Method and system for rapid stratification and block division of large-volume concrete in water conservancy and hydropower projects
By using BIM software for 3D modeling and automatic cutting in water conservancy and hydropower projects, the problems of inaccurate silo surface design and long manual calculation time in the layered and blocked large-volume concrete are solved, and efficient and accurate layered and blocked are achieved. processing, reducing management costs and improving construction quality.
Patent Information
- Application Number
- CN202011473217.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2020-12-15
- Publication Date
- 2024-10-29
- Estimated Expiration
- 2040-12-15
AI Technical Summary
In water conservancy and hydropower projects, during the layering and blocking process of large-volume concrete, due to structural complexity and limitations of two-dimensional drawings, the warehouse surface design is inaccurate, affecting construction efficiency and quality, and manual calculation time is long and management costs are high. .
Use BIM software to import the three-dimensional BIM model and hierarchical block data, create cutting planes, use loop statements to automatically cut and obtain sub-bin models, and calculate the engineering data of each sub-bin model, reducing manual calculations and improving accuracy and efficiency.
It greatly reduces staff's manual calculation time, improves the accuracy and efficiency of layering and blocking, reduces management costs, ensures project quality, and supports rapid task processing for subsequent design modifications.
Smart Images

Figure CN112560143B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the field of water conservancy and hydropower engineering, and in particular to a method and system for rapid stratification and block division of large-volume concrete in water conservancy and hydropower engineering. Background Art
[0002] In hydraulic structures, large-volume concrete projects range from tens of thousands to millions of cubic meters of concrete. A project may be divided into hundreds or thousands of warehouses. If it is calculated manually based on two-dimensional drawings, the amount of work is very large; if the subsequent layers and blocks are adjusted, the staff needs to manually calculate them all again, which is time-consuming and laborious. Secondly, due to the complex structure of the dam, not every warehouse is a regular geometric entity. It is very difficult to analyze the geometric dimensions, spatial positions and other data of holes, corridors, and metal joints in the dam body based on two-dimensional drawings, resulting in inaccurate warehouse design and affecting subsequent construction. Summary of the invention
[0003] Technical problem to be solved by the present invention: In view of the above-mentioned problems in the prior art, a method and system for rapid layering and block division of large-volume concrete in water conservancy and hydropower projects are provided. The present invention further optimizes the existing traditional three-dimensional modeling of large-volume concrete in hydraulic engineering projects, and entrusts a large amount of regular and repetitive work to be completed by computers. It has high speed and high accuracy, greatly reduces the time for staff to manually calculate according to two-dimensional drawings, reduces management costs, improves efficiency, ensures project quality, etc., has significant direct economic benefits, and has significant application advantages in the layering and block division of large-volume concrete.
[0004] In order to solve the above technical problems, the technical solution adopted by the present invention is:
[0005] A method for rapid layering and block division of large-volume concrete in water conservancy and hydropower engineering, comprising:
[0006] 1) Import the 3D BIM model of mass concrete and the layered and block data into the BIM software;
[0007] 2) Create horizontal and vertical cutting planes in BIM software based on the 3D BIM model and layered block data;
[0008] 3) Execute a pre-created cutting node in the BIM software, wherein the cutting node takes the three-dimensional BIM model, the horizontal cutting plane and the vertical cutting plane as input, and uses a loop statement to automatically cut and obtain a compartment model;
[0009] 4) Calculate the engineering data of each sub-compartment model in the BIM software.
[0010] Optionally, before step 1), the method also includes the steps of creating a three-dimensional BIM model of the mass concrete according to the two-dimensional construction drawings of the mass concrete, and exporting the three-dimensional BIM model of the mass concrete.
[0011] Optionally, after the creation of the three-dimensional BIM model of the mass concrete and before the exporting of the three-dimensional BIM model of the mass concrete, the step of extracting internal holes, corridors, metal joints and post-cast strips from the three-dimensional BIM model of the mass concrete is also included.
[0012] Optionally, the exported three-dimensional BIM model of mass concrete is a SAT model file, and importing the three-dimensional BIM model of mass concrete into the BIM software in step 1) means first using the File Path and File.FromPath nodes of the BIM software to pick up the SAT model file of the three-dimensional BIM model of mass concrete on the specified path, and then using the Geometry.ImportFromSAT node of the BIM software to extract the three-dimensional BIM model of mass concrete in the SAT model file.
[0013] Optionally, in step 1), the layered and block data of the mass concrete are imported into the BIM software as an Excel data file.
[0014] Optionally, the step of using the cutting node pre-created in step 3) to automatically cut the warehouse model using a loop statement using the three-dimensional BIM model, the cutting plane of the horizontal plane and the cutting plane of the vertical plane as input includes:
[0015] 3.1) The input content of the cutting node is stored as a list IN, such that the three-dimensional BIM model is the first input item IN[0] in the list IN, and the cutting plane of the horizontal plane and the cutting plane of the vertical plane are the second input item IN[1] in the list IN;
[0016] 3.2) Assign the 3D BIM model Geometry to the first input item IN[0], the cutting plane pa to the second input item IN[1], and the list gs is empty;
[0017] 3.3) For each element i in the horizontal cutting plane and the vertical cutting plane pa, the following processing is performed: first, the element i is segmented for the three-dimensional BIM model Geometry to obtain the segmentation result g1, and then the second element g1[1] of the segmentation result g1 is assigned to the list gs, and the first element g1[0] of the segmentation result g1 is assigned to the three-dimensional BIM model Geometry. If an error occurs during the execution, the processing of jumping to the next element i is ignored;
[0018] 3.4) Output the elements in the list gs as the segmentation results OUT of the warehouse model.
[0019] Optionally, the cutting node pre-created in step 3) is a node defined by a Python script in Dynamo.
[0020] Optionally, step 4) calculating the engineering data of each compartment model in the BIM software refers to using the Solid.Volume and Topology.Faces nodes in the BIM software to calculate in real time the concrete engineering volume, compartment surface area, and control point coordinate data of each compartment in the segmentation result OUT of the compartment model.
[0021] In addition, the present invention also provides a system for rapid layering and block division of large-volume concrete for water conservancy and hydropower projects, comprising a microprocessor and a memory connected to each other, wherein the microprocessor is programmed or configured to execute the steps of the method for rapid layering and block division of large-volume concrete for water conservancy and hydropower projects, or the memory stores a computer program programmed or configured to execute the method for rapid layering and block division of large-volume concrete for water conservancy and hydropower projects.
[0022] In addition, the present invention also provides a computer-readable storage medium, in which a computer program programmed or configured to execute the method for rapid layering and block division of large-volume concrete in water conservancy and hydropower projects is stored.
[0023] Compared with the prior art, the present invention has the following advantages:
[0024] 1. The present invention is a further optimization of the existing traditional three-dimensional modeling of large-volume concrete of hydraulic engineering projects, which allows a large amount of regular and repetitive work to be completed by computers. It has high speed and accuracy, greatly reduces the time for workers to manually calculate according to two-dimensional drawings, reduces management costs, improves efficiency, ensures project quality, etc., has significant direct economic benefits, and has significant advantages in the application of large-volume concrete stratification and block division.
[0025] 2. If the subsequent design modifies the layered and block information of the project, the task can be completed quickly by simply replacing the layered and block data accordingly, thus saving a lot of time for the staff. BRIEF DESCRIPTION OF THE DRAWINGS
[0026] Figure 1 The following is a basic flow chart of the method according to the embodiment of the present invention.
[0027] Figure 2 It is a schematic diagram of a three-dimensional model of an overflow dam of a water conservancy and hydropower project in an embodiment of the present invention.
[0028] Figure 3 Schematic diagram of the implementation of importing a three-dimensional BIM model in an embodiment of the present invention.
[0029] Figure 4 Schematic diagram of importing Excel data files in an embodiment of the present invention.
[0030] Figure 5 The diagram is a schematic diagram of creating a horizontal cutting plane and a vertical cutting plane in an embodiment of the present invention.
[0031] Figure 6 It is a schematic diagram of the implementation of the automatic cutting to obtain the warehouse model in an embodiment of the present invention.
[0032] Figure 7 This is an example of a loop statement code for cutting nodes in an embodiment of the present invention. DETAILED DESCRIPTION
[0033] The present invention will be further described in detail below with reference to the accompanying drawings and specific embodiments.
[0034] like Figure 1 As shown, the method for rapid stratification and block division of large-volume concrete in water conservancy and hydropower projects in this embodiment includes:
[0035] 1) Import the 3D BIM model of mass concrete and the layered and block data into the BIM software;
[0036] 2) Create horizontal and vertical cutting planes in BIM software based on the 3D BIM model and layered block data;
[0037] 3) Execute a pre-created cutting node in the BIM software, wherein the cutting node takes the three-dimensional BIM model, the horizontal cutting plane and the vertical cutting plane as input, and uses a loop statement to automatically cut and obtain a compartment model;
[0038] 4) Calculate the engineering data of each sub-compartment model in the BIM software.
[0039] Figure 2 The three-dimensional model example of the large-volume concrete in this embodiment (a water conservancy and hydropower project overflow dam) is shown below. Figure 2 Taking this as an example, the method for rapid layering and block division of large volume concrete in water conservancy and hydropower projects in this embodiment is further described in detail.
[0040] In this embodiment, before step 1), the steps of creating a three-dimensional BIM model of the mass concrete according to the two-dimensional construction drawings of the mass concrete and exporting the three-dimensional BIM model of the mass concrete are also included.
[0041] In this embodiment, after creating the three-dimensional BIM model of the mass concrete and before exporting the three-dimensional BIM model of the mass concrete, the step of extracting internal holes, corridors, metal joints and post-cast strips from the three-dimensional BIM model of the mass concrete is also included.
[0042] In this embodiment, the 3D BIM model of the mass concrete is exported as a SAT model file, such as Figure 3 As shown, in step 1), importing the three-dimensional BIM model of mass concrete into the BIM software means first using the File Path and File.FromPath nodes of the BIM software to pick up the SAT model file of the three-dimensional BIM model of mass concrete on the specified path, and then using the Geometry.ImportFromSAT node of the BIM software to extract the three-dimensional BIM model of mass concrete in the SAT model file.
[0043] In this embodiment, the layered and block data of the mass concrete imported into the BIM software in step 1) is an Excel data file. Figure 4 As shown, first use the File Path and File.FromPath nodes of the BIM software to pick up the Excel data file on the specified path, and then use the Data.ImportExcel node of the BIM software to extract data, including layer height, longitudinal seam width, warehouse surface name and other information. When preparing layered and block data, you need to manually extract the layered and block data into an Excel table, use formula links when extracting, and check whether the data is accurate after the extraction is completed.
[0044] like Figure 5 As shown, in step 2), creating a horizontal cutting plane and a vertical cutting plane in the BIM software according to the three-dimensional BIM model and the layered block data includes: creating a coordinate point with the layer width value in the layered block data as the X value and the layer height value as the Z value, and using the node Plane.ByOriginNormal to create a horizontal cutting plane and a vertical cutting plane at the coordinate point respectively.
[0045] like Figure 6 As shown, the cutting node pre-created in step 3) takes the three-dimensional BIM model, the cutting plane of the horizontal plane and the cutting plane of the vertical plane as input, and uses a loop statement to automatically cut to obtain a compartment model (the Solid list in the figure is a plurality of compartment models). The steps of using a loop statement to automatically cut the cutting node pre-created in step 3) of this embodiment to obtain a compartment model by using a three-dimensional BIM model, the cutting plane of the horizontal plane and the cutting plane of the vertical plane as input include:
[0046] 3.1) The input content of the cutting node is stored as a list IN, so that the 3D BIM model is the first input item IN[0] in the list IN, and the cutting plane of the horizontal plane and the cutting plane of the vertical plane are the second input item IN[1] in the list IN; see Figure 7 In line 4, Figure 7 The first line imports the clr library, the second line adds the parameter 'ProtoGeometry' to the clr library, and the third line imports all libraries of Autodesk.DesignScript.Geometry.
[0047] 3.2) Assign the 3D BIM model Geometry to the first input item IN[0], the cutting plane pa to the second input item IN[1], and the list gs is empty; see Figure 7 Lines 5 to 7 in
[0048] 3.3) For each element i (hierarchical block information such as elevation and pile number) in the horizontal cutting plane and the vertical cutting plane pa, the following processing is performed: first, the element i of the three-dimensional BIM model Geometry is segmented to obtain the segmentation result g1, and then the second element g1[1] of the segmentation result g1 is assigned to the list gs, and the first element g1[0] of the segmentation result g1 is assigned to the three-dimensional BIM model Geometry. If an error occurs during the execution, the processing of jumping to the next element i is ignored (see the pass statement in line 14 of the body); see Figure 7 Lines 8 to 14 in
[0049] 3.4) Output the elements in the list gs as the segmentation results OUT of the warehouse model, see Figure 7 Line 15 of the table.
[0050] In BIM software, to divide the model into layers and blocks, it is necessary to repeatedly use the cutting command to cut the model, generate the model of each warehouse in the form of a family, and then assemble all the warehouse surfaces as a whole, which is time-consuming and labor-intensive, and the precision is not high. In this embodiment, the cutting node pre-created in step 3) is a node defined by the Python script in Dynamo. The role of the cutting node is to use a loop statement to formulate a program that cuts the model with a cutting plane in turn and outputs the model group after cutting, which can achieve quick, convenient and high-precision warehouse division. The computer will automatically run the cutting node program to quickly cut the model.
[0051] In this embodiment, step 4) calculating the engineering data of each compartment model in the BIM software refers to using the Solid.Volume and Topology.Faces nodes in the BIM software to calculate in real time the concrete engineering volume, compartment surface area, and control point coordinate data of each compartment in the segmentation result OUT of the compartment model.
[0052] In summary, the method for rapid stratification and block division of large-volume concrete for water conservancy and hydropower projects in this embodiment is further optimized on the basis of the existing traditional three-dimensional modeling of large-volume concrete for hydraulic engineering projects, and a large amount of regular and repetitive work is handed over to the computer to complete, with fast speed and high accuracy, which greatly reduces the time for manual calculations by staff according to two-dimensional drawings, reduces management costs, improves efficiency, ensures project quality, etc., has significant direct economic benefits, and has significant application advantages in the stratification and block division of large-volume concrete. The method for rapid stratification and block division of large-volume concrete for water conservancy and hydropower projects in this embodiment has the advantages of fast speed, high accuracy, and dynamic modification. If the subsequent design modifies the stratification and block information of the project, it only needs to replace the data in the Excel table accordingly, and it can be completed quickly, which can save a lot of time for the staff.
[0053] In addition, this embodiment also provides a system for rapid layering and block division of large-volume concrete for water conservancy and hydropower projects, comprising an interconnected microprocessor and a memory, wherein the microprocessor is programmed or configured to execute the steps of the aforementioned method for rapid layering and block division of large-volume concrete for water conservancy and hydropower projects, or the memory stores a computer program programmed or configured to execute the aforementioned method for rapid layering and block division of large-volume concrete for water conservancy and hydropower projects.
[0054] In addition, this embodiment also provides a computer-readable storage medium, in which a computer program programmed or configured to execute the aforementioned method for rapid layering and block division of large-volume concrete in water conservancy and hydropower projects is stored.
[0055] Those skilled in the art will appreciate that the embodiments of the present application may be provided as methods, systems, or computer program products. Therefore, the present application may take the form of a complete hardware embodiment, a complete software embodiment, or an embodiment combining software and hardware. Moreover, the present application may take the form of a computer program product implemented on one or more computer-readable storage media (including but not limited to disk storage, CD-ROM, optical storage, etc.) containing computer-usable program codes. The present application is described with reference to the flowcharts and / or block diagrams of the methods, devices (systems), and computer program products according to the embodiments of the present application. It should be understood that each process and / or box in the flowchart and / or block diagram, as well as the combination of the processes and / or boxes in the flowchart and / or block diagram, may be implemented by computer program instructions. These computer program instructions may be provided to a processor of a general-purpose computer, a special-purpose computer, an embedded processor, or other programmable data processing device to produce a machine, so that the instructions executed by the processor of the computer or other programmable data processing device generate instructions for implementing the functions in the process. Figure 1 A process or multiple processes and / or boxes Figure 1 These computer program instructions can also be stored in a computer-readable memory that can guide a computer or other programmable data processing device to work in a specific way, so that the instructions stored in the computer-readable memory produce a product including an instruction device, which implements the functions specified in the process. Figure 1 A process or multiple processes and / or boxes Figure 1 These computer program instructions can also be loaded onto a computer or other programmable data processing device, so that a series of operation steps are executed on the computer or other programmable device to produce a computer-implemented process, so that the instructions executed on the computer or other programmable device provide for implementing the process in the process. Figure 1 A process or multiple processes and / or boxes Figure 1 The steps for the functions specified in one or more boxes.
[0056] The above is only a preferred embodiment of the present invention, and the protection scope of the present invention is not limited to the above embodiments. All technical solutions under the concept of the present invention belong to the protection scope of the present invention. It should be pointed out that for ordinary technicians in this technical field, some improvements and modifications without departing from the principle of the present invention should also be regarded as the protection scope of the present invention.
Claims
1. A method for rapid stratification and block division of large-volume concrete in water conservancy and hydropower projects. It is characterized in that include: 1) Import the 3D BIM model of mass concrete and the layered and block data into the BIM software; 2) Create horizontal and vertical cutting planes in BIM software based on the 3D BIM model and hierarchical block data; 3) Execute the pre-created cutting node in the BIM software. The cutting node takes the three-dimensional BIM model, the horizontal cutting plane and the vertical cutting plane as input, and uses a loop statement to automatically cut and obtain the compartment model; 4) Calculate the engineering data of each sub-compartment model in the BIM software; The cutting node pre-created in step 3) takes the three-dimensional BIM model, the horizontal cutting plane and the vertical cutting plane as input, and the steps of automatically cutting to obtain the compartment model by using the loop statement include: 3.1) The input content of the cutting node is stored as a list IN, such that the 3D BIM model is the first input item IN[0] in the list IN, and the cutting plane of the horizontal plane and the cutting plane of the vertical plane are the second input item IN[1] in the list IN; 3.2) Assign the 3D BIM model Geometry to the first input item IN[0], the cutting plane pa to the second input item IN[1], and the list gs is empty; 3.3) For each element i in the horizontal cutting plane and the vertical cutting plane pa, the following processing is performed: first, the element i is segmented for the three-dimensional BIM model Geometry to obtain the segmentation result g1, and then the second element g1[1] of the segmentation result g1 is assigned to the list gs, and the first element g1[0] of the segmentation result g1 is assigned to the three-dimensional BIM model Geometry. If an error occurs during the execution, the processing of jumping to the next element i is ignored; 3.4) Output the elements in the list gs as the segmentation results OUT of the warehouse model.
2. The method for rapid stratification and block division of large-volume concrete in water conservancy and hydropower engineering according to claim 1, It is characterized in that Step 1) also includes the steps of creating a three-dimensional BIM model of the mass concrete according to the two-dimensional construction drawings of the mass concrete, and exporting the three-dimensional BIM model of the mass concrete.
3. The method for rapid stratification and block division of large-volume concrete in water conservancy and hydropower engineering according to claim 2, It is characterized in that After the three-dimensional BIM model of the mass concrete is created and before the three-dimensional BIM model of the mass concrete is exported, the step of extracting internal holes, corridors, metal joints and post-cast strips from the three-dimensional BIM model of the mass concrete is also included.
4. The method for rapid stratification and block division of large-volume concrete in water conservancy and hydropower engineering according to claim 2, It is characterized in that The exported three-dimensional BIM model of the mass concrete is a SAT model file. In step 1), importing the three-dimensional BIM model of the mass concrete into the BIM software means first using the File Path and File.FromPath nodes of the BIM software to pick up the SAT model file of the three-dimensional BIM model of the mass concrete on the specified path, and then using the Geometry.ImportFromSAT node of the BIM software to extract the three-dimensional BIM model of the mass concrete in the SAT model file.
5. The method for rapid stratification and block division of large-volume concrete in water conservancy and hydropower engineering according to claim 1, It is characterized in that In step 1), the layered and block data of the mass concrete are imported into the BIM software as an Excel data file.
6. The method for rapid stratification and block division of large-volume concrete in water conservancy and hydropower engineering according to claim 1, It is characterized in that The cut nodes pre-created in step 3) are nodes defined by the Python script in Dynamo.
7. The method for rapid stratification and block division of large-volume concrete in water conservancy and hydropower engineering according to claim 6, It is characterized in that Step 4) Calculating the engineering data of each compartment model in the BIM software refers to using the Solid.Volume and Topology.Faces nodes in the BIM software to calculate the concrete engineering volume, compartment surface area, and control point coordinate data of each compartment in the segmentation result OUT of the compartment model in real time.
8. A system for rapid stratification and block division of large-volume concrete in water conservancy and hydropower engineering, comprising an interconnected microprocessor and a memory, It is characterized in that The microprocessor is programmed or configured to execute the steps of the method for rapid layering and block division of large-volume concrete for water conservancy and hydropower projects as described in any one of claims 1 to 7, or the memory stores a computer program that is programmed or configured to execute the method for rapid layering and block division of large-volume concrete for water conservancy and hydropower projects as described in any one of claims 1 to 7.
9. A computer-readable storage medium, It is characterized in that The computer-readable storage medium stores a computer program programmed or configured to execute the method for rapid layering and block division of large-volume concrete for water conservancy and hydropower projects as described in any one of claims 1 to 7.
Citation Information
Patent Citations
Method for BIM assisted dam cabin surface designing
CN106326588A
Method and system for rapidly calculating engineering quantity of any part of mass concrete in water conservancy and hydropower engineering and medium
CN110992475A