A high-speed deep mixing drilling rig and construction method thereof
By adding an annular cross-section and a constant pressure valve on the drill pipe, the problem of insufficient resistance to torsion and bending ability of the drill pipe in the prior art is solved, and the drilling depth is increased without increasing the drilling rig tower, and the Drilling capacity and working life of drilling rigs in a variety of soil and rock formations.
Patent Information
- Application Number
- CN202010598100.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2020-06-28
- Publication Date
- 2024-11-26
- Estimated Expiration
- 2040-06-28
AI Technical Summary
The existing multi-section telescopic drill rods are insufficient torsion and bending resistance when drilling, resulting in unstable transmission torque and axial forces, and low drilling efficiency when encountering hard rock layers, and the drill rods are easily soaked in mud and water, resulting in The short mechanical life increases construction costs.
A high-speed deep-stage mixing drill rig is designed, with the drill pipe having an annular cross-section. The internal pressure of the drill pipe is maintained by setting a constant pressure valve and exhaust valve, and the transmission of torque and axial force capacity is enhanced, and the drilling rig tower is not increased. Increase drilling depth in the case.
It effectively improves the strength and stiffness of the drill pipe, ensures stable drilling capacity in a variety of soil and rock layers, extends the working life of the drilling rig, and reduces the cost of steel use and movement.
Smart Images

Figure CN111577131B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the field of pile foundation construction equipment, and in particular to a high-speed deep mixing drill and a construction method thereof. Background Art
[0002] Cast-in-place piles are low in noise and highly adaptable, and are widely used. However, the excavation of pile bodies is difficult, and in the past, they have always been done manually, especially in places with limited construction space, such as tunnels and underground spaces of subway stations. These places cannot use tall machinery, and can only be excavated manually with simple machinery. Manual excavation accidents occur frequently, and excavation becomes more difficult when dynamic water intrudes into the pile body. Manual excavation is facing elimination and prohibition. When constructing on the ground, the depth of the hole to be drilled must be determined by the height of the drilling rig tower. Usually, the depth of the drilling hole is more than 20 meters, and the deepest is even more than 30 meters. This requires the configuration of a drilling rig tower of corresponding height. The increase in the height of the drilling rig tower not only wastes a lot of steel and increases costs, but also makes the long screw pile-driving drilling rig bulky, and the cost of moving it also increases.
[0003] The vertical pile driver that has been widely used in recent years can operate in the low space of subway tunnels. The key technology is that it is equipped with a retractable drill rod, which automatically extends downward with the depth of excavation. Driven by the power head, the multi-section retractable drill rod drives the rotary bucket or short spiral drill bit to work. The drill rod is pressurized by the pressurized cylinder, and the main winch lifts and lowers the drill rod through the wire rope. Therefore, the drill rod is required to transmit both torque and axial force, and the length is adjustable. The quality of its performance directly affects the quality of the hole and the drilling ability, and affects the performance of the whole machine.
[0004] The existing multi-section telescopic drill rods are square steel pipes, and the drilling is performed by pressurizing the friction force. The bending and torsion resistance are both small, so the ability to transmit torque and axial force is also small. The axial force during drilling is transmitted through the friction between the drill rods, so the transmitted force is unstable and cannot produce self-locking, and there is a retraction phenomenon during drilling. Especially when encountering hard rock formations, the drilling efficiency is low, or even drilling is impossible, and the construction requirements cannot be met. In addition, after the drilling depth reaches a certain depth, water comes out of the well, and a part or even most of the drill rods are immersed in muddy water or mud. The mud enters the gap between the outer slide rail and the inner slide rail of the cylinder, and after repeated extrusion and drying, it forms increasingly thick, solid and difficult-to-contain mud and dirt, which hinders the smooth sliding of the cylinder, has a short working life, high construction cost and seriously affects the construction period. Therefore, in order to solve the above problems, the present invention proposes a high-speed deep mixing drilling rig and a construction method thereof. Summary of the invention
[0005] In view of the above technical problems existing in the prior art, the present invention proposes a high-speed deep mixing drilling rig and a construction method thereof, which overcomes the shortcomings of the prior art. The equipment can transmit the drilling rig torque in a telescopic state. Compared with the existing pile driving and hole drilling rig, this structure can increase the drilling depth without increasing the height of the drilling rig tower. In this way, a large amount of steel used to increase the height of the drilling rig tower is saved, which greatly reduces the cost, and reduces the size of the pile driving and hole drilling rig, and the mobile cost is also reduced. The drill rod has a circular cross-section, which greatly improves the strength and rigidity of the drill rod, so that the torque and axial force can be effectively transmitted. There is no relative sliding between the sections of the drill rod during drilling, and the pressurization is stable and reliable, which can be applied to a variety of soil and rock layers. By setting a constant pressure valve and an exhaust valve, there is always pressure inside the drill rod, and water and mud in the borehole cannot enter, thereby increasing the working life of the drilling rig.
[0006] A high-speed deep mixing drilling rig, characterized in that it includes a chassis, a drilling rig front end, a drilling rig back end, a power system, a pile frame, and a control platform; the drilling rig back end includes a curing agent mixing system and a high-pressure gas supply system; the power system includes a cylinder power system, a circumferential rotation power system, a vertical rotation power system, a chassis power system, a pile frame power system, and a drilling rig accessory power system; the drilling rig front end includes a power head, a rotary joint, an air pipe, a slurry pipe, a hydraulic oil pipe, an exhaust valve, a constant pressure valve, a cylinder rod, a cylinder barrel, a pulley, a cylinder guide sleeve, an outer drill rod, an inner drill rod, a drill rod guide sleeve, an air pipe casing, a slurry pipe casing, a lowering wire rope, an upper pulling wire rope, and a drill bit; an air pipe and a slurry pipe are installed in the outer drill rod, a drill rod guide sleeve is installed at the bottom of the outer drill rod, a constant pressure valve is installed on the air pipe inside the outer drill rod close to the power head, and an exhaust valve is installed on the outer drill rod corresponding to the constant pressure valve; an air pipe and a slurry pipe are installed in the inner drill rod There are trachea casing and slurry pipe casing, and pulleys are installed on the top and bottom of the oil cylinder barrel; the swivel joint is connected to the power head through a flange, the outer drill rod is connected to the power head through a flange, the swivel joint is connected to the outer drill rod through an trachea and a slurry pipe, the trachea and slurry pipe are respectively plugged with the trachea casing and the slurry pipe casing, the top of the oil cylinder rod is connected to the flange through a pin shaft, the swivel joint is connected to the upper part of the oil cylinder rod through a hydraulic oil pipe, the oil cylinder barrel is fixed by a cylinder guide sleeve installed on the inner drill rod, a lowering wire rope is wound on the pulley at the bottom of the oil cylinder barrel, one end of the lowering wire rope is connected to an end of the outer drill rod close to the power head, and the other end of the lowering wire rope is connected to an end of the inner drill rod close to the power head, and an upper pulling wire rope is wound on the pulley at the top of the oil cylinder barrel, one end of the upper pulling wire rope is connected to an end of the outer drill rod away from the power head, and the other end of the upper pulling wire rope is connected to an end of the inner drill rod close to the power head.
[0007] Preferably, the diameter of the oil cylinder is smaller than the inner diameter of the inner drill rod and is 1-5 mm smaller than the inner diameter of the cylinder guide sleeve. During operation, the oil cylinder rod is stationary relative to the outer drill rod, and the oil cylinder moves relative to the outer drill rod.
[0008] Preferably, the air pipe is divided into two parts, one part is the part between the swivel joint and the outer drill rod, this part is a high-pressure rubber hose, and the other part is the part inside the outer drill rod, this part is a steel pipe; the slurry pipe is divided into two parts, one part is the part between the swivel joint and the outer drill rod, this part is a high-pressure rubber hose, and the other part is the part inside the outer drill rod, this part is a steel pipe; the hydraulic oil pipe is a high-pressure rubber hose.
[0009] Preferably, there are three pulleys, one pulley at the bottom of the cylinder barrel, which is consistent with the axis of the cylinder barrel, and two pulleys at the top of the cylinder barrel, which are symmetrically distributed along the axis of the cylinder barrel.
[0010] Preferably, the inner drill rod structure is a hexagonal drill rod, and the outer drill rod is a smooth round drill rod. A cylinder guide sleeve is arranged on the inner side of the top of the inner drill rod, the cylinder guide sleeve is welded to the inner drill rod and overlapped with the cylinder barrel, and a drill rod guide sleeve is arranged on the inner side of the bottom of the outer drill rod, the drill rod guide sleeve is welded to the outer drill rod and overlapped with the inner drill rod.
[0011] A construction method of a high-speed deep mixing drill, characterized in that a high-speed deep mixing drill is used for construction, and the specific construction steps are as follows:
[0012] Step 1: Start the drilling rig, put it in place according to the design requirements, adjust the pile frame and chassis, ensure that the drilling rig is in a horizontal state and the drill rod is in a vertical state, and test run the drilling rig for 5-10 minutes;
[0013] Step 2: Lift the power head to the top of the pile frame, start the oil cylinder power system, push the oil cylinder and the pulley downward, and then push the inner drill rod and the drill bit downward by lowering the wire rope. When the drill bit is 1.0-3.0m away from the ground, start the circumferential rotary power system and the vertical rotary power system to make the power head move downward while rotating forward;
[0014] Step 3: After the drill bit completely enters the soil, start the curing agent mixing system and the high-pressure gas supply system, and pump the curing agent and high-pressure gas into the soil through the rotary joint, the gas pipe, the slurry pipe and the drill bit in turn, so that the curing agent is efficiently and evenly added to the soil; at the same time, start the constant pressure valve to maintain the set pressure in the cavity of the outer drill rod;
[0015] Step 4: When the cylinder moves downward to the maximum stroke, the cylinder is locked, and the power head continues to drive the outer drill rod, inner drill rod and drill bit to rotate and move downward until the mixing reaches the set depth;
[0016] Step 5: Adjust the vertical rotary power system and the circumferential rotary power system to make the power head rotate in the opposite direction, and drive the outer drill rod, the inner drill rod and the drill bit to rotate and move upward, and the curing agent mixing system and the high-pressure gas supply system continue to pump the curing agent and high-pressure gas into the soil through the drill bit;
[0017] Step 6: Lift the power head to the top of the pile frame, turn off the vertical rotary power system to stop the power head and the outer drill rod from moving upward, start the oil cylinder power system, push the oil cylinder and the pulley upward, and then pull the inner drill rod and the drill bit upward by pulling up the wire rope;
[0018] Step 7: When the drill bit is completely out of the soil, turn off the curing agent mixing system and the high-pressure gas supply system, close the constant pressure valve and open the exhaust valve at the same time, so that the pressure in the outer drill pipe cavity is consistent with the external atmosphere;
[0019] Step 8: When the oil cylinder moves upward to the maximum stroke, the circumferential rotary power system is closed to stop the rotation of the power head. After locking the oil cylinder, the vertical rotary power system is started to move the power head, the outer drill rod, the inner drill rod and the drill bit downward by a set distance to ensure that the overall center of gravity of the drilling rig moves downward;
[0020] Step 9: Rinse the curing agent mixing system, swivel joint, slurry pipe and drill bit with clean water, level the site near the mixing pile, and move the drilling rig to construct the next mixing pile;
[0021] Step 10: Repeat steps 1 to 9 until the construction is completed.
[0022] Preferably, the speed at which the cylinder power system pushes the inner drill rod and the drill bit to slide downward is not greater than the speed at which the power head moves downward, and the speed at which the cylinder power system pulls the inner drill rod and the drill bit to slide upward is not greater than the speed at which the power head moves upward.
[0023] Preferably, the pressure in the outer drill rod cavity increases with the increase of stirring depth, the minimum pressure is not less than 0.2 MPa, and the maximum pressure is not more than 0.8 MPa.
[0024] Preferably, the compressive strength of the upper pull wire rope and the lower pull wire rope is greater than the maximum pulling force and the maximum downward force of the drilling rig, and the upper pull wire rope and the lower pull wire rope are set with an initial preload, and the initial preload range is 0-100kN.
[0025] Beneficial technical effects brought by the present invention:
[0026] (1) The equipment can transmit the drilling torque in the telescopic state. Compared with the existing pile-driving and hole-forming drilling rigs, this structure can increase the drilling depth without increasing the height of the drilling rig tower. This saves a lot of steel used to increase the height of the drilling rig tower, greatly reducing the cost, and makes the pile-driving and hole-forming drilling rig smaller, and the moving cost is also reduced. (2) The drill rod has a circular cross-section, which greatly improves the strength and rigidity of the drill rod, so that the torque and axial force can be effectively transmitted. (3) There is no relative sliding between the sections of the drill rod during drilling, and the pressurization is stable and reliable, which can be applied to a variety of soil and rock layers. (4) By setting a constant pressure valve and an exhaust valve, there is always pressure inside the drill rod, and water and mud in the borehole cannot enter, which increases the working life of the drilling rig. BRIEF DESCRIPTION OF THE DRAWINGS
[0027] Figure 1 The present invention is a schematic diagram of a high-speed deep mixing drilling rig and a drilling rig in a construction method thereof.
[0028] Figure 2 The present invention is a cross-sectional schematic diagram of a high-speed deep mixing drilling rig and a front end of the drilling rig in a construction method thereof.
[0029] Figure 3 The present invention discloses a high-speed deep mixing drilling rig and a rope winding schematic diagram of lowering a steel wire rope in a construction method thereof.
[0030] Figure 4 The present invention is a schematic diagram of the winding of the upper pull wire rope in a high-speed deep mixing drilling rig and a construction method thereof.
[0031] Among them, 1-power head, 2-swivel joint, 3-air pipe, 4-slurry pipe, 5-hydraulic oil pipe, 6-exhaust valve, 7-constant pressure valve, 8-cylinder rod, 9-cylinder barrel, 10-pulley, 11-cylinder guide sleeve, 12-external drill rod, 13-inner drill rod, 14-drill rod guide sleeve, 15-air pipe casing, 16-slurry pipe casing, 17-lowering wire rope, 18-pulling wire rope, 19-drill bit, 20-chassis. DETAILED DESCRIPTION
[0032] The present invention is further described in detail below with reference to the accompanying drawings and specific embodiments:
[0033] like Figures 1 to 4As shown, a high-speed deep mixing drilling rig is characterized in that it includes a chassis 20, a drilling rig front end, a drilling rig back end, a power system, a pile frame, and a control platform; the drilling rig back end includes a curing agent mixing system and a high-pressure gas supply system; the power system includes a cylinder power system, a circular rotary power system, a vertical rotary power system, a chassis power system, a pile frame power system, and a drilling rig accessory power system; the drilling rig front end includes a power head 1, a rotary joint 2, an air pipe 3, a slurry pipe 4, a hydraulic oil pipe 5, an exhaust valve 6, a constant pressure valve 7, a cylinder rod 8, an oil Cylinder 9, pulley 10, cylinder guide sleeve 11, outer drill rod 12, inner drill rod 13, drill rod guide sleeve 14, tracheal sleeve 15, slurry sleeve 16, lowering wire rope 17, pulling wire rope 18, drill bit 19; tracheal sleeve 3 and slurry sleeve 4 are installed in the outer drill rod 12, drill rod guide sleeve 14 is installed at the bottom of the outer drill rod 12, constant pressure valve 7 is installed on the side of the tracheal sleeve 3 inside the outer drill rod 12 close to the power head 1, and exhaust valve 6 is installed on the outer drill rod 12 corresponding to the constant pressure valve 7; tracheal sleeve is installed in the inner drill rod 13 15, slurry pipe sleeve 16, the top and bottom of the oil cylinder 9 are both installed with pulleys 10; the swivel joint 2 is connected to the power head 1 through a flange, the outer drill rod 12 is connected to the power head 1 through a flange, the swivel joint 2 is connected to the outer drill rod 12 through an air pipe 3 and a slurry pipe 4, the air pipe 3 and the slurry pipe 4 are plugged with the air pipe sleeve 15 and the slurry pipe sleeve 16 respectively, the top of the oil cylinder rod 8 is connected to the flange through a pin shaft, the swivel joint 2 is connected to the upper part of the oil cylinder rod 8 through a hydraulic oil pipe 5, and the oil cylinder 9 is installed on The oil cylinder guide sleeve 11 on the inner drill rod 13 is fixed, and a lowering wire rope 17 is wound on the bottom pulley 10 of the oil cylinder barrel 9, one end of the lowering wire rope 17 is connected to the end of the outer drill rod 12 close to the power head 1, and the other end of the lowering wire rope 17 is connected to the end of the inner drill rod 13 close to the power head 1, and a pulling wire rope 18 is wound on the top pulley 10 of the oil cylinder barrel 9, one end of the pulling wire rope 18 is connected to the end of the outer drill rod 12 away from the power head 1, and the other end of the pulling wire rope 18 is connected to the end of the inner drill rod 13 close to the power head 1.
[0034] Preferably, the diameter of the oil cylinder barrel 9 is smaller than the inner diameter of the inner drill rod 13 and 1-5 mm smaller than the inner diameter of the cylinder guide sleeve 11. During operation, the oil cylinder rod 8 is stationary relative to the outer drill rod 12, and the oil cylinder barrel 9 moves relative to the outer drill rod 12.
[0035] Preferably, the air pipe 3 is divided into two parts, one part is the part between the swivel joint 2 and the outer drill rod 12, this part is a high-pressure rubber hose, and the other part is the part inside the outer drill rod 12, this part is a steel pipe; the slurry pipe 4 is divided into two parts, one part is the part between the swivel joint 2 and the outer drill rod 12, this part is a high-pressure rubber hose, and the other part is the part inside the outer drill rod 12, this part is a steel pipe; the hydraulic oil pipe 5 is a high-pressure rubber hose.
[0036] Preferably, there are three pulleys 10 , one pulley 10 at the bottom of the cylinder barrel 9 , which is consistent with the axis of the cylinder barrel 9 , and two pulleys 10 at the top of the cylinder barrel 9 , which are symmetrically distributed along the axis of the cylinder barrel 9 .
[0037] Preferably, the inner drill rod 13 is a hexagonal drill rod, and the outer drill rod 12 is a smooth round drill rod. A cylinder guide sleeve 11 is arranged on the inner side of the top of the inner drill rod 13, and the cylinder guide sleeve 11 is welded to the inner drill rod 13 and overlapped with the cylinder barrel 9. A drill rod guide sleeve 14 is arranged on the inner side of the bottom of the outer drill rod 12, and the drill rod guide sleeve 14 is welded to the outer drill rod 12 and overlapped with the inner drill rod 13.
[0038] A construction method of a high-speed deep mixing drill, characterized in that a high-speed deep mixing drill is used for construction, and the specific construction steps are as follows:
[0039] Step 1: Start the drilling rig, put the drilling rig in place according to the design requirements, adjust the pile frame and chassis 20, ensure that the drilling rig is in a horizontal state as a whole and the drill rod is in a vertical state, and test run the drilling rig for 5-10 minutes;
[0040] Step 2: lift the power head 1 to the top of the pile frame, start the oil cylinder power system, push the oil cylinder barrel 9 and the pulley 10 to move downward, and then push the inner drill rod 13 and the drill bit 19 to slide downward by lowering the wire rope 17. When the drill bit 19 is 1.0-3.0m away from the ground, start the circumferential rotary power system and the vertical rotary power system, so that the power head 1 moves downward while rotating forward;
[0041] Step 3: After the drill bit 19 completely enters the soil, the curing agent mixing system and the high-pressure gas supply system are started, and the rotary joint 2, the gas pipe 3, the slurry pipe 4 and the drill bit 19 are used to pump the curing agent and the high-pressure gas into the soil in sequence, so that the curing agent is efficiently and evenly added to the soil; at the same time, the constant pressure valve 7 is started to maintain the set pressure in the cavity of the outer drill rod 12;
[0042] Step 4: When the oil cylinder 9 moves downward to the maximum stroke, the oil cylinder 9 is locked, and the power head 1 continues to drive the outer drill rod 12, the inner drill rod 13 and the drill bit 19 to rotate and move downward until the stirring reaches the set depth;
[0043] Step 5: Adjust the vertical rotary power system and the circumferential rotary power system to make the power head 1 rotate in the opposite direction, and drive the outer drill rod 12, the inner drill rod 13 and the drill bit 19 to rotate and move upward, and the curing agent mixing system and the high-pressure gas supply system continue to pump the curing agent and high-pressure gas into the soil through the drill bit 19;
[0044] Step 6: Lift the power head 1 to the top of the pile frame, turn off the vertical rotary power system to stop the power head 1 and the outer drill rod 12 from moving upward, start the oil cylinder power system, push the oil cylinder 9 and the pulley 10 to move upward, and then pull the inner drill rod 13 and the drill bit 19 upward by pulling up the wire rope 18;
[0045] Step 7: When the drill bit 19 is completely separated from the soil, the curing agent mixing system and the high-pressure gas supply system are turned off, and the constant pressure valve 7 is closed while the exhaust valve 6 is opened, so that the pressure in the cavity of the outer drill rod 12 is consistent with the external atmosphere;
[0046] Step 8: When the oil cylinder 9 moves upward to the maximum stroke, the circumferential rotary power system is closed to stop the rotation of the power head 1. After the oil cylinder 9 is locked, the vertical rotary power system is started to move the power head 1, the outer drill rod 12, the inner drill rod 13 and the drill bit 19 downward by a set distance to ensure that the overall center of gravity of the drilling rig moves downward;
[0047] Step 9: Rinse the curing agent mixing system, the rotary joint 2, the slurry pipe 4 and the drill bit 19 with clean water, level the site near the mixing pile, and move the drilling rig to construct the next mixing pile;
[0048] Step 10: Repeat steps 1 to 9 until the construction is completed.
[0049] Preferably, the speed at which the cylinder power system pushes the inner drill rod 13 and the drill bit 19 to slide downward is not greater than the speed at which the power head 1 moves downward, and the speed at which the cylinder power system pulls the inner drill rod 13 and the drill bit 19 to slide upward is not greater than the speed at which the power head 1 moves upward.
[0050] Preferably, the pressure in the cavity of the outer drill rod 12 increases with the increase of the stirring depth, the minimum pressure is not less than 0.2 MPa, and the maximum pressure is not more than 0.8 MPa.
[0051] Preferably, the compressive strength of the upper pull wire rope 18 and the lower pull wire rope 17 are both greater than the maximum pulling force and the maximum downward force of the drilling rig. The upper pull wire rope 18 and the lower pull wire rope 17 are set with an initial preload force, and the initial preload force range is 0-100kN.
[0052] The present invention provides a high-speed deep mixing drill and a construction method thereof. The device can transmit the torque of the drill in a telescopic state. Compared with the existing pile-driving and hole-forming drill, this structure can increase the drilling depth without increasing the height of the drill tower. This saves a large amount of steel used to increase the height of the drill tower, greatly reducing the cost, and reduces the size of the pile-driving and hole-forming drill, thereby reducing the moving cost. The drill rod has a circular cross-section, which greatly improves the strength and rigidity of the drill rod, so that the torque and axial force can be effectively transmitted. There is no relative sliding between the sections of the drill rod during drilling, and the pressurization is stable and reliable, which can be applied to a variety of soil layers and rock layers. By setting a constant pressure valve 7 and an exhaust valve 6, there is always pressure inside the drill rod, and water and mud in the borehole cannot enter, thereby increasing the working life of the drill.
[0053] Of course, the above description is not a limitation of the present invention, and the present invention is not limited to the above examples. Changes, modifications, additions or substitutions made by technicians in this technical field within the essential scope of the present invention also fall within the protection scope of the present invention.
Claims
1. A high-speed deep mixing drilling rig, characterized in that: It includes chassis, drilling rig front end, drilling rig back end, power system, pile frame, and control platform; the drilling rig back end includes a curing agent mixing system and a high-pressure gas supply system; the power system includes a cylinder power system, a circumferential rotation power system, a vertical rotation power system, a chassis power system, a pile frame power system, and a drilling rig accessory power system; the drilling rig front end includes a power head, a rotary joint, an air pipe, a slurry pipe, a hydraulic oil pipe, an exhaust valve, a constant pressure valve, a cylinder rod, a cylinder barrel, a pulley, a cylinder guide sleeve, an outer drill rod, an inner drill rod, a drill rod guide sleeve, an air pipe casing, a slurry pipe casing, a lowering wire rope, an upper pulling wire rope, and a drill bit; an air pipe and a slurry pipe are installed in the outer drill rod, a drill rod guide sleeve is installed at the bottom of the outer drill rod, a constant pressure valve is installed on the air pipe inside the outer drill rod close to the power head, and an exhaust valve is installed on the outer drill rod corresponding to the constant pressure valve; an air pipe casing and a slurry pipe casing are installed in the inner drill rod The top of the oil cylinder is connected with the hydraulic cylinder to form a hydraulic oil pipe, and the hydraulic oil pipe is connected with the hydraulic oil pipe of the hydraulic cylinder to form a hydraulic oil pipe.
2. A high-speed deep mixing drilling rig according to claim 1, characterized in that: The diameter of the oil cylinder is smaller than the inner diameter of the inner drill rod and is 1-5 mm smaller than the inner diameter of the oil cylinder guide sleeve. During operation, the oil cylinder rod is stationary relative to the outer drill rod, and the oil cylinder moves relative to the outer drill rod.
3. A high-speed deep mixing drilling rig according to claim 1, characterized in that: The air pipe is divided into two parts, one part is the part between the swivel joint and the outer drill rod, this part is a high-pressure rubber hose, and the other part is the part inside the outer drill rod, this part is a steel pipe; the slurry pipe is divided into two parts, one part is the part between the swivel joint and the outer drill rod, this part is a high-pressure rubber hose, and the other part is the part inside the outer drill rod, this part is a steel pipe; the hydraulic oil pipe is a high-pressure rubber hose.
4. A high-speed deep mixing drilling rig according to claim 1, characterized in that: There are three pulleys, one at the bottom of the oil cylinder barrel, which is consistent with the axis of the oil cylinder barrel, and two at the top of the oil cylinder barrel, which are symmetrically distributed along the axis of the oil cylinder barrel.
5. A high-speed deep mixing drilling rig according to claim 1, characterized in that: The inner drill rod structure is a hexagonal drill rod, and the outer drill rod is a smooth round drill rod. A cylinder guide sleeve is arranged on the inner side of the top of the inner drill rod, the cylinder guide sleeve is welded to the inner drill rod and overlapped with the cylinder barrel, and a drill rod guide sleeve is arranged on the inner side of the bottom of the outer drill rod, the drill rod guide sleeve is welded to the outer drill rod and overlapped with the inner drill rod.
6. A construction method of a high-speed deep mixing drilling rig, characterized in that: The high-speed deep mixing drilling rig described in claim 1 is used for construction, and the specific construction steps are as follows: Step 1: Start the drilling rig, put it in place according to the design requirements, adjust the pile frame and chassis, ensure that the drilling rig is in a horizontal state and the drill rod is in a vertical state, and test run the drilling rig for 5-10 minutes; Step 2: Lift the power head to the top of the pile frame, start the oil cylinder power system, push the oil cylinder and the pulley downward, and then push the inner drill rod and the drill bit downward by lowering the wire rope. When the drill bit is 1.0-3.0m away from the ground, start the circumferential rotary power system and the vertical rotary power system to make the power head move downward while rotating forward; Step 3: After the drill bit completely enters the soil, start the curing agent mixing system and the high-pressure gas supply system, and pump the curing agent and high-pressure gas into the soil through the rotary joint, the gas pipe, the slurry pipe and the drill bit in turn, so that the curing agent is efficiently and evenly added to the soil; at the same time, start the constant pressure valve to maintain the set pressure in the cavity of the outer drill rod; Step 4: When the cylinder moves downward to the maximum stroke, the cylinder is locked, and the power head continues to drive the outer drill rod, inner drill rod and drill bit to rotate and move downward until the mixing reaches the set depth; Step 5: Adjust the vertical rotary power system and the circumferential rotary power system to make the power head rotate in the opposite direction, and drive the outer drill rod, the inner drill rod and the drill bit to rotate and move upward, and the curing agent mixing system and the high-pressure gas supply system continue to pump the curing agent and high-pressure gas into the soil through the drill bit; Step 6: Lift the power head to the top of the pile frame, turn off the vertical rotary power system to stop the power head and the outer drill rod from moving upward, start the oil cylinder power system, push the oil cylinder and the pulley upward, and then pull the inner drill rod and the drill bit upward by pulling up the wire rope; Step 7: When the drill bit is completely out of the soil, turn off the curing agent mixing system and the high-pressure gas supply system, close the constant pressure valve and open the exhaust valve at the same time, so that the pressure in the outer drill pipe cavity is consistent with the external atmosphere; Step 8: When the oil cylinder moves upward to the maximum stroke, the circumferential rotary power system is closed to stop the rotation of the power head. After locking the oil cylinder, the vertical rotary power system is started to move the power head, the outer drill rod, the inner drill rod and the drill bit downward by a set distance to ensure that the overall center of gravity of the drilling rig moves downward; Step 9: Rinse the curing agent mixing system, swivel joint, slurry pipe and drill bit with clean water, level the site near the mixing pile, and move the drilling rig to construct the next mixing pile; Step 10: Repeat steps 1 to 9 until the construction is completed.
7. According to the construction method of a high-speed deep mixing drilling rig described in claim 6, the speed at which the cylinder power system pushes the inner drill rod and the drill bit to slide downward is not greater than the speed at which the power head moves downward, and the speed at which the cylinder power system pulls the inner drill rod and the drill bit to slide upward is not greater than the speed at which the power head moves upward.
8. According to the construction method of a high-speed deep mixing drilling rig as described in claim 6, the pressure in the cavity of the outer drill rod increases with the increase of the mixing depth, the minimum pressure is not less than 0.2MPa, and the maximum pressure is not more than 0.8MPa.
9. According to the construction method of a high-speed deep mixing drilling rig described in claim 6, the compressive strength of the upper pulling wire rope and the lowering wire rope are both greater than the maximum pulling force and the maximum downward pressure of the drilling rig, and the upper pulling wire rope and the lowering wire rope are set with an initial preload, and the initial preload range is 0-100kN.