A water-blocking steel plug for a water intake of a hydraulic tunnel and a method of using the same
By designing a water-blocking steel plug for the water intake of a hydraulic tunnel that utilizes water flow and an air pump, the problems of high cost, serious pollution, and long construction period during the maintenance of hydraulic tunnels have been solved, and an efficient and environmentally friendly maintenance process has been achieved, which is suitable for Various hole shapes.
Patent Information
- Application Number
- CN202110646985.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2021-06-10
- Publication Date
- 2024-10-01
- Estimated Expiration
- 2041-06-10
AI Technical Summary
The maintenance process of existing hydraulic tunnels involves high costs, water pollution, waste of human resources, long construction period, and complex operations.
A water-blocking steel plug for the water inlet of a hydraulic tunnel is designed. The pressure of the water flow is used to suck the cylinder into the entrance of the cave, and the gas is transferred to the rubber bag through the air pump to achieve sealing. It is suitable for work where the cave is uneven. The sealing progress is monitored through the pressure gauge, which simplifies the maintenance process, and the height adjustment and hydraulic control of the sealing cylinder are realized through the servo motor and oil pump.
It reduces maintenance costs, avoids water pollution, saves human resources, shortens the construction period, and improves maintenance efficiency and operation convenience.
Smart Images

Figure CN113202067B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of water conservancy and hydropower technology, and in particular to a water-blocking steel plug for a water intake of a hydraulic tunnel and a use method thereof. Background Art
[0002] Hydraulic tunnels such as water diversion tunnels and water diversion tunnels in water conservancy and hydropower projects usually undertake important tasks such as flood discharge, water diversion, emptying, and sand removal, which are accomplished by setting gates in the middle of the tunnel or at the exit.
[0003] As time goes by, the gate and related supporting embedded parts will corrode and deform, and need regular maintenance and replacement. The gate can be inspected and replaced by raising the gate, but this can only stop the water-blocking function, and the embedded parts in the cave and the shaft cannot be replaced and inspected. The existing method is to build a temporary cofferdam at the hole at one end of the water body to prevent water and soil from entering the maintenance position of the cave or the shaft. The construction height of the temporary cofferdam must be higher than the highest water level, and the construction is carried out at a water level of tens of meters deep. The construction is difficult, the construction period is long, and the cost is high. After the inspection and replacement, demolition work must be carried out and the whole process is likely to cause pollution to the water body. Summary of the invention
[0004] 1. Technical issues to be resolved
[0005] In view of the deficiencies in the prior art, the present invention provides a water-blocking steel plug for a water intake of a hydraulic tunnel and a method of using the same, which solves the problems of high maintenance costs, water pollution, waste of human resources, long construction period and complicated operation.
[0006] (II) Technical solution
[0007] To achieve the above objectives, the present invention is implemented through the following technical solutions: a water-blocking steel plug for a water intake of a hydraulic tunnel, comprising a gate pier, a frame fixedly connected at the center of the top of the gate pier, a gate hoist fixedly connected at the middle of the top of the frame, an output end at the bottom of the gate hoist penetrating the gate pier and fixedly connected to a gate, a hole body is provided at a position corresponding to the gate at the bottom of the inner end of the gate pier, embedded parts are provided at the bottom of the inner end of the gate pier located at the right sides of the upper and lower ends of the gate, an air pump is fixedly connected at a position close to the frame at the left side of the top of the gate pier, the output end of the air pump on the left side is fixedly connected to one end of a connecting pipe, and the other end of the connecting pipe is fixedly connected to the input end of an air distributor, five rubber hoses are evenly fixedly connected to the output end of the air distributor, the bottom ends of the rubber hoses all penetrate the support frame and the pressure plate and are fixedly connected to rubber bags, an insertion hole is provided at a position corresponding to the rubber hose at the middle end of the left top of the pressure plate, a cylinder is fixedly connected to the right end of the pressure plate, and six stiffening rings are evenly fixedly connected to the right outer diameter of the cylinder.
[0008] Preferably, a servo motor is fixedly connected to the middle position of the left end of the top of the support frame, the driving end of the servo motor penetrates the support frame and is fixedly connected to a screw, the bottom end of the screw is rotatably connected to the center of the top of the fixed plate, and a connecting block is threadedly connected to the outer diameter of the bottom of the screw at a position corresponding to the pressure plate, a sealing cylinder is fixedly connected to the center of the right end of the connecting block, an annular sealing plate is slidably connected to the right inner wall of the sealing cylinder, the right end of the annular sealing plate is fixedly connected to one end of the connecting rod at the center, the other end of the connecting rod penetrates the sealing cylinder and is fixedly connected to the center of the left end of the pressure plate, the left side of the top of the sealing cylinder is fixedly connected to one end of the oil pipe, the other end of the oil pipe penetrates the oil tank and is fixedly connected to an oil pump, a control console is fixedly connected to the middle position of the right end of the top of the pier, and the hoist, air pump, servo motor and oil pump are all connected to the control console through signal lines.
[0009] Preferably, a solenoid valve is provided in the middle of the connecting pipe, and the solenoid valve is connected to the control console via a signal line. A pressure gauge is provided at the top of the hose near the gas distribution device.
[0010] Preferably, rubber bags are fixedly connected between the stiffening rings, and the support frame is fixedly connected to the left top end of the gate pier.
[0011] Preferably, limit rods are slidably connected in through holes at symmetrical positions in the middle of the left and right sides of the connecting block, one end of the limit rod is fixedly connected to the bottom end of the support frame and the other end is fixedly connected to the top end of the fixing plate.
[0012] Preferably, the oil pump is fixedly connected to the left side of the inner wall at the bottom end of the oil tank, the oil tank is fixedly connected to the bottom end of the support frame, and an exhaust valve is fixedly connected to the right side of the top end of the sealing cylinder, and the exhaust valve is connected to the console through a signal line.
[0013] Preferably, a method for using a water-blocking steel plug for a water intake of a hydraulic tunnel comprises the following steps:
[0014] S1. Before maintenance, the servo motor drives the screw to rotate, and the screw drives the connection block to rotate. Since the through holes on both sides of the connection block are slidably connected with limit rods, the limit rods limit the rotation of the connection block with the screw, thereby realizing the linear movement of the connection block on the screw. The sealing cylinder is driven by the connection block to adjust the height in the vertical direction, so that the sealing cylinder is moved to a position at the same level as the hole body, and then the cylinder is sucked into the hole body under the action of the water flow. In this process, the pressure plate moves toward the entrance of the hole body. Under the action of the connecting rod, the annular sealing plate slides in the sealing cylinder. When the pressure plate fits the outer wall of the entrance of the hole body, the hydraulic oil in the oil tank is pumped into the sealing cylinder through the oil pipe by the oil pump, and the exhaust valve is opened to discharge the air inside the sealing cylinder;
[0015] S2. During maintenance, first close the gate, move the pressure plate to the same level as the cavern, then lift the gate part, and use the force generated by the water flow to suck the cylinder into the cavern entrance. Due to the pressure of the water, the pressure plate fits the outer wall of the cavern entrance. The air pump transmits the external gas to the inside of the gas distributor through the connecting pipe. Under the action of the gas distributor, the five corresponding rubber bags are inflated through five rubber hoses. After the rubber bags are inflated, they expand to achieve sealing. The rubber bag inflation sealing method can be applied to the working condition of uneven caverns. The sealing is monitored by a pressure gauge. After the inflation is completed, the valve shaft on the gate pier is used to observe whether the sealing is successful. Then, the gate, cavern and embedded parts are inspected and maintained;
[0016] S3. After the inspection is completed, lower the gate and deflate the rubber bag. Then, use the oil pump to pump the hydraulic oil in the sealing cylinder into the oil tank through the oil pipe. At this time, the exhaust valve is closed. Under the action of the pressure change in the sealing cylinder and the basically consistent water pressure on both sides of the pressure plate after the water enters the hole, the cylinder is separated from the hole. Then, under the action of the servo motor, the sealing cylinder is driven to return to its initial position.
[0017] (III) Beneficial effects
[0018] The present invention provides a water-blocking steel plug for a water intake of a hydraulic tunnel and a method for using the same. The invention has the following beneficial effects:
[0019] 1. The present invention lifts the gate part and uses the force generated by the water flow to suck the cylinder to the entrance of the cave. Due to the pressure of the water, the pressure plate and the outer wall of the through hole fit together, and the rubber bag is inflated through the hose. The rubber bag expands to achieve sealing. The rubber bag inflation and sealing method can be applied to the working condition of uneven cave. At the same time, the application occasions of this technology are not limited to the circular inlet of hydraulic tunnel, and the rectangular (including square) inlet is also applicable. The sealing progress is monitored by a pressure gauge, thereby realizing the maintenance of the gate, embedded parts and cave, reducing the maintenance cost and avoiding pollution to the water body.
[0020] 2. The present invention drives the pressure plate to move to the same horizontal position as the hole body on the screw by a servo motor before use. After use, the hydraulic oil in the sealing cylinder is extracted by an oil pump and the rubber bag is deflated. After water enters the hole body, the water pressure on both sides of the pressure plate is basically constant, and the change of pressure in the sealing cylinder is coordinated to achieve the removal of the oil from the cylinder hole body. The overall process is easy to operate, saves human resources and effectively shortens the length of the construction period, and is worthy of vigorous promotion. BRIEF DESCRIPTION OF THE DRAWINGS
[0021] Figure 1 It is a structural schematic diagram of the present invention;
[0022] Figure 2 for Figure 1 The enlarged view of point A in the middle;
[0023] Figure 3 for Figure 1 The enlarged view of point B in the middle;
[0024] Figure 4 It is a front view of the cylinder barrel in the present invention;
[0025] Figure 5 It is a three-dimensional diagram of the cylinder in the present invention;
[0026] Figure 6 It is a schematic diagram of the internal structure of the sealing cylinder in the present invention.
[0027] Among them, 1. gate pier; 2. rack; 3. gate opening and closing machine; 4. gate; 5. cavern; 6. embedded parts; 7. air pump; 8. connecting pipe; 9. air distributor; 10. hose; 11. support frame; 12. pressure plate; 13. rubber bag; 14. insertion hole; 15. cylinder; 16. stiffening ring; 17. servo motor; 18. screw; 19. fixing plate; 20. sealing cylinder; 21. annular sealing plate; 22. connecting rod; 23. oil pipe; 24. oil tank; 25. oil pump; 26. control console; 27. solenoid valve; 28. pressure gauge; 29. limit rod; 30. exhaust valve; 31. connecting block. DETAILED DESCRIPTION
[0028] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0029] Embodiment 1:
[0030] like Figure 1-6As shown, an embodiment of the present invention provides a water-blocking steel plug for a water intake of a hydraulic tunnel, including a gate pier 1, a frame 2 is fixedly connected to the center of the top of the gate pier 1, a gate hoist 3 is fixedly connected to the middle of the top of the frame 2, the bottom output end of the gate hoist 3 passes through the gate pier 1 and is fixedly connected to a gate 4, a hole 5 is arranged at a position corresponding to the gate 4 at the bottom end of the gate pier 1, embedded parts 6 are arranged at the bottom end of the gate pier 1 at the right sides of the upper and lower ends of the gate 4, and an air pump 7 is fixedly connected to the left side of the top of the gate pier 1 near the frame 2. The left output end of the air pump 7 is fixedly connected to one end of the connecting pipe 8, and the other end of the connecting pipe 8 is fixedly connected to the input end of the gas distribution device 9. Five rubber hoses 10 are evenly and fixedly connected to the output end of the gas distribution device 9. The bottom ends of the rubber hoses 10 all penetrate the support frame 11 and the pressure plate 12 and are fixedly connected to rubber bags 13. An insertion hole 14 is provided at the middle end of the left top of the pressure plate 12 corresponding to the rubber hose 10. The right end of the pressure plate 12 is fixedly connected to a cylinder 15. Six stiffening rings 16 are evenly and fixedly connected on the outer diameter of the right side of the cylinder 15. The pressure plate 12, cylinder 15 and stiffening ring 16 are welded into a whole. The pressure plate 12, cylinder 15, stiffening ring 16 and rubber bag 13 constitute a steel plug body with automatic inflation and water-stopping functions, which is used at the entrance of a hydraulic tunnel to replace earth or steel cofferdams. During maintenance, the gate 4 is first closed, the pressure plate 12 is moved to the same level as the cave 5, and then the gate 4 is partially lifted. The force generated by the water flow is used to suck the cylinder 15 into the entrance of the cave 5. Due to the pressure of the water, the pressure plate 12 and the entrance of the cave 5 are The outer walls are fitted together, and the external gas is transmitted to the inside of the gas distribution device 9 through the connecting pipe 8 by the air pump 7. Under the action of the gas distribution device 9, the corresponding five rubber bags 13 are inflated through five rubber hoses 10. After the rubber bag 13 is inflated, it expands to achieve sealing. The method of inflating and sealing the rubber bag 13 can be applied to the working condition of the uneven cave body 5. The sealing is monitored by the pressure gauge 28. After the inflation is completed, the success of the sealing is observed through the valve shaft on the gate pier 1. Subsequently, the gate 4, cave body 5 and embedded parts 6 are inspected and repaired.
[0031] A servo motor 17 is fixedly connected to the middle position of the left end of the top of the support frame 11, and the driving end of the servo motor 17 passes through the support frame 11 and is fixedly connected to a screw rod 18. The bottom end of the screw rod 18 is rotatably connected to the center of the top of the fixed plate 19, and a connecting block 31 is threadedly connected to the outer diameter of the bottom of the screw rod 18 at a position corresponding to the pressure plate 12. A sealing cylinder 20 is fixedly connected to the center of the right end of the connecting block 31, and an annular sealing plate 21 is slidably connected to the right inner wall of the sealing cylinder 20. The center of the right end of the annular sealing plate 21 is fixedly connected to one end of a connecting rod 22, and the other end of the connecting rod 22 passes through the sealing cylinder 20 and It is fixedly connected to the center of the left end of the pressure plate 12, the left side of the top of the sealing cylinder 20 is fixedly connected to one end of the oil pipe 23, the other end of the oil pipe 23 passes through the oil tank 24 and is fixedly connected to the oil pump 25, and the middle position of the right end of the top of the gate pier 1 is fixedly connected to the control console 26, the hoist 3, the air pump 7, the servo motor 17 and the oil pump 25 are all connected to the control console 26 through the signal line. Before maintenance, the servo motor 17 drives the screw 18 to rotate, and the screw 18 drives the connection block 31 to rotate. Since the through holes on both sides of the connection block 31 are slidably connected to the limit rods 29, under the action of the limit rods 29 The connection block 31 is restricted from rotating with the screw 18, thereby realizing the linear movement of the connection block 31 on the screw 18, and the sealing cylinder 20 is driven by the connection block 31 to adjust its height in the vertical direction, so that the sealing cylinder 20 moves to a position at the same level as the hole 5, and then the cylinder 15 is sucked into the hole 5 under the action of the water flow. In this process, the pressure plate 12 moves toward the entrance of the hole 5, and the annular sealing plate 21 is realized to slide in the sealing cylinder 20 under the action of the connecting rod 22. When the pressure plate 12 fits the outer wall of the entrance of the hole 5, the hydraulic pressure in the oil tank 24 is pumped into the oil tank 24 through the oil pump 25. The oil is pumped into the sealing cylinder 20 through the oil pipe 23, and the exhaust valve 30 is opened to discharge the air inside the sealing cylinder 20. After the inspection is completed, the gate 4 is lowered to deflate the rubber bag 13. Then, the hydraulic oil in the sealing cylinder 20 is pumped into the oil tank 24 through the oil pipe 23 by the oil pump 25. At this time, the exhaust valve 30 is in a closed state. Under the action of the pressure change in the sealing cylinder 20 and the basically consistent water pressure on both sides of the pressure plate 12 after the water enters the hole body 5, the cylinder 15 is separated from the hole body 5, and then under the action of the servo motor 17, the sealing cylinder 20 is driven to return to its initial position.
[0032] A solenoid valve 27 is provided in the middle of the connecting pipe 8 , and the solenoid valve 27 is connected to the control console 26 through a signal line. A pressure gauge 28 is provided at the top of the rubber hose 10 near the gas distributor 9 .
[0033] The rubber bags 13 are fixedly connected between the stiffening rings 16. The stiffening rings 16 support and fix the rubber bags 13. When the rubber bags 13 are inflated, the horizontal expansion of the rubber bags 13 is limited, and the vertical expansion is used to achieve fit with the entrance of the cave 5. The support frame 11 is fixedly connected to the top left side of the gate pier 1.
[0034] Limit rods 29 are slidably connected in the through holes at symmetrical positions in the middle of the left and right sides of the connecting block 31. One end of the limit rod 29 is fixedly connected to the bottom end of the support frame 11 and the other end is fixedly connected to the top end of the fixing plate 19.
[0035] The oil pump 25 is fixedly connected to the left side of the inner wall at the bottom end of the oil tank 24, the oil tank 24 is fixedly connected to the bottom end of the support frame 11, and the exhaust valve 30 is fixedly connected to the right side of the top end of the sealing cylinder 20. The exhaust valve 30 is connected to the console 26 through a signal line, and the purpose of convenient operation is achieved through the console 26.
[0036] Embodiment 2:
[0037] An embodiment of the present invention provides a method for using a water-blocking steel plug for a water intake of a hydraulic tunnel, comprising the following steps:
[0038] S1. Before maintenance, the servo motor 17 drives the screw 18 to rotate, and the screw 18 drives the connection block 31 to rotate. Since the through holes on both sides of the connection block 31 are slidably connected with the limit rods 29, the connection block 31 is limited to rotate with the screw 18 under the action of the limit rods 29, so that the connection block 31 can move linearly on the screw 18. The sealing cylinder 20 is driven by the connection block 31 to adjust its height in the vertical direction, so that the sealing cylinder 20 moves to a position at the same level as the hole 5, and then the cylinder 15 is sucked into the hole 5 under the action of the water flow. In this process, the pressure plate 12 moves toward the entrance of the hole 5. Under the action of the connecting rod 22, the annular sealing plate 21 slides in the sealing cylinder 20. When the pressure plate 12 fits the outer wall of the entrance of the hole 5, the hydraulic oil in the oil tank 24 is pumped into the sealing cylinder 20 through the oil pipe 23 by the oil pump 25, and the exhaust valve 30 is opened to discharge the air inside the sealing cylinder 20.
[0039] S2. During maintenance, first close the gate 4, move the pressure plate 12 to the same level as the cave body 5, then partially lift the gate 4, and use the force generated by the water flow to suck the cylinder 15 into the entrance of the cave body 5. Due to the pressure of the water, the pressure plate 12 fits the outer wall of the entrance of the cave body 5, and the air pump 7 transmits the external gas to the inside of the gas distribution device 9 through the connecting pipe 8. Under the action of the gas distribution device 9, the five corresponding rubber bags 13 are inflated through the five rubber hoses 10. After the rubber bags 13 are inflated, they expand to achieve sealing. The method of inflating and sealing the rubber bags 13 can be applied to the working condition of the uneven cave body 5. The sealing is monitored by the pressure gauge 28. After the inflation is completed, the valve shaft on the gate pier 1 is used to observe whether the sealing is successful. Then, the gate 4, the cave body 5 and the embedded parts 6 are inspected;
[0040] S3. After the inspection is completed, the gate 4 is lowered, and the rubber bag 13 is deflated. Then, the hydraulic oil in the sealing cylinder 20 is pumped into the oil tank 24 through the oil pipe 23 by the oil pump 25. At this time, the exhaust valve 30 is closed. Under the action of the pressure change in the sealing cylinder 20 and the water pressure on both sides of the pressure plate 12 being basically the same after the water enters the hole 5, the cylinder 15 is separated from the hole 5. Then, under the action of the servo motor 17, the sealing cylinder 20 is driven to return to its initial position.
[0041] Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and that the scope of the present invention is defined by the appended claims and their equivalents.
Claims
1. A water-blocking steel plug for a water intake of a hydraulic tunnel, comprising a gate pier (1), characterized in that: A rack (2) is fixedly connected to the center of the top of the gate pier (1), a gate hoist (3) is fixedly connected to the middle of the top of the rack (2), the bottom output end of the gate hoist (3) passes through the gate pier (1) and is fixedly connected to the gate (4), a hole (5) is provided at the bottom of the gate pier (1) at a position corresponding to the gate (4), and embedded parts (6) are provided at the bottom of the gate pier (1) at the right sides of the upper and lower ends of the gate (4), an air pump (7) is fixedly connected to the left side of the top of the gate pier (1) near the rack (2), the left output end of the air pump (7) is fixedly connected to one end of a connecting pipe (8), the other end of the connecting pipe (8) is fixedly connected to the input end of an air distributor (9), and five rubber hoses (10) are evenly fixedly connected to the output end of the air distributor (9), and the bottom ends of the rubber hoses (10) all pass through the support frame (11). and a pressure plate (12) and are fixedly connected to a rubber bag (13); an insertion hole (14) is provided at a position corresponding to the rubber hose (10) at the middle end of the left top of the pressure plate (12); a cylinder (15) is fixedly connected to the right end of the pressure plate (12); six stiffening rings (16) are evenly fixedly connected to the right outer diameter of the cylinder (15); a servo motor (17) is fixedly connected to the middle position of the left top end of the support frame (11); a driving end of the servo motor (17) passes through the support frame (11) and is fixedly connected to a screw rod (18); the bottom end of the screw rod (18) is rotatably connected to the center of the top end of the fixing plate (19); a connecting block (31) is threadedly connected to the outer diameter of the bottom of the screw rod (18) at a position corresponding to the pressure plate (12); the connecting block (31) A sealing cylinder (20) is fixedly connected at the center of the right end, and an annular sealing plate (21) is slidably connected to the inner wall of the right side of the sealing cylinder (20). The annular sealing plate (21) is fixedly connected to one end of a connecting rod (22) at the center of the right end. The other end of the connecting rod (22) penetrates the sealing cylinder (20) and is fixedly connected to the center of the left end of the pressure plate (12). The left end of the top of the sealing cylinder (20) is fixedly connected to one end of an oil pipe (23). The other end of the oil pipe (23) penetrates an oil tank (24) and is fixedly connected to an oil pump (25). A control console (26) is fixedly connected to the middle position of the right end of the top of the gate pier (1). The hoist (3), the air pump (7), The servo motor (17) and the oil pump (25) are connected to the control console (26) via a signal line. A rubber bag (13) is fixedly connected between the stiffening rings (16). The support frame (11) is fixedly connected to the top left side of the gate pier (1). Limit rods (29) are slidably connected in through holes at symmetrical positions in the middle of the left and right sides of the connecting block (31). One end of the limit rod (29) is fixedly connected to the bottom end of the support frame (11) and the other end is fixedly connected to the top end of the fixed plate (19). An exhaust valve (30) is fixedly connected to the right side of the top end of the sealing cylinder (20).
2. The water-blocking steel plug for a water intake of a hydraulic tunnel according to claim 1, characterized in that: A solenoid valve (27) is provided in the middle of the connecting pipe (8), and the solenoid valve (27) is connected to the control console (26) via a signal line. A pressure gauge (28) is provided at the top of the rubber hose (10) near the gas distribution device (9).
3. The water-blocking steel plug for the water intake of a hydraulic tunnel according to claim 2, characterized in that: The oil pump (25) is fixedly connected to the left side of the inner wall at the bottom end of the oil tank (24), the oil tank (24) is fixedly connected to the bottom end of the support frame (11), and the exhaust valve (30) is connected to the control console (26) via a signal line.
4. The method for using the water-blocking steel plug for the water intake of a hydraulic tunnel according to claim 2 or 3, characterized in that: The following steps are involved: S1. Before the inspection, the servo motor (17) drives the screw rod (18) to rotate, and the screw rod (18) drives the connection block (31) to rotate. Since the through holes on both sides of the connection block (31) are slidably connected to the limit rods (29), the connection block (31) is limited to rotate along with the screw rod (18) under the action of the limit rods (29), thereby realizing the linear movement of the connection block (31) on the screw rod (18). The sealing cylinder (20) is driven by the connection block (31) to adjust its height in the vertical direction, so that the sealing cylinder (20) moves to a position at the same level as the hole body (5), and then the cylinder (15) is sucked into the hole body (5) under the action of the water flow. During this process, the pressure plate (12) moves toward the entrance of the cavity (5), and under the action of the connecting rod (22), the annular sealing plate (21) slides in the sealing cylinder (20). When the pressure plate (12) is in contact with the outer wall of the entrance of the cavity (5), the hydraulic oil in the oil tank (24) is pumped into the sealing cylinder (20) through the oil pipe (23) by the oil pump (25), and the exhaust valve (30) is opened to discharge the air inside the sealing cylinder (20). S2. During maintenance, the gate (4) is first closed, the pressure plate (12) is moved to the same level as the cavern (5), and then the gate (4) is partially lifted. The force generated by the water flow is used to suck the cylinder (15) into the entrance of the cavern (5). Due to the pressure of the water, the pressure plate (12) fits the outer wall of the entrance of the cavern (5). The air pump (7) transmits the external gas to the inside of the gas distribution device (9) through the connecting pipe (8). Under the action of the gas distribution device (9), the corresponding five rubber bags (13) are inflated through five rubber hoses (10). After the rubber bags (13) are inflated, they expand to achieve sealing. The method of inflating and sealing the rubber bags (13) is suitable for working conditions where the cavern (5) is uneven. The sealing is monitored by a pressure gauge (28). After the inflation is completed, the valve shaft on the gate pier (1) is used to observe whether the sealing is successful. Subsequently, the gate (4), the cavern (5) and the embedded parts (6) are inspected. S3. After the inspection is completed, the gate (4) is lowered and the rubber bag (13) is deflated. Then, the hydraulic oil in the sealing cylinder (20) is pumped into the oil tank (24) through the oil pipe (23) by the oil pump (25). At this time, the exhaust valve (30) is closed. Under the action of the pressure change in the sealing cylinder (20) and the water pressure on both sides of the pressure plate (12) being basically the same after the water enters the hole (5), the cylinder (15) is separated from the hole (5). Subsequently, under the action of the servo motor (17), the sealing cylinder (20) is driven to return to the initial position.