A new type of wind turbine tower conversion section structure

By adopting a combination design of funnel-shaped tower, steel pipe concrete oblique support and horizontal bearing barrel in the fan tower conversion section structure, combined with the fastening method of prestressed anchor rod and buried iron, structural fatigue and slow construction progress are solved The problem has achieved a safer, simpler and more efficient construction process.

CN111894811BActive Publication Date: 2024-11-08欧添雁
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202010903263.9
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2020-09-01
Publication Date
2024-11-08
Estimated Expiration
2040-09-01

AI Technical Summary

Technical Problem

The fan tower conversion section structure is prone to structural fatigue damage under large loads and complex stresses. Due to the huge and complex structure and the cumbersome transportation and assembly processes, the construction progress is slow.

Method used

A new fan tower conversion section structure was designed, using a combined structure of funnel-shaped tower, steel pipe concrete oblique support and horizontal bearing barrel. The structure is simplified and reduced through the fastening method of prestressed anchor rod and buried iron. The amount of steel is used to achieve a more direct force transmission and a simple installation process.

Benefits of technology

It improves the safety and reliability of the structure, reduces the amount of steel, simplifies the construction process, shortens the construction cycle, and makes installation and transportation more convenient.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN111894811B_ABST
    Figure CN111894811B_ABST
Patent Text Reader

Abstract

The present invention discloses a novel wind turbine tower conversion section structure, comprising a platform, a funnel-shaped tower arranged on the upper part of the platform, a plurality of steel tube concrete inclined supports arranged around the funnel-shaped tower, and a plurality of horizontal transfer bearing cylinders arranged around the platform, and its design features are: a plurality of prestressed anchor rods are inserted in each steel tube concrete inclined support, and the two ends of each prestressed anchor rod are respectively extended into the corresponding horizontal transfer bearing cylinder and the funnel-shaped tower, and the two ends of each prestressed anchor rod are respectively fastened to the buried iron arranged in the horizontal transfer bearing cylinder and the buried iron of the reinforced concrete ring beam arranged in the funnel tower. The advantages of the present invention are: direct force transmission, simple structure, greatly convenient installation and transportation of components, safer and more reliable structure, reduced steel consumption, lowered project cost, and shortened construction period.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of wind turbine towers, and in particular to a novel wind turbine tower conversion section structure. Background Art

[0002] In the design of wind turbine tower structure, the design of the connection transition section between the upper tower and the lower legs is crucial. The location of this transition section has a large load and complex force. It is a key part of the safety and reliability of the entire wind turbine tower structure, and it has a decisive influence on the entire structure.

[0003] Under normal circumstances, due to the complex force in this transition section, concentrated stress is more likely to form, which is more likely to cause fatigue damage to the structure, thereby greatly reducing the service life of the structure.

[0004] In addition, usually, since the structure of this conversion section is relatively large and complex, considering its transportation size, it is often necessary to pre-split it into several small units, and then transport it to the construction site for assembly. The problem is that there are many units that need to be assembled, which are scattered and cumbersome, resulting in slow construction progress. Summary of the invention

[0005] In view of the problems in the background technology, the purpose of the present invention is to provide a new wind turbine tower conversion section structure with direct force transmission, simple structure, small amount of steel material and convenient and quick construction.

[0006] To achieve the above purpose, the technical solution adopted by the present invention is as follows:

[0007] A novel wind turbine tower conversion section structure comprises a platform, a funnel-shaped tower arranged on the upper part of the platform, a plurality of first steel tube concrete inclined supports arranged around the funnel-shaped tower, and a plurality of horizontal transfer bearings arranged around the platform, wherein the inner side of each horizontal transfer bearing is detachably fixedly connected to the platform, the upper part of each horizontal transfer bearing is connected to a first steel tube concrete inclined support via a second steel tube concrete inclined support, and the lower part is connected to one or two wind turbine tower leg connectors, and each of the first steel tube concrete inclined supports is connected to the funnel-shaped tower, wherein:

[0008] A plurality of prestressed anchor rods are inserted in each of the second steel tube concrete inclined supports, and one end of each of the prestressed anchor rods sequentially passes through the corresponding second steel tube concrete inclined supports and the first steel tube concrete inclined supports and extends into the funnel-shaped tower tube, and the other end of each of the prestressed anchor rods passes through the corresponding steel tube concrete inclined supports and extends into the corresponding horizontal transfer tube;

[0009] One end of each of the prestressed anchor rods extending into the funnel-shaped tower is correspondingly fastened to a first buried iron phase arranged in the funnel-shaped tower;

[0010] One end of each prestressed anchor rod extending into the corresponding horizontal transfer tube is fastened together with a second buried iron arranged in the corresponding horizontal transfer tube.

[0011] In the above technical solution, each of the first steel tube concrete inclined supports comprises a first inclined steel tube, a first concrete filling layer arranged in the first inclined steel tube, and a first flange arranged at one end of the first inclined steel tube;

[0012] Each of the second steel tube concrete inclined supports comprises a second inclined steel tube, a second concrete filling layer arranged in the second inclined steel tube, and a second flange arranged at one end of the second inclined steel tube;

[0013] During assembly, one end of the first inclined steel tube in each first steel tube concrete inclined support provided with a first flange is fixed to one end of the second inclined steel tube in a corresponding second steel tube concrete inclined support provided with a second flange by bolts; one end of the first inclined steel tube in each first steel tube concrete inclined support away from the first flange is welded and fixed to the outer wall of the funnel-shaped tower; one end of the second inclined steel tube in each second steel tube concrete inclined support away from the second flange is welded and fixed to a corresponding horizontal transfer bearing tube.

[0014] In the above technical solution, a plurality of first embedded sleeves for inserting prestressed anchor rods are arranged in the first concrete filling layer of each of the first steel tube concrete inclined supports;

[0015] A plurality of second embedded sleeves for inserting prestressed anchor rods are arranged in the second concrete filling layer of each of the second steel tube concrete inclined supports;

[0016] Among them, the first embedded sleeves arranged in the first concrete filling layer of each first steel tube concrete inclined support are connected one by one with the second embedded sleeves arranged in the second concrete filling layer of the corresponding second steel tube concrete inclined support.

[0017] In the above technical solution, the platform comprises a platform plate formed by splicing a first steel plate and a plurality of second steel plates, and a plurality of platform steel beams arranged at the lower part around the platform plate;

[0018] The plurality of second steel plates are evenly arranged around the first steel plate, and the side of each second steel plate away from the first steel plate is fixedly overlapped on a platform steel beam, and the side of each second steel plate close to the first steel plate is fixedly overlapped on the first steel plate; the first steel plate has a diagonal line, and each adjacent two second steel plates are welded together along the extension line of the diagonal line of the first steel plate;

[0019] Both ends of each platform steel beam are connected to two corresponding adjacent horizontal transfer bearing cylinders through a connecting plate A and two connecting plates B respectively.

[0020] In the above technical solution, a maintenance manhole is also opened in the middle of the first steel plate, and the maintenance manhole is connected to the lower part of the funnel-shaped tower.

[0021] In the above technical solution, the funnel-shaped tower includes a funnel-shaped steel cylinder and a reinforced concrete annular beam arranged in the funnel-shaped steel cylinder; a plurality of first embedded irons are arranged along the circumferential direction on the upper part of the inner casting surface of the reinforced concrete annular beam, and each of the first embedded irons corresponds to a first steel tube concrete inclined support and is used to fasten the upper ends of a plurality of prestressed anchor rods passing through the second steel tube concrete inclined support and the first steel tube concrete inclined support opposite thereto;

[0022] During assembly, the reinforced concrete annular beam arranged in the funnel-shaped steel cylinder and the first concrete filling layers in the plurality of first steel tube concrete inclined supports arranged around the funnel-shaped steel cylinder are interconnected and form a whole.

[0023] In the above technical solution, each of the horizontal transfer bearing cylinders comprises a horizontal steel pipe, a concrete annular casting layer arranged inside the horizontal steel pipe, and a steel plate connector arranged outside the horizontal steel pipe;

[0024] A second buried iron is also correspondingly arranged in the concrete annular casting layer of each horizontal transfer tube, and the second buried iron arranged in each horizontal transfer tube is correspondingly used to fasten the lower ends of a plurality of prestressed anchor rods passing through the second steel tube concrete inclined support opposite thereto;

[0025] Each steel plate connector is arranged on the outer wall of each corresponding horizontal transfer tube on the side facing the platform, and both ends of each steel plate connector are connected to the corresponding two adjacent platform steel beams through a connecting plate A and two connecting plates B respectively.

[0026] In the above technical solution, the number of the first steel tube concrete inclined support, the second steel tube concrete inclined support and the horizontal transfer bearing cylinder is 3 to 6.

[0027] Compared with the prior art, the advantages of the present invention are: 1) the force transmission is more direct, the structure is simpler, and the installation and transportation of components are greatly facilitated; 2) the structure is safer and more reliable, which greatly reduces the amount of steel used and reduces the project cost; 3) the construction period is shortened. BRIEF DESCRIPTION OF THE DRAWINGS

[0028] Figure 1 This is a front view of the novel wind turbine tower conversion section structure of the present invention;

[0029] Figure 2 for Figure 1 Schematic diagram of the structural steel of the wind turbine tower conversion section structure horizontally rotated 45 degrees;

[0030] Figure 3 for Figure 1 A top view of the wind turbine tower conversion section structure;

[0031] Figure 4 for Figure 3 Schematic diagram of the AA section;

[0032] Figure 5 for Figure 4 Schematic diagram of the aa section;

[0033] Figure 6 for Figure 4 Enlarged view of the M node;

[0034] Figure 7 for Figure 4 Enlarged view of the N node in the middle;

[0035] Figure 8 for Figure 1 A top view of the platform in the conversion section structure of the wind turbine tower;

[0036] Fig. 9 for Figure 8 Schematic diagram of the middle BB section;

[0037] Fig.10 for Figure 8 Enlarged view of the P node in the middle;

[0038] Fig.11 for Figure 8 A top view of the connection between a single horizontal transfer tube and two adjacent platform steel beams;

[0039] Fig.12 for Fig.11 K-direction view in;

[0040] Fig.13 for Fig.11 Schematic diagram of the bb section;

[0041] Fig.14A specific application embodiment of the present invention;

[0042] Explanation of reference numerals: 1. platform; 1.1. first steel plate; 1.2. second steel plate; 1.3. platform steel beam; 1.4. connection plate A; 1.5. connection plate B; 1.6. inspection manhole; 2. funnel-shaped tower; 2.1. funnel-shaped steel cylinder; 2.2. reinforced concrete ring beam; 3. first steel tube concrete inclined support; 3.1. first inclined steel tube; 3.2. first concrete filling layer; 3.3. first flange; 4. second steel tube concrete inclined support; 4.1. second inclined steel Pipe; 3.2, second concrete filling layer; 4.3, second flange; 5, horizontal swivel tube; 5.1, horizontal steel pipe; 5.2, concrete annular casting layer; 5.3, steel beam connecting plate; 6, wind turbine tower leg connector; 7, prestressed anchor rod; 8, first buried iron; 9, second buried iron; 10, first embedded casing; 11, second embedded casing; 100, wind turbine tower conversion section structure; 200, wind turbine tower; 300, wind turbine tower leg; 400, wind turbine. DETAILED DESCRIPTION

[0043] In order to make the technical means, creative features, objectives and effects achieved by the present invention easy to understand, the following further describes how the present invention is implemented in conjunction with the accompanying drawings and specific implementation methods.

[0044] See also Figures 1 to 4 As shown, a novel wind turbine tower conversion section structure provided by the present invention comprises a platform 1, a funnel-shaped tower 2 arranged on the upper part of the platform 1, a plurality of first steel tube concrete inclined supports 3 arranged around the funnel-shaped tower 2, and a plurality of horizontal transfer tubes 5 arranged around the platform 1, wherein the inner side of each horizontal transfer tube 5 is detachably fixedly connected to the platform 1, the upper part of each horizontal transfer tube 5 is connected to a first steel tube concrete inclined support 3 via a second steel tube concrete inclined support 4, and the lower part is connected to one or two wind turbine tower leg connectors 6, and each first steel tube concrete inclined support 3 is connected to the funnel-shaped tower 2; when in use, refer to Fig.14 As shown, each wind turbine tower leg connector 6 is connected to a wind turbine tower leg 300 , the funnel-shaped tower 2 is connected to the wind turbine tower 200 , and the wind turbine tower 200 is connected to the wind turbine 400 .

[0045] Specifically, in the present invention, refer to Figure 4As shown, a plurality of prestressed anchor rods 7 are penetrated in each second steel tube concrete inclined support 4, and the upper end of each prestressed anchor rod 7 successively penetrates the corresponding second steel tube concrete inclined support 4 and the first steel tube concrete inclined support 3 and extends into the funnel-shaped tower 2, and the lower end of each prestressed anchor rod 7 penetrates the corresponding steel tube concrete inclined support and extends into the corresponding horizontal transfer tube 5; and wherein, one end of each prestressed anchor rod 7 extending into the funnel-shaped tower 2 is fastened together with a first buried iron 8 arranged in the funnel-shaped tower 2; one end of each prestressed anchor rod 7 extending into the corresponding horizontal transfer tube 5 is fastened together with a second buried iron 9 arranged in the corresponding horizontal transfer tube 5.

[0046] As a preferred embodiment of the present invention: Figure 6 and Figure 7 As shown, each first steel tube concrete inclined support 3 comprises a first inclined steel tube 3.1, a first concrete filling layer 3.2 arranged in the first inclined steel tube 3.1 and a first flange 3.3 arranged at one end of the first inclined steel tube 3.1;

[0047] Each second steel tube concrete inclined support 4 comprises a second inclined steel tube 4.1, a second concrete filling layer 4.2 arranged in the second inclined steel tube 4.1 and a second flange 4.3 arranged at one end of the second inclined steel tube 4.1;

[0048] During assembly, one end of the first inclined steel tube 3.1 in each first concrete-filled steel tube inclined support 3 provided with a first flange 3.3 is fixed to one end of the second inclined steel tube 4.1 in a corresponding second concrete-filled steel tube inclined support 4 provided with a second flange 4.3 by bolts; one end of the first inclined steel tube 3.1 in each first concrete-filled steel tube inclined support 3 away from the first flange 3.3 is welded and fixed to the outer wall of the funnel-shaped tower 2; one end of the second inclined steel tube 4.1 in each second concrete-filled steel tube inclined support 4 away from the second flange 4.3 is welded and fixed to a corresponding horizontal transfer tube 5.

[0049] See also Figures 4 to 7 As shown, a plurality of first embedded sleeves 10 for inserting prestressed anchor rods 7 are arranged in the first concrete filling layer 3.2 of each first steel tube concrete inclined support 3;

[0050] A plurality of second embedded sleeves 11 for inserting prestressed anchor rods 7 are arranged in the second concrete filling layer 4.2 of each second steel tube concrete inclined support 4;

[0051] Among them, the first embedded sleeves 10 arranged in the first concrete filling layer 3.2 of each first steel tube concrete inclined support 3 are connected to the second embedded sleeves 11 arranged in the second concrete filling layer 4.2 of the corresponding second steel tube concrete inclined support 4 in a one-to-one correspondence.

[0052] As a preferred embodiment of the present invention: Figures 8 to 13 As shown, the platform 1 comprises a platform plate formed by splicing a first steel plate 1.1 and a plurality of second steel plates 1.2, and a plurality of platform steel beams 1.3 arranged at the lower part of the surrounding of the platform plate;

[0053] Among them, a plurality of second steel plates 1.2 are evenly arranged around the first steel plate 1.1, and each second steel plate 1.2 is fixedly overlapped on a platform steel beam 1.3 on the side away from the first steel plate 1.1, and each second steel plate 1.2 is fixedly overlapped on the side close to the first steel plate 1.1; the first steel plate 1.1 has a diagonal line, and each adjacent second steel plates 1.2 are welded together along the extension line of the diagonal line of the first steel plate 1.1;

[0054] Both ends of each platform steel beam 1.3 are connected to two corresponding adjacent horizontal transfer bearing cylinders 4 through a connecting plate A1.4 and two connecting plates B1.5.

[0055] In addition, for the convenience of inspection, please refer to Figure 8 and Fig. 9 As shown, in the embodiment of the platform 1 described above, a maintenance manhole 1.6 is further provided in the middle of the first steel plate 1.1, and the maintenance manhole 1.6 is communicated with the lower part of the funnel-shaped tower 2.

[0056] In order to increase the supporting strength of the platform 1, a certain out-of-plane supporting structure may be added to the first steel plate 1.1 and the second steel plate 1.2 in the above embodiment of the platform 1.

[0057] As a preferred embodiment of the present invention: Figure 6 As shown, the funnel-shaped tower 2 is composed of a funnel-shaped steel cylinder 2.1 and a reinforced concrete annular beam 2.2 arranged in the funnel-shaped steel cylinder 2.1; a plurality of first embedded irons 8 are arranged along the circumferential direction on the upper part of the inner casting surface of the reinforced concrete annular beam 2.2, and each first embedded iron 8 corresponds to a first steel tube concrete inclined support 3 and is used to fasten the upper ends of a plurality of prestressed anchor rods 7 passing through the second steel tube concrete inclined support 4 and the first steel tube concrete inclined support 3 opposite thereto;

[0058] During assembly, the reinforced concrete annular beam 2.2 disposed in the funnel-shaped steel cylinder 2.1 and the first concrete filling layer 3.2 in the plurality of first steel tube concrete inclined supports 3 disposed around the funnel-shaped steel cylinder 2.1 are interconnected and form a whole.

[0059] As a preferred embodiment of the present invention: Figure 7 As shown, each horizontal transfer tube 5 comprises a horizontal steel pipe 5.1, a concrete annular casting layer 5.2 arranged in the horizontal steel pipe 5.1, and a steel plate connecting member 5.3 arranged outside the horizontal steel pipe 5.1; a second buried iron 9 is also correspondingly arranged in the concrete annular casting layer 5.2 of each horizontal transfer tube 5, and the second buried iron 9 arranged in each horizontal transfer tube 5 is correspondingly used to tighten the lower ends of multiple prestressed anchor rods 7 passing through the second steel tube concrete inclined support 4 opposite thereto;

[0060] See also Figures 10 to 12 As shown, each steel plate connector 5.3 is arranged on the outer wall of each corresponding horizontal transfer tube 5 facing the platform 1, and the two ends of each steel plate connector 5.3 are connected to the corresponding two adjacent platform steel beams 1.3 through a connecting plate A1.4 and two connecting plates B1.5 respectively.

[0061] Specifically, in the present invention, the number of the first steel tube concrete inclined support 3, the second steel tube concrete inclined support 4 and the horizontal transfer tube 4 are all 3 to 6, and preferably 4.

[0062] Specifically, in the present invention, the number of prestressed anchor rods 7 inserted into each first steel tube concrete inclined support 3 and the second steel tube concrete inclined support 4 is 3 to 8, and preferably 4.

[0063] The specific construction and installation process of the wind turbine tower conversion section structure provided by the present invention is as follows:

[0064] (1) According to the design requirements, first, in the factory, the platform 1, the funnel-shaped tower 2, the first steel tube concrete inclined support 3, the second steel tube concrete inclined support 4, the horizontal transfer tube 5 and the wind turbine tower leg connector 6 in the wind turbine tower conversion section structure 100 are manufactured in sequence; and each of the first steel tube concrete inclined support 3 is pre-assembled with the funnel-shaped tower 2, each of the second steel tube concrete inclined support 4 is pre-assembled with a horizontal transfer tube 5, and each of the horizontal transfer tube 5 is pre-assembled with one or two wind turbine tower leg connectors 6;

[0065] (2) transporting the above-fabricated platform 1, the pre-assembled funnel-shaped tower 2 and the first steel tube concrete inclined support 3, and the pre-assembled horizontal transfer tube 5 and the second steel tube concrete inclined support 4 to the implementation site;

[0066] (3) After the foundation piles and the limbs 300 of the wind turbine tower corresponding to the wind turbine tower conversion section structure 100 in step (1) are installed, the horizontal swivel cylinder 5, the platform 1 and the funnel-shaped tower 2 are installed in sequence, that is, after the foundation piles and the limbs 300 of the wind turbine tower corresponding to the wind turbine tower conversion section structure 100 in step (1) are installed:

[0067] The first step is to sequentially hoist a plurality of horizontal transfer bearings 5 ​​in the wind turbine tower conversion section structure 100 corresponding to the wind turbine tower to the upper part of the wind turbine tower limb 300 that has been installed, and to install each horizontal transfer bearing 5 to the upper part of one or two wind turbine tower limbs 300, that is, to be fastened and connected to one or two wind turbine tower limbs 300 through the wind turbine tower limb connection member 6 connected to the lower part thereof;

[0068] The second step is to hoist the platform 1 in the wind turbine tower conversion section structure 100 corresponding to the wind turbine tower onto the upper part of the multiple installed horizontal transfer tubes 5, and to fix the platform 1 on the steel plate connector 5.3 provided on the inner side of each horizontal transfer tube 5;

[0069] Step 3: hoist the funnel-shaped tower 2 to the upper part of the installed platform 1, and make the lower part of the funnel-shaped tower 2 pass through the inspection manhole 1.6 provided in the middle part of the platform 1, and at the same time rotate the funnel-shaped tower 2 so that the multiple first steel tube concrete inclined supports 3 located around the funnel-shaped tower 2 are aligned one by one with the second steel tube concrete inclined supports 4 provided on the upper part of the multiple horizontal transfer tubes 5 that have been installed and located around the platform 1, and then fix them with flange bolts;

[0070] The fourth step is to sequentially insert a plurality of prestressed anchor rods 7 corresponding to each second steel tube concrete inclined support 4 into the first embedded sleeve 10 in the corresponding first steel tube concrete inclined support 3 and the second embedded sleeve 11 in the second steel tube concrete inclined support 4, and make the upper end of each prestressed anchor rod 7 sequentially pass through the corresponding second steel tube concrete inclined support 4 and the first steel tube concrete inclined support 3 and extend into the funnel-shaped steel cylinder 2, and be fastened together with a first embedded iron 8 provided in the corresponding funnel-shaped steel cylinder 2 through a prestressed nut, and the lower end passes through the corresponding second steel tube concrete inclined support 4 and extends into a corresponding horizontal transfer tube 5, and be fastened together with a second embedded iron 9 provided in the horizontal transfer tube 5 through a prestressed nut, so that the above-mentioned wind turbine tower conversion section structure 100 and the corresponding wind turbine tower foundation pile foundation and wind turbine tower limb 300 installation are completed;

[0071] (4) After the installation of the wind turbine tower conversion section structure 100 and the wind turbine tower legs 300 is completed, the subsequent installation of the wind turbine tower 200 and the wind turbine 400 can be started;

[0072] That is, the wind turbine tower 200 corresponding to the wind turbine tower conversion section structure 100 can be hoisted to the upper part of the wind turbine tower conversion section structure 100 by hoisting equipment, and its lower part is fastened together with the upper part of the funnel-shaped tower 2 in the wind turbine tower conversion section structure 100. After the wind turbine tower 200 and the wind turbine tower conversion section structure 100 are fixed, the wind turbine 400 is hoisted to the upper part of the wind turbine tower 200 by hoisting equipment, and is fastened together with the upper part of the wind turbine tower 200. At this point, the installation of the wind turbine tower 200 and the wind turbine 400 can be completed.

[0073] Finally, it should be noted that the above description is only an embodiment of the present invention, and does not limit the patent scope of the present invention. Any equivalent structure or equivalent process transformation made using the contents of the present invention specification and drawings, or directly or indirectly used in other related technical fields, are also included in the patent protection scope of the present invention.

Claims

1. A novel wind turbine tower conversion section structure, comprising a platform (1), a funnel-shaped tower (2) arranged on the upper part of the platform (1), a plurality of first steel tube concrete inclined supports (3) arranged around the funnel-shaped tower (2), and a plurality of horizontal transfer cylinders (5) arranged around the platform (1), wherein the inner side of each horizontal transfer cylinder (5) is detachably fixedly connected to the platform (1), the upper part of each horizontal transfer cylinder (5) is connected to a first steel tube concrete inclined support (3) via a second steel tube concrete inclined support (4), and the lower part is connected to one or two wind turbine tower leg connectors (6), and each of the first steel tube concrete inclined supports (3) is connected to the funnel-shaped tower (2), characterized in that: A plurality of prestressed anchor rods (7) are inserted into each of the second steel tube concrete inclined supports (4), and one end of each of the prestressed anchor rods (7) sequentially passes through the corresponding second steel tube concrete inclined supports (4) and the first steel tube concrete inclined supports (3) and extends into the funnel-shaped tower tube (2), and the other end of each of the prestressed anchor rods (7) passes through the corresponding steel tube concrete inclined supports and extends into the corresponding horizontal transfer tube (5); One end of each prestressed anchor rod (7) extending into the funnel-shaped tower (2) is correspondingly fastened to a first buried iron (8) arranged in the funnel-shaped tower (2); One end of each prestressed anchor rod (7) extending into the corresponding horizontal transfer tube (5) is fastened together with a second buried iron (9) arranged in the corresponding horizontal transfer tube (5); The platform (1) comprises a platform plate formed by splicing a first steel plate (1.1) and a plurality of second steel plates (1.2), and a plurality of platform steel beams (1.3) arranged at the lower part around the platform plate; The plurality of second steel plates (1.2) are evenly arranged around the first steel plate (1.1), and the side of each second steel plate (1.2) away from the first steel plate (1.1) is fixedly overlapped on a platform steel beam (1.3), and the side of each second steel plate (1.2) close to the first steel plate (1.1) is fixedly overlapped on the first steel plate (1.1); the first steel plate (1.1) has a diagonal line, and each two adjacent second steel plates (1.2) are welded together along the extension line of the diagonal line of the first steel plate (1.1); Both ends of each platform steel beam (1.3) are connected to two adjacent horizontal bearing cylinders (5) corresponding thereto through a connecting plate A (1.4) and two connecting plates B (1.5); Each of the horizontal transfer bearing cylinders (5) comprises a horizontal steel pipe (5.1), a concrete annular pouring layer (5.2) arranged inside the horizontal steel pipe (5.1), and a steel plate connecting piece (5.3) arranged outside the horizontal steel pipe (5.1); A second embedded iron (9) is also correspondingly arranged in the concrete annular casting layer (5.2) of each horizontal transfer tube (5), and the second embedded iron (9) arranged in each horizontal transfer tube (5) is correspondingly used to tighten the lower ends of a plurality of prestressed anchor rods (7) passing through the second steel tube concrete inclined support (4) opposite thereto; Each steel plate connecting member (5.3) is arranged on the outer wall of each corresponding horizontal transfer tube (5) on the side facing the platform (1), and the two ends of each steel plate connecting member (5.3) are respectively connected to the two corresponding adjacent platform steel beams (1.3) through a connecting plate A (1.4) and two connecting plates B (1.5).

2. The novel wind turbine tower conversion section structure according to claim 1 is characterized in that: Each of the first steel tube concrete inclined supports (3) comprises a first inclined steel tube (3.1), a first concrete filling layer (3.2) arranged inside the first inclined steel tube (3.1), and a first flange (3.3) arranged at one end of the first inclined steel tube (3.1); Each of the second steel tube concrete inclined supports (4) comprises a second inclined steel tube (4.1), a second concrete filling layer (4.2) arranged inside the second inclined steel tube (4.1), and a second flange (4.3) arranged at one end of the second inclined steel tube (4.1); During assembly, one end of the first inclined steel tube (3.1) provided with the first flange (3.3) in each first steel tube concrete inclined support (3) is fixedly connected to one end of the second inclined steel tube (4.1) provided with the second flange (4.3) in a corresponding second steel tube concrete inclined support (4) by bolts; one end of the first inclined steel tube (3.1) in each first steel tube concrete inclined support (3) away from the first flange (3.3) is welded and fixed to the outer wall of the funnel-shaped tower (2); one end of the second inclined steel tube (4.1) in each second steel tube concrete inclined support (4) away from the second flange (4.3) is welded and fixed to a corresponding horizontal transfer tube (5).

3. The novel wind turbine tower conversion section structure according to claim 2 is characterized in that: A plurality of first embedded sleeves (10) for inserting prestressed anchor rods (7) are arranged in the first concrete filling layer (3.2) of each of the first steel tube concrete inclined supports (3); A plurality of second embedded sleeves (11) for inserting prestressed anchor rods (7) are arranged in the second concrete filling layer (4.2) of each of the second steel tube concrete inclined supports (4); The plurality of first pre-buried sleeves (10) arranged in the first concrete filling layer (3.2) of each first steel tube concrete inclined support (3) are connected one by one with the plurality of second pre-buried sleeves (11) arranged in the second concrete filling layer (4.2) of the corresponding second steel tube concrete inclined support (4).

4. The novel wind turbine tower conversion section structure according to claim 1 is characterized in that: A maintenance manhole (1.6) is also provided in the middle of the first steel plate (1.1), and the maintenance manhole (1.6) is connected to the lower part of the funnel-shaped tower (2).

5. The novel wind turbine tower conversion section structure according to claim 4 is characterized in that: The funnel-shaped tower (2) comprises a funnel-shaped steel cylinder (2.1) and a reinforced concrete annular beam (2.2) arranged in the funnel-shaped steel cylinder (2.1); a plurality of first embedded irons (8) are arranged along the circumferential direction on the upper part of the reinforced concrete annular beam (2.2), and each of the first embedded irons (8) corresponds to a first steel tube concrete inclined support (3) and is used to fasten the upper ends of a plurality of prestressed anchor rods (7) extending from the second steel tube concrete inclined support (4) and the first steel tube concrete inclined support (3) opposite thereto; During assembly, the reinforced concrete annular beam (2.2) arranged in the funnel-shaped steel cylinder (2.1) and the first concrete filling layer (3.2) in the plurality of first steel tube concrete inclined supports (3) arranged around the funnel-shaped steel cylinder (2.1) are interconnected and form a whole.