A water tank overflow replenishment system for loading elevators

By setting up multiple water storage tanks in the elevator shaft and using overflow and water replenishment structures, combining gravity adjustment and float valve control, the problems of large energy consumption and water potential energy loss of the elevator system are solved, and the balanced operation and energy saving of the elevator system are achieved.

CN113443537BActive Publication Date: 2024-11-05GUANGDONG XINWEN ENERGY CONTROL TECH RES CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202110722642.2
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2021-06-28
Publication Date
2024-11-05
Estimated Expiration
2041-06-28

AI Technical Summary

Technical Problem

The existing elevator systems consume huge energy and lack energy recovery systems, resulting in huge recyclable energy being wasted, and the loading system has problems of balance and loss in terms of water potential energy.

Method used

Design a water storage tank overflow and water replenishment system for loading elevators. By setting up multiple water storage tanks in the elevator shaft, and using overflow and water replenishment structures, combined with gravity adjustment, we ensure the balance of water storage volume in each floor and minimize potential energy loss. , adopts float valve and water pump control valve to achieve automatic water replenishment and overflow.

Benefits of technology

It effectively ensures the balanced operation of the loading system, reduces water potential energy loss, avoids waste of water resources, and realizes energy-saving elevator operation.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN113443537B_ABST
    Figure CN113443537B_ABST
Patent Text Reader

Abstract

The present invention provides a water tank overflow replenishment system for loading elevators. A plurality of buffer water tanks are provided. The water tanks are provided at the floors where the elevators stop in the elevator shaft. The overflow outlet of the water tank on the upper floor is connected to the overflow inlet of the water tank on the lower floor through an overflow pipe, and the replenishment outlet of the water tank on the upper floor is connected to the replenishment inlet of the water tank on the lower floor through a replenishment pipe. Water tanks are provided on each floor where the elevator stops, and the water tanks on the upper and lower floors are connected. An overflow structure and a replenishment structure are formed between the water tanks on the upper and lower floors. The vertical system is adjusted by utilizing gravity. When the water storage is saturated, water is discharged to the water tank on the lower floor. When the water storage is insufficient, water is requested from the water tank on the upper floor, so that each floor has enough water storage for loading at every moment, and the replenishment system of the entire loading system is balanced, thereby realizing balanced operation of the loading system.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of elevators, and in particular to an overflow water replenishing system of a water storage tank for loading elevators. Background Art

[0002] There are many types of elevators nowadays, but the principles are basically the same. The car and counterweight are connected by traction cables, and the operation of the elevator is achieved by controlling the cables.

[0003] Existing elevators still have many shortcomings. For example, elevators consume a lot of energy. Elevators need to pull heavy objects to move vertically, and a lot of energy is converted into the potential energy of the heavy objects, so the energy consumption is naturally very high. In addition, elevators do not have an energy recovery system, so huge recoverable energy is wasted.

[0004] In order to solve the current problem of huge energy consumption of elevators, for example, 201510929005.7, the balanced dragging scheme of the traction system of the elevator counterweight dynamically compensates the balanced load, this patent application provides a solution for the counterweight to dynamically compensate the balanced load, and constructs a loaded elevator that can consume energy.

[0005] However, the above application only provides a theoretical solution and cannot be directly implemented. However, how to construct an energy-saving water replenishment system to ensure the balance of the water replenishment system of the entire loading system and minimize the potential energy loss of water is one of the core difficulties of loading elevators. Summary of the invention

[0006] The purpose of the present invention is to provide a water tank overflow replenishment system for loading elevators, which can ensure that the entire loading system does not lose balance due to water overflowing, and at the same time ensure that the potential energy loss of water is minimized.

[0007] The technical solution adopted by the present invention to solve its technical problem is:

[0008] A water tank overflow replenishment system for a loading elevator, comprising a plurality of water tanks, the water tanks being arranged at floors where elevators stop in an elevator shaft, and being used to counterweight the loading water tanks of the loading elevator;

[0009] The water storage tank has an overflow outlet, an overflow inlet, a water replenishment outlet, a water replenishment inlet and an air vent, and the position of the overflow outlet is higher than the position of the water replenishment outlet;

[0010] The overflow outlet of the water storage tank located at the upper layer is connected to the overflow inlet of the water storage tank located at the lower layer through an overflow pipe;

[0011] The water replenishment outlet of the water storage tank located at the upper layer is connected to the water replenishment inlet of the water storage tank located at the lower layer through a water replenishment pipe;

[0012] The water supply pipe is provided with a valve, and the water tank is set with a water shortage line. When the water storage amount in the water tank is lower than the water shortage line, the valve of the water supply pipe connected to the water supply inlet of the water tank on the current floor is opened; when the water storage amount in the water tank is higher than the water shortage line, the valve of the water supply pipe connected to the water supply inlet of the water tank on the current floor is closed.

[0013] Furthermore, the water shortage line is located at a water capacity that accommodates 1-1.5 times the rated load of the elevator.

[0014] Furthermore, the valve is a float valve, and the float valve is arranged at the lower port of the water supply pipe.

[0015] Furthermore, it also includes a cache water tank, which is provided in multiples. The cache water tank is arranged at the floor where the elevator stops. The cache water tank is connected to the water storage tank located on the same floor, and the bottom of the cache water tank is connected to the bottom of the water storage tank.

[0016] Furthermore, the cache water tank is arranged at regular intervals between floors, and must be arranged at the topmost floor and the bottommost floor.

[0017] Furthermore, the cache water tank has a return water outlet, a return water inlet and a second air vent, and the position of the return water inlet is higher than the position of the return water outlet;

[0018] The return water outlet of the cache water tank located at the lower layer is connected to the return water inlet of the cache water tank located at the upper layer through a return water pipe;

[0019] The return pipe is provided with a water pump. When the water storage amount in the cache water tank is lower than the water shortage line, the water pump of the return pipe connected to the return water inlet of the cache water tank on the current floor is turned on. When the water storage amount in the cache water tank is higher than the water shortage line, the water pump of the return pipe connected to the return water inlet of the cache water tank on the current floor is turned off.

[0020] Furthermore, the water shortage line is located at a water capacity that accommodates 1-1.5 times the rated load of the elevator.

[0021] Furthermore, the cache water tank is provided with a float switch, and the float switch is connected to a water pump signal of a return pipe connected to a return water inlet of the cache water tank at the current layer.

[0022] Furthermore, the cache water tank is connected to a wastewater access pipe.

[0023] Furthermore, the cache water tank is connected to a tap water access pipe.

[0024] The beneficial effects of the present invention are:

[0025] By adopting the above technical scheme, the water tank overflow and water replenishment system for loading elevators of the present invention is provided with a water tank on each floor where the elevator stops, and the water tanks on the upper and lower layers are connected, and an overflow structure and a water replenishment structure are formed between the water tanks on the upper and lower layers. The vertical system is adjusted by utilizing gravity. When the water storage capacity is saturated, water is discharged to the water tank on the lower layer. When the water storage capacity is insufficient, water is requested from the water tank on the upper layer, so that each floor has sufficient water storage for loading at all times, thereby ensuring that the water replenishment system of the entire loading system is balanced, thereby achieving balanced operation of the loading system. BRIEF DESCRIPTION OF THE DRAWINGS

[0026] The present invention is further described below in conjunction with the accompanying drawings and embodiments.

[0027] Figure 1 It is a first structural schematic diagram of the overflow water replenishment system of the present invention;

[0028] Figure 2 It is a schematic diagram of the main structure of the water storage tank of the present invention;

[0029] Figure 3 It is a schematic diagram of the overflow structure of the water storage tank of the present invention;

[0030] Figure 4 It is a schematic diagram of the water replenishment structure of the water storage tank of the present invention;

[0031] Figure 5 It is a second structural schematic diagram of the overflow water replenishment system of the present invention;

[0032] Figure 6 It is a schematic diagram of the water return structure of the buffer water tank of the present invention;

[0033] Figure 7 It is a schematic diagram of the overflow structure of the overflow water replenishment system of the present invention;

[0034] Figure 8 It is a schematic diagram of the water replenishment structure of the overflow water replenishment system of the present invention.

[0035] Figure numerals: 1. Water storage tank; 11. Overflow outlet; 12. Overflow inlet; 13. Water replenishment outlet; 14. Water replenishment inlet; 15. First air vent; 16. Outlet connected to the distribution water tank; 2. Overflow pipe; 3. Wastewater inlet pipe; 4. Tap water inlet pipe; 5. Wastewater discharge pipe; 6. Water replenishment pipe; 61. Valve; 7. Buffer water tank; 71. Return water outlet; 72. Return water inlet; 73. Second air vent; 8. Return water pipe; 81. Water pump; 82. Float switch. DETAILED DESCRIPTION

[0036] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0037] like Figure 1-4 As shown, a water tank overflow water replenishment system for a loading elevator comprises a plurality of water tanks 1, wherein the water tanks 1 are arranged at the floors where the elevators stop in the elevator shaft, and are used to counterweight the loading water tanks of the loading elevators; the water tanks 1 have an overflow outlet 11, an overflow inlet 12, a water replenishment outlet 13, a water replenishment inlet 14 and a first vent 15, wherein the overflow outlet 11 is located higher than the water replenishment outlet 13; the overflow outlet 11 of the water tank 1 located at the upper layer and the overflow inlet 12 of the water tank 1 located at the lower layer are connected to each other. The two layers are connected via an overflow pipe 2; the water replenishment outlet 13 of the water storage tank 1 on the upper layer is connected to the water replenishment inlet 14 of the water storage tank 1 on the lower layer via a water replenishment pipe 6; the cache water tank water replenishment pipe 6 is provided with a valve 61, when the water storage amount in the water storage tank 1 is lower than the set value, the valve 61 of the water replenishment pipe 6 connected to the water replenishment inlet 14 of the water storage tank 1 on the current layer is opened, and when the water storage amount in the water storage tank 1 is higher than the set value, the valve 61 of the water replenishment pipe 6 connected to the water replenishment inlet 14 of the water storage tank 1 on the current layer is closed.

[0038] The reason for constructing the overflow water replenishment system is that, because the operation mode of the loading elevator is to balance the loading through the weight in the elevator car, the loading system will bring the water used for configuration to different floors. For example, the loading system replenishes water on the fifth floor, and then discharges water on the eighth and tenth floors, which will reduce the water storage capacity of the water tank 1 on the fifth floor, and increase the water storage capacity of the water tank 1 on the eighth and tenth floors. At this time, if there is no water replenishment structure, the water storage capacity of the water tank 1 on the fifth floor may be insufficient to continue to provide water for the loading system next time; if there is no overflow structure, the water storage capacity of the water tank 1 on the eighth and tenth floors may overflow directly, resulting in excessive loss of the total water volume of the system. Even if the water tank 1 is designed to be large, this situation cannot be completely avoided, and it is impossible to set up a large water tank 1 on each floor, and if tap water input is connected to each floor, it will lead to a huge waste of water resources.

[0039] The implementation method is as follows: a water tank 1 is provided on each floor where the elevator stops, and the water tanks 1 on the upper and lower floors are connected. The vertical system is adjusted by utilizing gravity, so that each floor has sufficient water storage for loading at all times, ensuring the balance of the water replenishment system of the entire loading system, thereby achieving balanced operation of the loading system.

[0040] An overflow structure and a water replenishment structure are formed between the upper and lower water storage tanks 1. When the water storage capacity of the water storage tank 1 located at the upper layer is saturated, water is discharged to the water storage tank 1 located at the lower layer through the overflow structure; when the water storage capacity of the water storage tank 1 located at the lower layer is insufficient, water is requested from the water storage tank 1 located at the upper layer through the water replenishment structure; the combination of the overflow structure and the water replenishment structure ensures that the water storage tank 1 will not be short of water to affect the configuration work, and the total water volume of the system will not be excessively lost due to overflow.

[0041] The implementation method of the water replenishment structure is as follows Figure 4 , 8 As shown, the water tank 1 is set with a water shortage line, and the unit of the water shortage line is 1Q, where 1Q is the water capacity equal to 1-1.5 times the rated load of the elevator used. When the water storage capacity of the water tank 1 is lower than 1Q, the valve 61 of the water supply pipe 6 connected to the water supply inlet 14 of the water tank 1 on the current floor is opened to request water from the water tank 1 on the upper floor until the water storage capacity is replenished to 1Q and then the valve 61 is closed. The water tank 1 on each floor will implement this step, so that the water tank 1 on each floor will always have enough water storage capacity to provide to the loading system. Among them, the water tank 1 on the top floor is special because there is no water tank 1 on the upper floor. When the water storage capacity of the water tank 1 on the top floor is less than 1Q, water will be introduced from the wastewater access pipe 3 or the tap water access pipe 4. The wastewater access pipe 3 is preferred to introduce water, and the tap water access pipe 4 is generally used for emergency use. When the wastewater on the floor is used up, water will be introduced from the tap water access pipe 4. The wastewater access pipe 3 can be connected to rainwater recovery, domestic wastewater recovery, overflow recovery of the water tank 1 on the bottom floor, etc.

[0042] Among them, valve 61 is a float valve, which is arranged at the lower end of the water supply pipe 6, and the lower end of the water supply pipe 6 is arranged at the position of the water shortage line. When the water storage amount of the water storage tank 1 is higher than the water shortage line, the float valve closes the lower end of the water supply pipe 6. When the water storage amount of the water storage tank 1 is lower than the water shortage line, the float valve opens the lower end of the water supply pipe 6.

[0043] The implementation method of the overflow structure is as follows: Figure 3 , 7As shown, a saturation line of a water tank 1 is set. The saturation line is determined by the water capacity of the water tank 1. The water capacity of the water tank 1 is generally about 2Q, and the saturation line is about 1.7Q. The overflow outlet 11 is set at the saturation line. When the water storage capacity of the water tank 1 is higher than the overflow outlet 11, the water will be discharged to the water tank 1 located at the lower layer through the overflow pipe 2 until the replenishment water storage capacity is lower than the overflow outlet 11. Each layer of the water tank 1 will implement this step, and only when the water in the water tank 1 at the bottom layer overflows, it will directly flow out of the water storage system through the wastewater discharge pipe 5. The key point is that if only the water in the water tank 1 at the second layer overflows, the water in the water tank 1 at the second layer and the water tank 1 at the bottom layer must overflow at the same time to overflow the water out of the water storage system, and so on. Furthermore, when the loading system is in operation, the water storage capacity of each layer of the water storage tank 1 will be used. As a result, the water in the higher layer of the water storage tank 1 is more difficult to overflow the water storage system through the overflow structure, and the water in the water storage tanks 1 above the second layer will basically not overflow the water storage system. The total water volume of the entire water storage system will not be excessively lost due to overflow, and there is no need to frequently introduce water from the outside.

[0044] During the overflow water replenishment process, the negative pressure in the water storage tank 1 is stabilized through the first air vent 15 .

[0045] The further structure of the above overflow water replenishment system is as follows: Figure 5-6 As shown, a cache water tank 7 is introduced, and multiple cache water tanks 7 are provided. The cache water tank 7 is provided at the floor where the elevator stops. The cache water tank 7 is connected to the water storage tank 1 located on the same floor, and the cache water tank 7 is connected to the bottom of the water storage tank 1. Since the water storage tank 1 is provided in the elevator shaft, the volume cannot be set too large to avoid wasting the design space of the elevator shaft or affecting the operation of the elevator. The cache water tank 7 is introduced to increase the actual maximum water storage capacity of the water storage tank 1. The cache water tank 7 can be placed outside the elevator shaft and connected to the water storage tank 1 through a pipe. Since the cache water tank 7 is connected to the bottom of the water storage tank 1, the actual water storage capacity of the cache water tank 7 is equal to the actual water storage capacity of the connected water storage tank 1.

[0046] In order to save space, it is not necessary to set up a buffer water tank 7 on each floor. A buffer water tank 7 can be set up at certain intervals, which can basically meet the requirements of perfect operation of the system. However, after the introduction of the buffer water tank 7, the top floor and the bottom floor must be equipped with the buffer water tank 7, otherwise the meaning of introducing the buffer water tank 7 is lost. The buffer water tank 7 on the top floor can most effectively store water for the entire overflow water replenishment system, and the buffer water tank 7 on the bottom floor can most effectively prevent the entire overflow water replenishment system from overflowing.

[0047] In this further structure, a return water structure is formed, and the cache water tank 7 has a return water outlet 71, a return water inlet 72 and a second air vent 73, and the position of the return water inlet 72 is higher than the position of the return water outlet 71; the return water outlet 71 of the cache water tank 7 located at the lower layer is connected to the return water inlet 72 of the cache water tank 7 located at the upper layer through a return water pipe 8; the return water pipe 8 is provided with a water pump 81, when the water storage amount of the cache water tank 7 is lower than the set value, the water pump 81 of the return water pipe 8 connected to the return water inlet 72 of the cache water tank 7 of the current layer is turned on, and when the water storage amount in the cache water tank 7 is higher than the set value, the water pump 81 of the return water pipe 8 connected to the return water inlet 72 of the cache water tank 7 of the current layer is turned off.

[0048] The implementation method of the water return structure is as follows: Figure 6 , 8 As shown, when the actual water storage capacity of the cache water tank 7 is lower than the water shortage line, the water pump 81 of the return water pipe 8 connected to the return water inlet 72 of the cache water tank 7 on the current layer is turned on to ask for water from the cache water tank 7 on the lower layer until the actual water storage capacity is replenished to 1Q and then the water pump 81 is turned off. The position of the return water outlet 71 is generally higher than the water shortage line. When the actual water storage capacity of the cache water tank 7 on the lower layer is lower than the water shortage line, even if the actual water storage capacity of the cache water tank 7 on the upper layer is lower than the water shortage line, the cache water tank 7 on the lower layer cannot provide water for the cache water tank 7 on the upper layer. If the cache water tank 7 on the lower layer cannot provide water for the cache water tank 7 on the upper layer, water can be introduced from the wastewater access pipe 3 or the tap water access pipe 4.

[0049] During the water return process, the negative pressure in the buffer water tank 7 is stabilized through the second air vent 73 .

[0050] Among them, the cache water tank 7 is provided with a float switch 82, and the float switch 82 is connected to the signal of the water pump 81 of the return pipe 8 connected to the return water inlet 72 of the cache water tank 7 on the current layer. The float switch 82 is set at the water shortage line. When no water contacts the float switch 82, the float switch 82 sends an open signal to the water pump 81.

[0051] In addition, when the actual water storage capacity of the buffer water tank 7 is lower than 1Q, water will be introduced from the wastewater access pipe 3 or the tap water access pipe 4. The wastewater access pipe 3 is preferred to be used for water introduction, and the tap water access pipe 4 is generally used for emergency use. When the wastewater on the floor is used up, water will be introduced from the tap water access pipe 4. Generally, during the process of overflow, water replenishment, and water return, this step is performed only when a certain link of the internal circulation cannot be executed.

[0052] It will be apparent to those skilled in the art that the invention is not limited to the details of the exemplary embodiments described above and that the invention can be implemented in other specific forms without departing from the spirit or essential features of the invention. Therefore, the embodiments should be considered exemplary and non-limiting in all respects, and the scope of the invention is defined by the appended claims rather than the foregoing description, and it is intended that all variations falling within the meaning and scope of the equivalent elements of the claims be included in the invention. Any reference numeral in a claim should not be considered as limiting the claim to which it relates.

Claims

1. A water tank overflow replenishment system for loading elevators, Features: It comprises a plurality of water storage tanks (1), wherein the water storage tanks (1) are arranged at floors where elevators stop in an elevator shaft and are used to provide counterweight for the loading water tanks of the loading elevators; The water storage tank (1) comprises an overflow outlet (11), an overflow inlet (12), a water replenishment outlet (13), a water replenishment inlet (14) and a first air vent (15), wherein the position of the overflow outlet (11) is higher than the position of the water replenishment outlet (13); The overflow outlet (11) of the water storage tank (1) located at the upper layer is connected to the overflow inlet (12) of the water storage tank (1) located at the lower layer via an overflow pipe (2); The water replenishment outlet (13) of the water storage tank (1) located at the upper layer is connected to the water replenishment inlet (14) of the water storage tank (1) located at the lower layer via a water replenishment pipe (6); The water supply pipe (6) is provided with a valve (61), and the water storage tank (1) is set with a water shortage line. When the water storage amount of the water storage tank (1) is lower than the water shortage line, the valve (61) of the water supply pipe (6) connected to the water supply inlet (14) of the water storage tank (1) on the current floor is opened, and when the water storage amount in the water storage tank (1) is higher than the water shortage line, the valve (61) of the water supply pipe (6) connected to the water supply inlet (14) of the water storage tank (1) on the current floor is closed; a cache water tank (7), wherein a plurality of cache water tanks (7) are provided, and the cache water tanks (7) are provided at the floor where the elevator stops, and the cache water tanks (7) are connected to the water storage tank (1) on the same floor, and the bottom of the cache water tank (7) is connected to the bottom of the water storage tank (1); The buffer water tank (7) has a return water outlet (71), a return water inlet (72) and a second air vent (73), and the position of the return water inlet (72) is higher than that of the return water outlet (71); The return water outlet (71) of the cache water tank (7) located at the lower layer is connected to the return water inlet (72) of the cache water tank (7) located at the upper layer via a return water pipe (8), and the return water outlet (71) of the cache water tank (7) located at the uppermost layer is closed; The return water pipe (8) is provided with a water pump (81). When the water storage amount in the cache water tank (7) is lower than the water shortage line, the water pump (81) of the return water pipe (8) connected to the return water inlet (72) of the cache water tank (7) at the current layer is turned on. When the water storage amount in the cache water tank (7) is higher than the water shortage line, the water pump (81) of the return water pipe (8) connected to the return water inlet (72) of the cache water tank (7) at the current layer is turned off.

2. A water tank overflow replenishment system for loading elevators according to claim 1, Features: The water shortage line is located at a water capacity that accommodates 1-1.5 times the rated load of the elevator.

3. A water tank overflow replenishment system for loading elevators according to claim 1, Features: The valve (61) is a float valve, and the float valve is arranged at the lower end of the water supply pipe (6).

4. A water tank overflow replenishment system for loading elevators according to claim 1, Features: The buffer water tank (7) is arranged at regular intervals between floors, and must be arranged on the topmost floor and the bottommost floor.

5. A water tank overflow replenishment system for loading elevators according to claim 1, Features: The cache water tank (7) is provided with a float switch (82), and the float switch (82) is connected to the signal of a water pump (81) of a return water pipe (8) connected to the return water inlet (72) of the cache water tank (7) at the current layer.

6. A water tank overflow replenishment system for loading elevators according to claim 1, Features: The cache water tank (7) is connected to a wastewater access pipe (3).

7. A water tank overflow replenishment system for loading elevators according to claim 1, Features: The cache water tank (7) is connected to a tap water inlet pipe (4).