Ground subsidence value monitoring device and method

By using the plug-in assembly of the cylinder section and the insertion rod in the settlement rod, combined with the sealing filler and the limiting device, the straight embedded formation of the settlement rod is realized, and the problems of low accuracy and difficulty in burying in the existing technology are solved. Improve the accuracy and installation convenience of ground settlement monitoring around the foundation pit.

CN111910695BActive Publication Date: 2024-11-19CITIC GUOAN CONSTR GRP CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202010788432.9
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2020-08-07
Publication Date
2024-11-19
Estimated Expiration
2040-08-07

AI Technical Summary

Technical Problem

In the prior art, the ground settlement monitoring method based on settlement rods has the problem of low accuracy, especially during the excavation of foundation pits, since the bottom plate buried depth needs to be close to or greater than the depth of the precipitation well, it is difficult to bury the settlement rod, and the workload is Large and unable to effectively monitor ground settlement caused by drop in groundwater levels.

Method used

Using plug-in components including cylinder sections and plug-in rods, through sealing fillers and limiting devices, the plug-in rod slides in the cylinder section to achieve a straight embedding of the bottom layer, and pushes the plug-in rods to extend out in combination with pressure medium to avoid drilling and landfill. Enhance the synchronous sinking capability of settlement rods, ensure monitoring accuracy, and improve connection reliability through annular uniformity and welding connections.

Benefits of technology

It improves the accuracy and installation convenience of ground settlement monitoring, reduces the need for drilling compaction, avoids the impact of mud layer on settlement rods, and achieves high-accurate settlement value monitoring without drilling and landfill.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN111910695B_ABST
    Figure CN111910695B_ABST
Patent Text Reader

Abstract

The present invention discloses a device and method for monitoring ground settlement values, the device includes a settlement rod and a plug-in assembly; the plug-in assembly includes a barrel section and a plug-in rod, one end of the barrel section is fixedly connected to the settlement rod; the plug-in rod is located on the inner side of the barrel section, and the length direction of the plug-in rod is parallel to the length direction of the barrel section, and the plug-in rod can slide in the barrel section along the length direction of the barrel section; a sealing filler is also provided between the end of the plug-in rod close to the settlement rod and the inner wall of the plug-in rod, and the sealing filler is used to achieve axial sealing of the gap between the plug-in rod and the barrel section; a limiting device is also included for limiting the position of the sealing filler in the length direction of the plug-in rod; and a restraining device is also included for restraining the length of the plug-in rod relative to the free end of the barrel section. The method is based on the device. The device and method provided by this scheme can not only optimize the accuracy of bottom surface settlement monitoring based on the settlement rod, but also have the characteristics of easy installation.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of foundation pit construction, and in particular to a ground settlement value monitoring device and method. Background Art

[0002] The foundation pit generally refers to the earth pit excavated at the design location of the building foundation according to the building base elevation and foundation plane size. For the foundation pit construction, the foundation pit support mechanism is a temporary structure and a safety protection structure to prevent collapse during the foundation pit construction process. At the same time, during the foundation pit excavation and construction process, it is necessary to consider the precipitation of the foundation pit.

[0003] The above foundation pit excavation and precipitation will have adverse effects on the surrounding geology, one of which is that it will cause the surrounding ground subsidence. Therefore, in the existing construction, the ground subsidence is detected, and the data obtained are of great significance to the construction safety, the safety of surrounding buildings, and the analysis of the mechanism and scope of the impact of foundation pit excavation and precipitation on the surrounding environment.

[0004] In the prior art, there are many ways to complete ground settlement monitoring. The most widely used method is to use a settlement rod (marker rod) and a level to complete settlement monitoring. This implementation method has the advantages of low cost, simple operation, and easy testing. However, unlike other methods, the above monitoring method using a settlement rod has the problem of low accuracy. Summary of the invention

[0005] In response to the above-mentioned technical problem that the monitoring method using settlement rods has low accuracy in ground settlement monitoring, the present invention provides a ground settlement value monitoring device and method. The device and method provided by this scheme can not only optimize the accuracy of bottom surface settlement monitoring based on settlement rods, but also have the characteristic of easy installation.

[0006] The ground settlement value monitoring device and method provided by the present invention solve the problem through the following technical points: the ground settlement value monitoring device comprises a settlement rod, the settlement rod is a tubular structure with a blind end at the bottom, and also comprises a plug-in assembly arranged at the bottom end of the settlement rod;

[0007] The plug-in assembly includes a barrel section and an insertion rod, one end of the barrel section is fixedly connected to the sinking rod, and the internal space of the barrel section is communicated with the internal space of the sinking rod; the insertion rod is located inside the barrel section, and the length direction of the insertion rod is parallel to the length direction of the barrel section, and the insertion rod can slide inside the barrel section along the length direction of the barrel section;

[0008] A sealing filler is also provided between the end of the insertion rod close to the settlement rod and the inner wall of the insertion rod, and the sealing filler is used to achieve axial sealing of the gap between the insertion rod and the barrel section;

[0009] It also includes a limiting device for limiting the position of the sealing filler in the length direction of the insertion rod;

[0010] It also includes a restraining device for restraining the extension length of the insertion rod relative to the free end of the barrel section.

[0011] In the prior art, in the ground settlement value monitoring method based on the settlement rod, matching radar, level, etc., completing the effective embedding of the settlement rod in the ground is the basis for realizing the ground settlement value monitoring. At the same time, for the accuracy of the obtained results, the settlement rod can effectively settle with the ground, which has a decisive influence on the above accuracy. Therefore, in the prior art, in order to reduce the influence of mud adhesion on the settlement of the settlement rod, the settlement rod can settle with the ground. Generally, a bottom plate is set at the bottom of the settlement rod, so that the settlement rod can settle synchronously with the ground under the pressure of the bottom plate. This method is very convenient in the use of settlement monitoring of masonry dams: the masonry dam itself is a filling body, and it is very convenient to bury the bottom plate on the filling foundation. However, in order to deal with the surrounding ground settlement caused by the drop in groundwater level during foundation pit excavation, the burial depth of the bottom plate must generally be close to or greater than the depth of the precipitation well. In this way, the burial of settlement rods including the bottom plate is difficult and labor-intensive. Therefore, in the prior art, for monitoring the ground settlement around the foundation pit, the settlement rod method is generally not provided with the bottom plate, or in order to facilitate the burial of the settlement rod, the above bottom plate cannot achieve the ideal effect, which ultimately leads to low accuracy of the obtained results (generally too small).

[0012] In this solution, the plug assembly is used to play the role of the bottom plate mentioned above: when the settlement rod is buried, the size of the hole drilled on the ground meets the bottom size of the settlement rod when the rod is stored in the barrel section. After the settlement rod is embedded in the ground, the pressure medium is introduced from the top of the settlement rod. Since a sealing filler is provided between the rod and the barrel section, and the position of the sealing filler in the length direction of the rod is limited by the limiting device, the rod can be pushed out of the barrel section under the above pressure medium. In conjunction with the restraining device, the rod can be prevented from completely coming out of the barrel section and causing the rod to fail. Therefore, in the case of no drilling and burying, the rod on the bottom side of the settlement rod can be embedded in the formation in a straight state. In this way, when the formation settles, the pressure applied to the free end of the rod can effectively make the settlement rod sink synchronously with the ground. If the drilling and burying is not performed, a protective tube is installed on the outside of the settlement rod to prevent the mud layer from directly squeezing the settlement rod, which can achieve the purpose of facilitating the accuracy of settlement value monitoring.

[0013] Regarding the drilling of the holes, as mentioned above, the size of the holes does not actually need to take into account the need for rod compaction, so this solution also has the characteristic of easy installation.

[0014] Further technical solutions are:

[0015] As a specific implementation scheme of a restraining device and a limiting device with a simple structure and easy assembly, it also includes a first retaining ring fixed to the free end of the barrel section and located on the inner side of the barrel section; it also includes a second retaining ring fixed to the insertion rod; and it also includes a shaft elastic retaining ring for installation on the insertion rod;

[0016] The sealing filler is clamped between the shaft elastic retaining ring and the second retaining ring, and the shaft elastic retaining ring and the second retaining ring form the limiting device;

[0017] The second retaining ring is located between the shaft elastic retaining ring and the first retaining ring. When the plug rod slides out from the free end of the barrel section, the inner end face of the first retaining ring contacts the outer end face of the second retaining ring to realize the restriction of the length of the plug rod extending relative to the free end of the barrel section: the first retaining ring and the second retaining ring constitute the restraining device. During the specific assembly of this scheme, after the sealing filler is wrapped around the plug rod and compacted on the second retaining ring, the shaft elastic retaining ring is installed before the sealing filler recovers its deformation, so that sufficient sealing pressure ratios can be obtained between turns of the sealing filler and between the sealing filler and the plug rod and the barrel section to realize the corresponding axial sealing. During the process of the plug rod sliding out, when the inner end face of the first retaining ring contacts the outer end face of the second retaining ring, the limit of the plug rod sliding out stop point position is realized.

[0018] In order to avoid the presence of large rocks on the outside of the bottom of the settlement rod, reduce the possibility of the rod not being effectively embedded in the stratum, and ultimately causing the settlement rod to fail to achieve the expected burial quality, it is configured as follows: there are multiple plug-in components, and the free ends of each barrel section face different directions.

[0019] In the specific application of this scheme, since both the plug rod and the barrel section are sheared, in order to facilitate the reliability of the connection of this scheme and make the force in the circumferential direction of the bottom of the sinker rod relatively uniform, so as to avoid the sinking of the sinker rod being blocked due to the skewness of the sinker rod, it is set as follows: the sinker rod is a circular tube, the axial direction of each barrel section is along the radial direction of the sinker rod, and the barrel sections are evenly distributed in an annular shape relative to the axis of the sinker rod;

[0020] It also includes a base with a center hole, the lower end of the sinker rod is embedded in the center hole and is welded to the base through a ring weld;

[0021] The lower side of each barrel section is in contact with the upper surface of the base, and each barrel section and the base are welded together by a straight weld extending along the length of the barrel section. In this solution, the above welding connection form and the introduction of the base are aimed at the connection reliability problem mentioned above; the annular uniform distribution is aimed at avoiding the tilting of the sinker rod caused by the unilateral force on the bottom of the sinker rod as much as possible.

[0022] As a technical solution which has self-lubricating properties to facilitate smooth extrusion of the plug rod and avoid contamination of the formation: the sealing filler is a polytetrafluoroethylene sealing filler.

[0023] In order to increase the influence of the ground lowering on the lowering of the insertion rod, it is set as follows: the top surface of the insertion rod is a plane perpendicular to the settlement rod.

[0024] As a technical solution that enables the settlement rod to be partially removed for reuse after the settlement value monitoring is completed, and is easy to install and separate, the setting is as follows: the settlement rod is a two-section serially connected structure, and the connection relationship between the two rod sections that are serially connected to form the settlement rod is: the lower end of the rod section on the upper side and the upper end of the rod section on the lower side are both provided with connecting threads, and after the lower end of the rod section on the upper side and the upper end of the rod section on the lower side are aligned, a threaded connection relationship is formed by the relative rotation of the rod section on the upper side and the rod section on the lower side. This solution aims at the problems of high cost, manufacturing difficulty and assembly difficulty in the durable design of the sealing performance of the sealing packing, and the problem that if the sealing performance of the sealing packing is reliable, the force generated by the negative pressure adsorption may not be able to make the inserted rod retract. It provides a technical solution that only leaves the bottom part of the device underground after use. When this solution is used, the upper rod segment is pre-connected with the lower rod segment during installation. After the measurement is completed, the rod segments can be separated by rotating the upper rod segment so that the upper rod segment can be reused.

[0025] As a rod segment that is easy to match with a settlement rod, two threaded pairs are used at the same time to work underground with the corresponding threaded pairs. Due to the problem that the threaded pairs are not easy to disassemble due to rust, jamming, etc., a technical solution that can also increase the ease of separation of the settlement rod is provided: the lower end of the rod segment on the upper side and the upper end of the rod segment on the lower side are both provided with external threaded segments, and also include a sleeve with internal threaded segments at both ends, the sleeve serves as an intermediate connecting piece between the lower end of the rod segment on the upper side and the upper end of the rod segment on the lower side: the threaded connection relationship is formed by threading the two external threaded segments with the internal threaded segments. When completing the separation of the rod segments, this solution only requires that the sleeve and any one of the two rod segments can be separated smoothly.

[0026] In order to enable the rod segment on the upper side to adapt to the specific rod insertion depth and at the same time enable the rod segment monomers that constitute the corresponding rod segment to be reused, the rod segment on the upper side is a multi-section serial connection structure, and the formation of the multi-section serial connection is achieved by bolt connection.

[0027] The present invention also discloses a method for monitoring ground subsidence value, which is based on the device described in any one of the above items and is implemented by the following steps:

[0028] S1. Complete the installation of the device in the settlement monitoring area

[0029] S1-1: The device is inserted into the settlement monitoring hole in a manner that the rod is retracted into the barrel section;

[0030] S1-2: Connect a pressure medium source to the upper end of the settlement rod, and use the pressure medium to withdraw the rod until it extends relative to the barrel section, and make the end of the rod extending relative to the barrel section embed into the side wall at the bottom of the settlement monitoring hole;

[0031] S2. Use measuring instruments to complete the settlement monitoring of the settlement rod.

[0032] The above method includes the installation method and the use method of the device. As mentioned above, by adopting this scheme, not only accurate settlement monitoring values ​​can be obtained, but also it has the characteristic of easy implementation.

[0033] The present invention has the following beneficial effects:

[0034] In the device provided by the present scheme, the plug-in assembly is used to play the role of the bottom plate described above: when the settlement rod is buried, the size of the hole drilled on the ground meets the bottom size of the settlement rod when the rod is stored in the barrel section. After the settlement rod is embedded in the ground, the pressure medium is introduced from the top of the settlement rod. Since a sealing filler is provided between the rod and the barrel section, and the position of the sealing filler in the length direction of the rod is limited by the limiting device, the rod can be pushed out of the barrel section under the above pressure medium. In conjunction with the restraining device, the rod can be prevented from completely coming out of the barrel section and causing the rod to fail. Therefore, in the case of no drilling and burying, the rod on the bottom side of the settlement rod can be embedded in the formation in a straight state. In this way, when the formation settles, the pressure applied to the free end of the rod can effectively make the settlement rod sink synchronously with the ground. If the drilling and burying is not performed, a protective tube is installed on the drilled hole to prevent the mud layer from directly squeezing the settlement rod, which can achieve the purpose of facilitating the accuracy of settlement value monitoring.

[0035] Regarding the drilling of the holes, as mentioned above, the size of the holes does not actually need to take into account the need for rod compaction, so this solution also has the characteristic of easy installation.

[0036] The method provided in this solution includes the installation method and the use method of the device. As mentioned above, by adopting this solution, not only accurate settlement monitoring values ​​can be obtained, but also it has the characteristic of easy implementation. BRIEF DESCRIPTION OF THE DRAWINGS

[0037] Figure 1 It is a side view of a specific embodiment of the ground subsidence monitoring device of the present invention;

[0038] Figure 2 yes Figure 1 A partial enlarged view of section A is shown.

[0039] The reference numerals in the figure are: 1, sinker rod, 2, casing, 3, barrel section, 4, plug rod, 5, sealing packing, 6, first retaining ring, 7, second retaining ring, 8, base, 9, elastic retaining ring for shaft. DETAILED DESCRIPTION

[0040] The present invention will be further described in detail below in conjunction with the embodiments, but the structure of the present invention is not limited to the following embodiments.

[0041] Embodiment 1:

[0042] like Figure 1 and Figure 2 As shown, the ground settlement value monitoring device includes a settlement rod 1, wherein the settlement rod 1 is a tubular structure with a blind end at the bottom, and also includes a plug-in assembly arranged at the bottom end of the settlement rod 1;

[0043] The plug-in assembly includes a barrel section 3 and an insertion rod 4. One end of the barrel section 3 is fixedly connected to the sinking rod 1, and the internal space of the barrel section 3 is communicated with the internal space of the sinking rod 1. The insertion rod 4 is located on the inner side of the barrel section 3, and the length direction of the insertion rod 4 is parallel to the length direction of the barrel section 3. The insertion rod 4 can slide in the barrel section 3 along the length direction of the barrel section 3.

[0044] A sealing filler 5 is also provided between the end of the plug rod 4 close to the settling rod 1 and the inner wall of the plug rod 4, and the sealing filler 5 is used to achieve axial sealing of the gap between the plug rod 4 and the barrel section 3;

[0045] It also includes a limiting device for limiting the position of the sealing filler 5 in the length direction of the insertion rod 4;

[0046] It also includes a restraining device for restraining the extension length of the insertion rod 4 relative to the free end of the barrel section 3.

[0047] In the prior art, in the ground settlement value monitoring method based on the settlement rod 1, such as matching radar and level, completing the effective embedding of the settlement rod 1 in the ground is the basis for realizing the ground settlement value monitoring. At the same time, for the accuracy of the obtained results, the settlement rod 1 can effectively settle with the ground, which has a decisive influence on the above accuracy. Therefore, in the prior art, in order to reduce the influence of mud adhesion on the settlement of the settlement rod 1, the settlement rod 1 can be settled with the ground. Generally, a bottom plate is set at the bottom of the settlement rod 1, so that the settlement rod 1 can be synchronously settled with the ground under the pressure of the bottom plate. This method is very convenient in the use of settlement monitoring of masonry dams: the masonry dam itself is a filling body, and it is very convenient to bury the bottom plate on the filling foundation. However, in order to deal with the surrounding ground settlement caused by the drop in groundwater level during foundation pit excavation, the burial depth of the bottom plate must generally be close to or greater than the depth of the precipitation well. In this way, the burial of the settlement rod 1 including the bottom plate is difficult and requires a lot of work. Therefore, in the prior art, for monitoring the ground settlement around the foundation pit, the settlement rod 1 is generally not provided with the bottom plate, or in order to facilitate the burial of the settlement rod 1, the above bottom plate cannot achieve the ideal effect, which ultimately leads to low accuracy of the obtained results (generally too small).

[0048] In this scheme, the plug-in assembly is used to play the role of the base plate mentioned above: when the settlement rod 1 is buried, the size of the hole drilled on the ground is sufficient to meet the bottom size of the settlement rod 1 when the insertion rod 4 is received in the barrel section 3. After the settlement rod 1 is embedded in the ground, the pressure medium is introduced from the top of the settlement rod 1. Since a sealing filler 5 is provided between the insertion rod 4 and the barrel section 3, and the position of the sealing filler 5 in the length direction of the insertion rod 4 is limited by the limiting device, the insertion rod 4 can be pushed out of the barrel section 3 under the above pressure medium. In combination with the restraint device, it can be prevented that the insertion rod 4 completely comes out of the barrel section 3 and causes the failure of the insertion rod 4. Therefore, without drilling and filling, the insertion rod 4 on the bottom side of the settlement rod 1 can be embedded in the formation in a straight state. In this way, when the formation settles, the pressure applied to the free end of the insertion rod 4 can effectively make the settlement rod 1 sink synchronously with the ground. If drilling and filling is not carried out and a protective tube is installed on the drill hole and sleeved on the outside of the settlement rod 1 to prevent the mud layer from directly squeezing the settlement rod 1, the purpose of facilitating the accuracy of settlement value monitoring can be achieved.

[0049] Regarding the drilling of the holes, as mentioned above, the size of the holes does not actually need to take into account the compaction requirements of the insertion rod 4, so this solution also has the characteristic of easy installation.

[0050] This embodiment also provides a method for monitoring land subsidence value, which is based on the above-mentioned device and is implemented by the following steps:

[0051] S1. Complete the installation of the device in the settlement monitoring area

[0052] S1-1: The device is inserted into the settlement monitoring hole in a manner that the insertion rod 4 is retracted into the barrel section 3;

[0053] S1-2: Connect the pressure medium source to the upper end of the settlement rod 1, and use the pressure medium to withdraw the insertion rod 4 until it extends relative to the barrel section 3, and make the end of the insertion rod 4 extending relative to the barrel section 3 embed into the side wall at the bottom of the settlement monitoring hole;

[0054] S2. Use measuring instruments to complete the settlement monitoring of the settlement rod 1.

[0055] The above method includes the installation method and the use method of the device. As mentioned above, by adopting this scheme, not only accurate settlement monitoring values ​​can be obtained, but also it has the characteristic of easy implementation.

[0056] Embodiment 2:

[0057] like Figure 1 and Figure 2 As shown, this embodiment is further limited on the basis of embodiment 1:

[0058] As a specific implementation scheme of a restraining device and a limiting device with a simple structure and easy assembly, it also includes a first retaining ring 6 fixed to the free end of the barrel section 3 and located inside the barrel section 3; it also includes a second retaining ring 7 fixed to the insertion rod 4; it also includes a shaft elastic retaining ring 9 for installation on the insertion rod 4;

[0059] The sealing filler 5 is clamped between the shaft elastic retaining ring 9 and the second retaining ring 7, and the shaft elastic retaining ring 9 and the second retaining ring 7 form the limiting device;

[0060] The second retaining ring 7 is located between the shaft elastic retaining ring 9 and the first retaining ring 6. When the plug rod 4 slides out from the free end of the barrel section 3, the inner end face of the first retaining ring 6 contacts the outer end face of the second retaining ring 7 to realize the restriction of the length of the plug rod 4 relative to the free end of the barrel section 3: the first retaining ring 6 and the second retaining ring 7 constitute the constraint device. During the specific assembly of this scheme, after the sealing packing 5 is wrapped around the plug rod 4 and compacted on the second retaining ring 7, the shaft elastic retaining ring 9 is installed before the sealing packing 5 recovers its deformation, so that sufficient sealing pressure ratios between the turns of the sealing packing 5 and between the sealing packing 5 and the plug rod 4 and the barrel section 3 can be obtained to realize the corresponding axial sealing. During the sliding out process of the plug rod 4, when the inner end face of the first retaining ring 6 contacts the outer end face of the second retaining ring 7, the sliding stop point position of the plug rod 4 is limited.

[0061] In order to avoid the presence of large rocks on the outside of the bottom of the settlement rod 1, reduce the possibility that the insertion rod 4 cannot be effectively embedded in the formation, and ultimately cause the settlement rod 1 to fail to achieve the expected burial quality, it is configured as follows: there are multiple plug-in components, and the free ends of each barrel section 3 are facing different directions.

[0062] In the specific application of this scheme, since both the plug rod 4 and the barrel section 3 are sheared, in order to facilitate the reliability of the connection of this scheme and make the force in the circumferential direction of the bottom of the settlement rod 1 relatively uniform, so as to avoid the settlement of the settlement rod 1 being blocked due to the skewness of the settlement rod 1, it is set as follows: the settlement rod 1 is a round tube, the axial direction of each barrel section 3 is along the radial direction of the settlement rod 1, and the barrel sections 3 are evenly distributed in an annular shape relative to the axis of the settlement rod 1;

[0063] It also includes a base 8 provided with a center hole, the lower end of the sinker rod 1 is embedded in the center hole and is welded to the base 8 through a ring weld;

[0064] The lower side of each barrel section 3 is in contact with the upper surface of the base 8, and each barrel section 3 and the base 8 are welded and connected via a straight weld extending along the length direction of the barrel section 3. In this solution, the above welding connection form and the introduction of the base 8 are intended to address the connection reliability issues raised above; the annular uniform distribution is intended to avoid the skewing of the sinker rod 1 caused by the unilateral force on the bottom of the sinker rod 1 as much as possible.

[0065] As a technical solution which has self-lubricating property, so as to facilitate the smooth extrusion of the plug rod 4 and avoid pollution to the formation, the sealing filler 5 is a polytetrafluoroethylene sealing filler 5.

[0066] In order to increase the influence of the ground lowering on the lowering of the insertion rod 4 , it is set as follows: the top surface of the insertion rod 4 is a plane perpendicular to the settlement rod 1 .

[0067] As a technical solution that enables the settlement rod 1 to be partially removed for reuse after the settlement value monitoring is completed, and is convenient for installation and separation, it is set as follows: the settlement rod 1 is a two-section serially connected structure, and the connection relationship between the two rod sections that are serially connected to form the settlement rod 1 is: the lower end of the rod section on the upper side and the upper end of the rod section on the lower side are both provided with connecting threads, and after the lower end of the rod section on the upper side and the upper end of the rod section on the lower side are aligned, a threaded connection relationship is formed by the relative rotation of the rod section on the upper side and the rod section on the lower side. This solution aims at the problems of high cost, manufacturing difficulty and assembly difficulty in the durable design of the sealing performance of the sealing packing 5, and the problem that if the sealing performance of the sealing packing 5 is reliable, the force generated by the negative pressure adsorption may not be able to make the insertion rod 4 retreat, and provides a technical solution that only leaves the bottom part of the device underground after use. When this solution is used, the upper rod segment is pre-connected with the lower rod segment during installation. After the measurement is completed, the rod segments can be separated by rotating the upper rod segment so that the upper rod segment can be reused.

[0068] As a rod segment that is easy to match with the settlement rod 1, two threaded pairs are used at the same time to work underground with the corresponding threaded pairs. Due to the problem that the threaded pairs are not easy to disassemble due to rust, jamming, etc., a technical solution that can also increase the ease of separation of the settlement rod 1 is provided: the lower end of the rod segment on the upper side and the upper end of the rod segment on the lower side are both provided with external threaded segments, and also include a casing 2 with internal threaded segments at both ends, and the casing 2 serves as an intermediate connecting piece between the lower end of the rod segment on the upper side and the upper end of the rod segment on the lower side: the threaded connection relationship is formed by threading the two external threaded segments with the internal threaded segments. When completing the separation of the rod segments, this solution only requires that the casing 2 and any one of the two rod segments can be separated smoothly.

[0069] In order to enable the rod segment on the upper side to adapt to the specific burial depth of the inserted rod 4 and at the same time enable the rod segment monomers that constitute the corresponding rod segment to be reused, the rod segment on the upper side is a multi-section serially connected structure, and the formation of the multi-section serial connection is achieved by bolt connection.

[0070] The above contents are further detailed descriptions of the present invention in combination with specific preferred embodiments, and it cannot be determined that the specific embodiments of the present invention are limited to these descriptions. For ordinary technicians in the technical field to which the present invention belongs, other embodiments obtained without departing from the technical solution of the present invention should be included in the protection scope of the present invention.

Claims

1. A ground settlement monitoring device, comprising a settlement rod (1), characterized in that: The sinker rod (1) is a tubular structure with a blind end at the bottom, and further comprises a plug-in assembly arranged at the bottom end of the sinker rod (1); the plug-in assembly comprises a barrel section (3) and a plug-in rod (4); one end of the barrel section (3) is fixedly connected to the sinker rod (1), and the internal space of the barrel section (3) is communicated with the internal space of the sinker rod (1); the plug-in rod (4) is located on the inner side of the barrel section (3), and the length direction of the plug-in rod (4) is parallel to the length direction of the barrel section (3); the plug-in rod (4) can be inserted into the barrel section (3) along the length of the barrel section (3). The plunger (4) slides in the longitudinal direction; a sealing filler (5) is provided between one end of the plunger (4) close to the sinker rod (1) and the inner wall of the barrel section (3); the sealing filler (5) is used to achieve axial sealing of the gap between the plunger (4) and the barrel section (3); a limiting device is also included for limiting the position of the sealing filler (5) in the longitudinal direction of the plunger (4); and a limiting device is also included for limiting the extension length of the plunger (4) relative to the free end of the barrel section (3); the top of the sinker rod is used to introduce a pressure medium that pushes the plunger to extend out of the barrel section; It also includes a first retaining ring (6) fixed to the free end of the barrel section (3) and located on the inner side of the barrel section (3); it also includes a second retaining ring (7) fixed to the insertion rod (4); it also includes a shaft elastic retaining ring (9) for installation on the insertion rod (4); the sealing filler (5) is clamped between the shaft elastic retaining ring (9) and the second retaining ring (7), and the shaft elastic retaining ring (9) and the second retaining ring (7) form the limiting device; the second retaining ring (7) is located between the shaft elastic retaining ring (9) and the first retaining ring (6), and when the insertion rod (4) slides out from the free end of the barrel section (3), the inner end face of the first retaining ring (6) contacts the outer end face of the second retaining ring (7) to realize the extension length of the insertion rod (4) relative to the free end of the barrel section (3): the first retaining ring (6) and the second retaining ring (7) constitute the limiting device; There are multiple plug-in assemblies, and the free ends of the barrel sections (3) face in different directions; The sinker rod (1) is a circular tube, the axial direction of each barrel section (3) is along the radial direction of the sinker rod (1), and the barrel sections (3) are evenly distributed in a ring relative to the axis of the sinker rod (1); it also includes a base (8) provided with a center hole, the lower end of the sinker rod (1) is embedded in the center hole and is welded to the base (8) through a circumferential weld; the lower side of each barrel section (3) is in contact with the upper surface of the base (8), and each barrel section (3) and the base (8) are welded together through a straight weld extending along the length direction of the barrel section (3).

2. The ground subsidence monitoring device according to claim 1, characterized in that: The sealing filler (5) is a polytetrafluoroethylene sealing filler.

3. The ground subsidence monitoring device according to claim 1, characterized in that: The top surface of the insertion rod (4) is a plane perpendicular to the sedimentation rod (1).

4. The ground subsidence monitoring device according to claim 1, characterized in that: The settlement rod (1) is a two-section serially connected structure, and the connection relationship between the two rod sections that are serially connected to form the settlement rod (1) is as follows: the lower end of the rod section on the upper side and the upper end of the rod section on the lower side are both provided with connecting threads, and after the lower end of the rod section on the upper side and the upper end of the rod section on the lower side are aligned, a threaded connection relationship is formed by relative rotation of the rod section on the upper side and the rod section on the lower side.

5. The ground subsidence monitoring device according to claim 4, characterized in that: The lower end of the rod section on the upper side and the upper end of the rod section on the lower side are both provided with external thread sections, and also include a sleeve (2) with internal thread sections at both ends, the sleeve (2) serving as an intermediate connecting piece between the lower end of the rod section on the upper side and the upper end of the rod section on the lower side: the threaded connection relationship is formed by threading the two external thread sections with the internal thread sections.

6. The ground subsidence monitoring device according to claim 4, characterized in that: The rod section on the upper side is a multi-section serially connected structure, and the multi-section serial connection is achieved by bolt connection.

7. A method for monitoring ground subsidence, characterized in that: The method is based on the device described in any one of claims 1 to 6, and the method is implemented through the following steps: S1. Complete the installation of the device in the settlement monitoring area. S1-1: The device is embedded in the settlement monitoring hole in a manner that the rod (4) is retracted into the barrel section (3); S1-2: Connect a pressure medium source to the upper end of the settlement rod (1), and push the rod (4) out through the pressure medium so that the rod extends out of the barrel section (3), and the end of the rod (4) extending relative to the barrel section (3) is embedded in the side wall at the bottom of the settlement monitoring hole; S2. Use a measuring instrument to complete the settlement monitoring of the settlement rod (1).