, step S2.1 is executed. If the energy storage unit is full, step S2.2 is executed. If the power generation cannot meet the consumption of the load unit, the power shortage of the load unit is calculated, and it is determined whether the current time is a peak period or an underestimated time. If it is a peak period, step S3.1 is executed. If it is an underestimated period, step S3.2 is executed.
[0045] Step S2.1, supplying the excess power of the power generation unit to the energy storage unit for charging and storage;
[0046] Step S2.2, uploading the excess power of the power generation unit to the public grid unit;
[0047] Step S3.1, determine whether the power shortage of the load unit is greater than the maximum output power of the energy storage unit. If so, execute step S3.2. If not, enable the energy storage unit to discharge to compensate for the power shortage of the load unit.
[0048] Step S3.2, connecting the public grid unit to the microgrid to compensate for the power shortage of the load unit, and determining whether the current discharge depth of the energy storage unit is less than the maximum discharge depth of the energy storage unit set by the system, if so, executing step S4;
[0049] Step S4: the public grid unit supplies power to the microgrid and charges the energy storage unit.
[0050] The method reduces the number of charge and discharge times of the energy storage unit through reasonable scheduling of electric energy, prolongs its service life, and improves economic benefits.
[0051] The above is only a preferred specific embodiment of the present invention, which is an implementation method based on the overall concept of the present invention, and the protection scope of the present invention is not limited thereto. Any changes or substitutions that can be easily thought of by a person skilled in the art within the technical scope disclosed by the present invention should be included in the protection scope of the present invention. Therefore, the protection scope of the present invention should be based on the protection scope of the claims.
Claims
1. A photovoltaic storage and charging integrated microgrid energy management system, characterized in that: include: The power generation unit generates electricity through solar photovoltaic and connects to the AC bus; The public grid unit is used to connect the public grid to the microgrid for power supply, and to upload the excess power of the microgrid to the public grid; An energy storage unit, used to store the electric energy generated by the power generation unit in the form of direct current; A load unit, used to connect a load to the microgrid to consume electrical energy; A monitoring unit for monitoring and controlling the devices in the microgrid; The emergency unit is used to supply power in the event of a microgrid failure or power outage. The emergency unit includes a generator, a transformer, a supercapacitor and a rectifier. The generator is connected to the AC bus through a transformer, the supercapacitor is connected to the AC bus through a rectifier, and the supercapacitor is connected to the generator. The supercapacitor provides instantaneous starting power for the generator, and the supercapacitor is charged and discharged through a rectifier and a circuit breaker for maintenance.
2. According to claim 1, a photovoltaic storage and charging integrated microgrid energy management system is characterized in that: The power generation unit comprises a photovoltaic panel and a photovoltaic grid-connected inverter, and the photovoltaic panel is connected to an AC busbar through the photovoltaic grid-connected inverter.
3. The photovoltaic storage and charging integrated microgrid energy management system according to claim 1 is characterized in that: The public grid unit includes a public grid and a distribution transformer, and the public grid is connected to an AC busbar through the distribution transformer.
4. The photovoltaic storage and charging integrated microgrid energy management system according to claim 1 is characterized in that: The energy storage unit includes an energy storage converter and an energy storage battery pack, and the energy storage battery pack is connected to the AC bus through the energy storage converter.
5. The photovoltaic storage and charging integrated microgrid energy management system according to claim 1 is characterized in that: The load unit includes a DC load, a rectifier, an AC load and a transformer. The DC load is connected to the AC bus through the rectifier, and the AC load is connected to the AC bus through the transformer.
6. The photovoltaic storage and charging integrated microgrid energy management system according to claim 1 is characterized in that: The monitoring unit comprises an acquisition control terminal and a human-computer interaction terminal, and the acquisition control terminal and the human-computer interaction terminal are connected to an AC bus through a switching power supply.
7. The photovoltaic storage and charging integrated microgrid energy management system according to claim 1 is characterized in that: Circuit breakers are provided between the power generation unit, the public grid unit, the energy storage unit, the load unit, the monitoring unit, the emergency unit and the AC bus, and the circuit breakers are connected to the monitoring unit.
8. A method for energy management of a photovoltaic, storage and charging integrated microgrid, using a photovoltaic, storage and charging integrated microgrid energy management system as claimed in claim 1, characterized in that: The method comprises the following steps: Step S1, the power generation unit generates electric energy to supply the load unit. If the power generation is excessive, it is determined whether the energy storage unit is full. If the energy storage unit is not full, step S2.1 is executed. If the energy storage unit is full, step S2.2 is executed. If the power generation cannot meet the consumption of the load unit, the power shortage of the load unit is calculated, and it is determined whether the current time is a peak period or an underestimated time. If it is a peak period, step S3.1 is executed. If it is an underestimated period, step S3.2 is executed. Step S2.1, supplying the excess power of the power generation unit to the energy storage unit for charging and storage; Step S2.2, uploading the excess power of the power generation unit to the public grid unit; Step S3.1, determine whether the power shortage of the load unit is greater than the maximum output power of the energy storage unit. If so, execute step S3.
2. If not, enable the energy storage unit to discharge to compensate for the power shortage of the load unit. Step S3.2, connecting the public grid unit to the microgrid to compensate for the power shortage of the load unit, and determining whether the current discharge depth of the energy storage unit is less than the maximum discharge depth of the energy storage unit set by the system, if so, executing step S4; Step S4: the public grid unit supplies power to the microgrid and charges the energy storage unit.