A production allocation design method for controlling the pressure drop rate of gas wells

By calculating the gas production per unit pressure drop in the gas well and adjusting the production allocation, the problem of high cost and difficulty in controlling the pressure drop speed of the gas well is solved, and low-cost and highly operable pressure drop speed adjustment is achieved, which has good promotion value.

CN113515833BActive Publication Date: 2024-10-11CHINA PETROLEUM & CHEMICAL CORP +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202010275839.1
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2020-04-09
Publication Date
2024-10-11
Estimated Expiration
2040-04-09

AI Technical Summary

Technical Problem

In the production process of gas wells, especially low-permeability gas wells, the existing technology for controlling the pressure drop rate of gas wells requires testing to determine changes in formation pressure, which is costly and difficult, and has poor practicality.

Method used

By determining the wellhead casing pressure and cumulative gas production when the gas well reaches the pseudo-stable production stage, the gas production per unit pressure drop is calculated, and the production allocation is adjusted according to the target pressure drop speed to control the pressure drop speed and achieve low pressure drop without obtaining formation pressure change data. Low cost, high operability design.

Benefits of technology

It realizes the adjustment of gas well pressure drop speed without formation pressure change data, reduces costs, improves the operability and practicality of the design, and has good promotion value.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN113515833B_ABST
    Figure CN113515833B_ABST
Patent Text Reader

Abstract

The present invention belongs to the technical field of gas field development, and specifically relates to a production allocation design method for controlling the pressure drop rate of a gas well. The method first determines the unit pressure drop gas production q of the gas well according to the wellhead casing pressure and the corresponding cumulative gas production in the quasi-stable production stage of the gas well. unitp The quasi-stable production stage refers to the period of time when the wellhead casing pressure and time are linearly changing; then according to the target pressure drop rate DPR obj And the gas production per unit pressure drop q unitp , substitute into the formula q obj =DPR obj ×q unitp The target pressure drop rate DPR is calculated obj The corresponding gas well design production allocation q obj ; Finally, refer to the target pressure drop rate DPR obj The corresponding gas well design production allocation q obj , adjust the production allocation of the gas well to adjust the pressure drop rate to the target pressure drop rate. The present invention can adjust the pressure drop rate to the target pressure drop rate without obtaining formation pressure change data, has low cost, strong operability, effectiveness and practicality, and has good promotion and use value.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the technical field of gas field development, and in particular relates to a production allocation design method for controlling the pressure drop rate of a gas well. Background Art

[0002] In the production process of gas wells, especially those in low-permeability gas reservoirs, it is necessary to control the pressure drop rate of the gas wells to maintain the formation pressure of the gas wells and provide sufficient lifting energy for the gas wells to carry liquid, so as to achieve stable production of the gas wells. How to quantitatively design the gas well production allocation to control the pressure drop rate around the target value? In the existing technology, it is necessary to test and determine the change of the formation pressure of the gas wells. The application cost is relatively high and difficult, and the practicality is poor. Summary of the invention

[0003] The present invention provides a production allocation design method for controlling the pressure drop rate of a gas well, which is used to solve the problems of high cost and great difficulty caused by the need to determine the change of the formation pressure of the gas well in the prior art.

[0004] In order to solve the above technical problems, the technical solution of the present invention includes:

[0005] The present invention provides a production allocation design method for controlling the pressure drop rate of a gas well, comprising the following steps:

[0006] 1) According to the wellhead casing pressure and the corresponding cumulative gas production in the quasi-stable production stage of the gas well, determine the unit pressure drop gas production q of the gas well unitp ; The quasi-stable production stage refers to the period of time when the wellhead casing pressure and time change linearly;

[0007] 2) According to the target pressure drop rate DPR obj And the gas production per unit pressure drop q unitp , substitute into the formula q obj =DPR obj ×q unitp The target pressure drop rate DPR is calculated obj The corresponding gas well design production allocation q obj :

[0008] 3) Refer to the target pressure drop rate DPR obj The corresponding gas well design production allocation q obj , adjust the production allocation of the gas well to adjust the pressure drop rate to the target pressure drop rate.

[0009] The beneficial effects of the above technical solution are as follows: the present invention utilizes the wellhead casing pressure and the corresponding cumulative gas production when the gas well reaches the quasi-stable production stage, and can determine the unit pressure drop gas production of the gas well according to the flow material balance theory, and then multiply the unit pressure drop gas production and the target pressure drop rate to obtain the gas well design production corresponding to the target pressure drop rate. Compared with the method of obtaining formation pressure, the method of obtaining wellhead casing pressure is simple, so that the pressure drop rate can be adjusted to the target pressure drop rate without obtaining the formation pressure change data, which is low in cost, strong in operability, effective and practical, and has a good value for promotion and use.

[0010] Furthermore, the gas production per unit pressure drop q of the gas well is determined according to the wellhead casing pressure and the corresponding cumulative gas production in the quasi-stable production stage of the gas well. unitp The method includes: performing linear fitting on the wellhead casing pressure and the corresponding cumulative gas production in the quasi-stable production stage of the gas well to obtain a linear relationship expression between the wellhead casing pressure and the cumulative gas production, and determining the unit pressure drop gas production q of the gas well according to the linear relationship expression. unitp . BRIEF DESCRIPTION OF THE DRAWINGS

[0011] Figure 1 It is a flow chart of the production allocation design method for controlling the pressure drop rate of a gas well of the present invention;

[0012] Figure 2 It is a schematic diagram of the change of the wellhead casing pressure and the cumulative gas production during the period of the proposed stable production of the gas well of the present invention;

[0013] Figure 3 It is a schematic diagram of the change of the wellhead casing pressure with time during the simulated stable production time period of the gas well of the present invention. DETAILED DESCRIPTION

[0014] Based on the relationship between the gas production of a gas well, the pressure drop rate of a gas well and the elastic capacity of a gas well (gas production per unit pressure drop), the present invention can quantitatively design the gas well production allocation to control its pressure drop rate to be around the target pressure drop rate. The derivation process of the relationship between the above three is first described below.

[0015] 1. Derivation of the relationship model between gas well pressure drop rate and gas well gas production

[0016] Let the total gas-bearing pore volume in the gas supply area controlled by the gas well be V, and the gas reservoir temperature be T. The changes of the two are very small during the entire development process, so it is assumed that the two remain unchanged during the development process. Let the average pressure in the gas supply area of ​​the gas well at time a be P a , the number of moles of gas is n a , the gas deviation factor is Z a ; Let the average pressure in the gas well control area at time b be P b , the number of moles of gas is n b, the gas deviation factor is Z b .

[0017] The ratio of pressure to deviation factor is defined as pseudo-pressure, that is:

[0018]

[0019] Then the pseudo-pressure ratios at time a and time b are:

[0020]

[0021]

[0022] Then the gas state equation of the gas supply area of ​​gas well a is:

[0023] P a V=Z a n a RT (4)

[0024] Similarly, the gas state equations in the gas supply area of ​​the gas well at time b are:

[0025] P b V=Z b n b RT (5)

[0026] From formula (2) and formula (4), we can get:

[0027] P sa V=n a RT (6)

[0028] From formula (3) and formula (5), we can get:

[0029] P sb V=n b RT (7)

[0030] From formula (6) and formula (7), we can get:

[0031] (P sa -P sb )V=(n a -n b )RT (8)

[0032] Let the number of production days from time a to time b be Δt days, and the average daily surface gas production be q sc , the surface density of the produced gas is ρ sc , then during this period, the gas mass produced by the gas reservoir is:

[0033] m=ρ sc q sc Δt (9)

[0034] Let the molar molecular weight of natural gas be M. Then, according to the relationship between the number of moles and mass of produced natural gas, we can get:

[0035] m=(n a -n b )M (10)

[0036] From formula (9) and formula (10), we can get:

[0037] ρ sc q sc Δt=(n a -n b )M 11)

[0038] From formula (11), we can get:

[0039]

[0040] From equation (8) and equation (12), we can get:

[0041]

[0042] If the production time Δt from time a to time b is not very long and the gas output is not too much, the formation pressure will not change much. Therefore, it can be approximately considered that the deviation factors at time a and time b are approximately equal and equal to the deviation factor under the average formation pressure during the production period between the two moments. (referred to as the average deviation factor during the production period), that is:

[0043]

[0044] From equation (2), equation (3) and equation (14), we can get:

[0045]

[0046] From formula (13) and formula (15), we can get:

[0047]

[0048] Let the formation pressure drop rate from time a to time b be DPR, that is:

[0049]

[0050] From equation (16) and equation (17), we can get:

[0051]

[0052] Formula (18) is the relationship model between the pressure drop rate of a gas well and its gas production. It can be seen from the model that the pressure drop rate in the gas supply area of ​​a gas well is directly proportional to its gas production, and inversely proportional to the gas-bearing pore volume in the gas supply area.

[0053] 2. Derivation of gas well design production allocation model under target pressure drop rate

[0054] From formula (16), we get:

[0055]

[0056] Let the cumulative gas production volume of the gas well from time a to time b be Q cum , then we have:

[0057] Q cum =q sc Δt (20)

[0058] From formula (19) and formula (20), we can get:

[0059]

[0060] From formula (21), we get:

[0061]

[0062] From formula (18) and formula (22), we can get:

[0063]

[0064] make:

[0065]

[0066] From equation (23) and equation (24), we can get:

[0067] q sc =DPR×q unitp (25)

[0068] Formula (25) is the gas well production allocation model based on pressure drop rate, q sc is the gas production of the gas well, DPR is the pressure drop rate of the gas well, q unitp It is the gas production under unit pressure drop of the gas well (elastic production capacity of the gas well). According to the theory of flow material balance, when the gas well reaches the quasi-stable seepage state, the change value of the wellhead casing pressure (casing pressure drop rate) and the change value of the formation pressure (formation pressure drop rate) are basically consistent. In practical applications, the relationship between the cumulative gas production of the gas well and the wellhead casing pressure can be linearly fitted to obtain the unit pressure drop gas production of the gas well after reaching the quasi-stable stage.

[0069] On this basis, a production allocation design method for controlling the pressure drop rate of a gas well of the present invention can be realized, and its process is as follows: Figure 1 shown.

[0070] Step 1: According to the dynamic data of the gas well, the data of the gas well reaching the quasi-stable production stage are selected for analysis. In this stage, the wellhead casing pressure and time have a linear change relationship, and the production data in this time period is called the quasi-stable production data segment.

[0071] Step 2: Based on the wellhead casing pressure and the corresponding cumulative gas production data in the quasi-stable production data segment in step 1, a linear relationship expression is obtained by fitting the two, and the gas production per unit pressure drop q of the gas well is determined by using methods such as flow material balance. unitp .

[0072] Step 3: According to the target pressure drop rate DPR obj And the gas production per unit pressure drop q unitp , by formula q obj =DPR obj ×q unitp Then you can get the speed reduction DPR of the target location. obj The corresponding gas well design production allocation q obj . Refer to the gas well design production allocation q obj , adjust the production allocation of the gas well to adjust the pressure drop rate to the target pressure drop rate.

[0073] The following is an application of this method to a specific example to illustrate the effectiveness of this method. For example, the relationship curve between the wellhead casing pressure and time of the XX gas well one year after it was put into production is as follows: Figure 3 As shown in the figure, the horizontal axis is the time Date, and the vertical axis is the wellhead casing pressure Pcasing. Figure 3 It can be seen that the wellhead casing pressure between January 1, 2019 and January 31, 2019 has a linear relationship with time and has reached a quasi-stable seepage state. During this period, the pressure drop rate was 0.0066MPa / d. In order to further adjust the pressure drop rate to 0.005MPa / d, production adjustment design is required.

[0074] Step 1, Figure 3 In the data, the wellhead casing pressure of XX gas well from January 1, 2019 to January 31, 2019 is in a linear relationship with time, and the time period from January 1, 2019 to January 31, 2019 can be regarded as the simulated stable production time period.

[0075] Step 2: Obtain the wellhead casing pressure and cumulative gas production of the XX gas well during the planned stable production period (between January 1, 2019 and January 31, 2019), such as Figure 2As shown in the figure, the wellhead casing pressure Pcasing is used as the ordinate and the cumulative gas production Gp is ​​used as the abscissa. Linear fitting is performed on the two, and the linear relationship expression between the two is obtained as y=-0.0054x+14.407, and the correlation R 2 =0.9386. The absolute value of the slope of the fitted straight line corresponding to the linear expression is 0.0054Mpa / 10,000m3, so the gas production per unit pressure drop of the XX well during the proposed stable production period is:

[0076] Step 3: According to the target pressure drop rate DPR obj =0.005Mpa / d and the unit pressure drop gas production q obtained in step 2 unitp =1.8519 million cubic meters / Mpa, according to the formula q obj =DPR obj ×q unitp The target pressure drop rate DPR can be calculated obj The corresponding gas well design production allocation q obj =0.9259×10 4 m 3 / d.

[0077] During February 2019, the gas well design production q obtained in step 3 was used. obj =0.9259×10 4 m 3 / d The production allocation of the XX gas well was adjusted. The actual average daily gas production in February was 0.96×10 4 m 3 / d, such as Figure 3 As shown in the figure, the wellhead casing pressure and time are linearly fitted, and the linear relationship expression between the two is y = -0.0052x + 238.9, and the correlation R 2 =0.7659, that is, the actual pressure drop rate during February was 0.0052 MPa / d, which is basically consistent with the target pressure drop rate of 0.005 MPa / d.

[0078] On the whole, this method does not require obtaining data on changes in formation pressure. When used to guide the quantitative production design for controlling the pressure drop rate of gas wells, the method is simple, low-cost, highly operational, effective and practical, and has great value for promotion and use.

Claims

1. A production allocation design method for controlling the pressure drop rate of a gas well, characterized in that: The steps include: 1) According to the wellhead casing pressure and the corresponding cumulative gas production in the quasi-stable production stage of the gas well, determine the unit pressure drop gas production q of the gas well unitp The quasi-stable production stage refers to the period of time when the wellhead casing pressure and time show a linear change relationship; the gas production per unit pressure drop q of the gas well is determined according to the wellhead casing pressure and the corresponding cumulative gas production in the quasi-stable production stage. unitp The method includes: performing linear fitting on the wellhead casing pressure and the corresponding cumulative gas production in the quasi-stable production stage of the gas well to obtain a linear relationship expression between the wellhead casing pressure and the cumulative gas production; and determining the gas production per unit pressure drop q of the gas well according to the linear relationship expression. unitp ; 2) According to the target pressure drop rate DPR obj And the gas production per unit pressure drop q unitp , substitute into the formula q obj =DPR obj ×q unitp The target pressure drop rate DPR is calculated obj The corresponding gas well design production allocation q obj ; 3) Refer to the target pressure drop rate DPR obj The corresponding gas well design production allocation q obj , adjusting the production allocation of the gas well to adjust the pressure drop rate to the target pressure drop rate; Derivation of the relationship model between gas well pressure drop rate and gas well gas production: Let the total gas-bearing pore volume in the gas supply area controlled by the gas well be V, and the gas reservoir temperature be T. The changes of the two are very small during the entire development process, so it is assumed that the two remain unchanged during the development process; let the average pressure in the gas supply area of ​​the gas well at time a be P a , the number of moles of gas is n a , the gas deviation factor is Z a ; Let the average pressure in the gas well control area at time b be P b , the number of moles of gas is n b , the gas deviation factor is Z b , The ratio of pressure to deviation factor is defined as pseudo-pressure, that is: Then the pseudo-pressure ratios at time a and time b are: Then the gas state equation of the gas supply area of ​​gas well a is: P a V=Z a n a RT (4) Similarly, the gas state equations in the gas supply area of ​​the gas well at time b are: P b V=Z b n b RT (5) From formula (2) and formula (4), we can get: P sa V=n a RT (6) From formula (3) and formula (5), we can get: P sb V=n b RT (7) From formula (6) and formula (7), we can get: (P sa -P sb )V=(n a -n b )RT (8) Let the number of production days from time a to time b be Δt days, and the average daily surface gas production be q sc , the surface density of the produced gas is ρ sc , then during this period, the gas mass produced by the gas reservoir is: m=ρ sc what sc Δt (9) Let the molar molecular weight of natural gas be M. Then, according to the relationship between the number of moles and mass of produced natural gas, we can get: m=(n a -n b )M (10) From formula (9) and formula (10), we can get: ρ sc what sc Δt=(n a -n b )M (11) From formula (11), we can get: From equation (8) and equation (12), we can get: If the production time Δt from time a to time b is not very long and the gas output is not too much, the formation pressure will not change much. Therefore, it is considered that the deviation factors at time a and time b are approximately equal and equal to the deviation factor under the average formation pressure during the production period between the two moments. Right now: From equation (2), equation (3) and equation (14), we can get: From formula (13) and formula (15), we can get: Let the formation pressure drop rate from time a to time b be DPR, that is: From equation (16) and equation (17), we can get: Formula (18) is the relationship model between the gas well pressure drop rate and the gas production of the gas well; Derivation of gas well design production allocation model under target pressure drop rate: From formula (16), we get: Let the cumulative gas production volume of the gas well from time a to time b be Q cum , then we have: Q cum =q sc Δt (20) From formula (19) and formula (20), we can get: From formula (21), we get: From formula (18) and formula (22), we can get: make: From equation (23) and equation (24), we can get: q sc =DPR×q unitp (25) Formula (25) is the gas well production allocation model based on pressure drop rate, q sc is the gas production of the gas well, DPR is the pressure drop rate of the gas well, q unitp It is the gas production under unit pressure drop of the gas well.