Isotope sample purification and collection preparation system and method and application thereof

By designing an isotope sample purification and collection preparation system, the problem of interfering ions in methane binary isotope detection has been solved, and high-precision isotope detection has been achieved. It is suitable for samples of different magnitudes and meets the detection needs of oil, gas and rare samples. .

CN112629985BActive Publication Date: 2024-10-29NORTHWEST INST OF ECO ENVIRONMENT & RESOURCES CAS
View PDF 1 Cites 0 Cited by

Patent Information

Application Number
CN201910920116.X
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2019-09-26
Publication Date
2024-10-29
Estimated Expiration
2039-09-26

AI Technical Summary

Technical Problem

The problem of existing isotope samples requiring higher purity in mass spectrometry detection, especially the detection of binary isotopes of methane, is the presence of interfering ion interference, and the existing system cannot meet the requirements for the detection of large quantities of oil and gas and small quantities of rare samples at the same time. need.

Method used

An isotope sample purification and collection preparation system is designed, including a sampling unit, VOC trap, adsorption trap group, liquid nitrogen cold trap, liquid nitrogen enrichment trap, chromatographic column and purification and re-enrichment trap. Through multi-stage impurity removal and The enrichment process realizes the purification and collection of samples and is suitable for methane 13C-D isotope detection. It provides two methods of syringe sampling and cylinder injection.

Benefits of technology

It achieves high-precision detection of methane binary isotopes, with internal and external accuracy reaching 0.3‰ and 2.5‰. It is also suitable for samples of different magnitudes, improving the accuracy and applicability of detection.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN112629985B_ABST
    Figure CN112629985B_ABST
Patent Text Reader

Abstract

The present invention discloses an isotope sample purification and collection preparation system and method thereof. The purification and collection preparation system comprises a sample injection unit, a VOC trap, an adsorption trap group, a liquid nitrogen cold trap, a liquid nitrogen enrichment trap, a chromatographic column, a purification and re-enrichment trap and a sample collection tube which are sequentially connected through pipelines. The purification and collection preparation method comprises the following steps: 1. Purification and enrichment process: Step 1, the sample is introduced through the sample injection unit, and the gas sample sequentially enters the VOC trap to remove water and VOC components; Step 2, the carrier gas introduced into the second carrier gas supply pipeline sends the sample in the liquid nitrogen enrichment trap into the chromatographic column GC, and separation is performed in the chromatographic column GC according to different retention times. 2. Transfer, re-enrichment and collection process: Step 1, cut off the pipeline connecting the purification and re-enrichment trap and the chromatographic column, and the carrier gas introduced into the third carrier gas supply pipeline passes through the purification and re-enrichment trap and its connecting pipeline, and is discharged from the sample discharge pipeline; the purification and re-enrichment trap and the sample collection tube and their connecting pipeline are evacuated through the vacuum pipeline to discharge impurity gases and carrier gas; the target gas enriched in the purification and re-enrichment trap is diffused into the sample collection tube.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of isotope detection, and in particular to an isotope sample purification and collection preparation system and a method and application thereof. Background Art

[0002] The development of isotope theory and mass spectrometers from the determination of one-element one-dimensional to one-element multi-dimensional isotopes has become a milestone in the method of single-element stable isotope systems and has been applied to explore many disciplines such as astrochemistry and geochemistry, geology and biology. At the beginning of this century, a new perspective on isotope research, "cluster isotope geochemistry", was introduced. It studies the geochemical behavior of "isotopologues" from the perspective of mutual combination of isotopes, and can obtain information that traditional isotope studies cannot provide for overall composition. It is a revolutionary technology with great potential after traditional stable isotopes. In particular, the advent of MAT 253-Ultra (Thermo Fisher) and Panoroma (Nu instruments) analysis equipment has enabled isotope analysis technology to advance from the determination of simple molecules to the analysis of molecular isotopes, such as the determination of molecular cluster isotope ratios and molecular special sites.

[0003] However, even the most advanced mass spectrometers must use various methods to prepare or convert the original sample (inorganic substances or complex organic substances) into pure gases such as N 2 , O 2 , H 2 , CO 2 、SO 2 、N 2 O、CH 4 The samples can then be tested by mass spectrometry for isotope detection. Therefore, sample pretreatment technology and supporting pretreatment devices are the key to successful mass spectrometry detection. In addition to the complex impurity removal process, the acquisition of pure gas also requires the enrichment and separation of trace gases, as well as the collection and conversion of target gases.

[0004] The collection of samples from different sources and different target gases corresponds to different pre-treatment methods. 13 CH 3 D and 12 CH 2 D 2 ) analysis technology has become an important detection method for natural gas research after carbonate. The detection technology of methane binary isotopes is mainly aimed at the two isotopes with a mass-to-charge ratio of 18 in methane isotopes ( 13 CH 3 D and 12 CH 2 D 2) for detection. Since these two isotopologues of methane have two heavy isotope substitutions (also called cluster isotopes), their relative abundances are very low (6.92*10 -6 and 1.44*10 -7 ), to accurately obtain its abundance, the mass spectrometer is first required to have extremely high sensitivity and precision; at the same time, the sample must be of extremely high purity to avoid any interference from other substances to obtain a good mass spectrometry separation effect.

[0005] At present, large-scale high-resolution double-focusing stable isotope mass spectrometers have already achieved very high resolution, such as MAT253Ultra (Thermo Scientific) and Panorama (NU), the former has a resolution of up to 27000, which can be used to analyze the isotopes in methane clusters. 13 CH 3 D and 12 CH 2 D 2 The total concentration of methane (expressed as Δ18) can be tested; the latter has a resolution of 40,000 and can be used to measure the total concentration of methane binary isotopes. 13 CH 3 D and 12 CH 2 D 2 The concentrations of methane were tested separately. 13 CH 3 D and 12 CH 2 D 2 The molecular weight integer is 18amu. After the methane sample enters the mass spectrometer and is ionized, each atom in the ion source will combine into corresponding ions with a certain probability. If there are water molecules, oxygen atoms (derived from oxygen and oxygen-containing compounds), nitrogen atoms (derived from nitrogen and nitrogen-containing compounds), hydrogen atoms other than methane (which will combine with carbon, nitrogen, and oxygen atoms to form interfering ions), carbon atoms other than methane, and argon atoms (isotopes) in the sample, the methane sample will be ionized. 36 Ar doubly charged ions) and other components with a mass number of about 18 amu will seriously interfere with the binary isotopes of methane. 13 CH 3 D and 12 CH 2 D 2 Accurately test gas purity.

[0006] Since the relative abundance of methane cluster isotope molecules is very low and there is much interference from other substances, accurate determination is a very challenging task. Currently, Imperial College London and Protium have developed an automatic purification system (Imperial Batch Extraction, IBEX,). The main working principle of this system is to use an ultra-low temperature helium refrigeration pump to remove H from methane in a liquid helium environment with a temperature range of 10K to 320K. 2 , He, CO 2 , O 2 , N 2 The impurity gas is then released by heating the frozen methane, and the methane is transferred to a sample tube filled with 5A molecular sieves with liquid nitrogen for burning, and then heated and released to complete the measurement on the mass spectrometer. The liquid helium refrigeration pump used in this system is expensive to maintain; and this system has not yet achieved commercial production; in addition, this system only gives one indicator after methane purification: the internal accuracy of Δ18 is 0.4‰.

[0007] In addition, for different amounts of samples, the injection and collection processes have different requirements. For large amounts of samples (such as oil and natural gas) and small amounts of samples (such as rare samples collected in cold regions (Antarctica or the Arctic)), it is necessary to distinguish between the injection method and the collection method. The existing purification and collection preparation systems cannot meet the needs of both at the same time.

[0008] Therefore, it is necessary to establish a sample purification and collection preparation system for binary isotope detection to ensure that all possible interfering ions are removed before the sample gas enters the mass spectrometer analysis, to enrich rare samples, and to achieve accurate detection of isotope compounds. It can also be applied to methane binary isotopes. 13 CH 3 D and 12 CH 2 D 2 Testing underway. Summary of the invention

[0009] The purpose of the present invention is to provide an isotope sample purification and collection preparation system in view of the problem that isotope samples in the prior art need higher purity in mass spectrometry detection, and the corresponding isotope purification and enrichment device and the isotope mass spectrometer are connected online. For small samples, the samples can be injected through a syringe injection unit, and then enriched after passing through GC. After enrichment in a sample bottle, the sample bottle enters the mass spectrometer for analysis. After enrichment, the sample can be inspected in batches. When necessary, the sample bottle can be inserted into the mass spectrometer. For large samples, the samples can be injected through a natural gas sample cylinder, and then directly enter the mass spectrometer for analysis after passing through GC.

[0010] Another object of the present invention is to provide an application of the isotope sample purification and collection preparation system in isotope detection, which can complete the detection of methane 13 CD( 13 CH 3 D. 13 CH 2 D 2 , 13 CHD 3 , 13 CD 4 ) isotope detection provides technical support for oil exploration, deep-earth resource exploration, global climate change, and water resource evaluation. It can also be applied to the purification and collection of other types of isotopes, and use this technology to expand cluster isotope monitoring of various greenhouse gases in the three polar regions (Antarctica, the Arctic, and the Qinghai-Tibet Plateau).

[0011] Another object of the present invention is to provide a method for purifying and collecting isotope samples. The method can be used to purify methane to achieve the main technical indicators of methane internal accuracy: the internal accuracy of Δ18 is 0.3‰, the internal accuracy of Δ13CH3D is 0.4‰, and the external accuracy of methane: Δ18 is 2‰, and Δ13CH3D is 2.5‰.

[0012] The technical solution adopted to achieve the purpose of the present invention is:

[0013] An isotope sample purification and collection preparation system comprises a sampling unit, a VOC trap, an adsorption trap group, a liquid nitrogen cold trap, a liquid nitrogen enrichment trap, a chromatographic column, a purification and re-enrichment trap and a sample collection tube which are sequentially connected through pipelines, wherein:

[0014] The inlet of the VOC trap is connected to a first carrier gas supply pipeline, and the outlet is connected to a discharge pipeline to discharge the chilled water and VOC components in the VOC trap;

[0015] A carrier gas purge pipeline is provided on the pipeline connecting the adsorption trap group and the liquid nitrogen cold trap, wherein the carrier gas purge pipeline includes a zero carrier gas supply pipeline that provides carrier gas to the inlet of the adsorption trap group and an impurity gas discharge pipeline connected to the outlet of the liquid nitrogen cold trap;

[0016] The outlet of the liquid nitrogen enrichment trap is connected to a permanent gas discharge pipe to discharge permanent gases (such as nitrogen, oxygen, hydrogen, argon and other gas components) that cannot be condensed in the liquid nitrogen enrichment trap;

[0017] The inlet of the liquid nitrogen enrichment trap is connected to a second carrier gas supply pipeline. During sampling, the carrier gas introduced into the second carrier gas supply pipeline delivers the sample enriched in the liquid nitrogen enrichment trap to the inlet of the chromatographic column. The outlet of the chromatographic column is respectively connected to a heavy gas discharge pipeline and a purification and re-enrichment trap. The heavy gas discharge pipeline is used to discharge impurity gases whose retention time is later than that of the target gas. For example, after methane is purified, the retention time of ethane and ethylene that may be mixed in methane is later than that of methane. After the extraction of methane is completed, the others are discharged through the heavy gas discharge pipeline.

[0018] The inlet of the purification and re-enrichment trap is connected to a third carrier gas supply pipeline, and the outlet of the purification and re-enrichment trap is respectively connected to a sample collection tube and a sample discharge pipeline. The sample collection tube is located in the sample collection trap, and the outlet of the sample collection tube is connected to a vacuum pipeline for removing impurity gases and carrier gas.

[0019] In the above technical solution, the zero carrier gas supply pipeline is connected to the inlet of the adsorption trap group, or the zero carrier gas supply pipeline is connected to the injection unit, and the injection unit is connected to the inlet of the adsorption trap group through a pipeline.

[0020] In the above technical solution, the sampling unit is a syringe sampling unit and / or a steel bottle sampling unit.

[0021] In the above technical solution, the syringe injection unit includes an injection injector connected to the VOC trap through a pipeline, and the zero carrier gas supply pipeline is connected to the injection injector; the cylinder injection unit includes a natural gas sample cylinder connected to the VOC trap through a connecting pipeline, and a cylinder pressure reducing gauge is provided on the connecting pipeline.

[0022] In the above technical solution, the adsorption trap group includes at least a CO oxidation trap and an acid gas adsorption trap.

[0023] In the above technical solution, a verification enrichment trap is provided on the pipeline between the liquid nitrogen enrichment trap and the chromatographic column to verify whether the sample in the liquid nitrogen enrichment trap is completely enriched. In particular, for unknown samples to be tested, the verification enrichment trap can be used to verify whether the length of the pipeline connected to the liquid nitrogen cold trap and the liquid nitrogen enrichment trap in the early stage and the carrier gas flow rate match, and timely adjust them until it is verified that no methane target gas is released in the enrichment trap, indicating that the parameters set for the liquid nitrogen cold trap and the liquid nitrogen enrichment trap are reasonable.

[0024] In the above technical solution, the vacuum pipeline includes a primary vacuum pipeline connected to the dry pump and a secondary vacuum pipeline connected to the molecular pump.

[0025] In another aspect of the present invention, the isotope sample purification and collection preparation system is in methane 13 CD( 13 CH3 D. 13 CH 2 D 2 , 13 CHD 3 , 13 CD 4 )Application in isotope detection.

[0026] In another aspect of the present invention, the purification and collection method of the isotope sample purification and collection preparation system comprises the following steps:

[0027] 1. Purification and enrichment process:

[0028] Step 1: The sample is introduced through the sampling unit, and the gas sample enters the VOC trap to remove water and VOC components, enters the adsorption trap group to remove impurities, enters the liquid nitrogen cold trap to remove impurities with a boiling point higher than the target gas, and finally enters the liquid nitrogen enrichment trap for enrichment. Other non-condensable impurity gases are discharged through the permanent gas discharge pipe;

[0029] Step 2, the carrier gas introduced into the second carrier gas supply pipeline sends the sample in the liquid nitrogen enrichment trap into the chromatographic column GC, and is separated in the chromatographic column GC according to the difference in retention time. After separation, the target gas is enriched in the purification and re-enrichment trap, and impurities other than the target gas are discharged through the heavy gas discharge pipeline.

[0030] 2. Transfer, enrichment and collection process:

[0031] Step 1, cutting off the pipeline connecting the purification and re-enrichment trap and the chromatographic column, the carrier gas introduced into the third carrier gas supply pipeline passes through the purification and re-enrichment trap and its connecting pipeline, and then is discharged from the sample discharge pipeline to purge the pipeline;

[0032] Step 2, evacuating the purification and re-enrichment trap and the sample collection tube and their connecting pipelines through a vacuum pipeline to discharge impurity gases and carrier gas;

[0033] Step 3, purify and diffuse the target gas enriched in the re-enrichment trap into the sample collection tube.

[0034] In the above technical solution, in step 1 of the transfer-re-enrichment collection process, the third carrier gas completes the complete transfer and enrichment of the target gas while purging the pipeline, and stores it in the purification-re-enrichment trap.

[0035] In the above technical solution, when the purification and re-enrichment trap and the connecting pipeline of the sample collection tube are evacuated, the impurity gas is firstly evacuated by a dry pump, and then the carrier gas is evacuated by a molecular pump.

[0036] In the above technical solution, during or after the transfer, re-enrichment and collection process, the pipeline before the chromatographic column can be cleaned, including:

[0037] (1) VOC trap function recovery: the temperature of the VOC trap T1 is increased, carrier gas is introduced into the first carrier gas supply pipeline, and the water and VOC components remaining in the VOC trap are discharged through the discharge pipeline;

[0038] (2) Purging of the adsorption trap group and liquid nitrogen cold trap: The carrier gas is introduced into the zero carrier gas supply pipeline, passes through the adsorption trap group and liquid nitrogen cold trap, and is discharged from the impurity gas discharge pipeline;

[0039] An isotope sample purification and collection preparation system comprises a sample injection unit, a first conversion valve (ValcoB), a VOC trap, an adsorption trap group, a liquid nitrogen cold trap, a second conversion valve (ValcoC), a chromatographic column, a third conversion valve (ValcoD) and a purification and re-enrichment trap, wherein:

[0040] The sampling unit is connected with a zero carrier gas supply pipeline;

[0041] The port of the first conversion valve is connected to the sampling pipeline, the sampling port of the VOC trap, the sampling outlet of the VOC trap, the sampling port of the adsorption trap group, the first carrier gas supply pipeline and the discharge pipeline through pipelines respectively, the sampling pipeline is connected to the sampling unit, when the first conversion valve is in a sampling state (load), the sampling pipeline, the VOC trap, and the sampling port of the adsorption trap group are connected in sequence, the first carrier gas supply pipeline is connected to the discharge pipeline, when the first conversion valve is in an injection state (inject), the sampling pipeline is connected to the adsorption trap group, the first carrier gas supply pipeline, the VOC trap and the discharge pipeline are connected in sequence, the first carrier gas supply pipeline is connected to the sampling port of the VOC trap, and the sampling outlet of the VOC trap is connected to the discharge pipeline;

[0042] The sample outlet of the adsorption trap group is connected to the sample inlet of the liquid nitrogen cold trap through a pipeline, and the port of the second conversion valve is respectively connected to the sample outlet of the liquid nitrogen cold trap, the sample inlet and sample outlet of the liquid nitrogen enrichment trap, the second carrier gas supply pipeline, the sample inlet of the chromatographic column and the impurity gas discharge pipeline through pipelines, wherein: when the second conversion valve is in a sampling state (load), the liquid nitrogen cold trap, the liquid nitrogen enrichment trap and the impurity gas discharge pipeline are connected in sequence, the sample inlet of the liquid nitrogen cold trap is connected to the sample outlet of the adsorption trap group, and the outlet of the liquid nitrogen cold trap is connected to the sample outlet of the adsorption trap group. The sample port is connected to the sample inlet of the liquid nitrogen enrichment trap, the sample outlet of the liquid nitrogen enrichment trap is connected to the impurity gas discharge pipe, the second carrier gas supply pipeline is connected to the sample inlet of the chromatographic column, when the second conversion valve is in the injection state (inject), the sample outlet of the liquid nitrogen cold trap is connected to the impurity gas discharge pipeline, the second carrier gas supply pipeline is connected to the liquid nitrogen enrichment trap and the sample inlet of the chromatographic column in sequence, the second carrier gas supply pipeline is connected to the sample inlet of the liquid nitrogen enrichment trap, and the sample outlet of the liquid nitrogen enrichment trap is connected to the sample inlet of the chromatographic column;

[0043] The port of the third conversion valve is respectively connected to the sample outlet of the chromatographic column, the sample inlet of the purification and re-enrichment trap, the third carrier gas supply pipeline and the heavy gas discharge pipeline through pipelines, wherein: when the third conversion valve is in a sampling state, the sample outlet of the chromatographic column is connected to the sample inlet of the purification and re-enrichment trap, the third carrier gas supply pipeline is connected to the heavy gas discharge pipeline, and when the third conversion valve is in an injection state, the sample outlet of the chromatographic column is connected to the heavy gas discharge pipeline, and the third carrier gas supply pipeline is connected to the sample inlet of the purification and re-enrichment trap;

[0044] The sample outlet of the purification and re-enrichment trap is connected to a sample discharge pipeline and a sample collection tube through pipelines, wherein the sample collection tube is located in a sample collection trap providing a low temperature environment, and a vacuum pipeline for removing carrier gas and impurities is connected to the sample collection tube.

[0045] In the above technical solution, the sampling unit includes an injection sampler, a natural gas sample cylinder and a conversion valve (ValcoA), wherein the port of the conversion valve is respectively connected to the sample outlet of the injection sampler, the sample outlet of the natural gas sample cylinder, the exhaust pipeline and the inlet of the first conversion valve through pipelines, when the conversion valve is in a sampling state (when the sample amount is small (load)), the sample outlet of the injection sampler is connected to the inlet of the injection pipeline (first conversion valve), and the sample outlet of the natural gas sample cylinder is connected to the exhaust pipeline, when the conversion valve is in an injection state (when the sample amount is large (inject)), the sample outlet of the natural gas sample cylinder is connected to the inlet of the injection pipeline (first conversion valve), and the sample outlet of the injection sampler is connected to the exhaust pipeline. In the above technical solution, the adsorption trap group includes at least a CO adsorption trap and an acid gas adsorption trap.

[0046] In the above technical solution, a verification enrichment trap is provided on the pipeline between the liquid nitrogen enrichment trap and the chromatographic column to verify whether the sample in the liquid nitrogen enrichment trap is completely enriched, the sample outlet of the liquid nitrogen enrichment trap is connected to the sample inlet of the verification enrichment trap, and the sample outlet of the verification enrichment trap is connected to the sample inlet of the liquid nitrogen enrichment trap.

[0047] In the above technical solution, the vacuum pipeline includes a primary vacuum pipeline connected to a dry pump and a secondary vacuum pipeline connected to a molecular pump to remove impurities and carrier gas in the pipeline.

[0048] In another aspect of the present invention, the isotope sample purification and collection preparation system is in methane 13 CD( 13 CH 3 D. 13 CH 2 D 2 ,13 CHD 3 , 13 CD 4 )Application in isotope detection.

[0049] Another aspect of the present invention also includes that the purification and collection method of the isotope sample purification and collection preparation system comprises the following steps:

[0050] 1. Purification and enrichment process:

[0051] Step 1: The first conversion valve and the second conversion valve are in the sampling state, and the gas sample enters the VOC trap in turn to remove water and VOC components; enters the adsorption trap group to remove impurities, enters the liquid nitrogen cold trap to remove impurities with a boiling point higher than the target gas, and finally enters the liquid nitrogen enrichment trap for enrichment, and other non-condensable impurity gases are discharged through the permanent gas discharge pipeline;

[0052] Step 2, the second conversion valve is in the injection state, the carrier gas introduced into the second carrier gas supply pipeline sends the sample in the liquid nitrogen enrichment trap into the chromatographic column GC, and the gas is separated in the chromatographic column GC according to the different retention times of different component gases. When the target gas flows out, the third conversion valve is in the sampling state, and the target gas after separation is enriched in the purification and re-enrichment trap. When the heavy gas with a retention time after the target gas flows out, the third conversion valve is in the injection state and discharged through the heavy gas discharge pipeline.

[0053] 2. Transfer, enrichment and collection process:

[0054] The third conversion valve is in the injection state:

[0055] Step 1, the carrier gas introduced into the third carrier gas supply pipeline passes through the purification re-enrichment trap and its connecting pipeline, and then is discharged from the sample discharge pipeline to purge the purification re-enrichment trap and its connecting pipeline;

[0056] Step 2, evacuating the purification and re-enrichment trap and the sample collection tube and their connecting pipelines through a vacuum pipeline to discharge impurity gases and carrier gas;

[0057] Step 3, purify and diffuse the target gas enriched in the re-enrichment trap into the sample collection tube.

[0058] In the above technical solution, in step 1 of the transfer-re-enrichment collection process, the third carrier gas completes the complete transfer and enrichment of the target gas while purging the pipeline, and stores it in the purification-re-enrichment trap.

[0059] In the above technical solution, when the purification and re-enrichment trap and the connecting pipeline of the sample collection tube are evacuated, the impurity gas is first evacuated by a dry pump, and then the impurity gas and the carrier gas are evacuated by a molecular pump.

[0060] The above technical solution also includes a pipeline cleaning method:

[0061] (1) The first conversion valve is in the injection state: carrier gas is introduced into the first carrier gas supply pipeline, and the water and VOC components remaining in the VOC trap T1 are discharged through the discharge pipeline;

[0062] (2) The first conversion valve is in the sampling state: the carrier gas is introduced into the zero carrier gas supply pipeline, and the impurities remaining in the adsorption trap group, the liquid nitrogen cold trap, and the liquid nitrogen enrichment trap are discharged from the impurity gas discharge pipeline;

[0063] An isotope sample purification and collection preparation system includes a two-position four-way valve A, a two-position six-way valve B, a two-position six-way valve C, a two-position four-way valve D, a VOC trap T1, an adsorption trap T2, an adsorption trap T3, a chemical trap T4, a liquid nitrogen cold trap T5, a liquid nitrogen enrichment trap T6, a verification enrichment trap T7, a purification and re-enrichment trap T8, and a sample collection trap T9, wherein:

[0064] The two-position four-way valve A has four hole positions a1, a2, a3, and a4, wherein a2 is connected to a natural gas sample cylinder through a connecting pipe, a4 is connected to an injection injector through a pipe, a GC injection port is provided on the injection injector, a zero carrier gas input pipe is provided on the injection injector, and a1 is connected to an exhaust pipeline;

[0065] The two-position six-way valve B has six hole positions, namely, b1, b2, b3, b4, b5 and b6; b2 is connected to a3 through a pipeline; b3 is connected to the inlet of the VOC trap T1 through a pipeline; the outlet of the VOC trap T1 is connected to b6 through a pipeline; b1 is connected to the inlet of the liquid nitrogen cold trap T5 through an impurity removal pipeline; the impurity removal pipeline is sequentially connected to an adsorption trap T2, an adsorption trap T3 and a chemical trap T4; b4 is connected to a first load gas input pipeline; and b5 is connected to a discharge pipeline;

[0066] The two-position six-way valve C has six hole positions, namely c1, c2, c3, c4, c5 and c6; the outlet of the liquid nitrogen cold trap T5 is connected to the c2 through a pipeline; the c3 is connected to the inlet of the liquid nitrogen enrichment trap T6 through a pipeline; the outlet of the liquid nitrogen enrichment trap T6 is connected to the inlet of the verification enrichment trap T7 through a pipeline; the outlet of the verification enrichment trap T7 is connected to the c6 through a pipeline; the c1 is connected to the impurity gas discharge pipeline; the c4 is connected to the second load gas input pipeline; and the c5 is connected to the inlet of the chromatographic column GC8 through a pipeline;

[0067] The two-position four-way valve D has four hole positions, d1, d2, d3, and d4. The d1 is connected to the outlet of the chromatographic column GC through a pipeline, the d2 is connected to the inlet of the purification and re-enrichment trap T8 through an enrichment pipeline, the d3 is connected to the third load gas input pipeline, and the d4 is connected to the heavy gas discharge pipe. The enrichment pipeline is provided with a switch valve V1, the outlet of the purification and re-enrichment trap T8 is connected to the inlet of the sample collection trap T9 through a pipeline, and the sample collection trap T9 is respectively connected to the sample discharge pipeline and the collection pipeline through a connecting pipeline, wherein the connecting pipeline is provided with a switch valve V2, the sample discharge pipeline is provided with a switch valve V3, and the collection pipeline is provided with a switch valve V4. The collection pipeline is respectively connected to the vacuum branch pipe and the collection branch pipe, the vacuum branch pipe is connected to a vacuum source, and the collection branch pipe is provided with a switch valve V5 and a switch valve V10. The end of the collection branch pipe is connected to a sample collection pipe, and the sample collection pipe is located in the sample collection trap.

[0068] In the above technical scheme, the low vacuum gauge P1 is connected to the vacuum branch pipe through a first connecting pipe, and a switch valve V8 is provided on the first connecting pipe. The dry pump is connected to the vacuum branch pipe through a second connecting pipe, and a switch valve V6 is provided on the second connecting pipe. The high vacuum gauge P2 is connected to the vacuum branch pipe through a third connecting pipe, and a switch valve V9 is provided on the third connecting pipe. The molecular pump is connected to the vacuum branch pipe through a fourth connecting pipe, and a switch valve V7 is provided on the fourth connecting pipe.

[0069] In the above technical solution, a cylinder pressure reducing gauge is installed on the connecting pipeline.

[0070] In another aspect of the present invention, the isotope sample purification and collection preparation system is in methane 13 CD( 13 CH 3 D. 13 CH 2 D 2 , 13 CHD 3 , 13 CD 4 )Application in isotope detection.

[0071] Compared with the prior art, the present invention has the following beneficial effects:

[0072] 1. The present invention completes the sample purification and collection preparation for methane binary isotope detection by implementing the functions of impurity removal, enrichment, purification, transfer, carrier gas release and collection on the collected gas samples. Each component in the system is reasonably designed, easy to operate, and is combined together to achieve the purification and collection of sample gas.

[0073] 2. The present invention accommodates two sampling methods of source samples, injection sampling and cylinder sampling. The two methods can be freely switched through the valve body, which is convenient to use and has strong applicability.

[0074] 3. The collected methane gas can be injected manually or automatically, and connected to the dual-channel injection system of the isotope mass spectrometer to achieve binary isotope analysis of methane. 13 CH 3 D and 12 CH 2 D 2 Δ18 and Δ13CH 3 DAnalysis and detection.

[0075] 4. The principle of the present invention is simple, and the structural design integrates the functions of sampling, adsorption, separation, enrichment, purification, transfer, collection, etc., making the sample testing process simple and convenient, easy to operate, and can effectively improve the accuracy of the test value. It is a set of sample preparation system with scientific research significance and strong pertinence. It has good use and promotion value. BRIEF DESCRIPTION OF THE DRAWINGS

[0076] Figure 1 It is a system block diagram of embodiment 1 of the present invention.

[0077] Figure 2 It is a pipeline connection diagram of embodiment 1 of the present invention.

[0078] Figure 3 This is a sampling enrichment state diagram of the methane sample in Example 2 of the present invention.

[0079] Figure 4 This is a diagram of the purification, transfer and collection status of the methane sample in Example 2 of the present invention. DETAILED DESCRIPTION

[0080] The present invention is further described in detail below in conjunction with specific embodiments. It should be understood that the specific embodiments described herein are only used to explain the present invention and are not used to limit the present invention.

[0081] Example 1

[0082] An isotope sample purification and collection preparation system includes a sampling unit, a VOC trap T1, an adsorption trap T2, an adsorption trap T3, a chemical trap T4, a liquid nitrogen cold trap T5, a liquid nitrogen enrichment trap T6, a verification enrichment trap T7, a chromatographic column GC, a purification and re-enrichment trap T8, and a sample collection trap T9, which are sequentially connected through pipelines, wherein:

[0083] The inlet of the injection unit is connected to a GC injection port 1 and a zero carrier gas supply pipeline, a switch valve V24 is provided on the GC injection port 1, and a switch valve V23 is provided on the zero carrier gas supply pipeline;

[0084] The outlet of the injection unit is connected to the inlet of the VOC trap T1 through a first pipeline, on which a switch valve V11 is provided, and the outlet of the injection unit is connected to the inlet of the adsorption trap T2 through a second pipeline, on which a switch valve V12 is provided;

[0085] The inlet of the VOC trap T1 is connected to a first carrier gas supply pipeline, and the outlet is connected to a discharge pipeline to discharge the chilled water and VOC components in the VOC trap; a switch valve V13 is provided on the first carrier gas supply pipeline, and a V14 is provided on the discharge pipeline;

[0086] A carrier gas purge pipeline is provided on the pipeline connecting the adsorption trap T2, the adsorption trap T3, the chemical trap T4 and the liquid nitrogen cold trap T5, wherein the carrier gas purge pipeline includes a pipeline for supplying the zero carrier gas and an impurity gas discharge pipeline connected to the outlet of the liquid nitrogen cold trap T5, and a switch valve V15 is provided on the impurity gas discharge pipeline;

[0087] A switch valve V16 is provided on the pipeline between the liquid nitrogen cold trap T5 and the liquid nitrogen enrichment trap T6, a second carrier gas supply pipeline is connected to the inlet of the liquid nitrogen enrichment trap T6, a switch valve V17 is provided on the second carrier gas supply pipeline, the second carrier gas supply pipeline is connected to the inlet of the chromatographic column GC through a third pipeline, a switch valve V18 is provided on the third pipeline;

[0088] The outlet of the verification enrichment trap T7 is connected to a permanent gas discharge pipe to discharge gases that cannot be condensed in the liquid nitrogen cold trap and the liquid nitrogen enrichment trap, such as nitrogen, oxygen, hydrogen, argon, etc., and a switch valve V19 is provided on the permanent gas discharge pipe;

[0089] The inlet of the purification and re-enrichment trap T8 is connected to a third carrier gas supply pipeline, on which a switch valve V20 is provided, a valve V1 is provided on the pipeline between the chromatographic column GC and the purification and re-enrichment trap T8, the outlet of the purification and re-enrichment trap is respectively connected to a heavy gas discharge pipeline, a sample collection tube and a sample discharge pipeline, a switch valve V22 is provided on the heavy gas discharge pipeline, the sample collection tube is located in the sample collection trap, and the outlet of the sample collection tube is connected to a vacuum pipeline for removing the carrier gas. When sampling, the carrier gas introduced by the second carrier gas supply pipeline delivers the sample enriched in the liquid nitrogen enrichment trap into the inlet of the chromatographic column; the outlet of the chromatographic column is connected to a heavy gas discharge pipeline to discharge impurity gases whose retention time is after the target gas, for example, when purifying methane, the retention time of ethane doped in the sample is after methane, and when the methane extraction is completed, ethane is discharged through the heavy gas discharge pipeline.

[0090] As a preferred embodiment, the sampling unit is a syringe sampling unit and / or a cylinder sampling unit. The syringe sampling unit includes an injection injector connected to the VOC trap through a pipeline; the cylinder sampling unit includes a natural gas sample cylinder connected to the VOC trap through a connecting pipeline, and a cylinder pressure reducing gauge is provided on the connecting pipeline.

[0091] A verification enrichment trap is provided on the pipeline between the liquid nitrogen enrichment trap and the chromatographic column to verify whether the sample in the liquid nitrogen enrichment trap is completely enriched. Especially when a new sample is to be tested, the verification enrichment trap can be used to verify whether the length of the cooling pipeline in the previous liquid nitrogen cold trap and the liquid nitrogen enrichment trap is appropriate, whether the cooling temperature is appropriate, and timely adjustments are made until it is verified that the sample is not enriched in the enrichment trap, indicating that the parameters set for the liquid nitrogen cold trap and the liquid nitrogen enrichment trap are reasonable.

[0092] As a preferred embodiment, the vacuum pipeline includes a primary vacuum pipeline connected to a dry pump and a secondary vacuum pipeline connected to a molecular pump. Specifically, the low vacuum gauge P1 is connected to the vacuum branch pipe through a first connecting pipeline, and a switch valve V8 is provided on the first connecting pipeline. The dry pump 6 is connected to the vacuum branch pipe through a second connecting pipeline, and a switch valve V6 is provided on the second connecting pipeline. The high vacuum gauge P2 is connected to the vacuum branch pipe through a third connecting pipeline, and a switch valve V9 is provided on the third connecting pipeline. The molecular pump 7 is connected to the vacuum branch pipe through a fourth connecting pipeline, and a switch valve V7 is provided on the fourth connecting pipeline.

[0093] Example 2

[0094] The purification and collection method of the isotope sample purification and collection preparation system described in Example 1 comprises the following steps:

[0095] 1. Enrichment process:

[0096] Step 1, the sample is introduced through the injection unit, the switch valves V24, V11, V16, V18 and V19 are opened, and the other switch valves are closed, and the gas sample enters the VOC trap T1 to remove water and VOC components (the temperature control range of the VOC trap T1 is between -24°C and -0°C. It has built-in HayeSep D or PoraPLOT Q resin or molecular sieve fillers to remove a large amount of VOC components in the sample), and then enters the adsorption trap T2 (filled with iodine pentoxide to oxidize CO to carbon dioxide), adsorption trap T3 (filled with soda lime or sodium hydroxide to remove acidic gas carbon dioxide, etc.), chemical trap T4 (spare trap to remove other impurities in a targeted manner), liquid nitrogen cold trap T5 (liquid nitrogen cold trap without filler to remove sulfur dioxide and volatile gases) and liquid nitrogen enrichment trap T6, verification enrichment trap T7, and finally the sample is enriched in the liquid nitrogen enrichment trap T6, and other impurity gases are discharged through the permanent gas discharge pipe;

[0097] Step 2, the switch valves V17, V21, V1 and V3 are opened, and the other switch valves are closed. The carrier gas introduced into the second carrier gas supply pipeline sends the sample in the liquid nitrogen enrichment trap T6 to the chromatographic column GC, and is separated according to the retention time in the chromatographic column GC. When the target gas flows out, V1 is opened, and the target gas is enriched in the purification and re-enrichment trap T8. When the heavy gas (the gas with a retention time after the target gas) flows out, V1 is closed, V22 is opened, and the heavy gas is discharged through the heavy gas discharge pipeline.

[0098] 2. Transfer, enrichment and collection process:

[0099] Step 1, the switch valves V20, V1, V2 and V3 are opened, and the other switch valves are closed. The carrier gas introduced into the third carrier gas supply pipeline passes through the purification and re-enrichment trap T8 and is discharged from the sample discharge pipeline.

[0100] Step 2, close V1, V2 and V5, open V2, V4, V6, V8, use dry pump 6 to exhaust the impurities in the passage, when the vacuum gauge P1 displays a value of 0.1 mbar, close vacuum valve V6, open vacuum valves V7 and V9, and continue to exhaust the carrier gas with molecular pump unit 7, when the vacuum gauge P2 displays that the requirement is met, close V7, open V10, and purify and enrich the methane sample in well T8 to release and diffuse it into the pre-pumped sample collection tube 5, and the sample collection tube 5 is placed in the sample collection well T9.

[0101] During or after the transfer, re-enrichment and collection process, the front pipeline can be cleaned. Specifically:

[0102] (1) Restoration of the VOC trap T1 function: Open V13 and V14, close other valves, increase the temperature of the VOC trap T1 (100° C.), introduce carrier gas into the first carrier gas supply pipeline, and discharge the water and VOC components remaining in the VOC trap T1 through the discharge pipeline;

[0103] (2) Purging of the adsorption trap group, chemical trap, and liquid nitrogen cold trap: Open V23, V12, V16, and V19, close other switch valves, and introduce carrier gas into the zero carrier gas supply pipeline, and then pass through the adsorption trap T2, adsorption trap T3, chemical trap T4, and liquid nitrogen cold trap T5, and then be discharged from the impurity gas discharge pipeline;

[0104] Example 3

[0105] An isotope sample purification and collection preparation system includes a two-position four-way valve A, a two-position six-way valve B, a two-position six-way valve C, a two-position four-way valve D, a VOC trap T1, an adsorption trap T2, an adsorption trap T3, a chemical trap T4, a liquid nitrogen cold trap T5, a liquid nitrogen enrichment trap T6, a verification enrichment trap T7, a purification and re-enrichment trap T8, and a sample collection trap T9, wherein:

[0106] The two-position four-way valve A has four hole positions a1, a2, a3, and a4. The a2 is connected to the natural gas sample cylinder 3 through a connecting pipe, and a cylinder pressure reducing gauge 4 is installed on the connecting pipe. The a4 is connected to the injection injector 2 through a pipe. The injection injector 2 is provided with a GC injection port 1, and the injection injector 2 is provided with a zero carrier gas input pipe;

[0107] The two-position six-way valve B has six hole positions, namely, b1, b2, b3, b4, b5 and b6; b2 is connected to a3 through a pipeline; b3 is connected to the inlet of the VOC trap T1 through a pipeline; the outlet of the VOC trap T1 is connected to b6 through a pipeline; b1 is connected to the inlet of the liquid nitrogen cold trap T5 through an impurity removal pipeline; the impurity removal pipeline is sequentially connected to an adsorption trap T2, an adsorption trap T3 and a chemical trap T4; b4 is connected to a first load gas input pipeline; and b5 is connected to a discharge pipeline;

[0108] The two-position six-way valve C has six hole positions, namely c1, c2, c3, c4, c5 and c6; the outlet of the liquid nitrogen cold trap T5 is connected to the c2 through a pipeline; the c3 is connected to the inlet of the liquid nitrogen enrichment trap T6 through a pipeline; the outlet of the liquid nitrogen enrichment trap T6 is connected to the inlet of the verification enrichment trap T7 through a pipeline; the outlet of the verification enrichment trap T7 is connected to the c6 through a pipeline; the c1 is connected to the impurity gas discharge pipeline; the c4 is connected to the second load gas input pipeline; and the c5 is connected to the inlet of the chromatographic column GC8 through a pipeline;

[0109] The two-position four-way valve D has four hole positions, d1, d2, d3, and d4. The d1 is connected to the outlet of the chromatographic column GC8 through a pipeline, the d2 is connected to the inlet of the purification and re-enrichment trap T8 through an enrichment pipeline, the d3 is connected to the third load gas input pipeline, the d4 is connected to the permanent gas discharge pipe, the enrichment pipeline is provided with a switch valve V1, the outlet of the purification and re-enrichment trap T8 is connected to the inlet of the sample collection trap T9 through a pipeline, the sample collection trap T9 is respectively connected to the sample discharge pipeline and the collection pipeline through a connecting pipeline, wherein the connecting pipeline is provided with a switch valve V2, the sample discharge pipeline is provided with a switch valve V3, the collection pipeline is provided with a switch valve V4, the The collecting pipe is respectively connected with the vacuum branch pipe and the collecting branch pipe, and the collecting branch pipe is provided with a switch valve V5 and a switch valve V10. The end of the collecting branch pipe is connected with a sample collecting pipe 5, and the sample collecting pipe 5 is located in the sample collecting well T9. The low vacuum gauge P1 is connected to the vacuum branch pipe through a first connecting pipe, and the first connecting pipe is provided with a switch valve V8. The dry pump 6 is connected to the vacuum branch pipe through a second connecting pipe, and the second connecting pipe is provided with a switch valve V6. The high vacuum gauge P2 is connected to the vacuum branch pipe through a third connecting pipe, and the third connecting pipe is provided with a switch valve V9. The molecular pump 7 is connected to the vacuum branch pipe through a fourth connecting pipe, and the fourth connecting pipe is provided with a switch valve V7.

[0110] In the vacuum control unit, in order to reduce the gas diffusion volume, avoid the possible outgassing effect of the low vacuum gauge P1 and the safety protection of the high vacuum gauge P2 and the influence of ionization of the high vacuum gauge P2, the low vacuum gauge P1 and high vacuum gauge P2 in the system are connected to the vacuum system through vacuum valves V8 and V9 respectively.

[0111] In this embodiment, the temperature control range of VOC trap T1 is between -24℃ and -0℃. Built-in HayeSep D or PoraPLOT Q resin or molecular sieve fillers remove a large amount of VOC components in the sample; adsorption trap T2 is filled with iodine pentoxide (to oxidize CO to carbon dioxide); adsorption trap T3 is filled with soda lime or sodium hydroxide (to remove acidic gases such as carbon dioxide); chemical trap T4 is a spare trap (to remove other impurities in a targeted manner); liquid nitrogen cold trap T5 is a liquid nitrogen cold trap without filler (the cooling pipeline is shorter than that in liquid nitrogen enrichment trap T6, to remove sulfur dioxide and some volatile impurity gases); liquid nitrogen enrichment trap T6 and verification enrichment trap T7 are two completely identical series liquid nitrogen cold traps, with built-in molecular sieve or resin fillers and connected in series. Switch valves V1, V2, V3, V4, V5, V6, V7, V8, V9, and V10 are vacuum manual valves, distributed in each pipeline to cooperate in completing the collection of target gas.

[0112] The two positions of the four rotary valves are respectively the injection state when rotating clockwise and the sampling state when rotating counterclockwise. By switching and combining the hole positions of the two-position four-way valve (A), the two-position six-way valve (B), the two-position six-way valve (C), and the two-position four-way valve (D), the functions of removing impurities, enriching, purifying, separating, and transferring the sample gas can be realized; the coordinated use of the vacuum switch valves V1, V2, V3, V4, V5, V6, V7, V8, V9, and V10 can realize the functions of re-enrichment, transfer, collection, and online injection analysis of the target gas. Combination use of the above valve bodies.

[0113] Ⅰ) Sample injection method: ① For concentrated gas samples, connect the injection injector 2, the sampling (load) state holes a4 and a3 of the two-position four-way valve A, and the sampling (load) state holes b2 and b3 of the two-position six-way valve B, and introduce He0 carrier gas from the GC injection port 1 to introduce the sample in the injection injector 2 into the system; ② For low-concentration cylinder gas, connect the low-concentration sample gas in the natural gas sample cylinder 3, the injection (Inject) state holes a2 and a3 of the two-position four-way valve A, and the sampling (load) state holes b2 and b3 of the two-position six-way valve B, and introduce He0 carrier gas from the GC injection port 1 into the system;

[0114] Ⅱ) Removal of impurity gases: After the sample gas enters the system, the He0 carrier gas passes through the VOC trap T1 in sequence to remove water and VOC components; the two-position six-way valve B (load) holes b6 and b1 are connected to the adsorption trap T2, the adsorption trap T3, the chemical trap T4, the liquid nitrogen cold trap T5, the two-position six-way valve C (load) holes c2 and c3, and the liquid nitrogen enrichment trap T6, and a chemical trap combination is set to remove impurity gas components; the sample is purified and enriched in the liquid nitrogen enrichment trap T6 for storage, and then the enrichment effect of the enriched target gas is verified in the verification enrichment trap T7 (by adjusting the length of the connecting pipelines of the liquid nitrogen cold trap T5 and the liquid nitrogen enrichment trap T6 and the carrier gas flow rate, so that the sample is completely enriched in the liquid nitrogen enrichment trap T6); other impurity gases in the sample gas are vented and discharged through the two-position six-way valve C (load) holes c6 and c1 and the impurity gas discharge pipeline to discharge permanent gases.

[0115] III) Chromatographic separation and re-enrichment of methane gas: Remove the carrier gas to collect methane, complete the transfer and collection of methane gas. Connect the holes c4 and c3 of the two-position six-way valve C (Inject), the liquid nitrogen enrichment trap T6, the verification enrichment trap T7, the holes c6 and c5 of the two-position six-way valve C (Inject), the chromatographic column 8, the holes d1 and d2 of the two-position four-way valve D (load), the vacuum valve V1, and the purification re-enrichment trap T8. The He2 carrier gas is introduced from the hole c4 of the two-position six-way valve C, and the purified methane gas stored in the liquid nitrogen enrichment trap T6 enters the chromatographic column 8. The separation chromatographic column or capillary column is used to complete the separation of methane. The separated methane gas is set through the valve body conversion to complete the methane enrichment and is stored in the purification re-enrichment trap T8, waiting for the next step of transfer and collection.

[0116] IV) Carrier gas removal and methane collection: Close vacuum valves V1, V3, and V5, open vacuum valves V2, V4, V6, and V8, and use dry pump 6 to exhaust the impurities in the passage. When the vacuum gauge P1 displays a value of 0.1 mbar, close vacuum valve V6, open vacuum valves V5, V7, and V9, and continue to exhaust the carrier gas with molecular pump unit 7. When the vacuum gauge P2 displays a value that meets the requirements (the displayed value is not less than 1*10 - 6 mbar), close V7, open V5 and V10, release and diffuse the methane sample in the purified and re-enriched well T8 into the pre-pumped sample collection tube 5, and the sample collection tube 5 is placed in the sample collection well T9.

[0117] V) Gas stable isotope mass spectrometry test: The sample collection tube 5 is directly connected to the dual-channel injection system of the gas stable isotope mass spectrometer (MAT253Ultra Thermo Scientific), or V5 is opened for direct equilibrium diffusion into the dual-channel injection storage tank of the isotope mass spectrometer, and the analysis and determination of binary isotopes 13CH3D and 12CH2D2 in the methane sample are completed in cooperation with the gas isotope mass spectrometer MAT253 Ultra (ThermoScientific), and the Δ18 and Δ13CH3D analysis and detection of binary isotopes 13CH3D and 12CH2D2 of methane are completed.

[0118] In addition, this system also has the following functions:

[0119] Ⅰ) VOC trap T1 function recovery: adjust the temperature of VOC trap T1 to 100°C, connect the holes b4 and b3 of the two-position six-way valve B (Inject), VOC trap T1, and the holes b6 and b5 of the two-position six-way valve B, and introduce He1 carrier gas from the hole b4 of the two-position six-way valve B. The frozen water and other VOC components in the system are discharged for reuse;

[0120] II) Chemical trap purge mode: connect the two-position four-way valve A (load) holes a4 and a3, the two-position six-way valve B (Inject) holes b2 and b1, the adsorption trap T2, the adsorption trap T3, the chemical trap T4, the liquid nitrogen cold trap T5, the two-position six-way valve C holes c2 and c1, and the He0 carrier gas is introduced from the GC injection port 1, and then vented and discharged through the pipeline to keep the gas system clean;

[0121] III) Permanent gas exhaust mode: connect the liquid nitrogen cold trap T5 and the two-position six-way valve C (load) holes c2, c3, the liquid nitrogen enrichment trap T6, the verification enrichment trap T7, the two-position six-way valve C (load) holes c6, c1, and introduce He0 carrier gas from the two-position six-way valve A (load) and the two-position six-way valve B (load) in sequence to vent and discharge the permanent gas remaining in this connecting pipeline and maintain the system clean.

[0122] IV) Purification and re-enrichment mode: connect the two-position four-way valve D (inject) holes d3 and d2, vacuum valve V1, purification and re-enrichment trap T8, vacuum valve V2, vacuum valve V3, He3 carrier gas is introduced from the two-position four-way valve D holes d3 and d2, and discharged from the system by vacuum valve V3, completing the purification and re-enrichment of the methane sample.

[0123] The above is only a preferred embodiment of the present invention. It should be pointed out that, for ordinary technicians in this technical field, several improvements and modifications can be made without departing from the principle of the present invention. These improvements and modifications should also be regarded as the scope of protection of the present invention.

Claims

1. An isotope sample purification and collection preparation system, characterized in that: It includes two-position four-way valve A, two-position six-way valve B, two-position six-way valve C, two-position four-way valve D, VOC trap T1, adsorption trap T2, adsorption trap T3, chemical trap T4, liquid nitrogen cold trap T5, liquid nitrogen enrichment trap T6, verification enrichment trap T7, purification and re-enrichment trap T8, and sample collection trap T9, among which: The two-position four-way valve A has four hole positions a1, a2, a3, and a4, wherein a2 is connected to a natural gas sample cylinder through a connecting pipe, a4 is connected to an injection injector through a pipe, a GC injection port is provided on the injection injector, a zero carrier gas input pipe is provided on the injection injector, and a1 is connected to an exhaust pipeline; The two-position six-way valve B has six hole positions, namely, b1, b2, b3, b4, b5 and b6; b2 is connected to a3 through a pipeline; b3 is connected to the inlet of the VOC trap T1 through a pipeline; the outlet of the VOC trap T1 is connected to b6 through a pipeline; b1 is connected to the inlet of the liquid nitrogen cold trap T5 through an impurity removal pipeline; the impurity removal pipeline is sequentially connected to an adsorption trap T2, an adsorption trap T3 and a chemical trap T4; b4 is connected to a first load gas input pipeline; and b5 is connected to a discharge pipeline; The two-position six-way valve C has six hole positions, namely c1, c2, c3, c4, c5 and c6; the outlet of the liquid nitrogen cold trap T5 is connected to the c2 through a pipeline; the c3 is connected to the inlet of the liquid nitrogen enrichment trap T6 through a pipeline; the outlet of the liquid nitrogen enrichment trap T6 is connected to the inlet of the verification enrichment trap T7 through a pipeline; the outlet of the verification enrichment trap T7 is connected to the c6 through a pipeline; the c1 is connected to the impurity gas discharge pipeline; the c4 is connected to the second load gas input pipeline; and the c5 is connected to the inlet of the chromatographic column GC8 through a pipeline; The two-position four-way valve D has four hole positions, d1, d2, d3, and d4. The d1 is connected to the outlet of the chromatographic column GC through a pipeline, the d2 is connected to the inlet of the purification and re-enrichment trap T8 through an enrichment pipeline, the d3 is connected to the third load gas input pipeline, and the d4 is connected to the heavy gas discharge pipe. The enrichment pipeline is provided with a switch valve V1, the outlet of the purification and re-enrichment trap T8 is connected to the inlet of the sample collection trap T9 through a pipeline, and the sample collection trap T9 is respectively connected to the sample discharge pipeline and the collection pipeline through a connecting pipeline, wherein the connecting pipeline is provided with a switch valve V2, the sample discharge pipeline is provided with a switch valve V3, and the collection pipeline is provided with a switch valve V4. The collection pipeline is respectively connected to the vacuum branch pipe and the collection branch pipe, the vacuum branch pipe is connected to a vacuum source, and the collection branch pipe is provided with a switch valve V5 and a switch valve V10. The end of the collection branch pipe is connected to a sample collection pipe, and the sample collection pipe is located in the sample collection trap.

2. The isotope sample purification and collection preparation system according to claim 1, characterized in that: The low vacuum gauge P1 is connected to the vacuum branch pipe through a first connecting pipe, and a switch valve V8 is provided on the first connecting pipe. The dry pump is connected to the vacuum branch pipe through a second connecting pipe, and a switch valve V6 is provided on the second connecting pipe. The high vacuum gauge P2 is connected to the vacuum branch pipe through a third connecting pipe, and a switch valve V9 is provided on the third connecting pipe. The molecular pump is connected to the vacuum branch pipe through a fourth connecting pipe, and a switch valve V7 is provided on the fourth connecting pipe.

3. The isotope sample purification and collection preparation method of the isotope sample purification and collection preparation system according to any one of claims 1 to 2, comprising the following steps: Ⅰ) Sample injection: ① For concentrated gas samples, connect the syringe injector, the sampling state holes a4 and a3 of the two-position four-way valve A, and the sampling state holes b2 and b3 of the two-position six-way valve B, and introduce He0 carrier gas from the GC injection port, and introduce the sample in the syringe injector into the system; ② For low-concentration cylinder gas, connect the low-concentration sample gas in the natural gas sample cylinder, the sampling state holes a2 and a3 of the two-position four-way valve A, and the sampling state holes b2 and b3 of the two-position six-way valve B, and introduce He0 carrier gas from the GC injection port 1 into the system; Ⅱ) Removal of impurity gases: After the sample gas enters the system, the He0 carrier gas passes through the VOC trap T1 in turn to remove water and VOC components; The holes b6 and b1 of the two-position six-way valve B are connected to the adsorption trap T2, the adsorption trap T3, the chemical trap T4, the liquid nitrogen cold trap T5, the holes c2 and c3 of the two-position six-way valve C, and the liquid nitrogen enrichment trap T6. The chemical trap combination is set to remove the impurity gas components; the sample is purified and enriched in the liquid nitrogen enrichment trap T6 for storage, and then the enrichment effect of the enriched target gas is verified in the verification enrichment trap T7; Other impurity gases in the sample gas are discharged through the two-position six-way valve C hole position c6, c1 and the impurity gas discharge pipeline to discharge permanent gases; III) Chromatographic separation and re-enrichment of methane gas: remove the carrier gas to collect methane, complete the transfer and collection of methane gas, connect the holes c4 and c3 of the two-position six-way valve C, the liquid nitrogen enrichment trap T6, the verification enrichment trap T7, the holes c6 and c5 of the two-position six-way valve C, the chromatographic column 8, the holes d1 and d2 of the two-position four-way valve D, the vacuum valve V1, and the purification and re-enrichment trap T8, and introduce He2 carrier gas from the hole c4 of the two-position six-way valve C, and the purified methane gas stored in the liquid nitrogen enrichment trap T6 into the chromatographic column 8, and use a separation chromatographic column or a capillary column to complete the separation of methane. The separated methane gas is set through the valve body conversion to complete the methane enrichment and store it in the purification and re-enrichment trap T8, waiting for the next step of transfer and collection; IV) Carrier gas removal and methane collection: close vacuum valves V1, V3, and V5, open vacuum valves V2, V4, V6, and V8, and use dry pumping to exhaust impurities in the passage. When the vacuum gauge P1 displays a value of 0.1 mbar, close vacuum valve V6, open vacuum valves V5, V7, and V9, and continue to exhaust the carrier gas therein with a molecular pump unit. When the vacuum gauge P2 displays that the requirement is met, close V7, open V5 and V10, and release and diffuse the methane sample in the purified and enriched well T8 into the pre-pumped sample collection tube, and the sample collection tube is placed in the sample collection well T9; V) Gas stable isotope mass spectrometry test: The sample collection tube is directly connected to the dual-channel injection system of the gas stable isotope mass spectrometer, or V5 is opened to directly balance and diffuse into the dual-channel injection storage tank of the isotope mass spectrometer, and the isotope analysis and detection are completed together with the gas isotope mass spectrometer.

4. An isotope sample purification and collection preparation system, characterized in that: It includes a sample injection unit, a first conversion valve, a VOC trap, an adsorption trap group, a liquid nitrogen cold trap, a second conversion valve, a chromatographic column, a third conversion valve and a purification and re-enrichment trap, wherein: The sampling unit is connected with a zero carrier gas supply pipeline; The port of the first conversion valve is respectively connected to an injection pipeline, an injection port of the VOC trap, an outlet of the VOC trap, an injection port of the adsorption trap group, a first carrier gas supply pipeline and an exhaust pipeline through pipelines, the injection pipeline is connected to the injection unit, when the first conversion valve is in a sampling state, the injection pipeline, the VOC trap, and the adsorption trap group are connected in sequence, the first carrier gas supply pipeline is connected to the exhaust pipeline, when the first conversion valve is in an injection state, the injection pipeline is connected to the adsorption trap group, the first carrier gas supply pipeline, the VOC trap and the exhaust pipeline are connected in sequence; The sample outlet of the adsorption trap group is connected to the sample inlet of the liquid nitrogen cold trap through a pipeline, and the sample outlet of the liquid nitrogen cold trap, the sample inlet and sample outlet of the liquid nitrogen enrichment trap, the second carrier gas supply pipeline, the sample inlet of the chromatographic column and the impurity gas discharge pipeline are respectively connected to the port of the second conversion valve through pipelines, wherein: when the second conversion valve is in a sampling state, the liquid nitrogen cold trap, the liquid nitrogen enrichment trap and the impurity gas discharge pipeline are sequentially connected, the second carrier gas supply pipeline is connected to the sample inlet of the chromatographic column, and when the second conversion valve is in an injection state, the sample outlet of the liquid nitrogen cold trap is connected to the impurity gas discharge pipeline, and the second carrier gas supply pipeline is sequentially connected to the liquid nitrogen enrichment trap and the sample inlet of the chromatographic column; The port of the third conversion valve is respectively connected to the sample outlet of the chromatographic column, the sample inlet of the purification and re-enrichment trap, the third carrier gas supply pipeline and the heavy gas discharge pipeline through pipelines, wherein: when the third conversion valve is in a sampling state, the sample outlet of the chromatographic column is connected to the sample inlet of the purification and re-enrichment trap, the third carrier gas supply pipeline is connected to the heavy gas discharge pipeline, and when the third conversion valve is in an injection state, the sample outlet of the chromatographic column is connected to the heavy gas discharge pipeline, and the third carrier gas supply pipeline is connected to the sample inlet of the purification and re-enrichment trap; The sample outlet of the purification and re-enrichment trap is connected to a sample discharge pipeline and a sample collection tube through pipelines, wherein the sample collection tube is located in a sample collection trap providing a low temperature environment, and a vacuum pipeline for removing carrier gas and impurities is connected to the sample collection tube.

5. The isotope sample purification and collection preparation system according to claim 4, characterized in that: The sampling unit includes an injection sampler, a natural gas sample cylinder and a conversion valve, wherein the conversion valve is respectively connected to the sample outlet of the injection sampler, the sample outlet of the natural gas sample cylinder, an exhaust pipeline and an inlet of a first conversion valve. When the sample amount is small, the sample outlet of the injection sampler is connected to the sampling pipeline, and the sample outlet of the natural gas sample cylinder is connected to the exhaust pipeline. When the sample amount is large, the sample outlet of the natural gas sample cylinder is connected to the sampling pipeline, and the sample outlet of the injection sampler is connected to the exhaust pipeline.

6. The isotope sample purification and collection preparation system according to claim 4, characterized in that: The adsorption trap group includes at least a CO adsorption trap and an acid gas adsorption trap.

7. The isotope sample purification and collection preparation system according to claim 4, characterized in that: A verification enrichment trap is arranged on the pipeline between the liquid nitrogen enrichment trap and the chromatographic column to verify whether the sample in the liquid nitrogen enrichment trap is completely enriched.

8. The isotope sample purification and collection preparation system according to claim 4, characterized in that: The vacuum pipeline includes a primary vacuum pipeline connected to a dry pump and a secondary vacuum pipeline connected to a molecular pump to remove impurities and carrier gas in the pipeline.

9. The purification and collection preparation method of the isotope sample purification and collection preparation system as claimed in claim 4 comprises the following steps:

1. Purification and enrichment process: Step 1: The first conversion valve and the second conversion valve are in the sampling state, and the gas samples enter the VOC trap in turn to remove water and VOC components; It enters the adsorption trap group to remove impurities, enters the liquid nitrogen cold trap to remove impurities with a boiling point higher than the target gas, and finally enters the liquid nitrogen enrichment trap for enrichment. Other non-condensable impurity gases are discharged through the permanent gas discharge pipeline; Step 2, the second conversion valve is in the injection state, the carrier gas introduced into the second carrier gas supply pipeline sends the sample in the liquid nitrogen enrichment trap into the chromatographic column GC, and the gas is separated in the chromatographic column GC according to the different retention times of different component gases. When the target gas flows out, the third conversion valve is in the sampling state, and the target gas after separation is enriched in the purification and re-enrichment trap. When the heavy gas with a retention time after the target gas flows out, the third conversion valve is in the injection state and discharged through the heavy gas discharge pipeline; 2. Transfer, enrichment and collection process: The third conversion valve is in the injection state: Step 1, the carrier gas introduced into the third carrier gas supply pipeline passes through the purification re-enrichment trap and its connecting pipeline, and then is discharged from the sample discharge pipeline to purge the purification re-enrichment trap and its connecting pipeline; Step 2, evacuating the purification and re-enrichment trap and the sample collection tube and their connecting pipelines through a vacuum pipeline to discharge impurity gases and carrier gas; Step 3, purify and diffuse the target gas enriched in the re-enrichment trap into the sample collection tube.

10. The method for purifying and collecting isotope samples according to claim 9, characterized in that: In step 1 of the transfer, re-enrichment and collection process, the third carrier gas completes the transfer and enrichment of the target gas while purging the pipeline, and stores it in the purification and re-enrichment trap.

11. The method for purifying and collecting isotope samples according to claim 9, characterized in that: When the connecting pipelines of the purification and re-enrichment trap and the sample collection tube are evacuated, the impurity gas is first evacuated by a dry pump, and then the impurity gas and the carrier gas are evacuated by a molecular pump.

12. The method for purifying and collecting isotope samples according to claim 9, characterized in that: Also includes pipeline cleaning methods: (1) The first conversion valve is in the injection state: carrier gas is introduced into the first carrier gas supply pipeline, and the water and VOC components remaining in the VOC trap T1 are discharged through the discharge pipeline; (2) The first conversion valve is in the sampling state: the carrier gas is introduced into the zero carrier gas supply pipeline, and the impurities remaining in the adsorption trap group, the liquid nitrogen cold trap, and the liquid nitrogen enrichment trap are discharged from the impurity gas discharge pipeline.

13. An isotope sample purification and collection preparation system, characterized in that: It includes a sampling unit, a VOC trap, an adsorption trap group, a liquid nitrogen cold trap, a liquid nitrogen enrichment trap, a chromatographic column, a purification and re-enrichment trap and a sample collection tube which are sequentially connected through pipelines, wherein: The inlet of the VOC trap is connected to a first carrier gas supply pipeline, and the outlet is connected to a discharge pipeline to discharge the chilled water and VOC components in the VOC trap; A carrier gas purge pipeline is provided on the pipeline connecting the adsorption trap group and the liquid nitrogen cold trap, wherein the carrier gas purge pipeline includes a zero carrier gas supply pipeline that provides carrier gas to the inlet of the adsorption trap group and an impurity gas discharge pipeline connected to the outlet of the liquid nitrogen cold trap; The outlet of the liquid nitrogen enrichment trap is connected to a permanent gas discharge pipe to discharge the permanent gas that cannot be condensed in the liquid nitrogen enrichment trap; The inlet of the liquid nitrogen enrichment trap is connected to a second carrier gas supply pipeline. During sampling, the carrier gas introduced through the second carrier gas supply pipeline delivers the sample enriched in the liquid nitrogen enrichment trap to the inlet of the chromatographic column. The outlet of the chromatographic column is respectively connected to a heavy gas discharge pipeline and a purification and re-enrichment trap. The heavy gas discharge pipeline is used to discharge impurity gases whose retention time is later than that of the target gas. The inlet of the purification and re-enrichment trap is connected to a third carrier gas supply pipeline, and the outlet of the purification and re-enrichment trap is respectively connected to a sample collection tube and a sample discharge pipeline. The sample collection tube is located in the sample collection trap, and the outlet of the sample collection tube is connected to a vacuum pipeline for removing impurity gases and carrier gas.

14. The isotope sample purification and collection preparation system according to claim 13, characterized in that: The zero-carrier gas supply pipeline is connected to the inlet of the adsorption trap group, or the zero-carrier gas supply pipeline is connected to the injection unit, and the injection unit is connected to the inlet of the adsorption trap group through a pipeline.

15. The isotope sample purification and collection preparation system according to claim 13, characterized in that: The sample injection unit is a syringe sample injection unit and / or a steel bottle sample injection unit; The syringe injection unit includes an injection injector connected to the VOC trap through a pipeline, and the zero carrier gas supply pipeline is connected to the injection injector; the cylinder injection unit includes a natural gas sample cylinder connected to the VOC trap through a connecting pipeline, and a cylinder pressure reducing gauge is provided on the connecting pipeline.

16. The isotope sample purification and collection preparation system according to claim 13, characterized in that: The adsorption trap group includes at least a CO oxidation trap and an acid gas adsorption trap.

17. The isotope sample purification and collection preparation system according to claim 13, characterized in that: A verification enrichment trap is provided on the pipeline between the liquid nitrogen enrichment trap and the chromatographic column to verify whether the sample in the liquid nitrogen enrichment trap is completely enriched.

18. The isotope sample purification and collection preparation system according to claim 13, characterized in that: The vacuum pipeline includes a primary vacuum pipeline connected to a dry pump and a secondary vacuum pipeline connected to a molecular pump.

19. The isotope sample purification and collection preparation system according to claim 1, 4 or 13, characterized in that: The isotope sample purification and collection preparation system is used in the detection of methane 13C-D isotopes.

20. A method for working the isotope sample purification and collection preparation system according to claim 4, characterized in that: The following steps are involved:

1. Purification and enrichment process: Step 1: The sample is introduced through the sampling unit, and the gas sample enters the VOC trap to remove water and VOC components, enters the adsorption trap group to remove impurities, enters the liquid nitrogen cold trap to remove impurities with a boiling point higher than the target gas, and finally enters the liquid nitrogen enrichment trap for enrichment. Other non-condensable impurity gases are discharged through the permanent gas discharge pipe; Step 2, the carrier gas introduced into the second carrier gas supply pipeline delivers the sample in the liquid nitrogen enrichment trap to the chromatographic column GC, and the sample is separated in the chromatographic column GC according to the retention time. After separation, the target gas is enriched in the purification and re-enrichment trap, and impurities other than the target gas are discharged through the heavy gas discharge pipeline; 2. Transfer, enrichment and collection process: Step 1, cutting off the pipeline connecting the purification and re-enrichment trap and the chromatographic column, the carrier gas introduced into the third carrier gas supply pipeline passes through the purification and re-enrichment trap and its connecting pipeline, and then is discharged from the sample discharge pipeline to purge the pipeline; Step 2, evacuating the purification and re-enrichment trap and the sample collection tube and their connecting pipelines through a vacuum pipeline to discharge impurity gases and carrier gas; Step 3, purify and diffuse the target gas enriched in the re-enrichment trap into the sample collection tube.

21. The working method according to claim 20, characterized in that: In step 1 of the transfer, re-enrichment and collection process, the third carrier gas completes the transfer and enrichment of the target gas while purging the pipeline, and stores it in the purification and re-enrichment trap.

22. The working method according to claim 20, characterized in that: When the connecting pipelines of the purification and re-enrichment trap and the sample collection tube are evacuated, the impurity gas is firstly evacuated by a dry pump, and then the carrier gas is evacuated by a molecular pump.

23. The working method according to claim 20, characterized in that: During or after the transfer and re-enrichment collection process, the pipeline before the chromatographic column can be cleaned, including: (1) VOC trap function recovery: the temperature of the VOC trap T1 is increased, carrier gas is introduced into the first carrier gas supply pipeline, and the water and VOC components remaining in the VOC trap are discharged through the discharge pipeline; (2) Purging of the adsorption trap group and liquid nitrogen cold trap: The carrier gas is introduced into the zero carrier gas supply pipeline, passes through the adsorption trap group and liquid nitrogen cold trap, and is discharged from the impurity gas discharge pipeline.

Citation Information

Patent Citations

  • Isotope sample purification and collection preparation system

    CN211205971U