A method for compiling weekly operation plan of multi-provincial power grid

By creating long-cycle and short-cycle optimal dispatch models in multi-provincial power grids to optimize grid operation decisions, it solves the problem of difficulty in achieving grid feasibility and safety through manual experience compilation in the existing technology, and improves the reliability and safety of grid operations. Delicate management.

CN113919580BActive Publication Date: 2024-10-29ELECTRIC POWER RES INST CHINA SOUTHERN POWER GRID CO LTD +1
View PDF 2 Cites 0 Cited by

Patent Information

Application Number
CN202111218484.3
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2021-10-19
Publication Date
2024-10-29
Estimated Expiration
2041-10-19

AI Technical Summary

Technical Problem

The existing power grid operation plans in many provinces and regions mainly rely on manual experience preparation, which makes it difficult to achieve in-depth optimization of feasibility and safety. Especially after large-scale renewable energy is connected to the power grid, power grid operation faces uncertainty and security challenges.

Method used

A multi-provincial power grid weekly operation plan preparation method is adopted to create a long-period optimal dispatch model and a short-period optimal dispatch model by obtaining boundary data, perform multi-day rolling optimization calculations, and generate a daily power generation and transmission plan, combining unit generation power, operating costs, System load balancing, network power flow transmission and hydropower operation constraints optimize power grid operation decisions.

Benefits of technology

It improves the feasibility and safety of power grid operation, reduces the impact of uncertainty, promotes the consumption of renewable energy, and improves the level of refined operation of the power grid.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN113919580B_ABST
    Figure CN113919580B_ABST
Patent Text Reader

Abstract

The present application relates to a method for compiling a weekly operation plan for a multi-provincial power grid, the method comprising: obtaining boundary data for calculating the power grid operation cycle; creating a long-cycle optimization scheduling model based on the boundary data, and obtaining daily boundary data for the next week through the long-cycle optimization scheduling model; performing multi-day rolling optimization calculations on the daily boundary data for the next week to obtain a daily power generation and transmission plan. Compared with the prior art, the present invention can propose an invention that splits the compilation problem of the power grid weekly operation plan into two processes: long-cycle unified optimization calculation and multi-day rolling optimization calculation. By adopting differentiated modeling in the long-cycle unified optimization model and the day-ahead optimization scheduling model, the accuracy and solution efficiency of the model are guaranteed, which improves the feasibility and safety of the operation of the multi-provincial power grid considering cascade hydropower, and meets the actual application needs.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the technical field of power grid operation, and in particular to a method for compiling a weekly operation plan for a multi-provincial power grid. Background Art

[0002] The power system operation plan is to formulate an operation plan that is superior in both reliability and economy based on various specific constraints of the system. At present, the power grid dispatching agency first prepares the annual power plan and unit maintenance plan, then prepares the monthly power plan based on the annual power plan, and finally prepares the unit power generation plan for 96 periods of each day based on the monthly power plan.

[0003] With the access of large-scale renewable energy and flexible loads to the power grid, the safe operation of the power system has been greatly challenged. The preparation of weekly operation plans is conducive to gradually reducing the adverse effects of uncertainties on the operation of the power grid, improving the level of refined operation of the power grid, and promoting the consumption of renewable energy.

[0004] However, the current preparation of multi-provincial power grid operation plans is mainly based on manual experience to prepare inter-provincial operation plans, taking the inter-provincial operation plans as boundary conditions and then preparing the intra-provincial operation plans. When preparing inter-provincial operation plans, it mainly relies on manual subjective experience, which makes it difficult to achieve deep optimization of feasibility and safety. Summary of the invention

[0005] Based on this, it is necessary to provide a method for compiling weekly operation plans for multi-provincial power grids that can support dispatching and operation auxiliary decisions on a weekly time scale for the power system and improve the feasibility and safety of power grid operation in response to the above technical problems.

[0006] An embodiment of the present invention provides a method for compiling a weekly operation plan for a multi-provincial power grid, the method comprising the following steps:

[0007] Obtain boundary data for calculating the power grid operation cycle;

[0008] Creating a long-term optimization scheduling model based on the boundary data, and obtaining daily boundary data for the next week through the long-term optimization scheduling model;

[0009] Perform multi-day rolling optimization calculations on the daily boundary data for the next week to obtain a daily power generation and transmission plan;

[0010] Furthermore, the method for creating a long-cycle optimization scheduling model according to the boundary data includes:

[0011] Create a long-term objective function based on the unit's power generation, operating cost, and startup cost in the first period;

[0012] According to the long-term system load balance constraints, long-term positive reserve constraints, and long-term network power transmission constraints, long-term system side constraints are constructed;

[0013] Create output constraints for conventional generator sets based on the maximum / minimum power generation of conventional generator sets, the ramp rate constraints of conventional generator sets, and the minimum continuous start / stop time constraints of conventional generator sets;

[0014] Create long-period cascade hydropower operation constraints based on the output of the current hydropower station in the first period and the given power value of the current hydropower station in the dispatching period;

[0015] A long-period optimal scheduling model is constructed based on the long-period objective function, long-period system-side constraints, conventional generator output constraints and long-period cascade hydropower operation constraints.

[0016] Furthermore, the long-term objective function is:

[0017]

[0018] Where N is the total number of optimized units; T1 is the total number of time periods that require medium- and long-term optimization; P i,t is the power generation of unit i in period t; C i,t (P i,t ), are the operating cost and startup cost of unit i in period t, and the unit operating cost C i,t (P i,t ) is a multi-segment linear function related to each power range reported by the unit and the corresponding electric energy price.

[0019] Furthermore, the long-period system-side constraints specifically include:

[0020] Long-term system load balancing constraints:

[0021] Among them, P i,t is the power generation of unit i in period t; T j,t,o is the planned power of the out-of-region tie line j in time period t; N T is the total number of contact lines outside the region; D t is the system load forecast value for period t;

[0022] Long-period positive standby constraints:

[0023] Among them, α i,t is the operating status of unit i in period t, α i,t =0 means the unit is shut down, α i,t =1 means the unit is turned on; is the maximum power generation of unit i in period t; is the system positive reserve capacity requirement value for period t;

[0024] Long-term network power transmission constraints:

[0025] in, is the transmission limit of the out-of-region tie line j in time period t.

[0026] Furthermore, the conventional generator set output constraints specifically include:

[0027] Maximum / minimum power generation of conventional units:

[0028] Among them, α i,t is the operating status of unit i in period t, α i,t =0 means the unit is shut down, α i,t =1 means the unit is turned on; is the maximum power generation of unit i in period t; is the system positive reserve capacity requirement value for period t;

[0029] Conventional unit ramp rate constraints:

[0030]

[0031]

[0032] Among them, ΔP i U , ΔP i D are the ramp-up rate and ramp-down rate of the i-th conventional unit respectively;

[0033] Minimum continuous start-stop time constraints for conventional units:

[0034]

[0035]

[0036]

[0037]

[0038] Among them, α i,t is the operating status of conventional unit i in period t; T U , T D The minimum continuous start-up time and minimum continuous shutdown time of conventional units; is the continuous start-up time and continuous shutdown time of conventional unit i in period t, which can be expressed as state variable α i,t To express.

[0039] Furthermore, the long-period cascade hydropower operation constraints are:

[0040]

[0041] Among them, P h,t is the output of the hth hydropower station in time period t, Q h is the given power value of the h-th hydropower station in the dispatching period;

[0042] The model of daily boundary data for the next week obtained through the long-term optimization scheduling model is:

[0043]

[0044] Among them, Z h,t is the water level of hydropower station h at time t, η h is the water consumption rate of the hydropower station h, I h,t is the natural water supply of hydropower station h at time t, S h The water surface area of ​​hydropower station h, then the water level value of hydropower station h at the end of the dispatching time on the kth day is Z h,tend (tend=24*k).

[0045] Furthermore, the method for performing multi-day rolling optimization calculation on the daily boundary data for the next week includes:

[0046] Create a short-term objective function based on the unit's power generation, operating cost, and startup cost in the second period;

[0047] According to the short-period system load balance constraint, short-period positive reserve constraint, and short-period network power flow transmission constraint, the short-period system side constraint is constructed;

[0048] Create output constraints for conventional generator sets based on the maximum / minimum power generation of conventional generator sets, the ramp rate constraints of conventional generator sets, and the minimum continuous start / stop time constraints of conventional generator sets;

[0049] Create end-cycle cascade hydropower operation constraints based on water balance constraints, reservoir capacity-water level relationship, water level constraints and hydropower plant water level control;

[0050] According to the short-cycle objective function, short-cycle system-side constraints, conventional generator output constraints and short-cycle cascade hydropower operation constraints, a short-cycle optimization scheduling model is constructed, and a multi-day rolling optimization calculation is performed on the daily boundary data for the next week.

[0051] Furthermore, the end period objective function is:

[0052]

[0053] Where N is the total number of optimized units; T2 is the total number of time periods that require short-term optimization; P i,t is the power generation of unit i in period t; C i,t (P i,t ), are the operating cost and startup cost of unit i in period t, and the unit operating cost C i,t (P i,t ) is a multi-segment linear function related to each power range reported by the unit and the corresponding electric energy price.

[0054] Furthermore, the long-period network power flow transmission constraint is:

[0055]

[0056] Among them, P l max is the power transmission limit of line l; G l-i is the generator output power transfer distribution factor of the node where unit i is located to line l; K is the number of nodes in the system; G l-k is the generator output power transfer distribution factor of node k to line l; D k,t is the bus load value of node k in period t.

[0057] Furthermore, the short-term cascade hydropower constraints specifically include:

[0058] Water balance constraints:

[0059]

[0060]

[0061] q h,t =η h P h,t

[0062] Among them, V h,t is the storage capacity of hydropower station h in time period t; q h,t , Q h,t are the power generation flow, abandoned water flow, and interval water flow of the hydropower plant in time period t, and the interval water flow is the natural water flow I h,t and the power generation flow q of the upper hydropower plant m-1,t and abandoned water flow The sum of the three;

[0063] The relationship between reservoir capacity and water level is:

[0064] V h,t =a1×Z h,t +a2

[0065] Among them, Z h,t is the water level of the hydropower plant in time period t, a1 and a2 are the coefficient of the first-order term and the constant term respectively;

[0066] The water level constraint is:

[0067]

[0068] in, is the upper limit of the water level of the hydropower plant; It is the upper limit of the water level of the hydropower plant.

[0069] The water level control of the hydropower plant is:

[0070]

[0071] Among them, Z h,tend is the water level at the last moment of the hydropower station h.

[0072] Another embodiment of the present invention provides a system for compiling a weekly operation plan for a multi-provincial power grid, comprising:

[0073] An acquisition module, used for acquiring boundary data for calculating the operation cycle of the power grid;

[0074] A creation module, used to create a long-term optimization scheduling model according to the boundary data, and obtain daily boundary data for the next week through the long-term optimization scheduling model;

[0075] The calculation module is used to perform multi-day rolling optimization calculations on the daily boundary data for the next week to obtain a daily power generation and transmission plan.

[0076] Another embodiment of the present invention further proposes a computer-readable storage medium, which includes a stored computer program; wherein, when the computer program is running, it controls the device where the computer-readable storage medium is located to execute the method for compiling a weekly operation plan for a multi-provincial power grid as described above.

[0077] Another embodiment of the present invention also proposes an electric power terminal, comprising a processor, a memory, and a computer program stored in the memory and configured to be executed by the processor, wherein the processor implements the method for compiling a weekly operation plan for a multi-provincial power grid as described above when executing the computer program.

[0078] The above-mentioned method for compiling weekly operation plans for power grids in multiple provinces and regions obtains boundary data for calculating the operation cycle of power grids; creates a long-cycle optimization scheduling model based on the boundary data, and obtains daily boundary data for the next week through the long-cycle optimization scheduling model; performs multi-day rolling optimization calculations on the daily boundary data for the next week to obtain a daily power generation and transmission plan. Compared with the prior art, the present invention can support scheduling and operation auxiliary decision-making on a weekly time scale for power systems, improve the feasibility and safety of power grid operation, and meet practical application needs. BRIEF DESCRIPTION OF THE DRAWINGS

[0079] Figure 1 A flow chart of a method for compiling a weekly operation plan for a multi-provincial power grid provided by an embodiment of the present invention;

[0080] Figure 2 The power generation plan of all the generator sets in each province and region in the daily power generation and transmission plan in another embodiment;

[0081] Figure 3 A power transmission plan for the inter-provincial interconnection lines in the daily power transmission plan in another embodiment;

[0082] Figure 4 A water level curve of a hydropower station in a daily power generation and transmission plan in another embodiment;

[0083] Figure 5 A structural diagram of a power terminal provided in an embodiment of the present invention. DETAILED DESCRIPTION

[0084] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this technical field without creative work are within the scope of protection of the present invention.

[0085] It should be noted that the step numbers in the text are only for the convenience of explaining the specific embodiment and do not limit the order of execution of the steps. The method provided in this embodiment can be executed by a related server, and the following description will be given by taking the server as the execution subject as an example.

[0086] like Figure 1 As shown, the method for compiling a weekly operation plan for a multi-provincial power grid provided in an embodiment of the present invention is executed by a power compilation device for controlling the compilation of the weekly operation plan for the multi-provincial power grid, and the method includes steps S11 to S13:

[0087] Step S11, obtaining and calculating boundary data of the power grid operation cycle.

[0088] Specifically, the system-side boundary data is exported from the energy-saving dispatching system, including the load forecast value for the next month and the wind power and photovoltaic output forecast values; the grid data and unit data are exported from the power grid operation and control system, the grid data includes the grid information such as the nodes and lines of the whole network, the unit data includes the basic parameters such as the upper and lower limits of the output of the generator set, the climbing rate, the coal consumption rate, and the hydropower station-specific data such as the water inflow, storage capacity, water consumption, and water level area; the unit and line maintenance plan is exported from the power grid operation and management system, including the maintenance plan and commissioning plan of the lines, transformers, and units within the next month; the model parameters and calculation parameters for the next month are set, the model parameters include the allowable deviation rate of the inter-provincial electricity plan, the reserved positive and negative reserve ratio, the allowable deviation rate of the water level at the end of the dispatch, the water level control value, the monthly electricity plan, etc.; the calculation parameters include the model convergence accuracy, the maximum calculation time, the solver selection, etc.

[0089] Step S12, creating a long-term optimization scheduling model according to the boundary data, and obtaining the daily boundary data for the next week through the long-term optimization scheduling model.

[0090] Specifically, according to the power generation, operation cost and startup cost of the unit in the first period, a long-term objective function is created; according to the long-term system load balance constraint, the long-term positive standby constraint and the long-term network power transmission constraint, a long-term system side constraint is constructed; according to the maximum / minimum power generation of the conventional unit, the conventional unit ramp rate constraint and the minimum continuous start-stop time constraint of the conventional unit, the conventional generator unit output constraint is created; according to the output of the current hydropower station in the first period and the given power value of the current hydropower station in the dispatching period, a long-term cascade hydropower operation constraint is created; according to the long-term objective function, the long-term system side constraint, the conventional generator unit output constraint and the long-term cascade hydropower operation constraint, a long-term optimization scheduling model is constructed. Among them, the calculation period of the long-term unified optimization model is 1 month, and the time granularity is 4h (assuming that there are 31 days in a month, the number of dispatching periods is 186).

[0091] Furthermore, the long-term objective function is:

[0092]

[0093] Where N is the total number of optimized units; T1 is the total number of time periods that require medium- and long-term optimization; P i,t is the power generation of unit i in period t; C i,t (P i,t ), are the operating cost and startup cost of unit i in period t, and the unit operating cost C i,t (P i,t ) is a multi-segment linear function related to each power range reported by the unit and the corresponding electric energy price.

[0094] Furthermore, the long-period system-side constraints specifically include:

[0095] Long-term system load balancing constraints:

[0096] Among them, P i,t is the power generation of unit i in period t; T j,t,o is the planned power of the out-of-region tie line j in time period t (input is positive, output is negative); N T is the total number of contact lines outside the region; D t is the system load forecast value for period t;

[0097] Long-period positive standby constraints:

[0098] Among them, α i,t is the operating status of unit i in period t, α i,t =0 means the unit is shut down, α i,t =1 means the unit is turned on; is the maximum power generation of unit i in period t; is the system positive reserve capacity requirement value for period t;

[0099] Long-term network power transmission constraints:

[0100] in, is the transmission limit of the out-of-region tie line j in time period t.

[0101] Furthermore, the conventional generator set output constraints specifically include:

[0102] Maximum / minimum power generation of conventional units:

[0103] Among them, α i,t is the operating status of unit i in period t, α i,t =0 means the unit is shut down, α i,t =1 means the unit is turned on; is the maximum power generation of unit i in period t; is the system positive reserve capacity requirement value for period t;

[0104] Conventional unit ramp rate constraints:

[0105]

[0106]

[0107] Among them, ΔP i U , ΔPi D are the ramp-up rate and ramp-down rate of the i-th conventional unit respectively;

[0108] Minimum continuous start-stop time constraints for conventional units:

[0109]

[0110]

[0111]

[0112]

[0113] Among them, α i,t is the operating status of conventional unit i in period t; T U , T D The minimum continuous start-up time and minimum continuous shutdown time of conventional units; is the continuous start-up time and continuous shutdown time of conventional unit i in period t, which can be expressed as state variable α i,t To express.

[0114] Furthermore, the long-period cascade hydropower operation constraints are:

[0115]

[0116] Among them, P h,t is the output of the hth hydropower station in time period t, Q h is the given power value of the h-th hydropower station in the dispatching period;

[0117] The model of daily boundary data for the next week obtained through the long-term optimization scheduling model is:

[0118]

[0119] Among them, Z h,t is the water level of hydropower station h at time t, η h is the water consumption rate of the hydropower station h, I h,t is the natural water supply of hydropower station h at time t, S h The water surface area of ​​hydropower station h, then the water level value of hydropower station h at the end of the dispatching time on the kth day is Z h,tend (tend=24*k).

[0120] Furthermore, the long-term optimization scheduling model is used to perform long-term unified optimization calculations and output daily boundary data, mainly including the water level at the moment of daily scheduling of the hydropower station.

[0121] Through the output of all hydropower stations Ph,t and hydropower station parameters, the water level of the hydropower station at each time can be calculated as:

[0122]

[0123] Among them, Z h,t is the water level of hydropower station h at time t, η h is the water consumption rate of the hydropower station h, I h,t is the natural water supply of hydropower station h at time t, S h The water surface area of ​​hydropower station h, then the water level value of hydropower station h at the end of the dispatching time on the kth day is Z h,tend (tend=24*k).

[0124] Step S13, performing a multi-day rolling optimization calculation on the daily boundary data for the next week to obtain a daily power generation and transmission plan.

[0125] Specifically, according to the generating power, operating cost and startup cost of the unit in the second period, a short-term objective function is created; according to the short-term system load balance constraint, the short-term positive standby constraint and the short-term network flow transmission constraint, a short-term system side constraint is constructed; according to the maximum / minimum generating power of the conventional unit, the climbing rate constraint of the conventional unit and the minimum continuous start-up and shutdown time constraint of the conventional unit, a conventional generating unit output constraint is created; according to the water balance constraint, the reservoir capacity-water level relationship, the water level constraint and the water level control of the hydropower plant, an end-cycle cascade hydropower operation constraint is created; according to the short-term objective function, the short-term system side constraint, the conventional generating unit output constraint and the short-term cascade hydropower operation constraint, a short-term optimization scheduling model is constructed, and a multi-day rolling optimization calculation is performed on the daily boundary data for the next week. Among them, the calculation cycle of the multi-day rolling optimization calculation is 1 day, the time granularity is 15 minutes, and the number of time periods for each rolling calculation is 96.

[0126] Furthermore, the end period objective function is:

[0127]

[0128] Where N is the total number of optimized units; T2 is the total number of time periods that require short-term optimization; P i,t is the power generation of unit i in period t; C i,t (P i,t ), are the operating cost and startup cost of unit i in period t, and the unit operating cost C i,t (P i,t ) is a multi-segment linear function related to each power range reported by the unit and the corresponding electric energy price.

[0129] Furthermore, the short-term system load balance constraint is consistent with the long-term system load balance constraint, and the short-term positive reserve constraint is consistent with the long-term positive reserve constraint. The long-term network power transmission constraint includes the intra-provincial line power constraint and the inter-provincial tie line power constraint, the inter-provincial tie line power constraint is consistent with the long-term network power transmission constraint, and the intra-provincial power line constraint is:

[0130]

[0131] Among them, P l max is the power transmission limit of line l; G l-i is the generator output power transfer distribution factor of the node where unit i is located to line l; K is the number of nodes in the system; G l-k is the generator output power transfer distribution factor of node k to line l; D k,t is the bus load value of node k in period t

[0132] Furthermore, the short-term cascade hydropower constraints specifically include:

[0133] Water balance constraints:

[0134]

[0135]

[0136] q h,t =η h P h,t

[0137] Among them, V h,t is the storage capacity of hydropower station h in time period t; q h,t , Q h,t are the power generation flow, abandoned water flow, and interval water flow of the hydropower plant in time period t, and the interval water flow is the natural water flow I h,t and the power generation flow q of the upper hydropower plant m-1,t and abandoned water flow The sum of the three;

[0138] The relationship between reservoir capacity and water level is:

[0139] V h,t =a1×Z h,t +a2

[0140] Among them, Z h,t is the water level of the hydropower plant in time period t, a1 and a2 are the coefficient of the first-order term and the constant term respectively;

[0141] The water level constraint is:

[0142]

[0143] in, is the upper limit of the water level of the hydropower plant; It is the upper limit of the water level of the hydropower plant.

[0144] The water level control of the hydropower plant is:

[0145]

[0146] Among them, Z h,tend is the water level at the last moment of the hydropower station h.

[0147] In addition, the output constraints of the conventional generator sets are consistent with the output constraints of the conventional generator sets in the long-term optimal scheduling model, which will not be described in detail here. The obtained daily power generation and transmission plan includes the power generation plan P of all generator sets in each province and region. i,t , Transmission plan of inter-provincial interconnection lines j,t,o , water level curve Z of hydropower station h,t .

[0148] For example, based on the actual operation data of the Southern Power Grid from March 1 to 31, 2019, the status of grid-connected units in various provinces and regions is shown in the following table:

[0149] Table 1 Status of grid-connected units in various provinces and regions

[0150]

[0151] Through long-term unified optimization calculation, the output daily boundary data is as follows:

[0152] Table 2 Daily boundary data of major hydropower stations (taking Nuozhadu Hydropower Station as an example)

[0153]

[0154]

[0155] The output power generation plan of all generators in each province is as follows: Figure 2 The transmission plan of inter-provincial interconnection lines is shown in Figure 3 As shown in Figure 2, the water level curve of the hydropower station is as follows: Figure 4 shown.

[0156] The above-mentioned method for compiling weekly operation plans for multi-provincial power grids obtains boundary data for calculating the operation cycle of the power grid; creates a long-cycle optimization scheduling model based on the boundary data, and obtains daily boundary data for the next week through the long-cycle optimization scheduling model; performs multi-day rolling optimization calculations on the daily boundary data for the next week to obtain a daily power generation and transmission plan. Compared with the prior art, the present invention can propose an invention that splits the compilation problem of the weekly operation plan of the power grid into two processes: long-cycle unified optimization calculation and multi-day rolling optimization calculation. By adopting differentiated modeling in the long-cycle unified optimization model and the day-ahead optimization scheduling model, the accuracy and solution efficiency of the model are guaranteed, which improves the feasibility and safety of the operation of the multi-provincial power grid considering cascade hydropower, and meets the actual application needs.

[0157] It should be understood that, although the various steps in the above-mentioned flow chart are displayed in sequence according to the indication of the arrows, these steps are not necessarily executed in sequence according to the order indicated by the arrows. Unless there is a clear explanation in this article, the execution of these steps is not strictly limited in order, and these steps can be executed in other orders. Moreover, at least a part of the steps in the above-mentioned flow chart may include a plurality of sub-steps or a plurality of stages, and these sub-steps or stages are not necessarily executed at the same time, but can be executed at different times, and the execution order of these sub-steps or stages is not necessarily to be carried out in sequence, but can be executed in turn or alternately with other steps or at least a part of the sub-steps or stages of other steps.

[0158] The present invention also provides a system for compiling weekly operation plans of power grids in multiple provinces and regions, the system comprising:

[0159] An acquisition module, used for acquiring boundary data for calculating the operation cycle of the power grid;

[0160] A creation module, used to create a long-term optimization scheduling model according to the boundary data, and obtain daily boundary data for the next week through the long-term optimization scheduling model;

[0161] The calculation module is used to perform multi-day rolling optimization calculations on the daily boundary data for the next week to obtain a daily power generation and transmission plan.

[0162] Another embodiment of the present invention further proposes a computer-readable storage medium, which includes a stored computer program; wherein, when the computer program is running, it controls the device where the computer-readable storage medium is located to execute the method for compiling a weekly operation plan for a multi-provincial power grid as described above.

[0163] The multi-province power grid weekly operation plan compilation system provided by the embodiment of the present invention obtains boundary data for calculating the power grid operation cycle; creates a long-cycle optimization scheduling model based on the boundary data, and obtains the daily boundary data of the next week through the long-cycle optimization scheduling model; performs multi-day rolling optimization calculations on the daily boundary data of the next week to obtain a daily power generation and transmission plan. Compared with the prior art, the present invention can propose an invention that splits the compilation problem of the power grid weekly operation plan into two processes: long-cycle unified optimization calculation and multi-day rolling optimization calculation. By adopting differentiated modeling in the long-cycle unified optimization model and the day-ahead optimization scheduling model, the accuracy and solution efficiency of the model are guaranteed, which improves the feasibility and safety of the operation of the multi-province power grid considering cascade hydropower, and meets the actual application needs.

[0164] An embodiment of the present invention also provides a computer-readable storage medium, which includes a stored computer program; wherein, when the computer program is running, it controls the device where the computer-readable storage medium is located to execute the method for compiling a weekly operation plan for a multi-provincial power grid as described above.

[0165] The present invention also provides a power terminal. Figure 5 As shown, it is a structural block diagram of a preferred embodiment of a power terminal provided by the present invention, the power terminal includes a processor 10, a memory 20, and a computer program stored in the memory 20 and configured to be executed by the processor 10, and the processor 10 implements the above-mentioned method for compiling weekly operation plans for multi-provincial power grids when executing the computer program.

[0166] Preferably, the computer program can be divided into one or more modules / units (such as computer program 1, computer program 2, ...), and the one or more modules / units are stored in the memory 20 and executed by the processor 10 to complete the present invention. The one or more modules / units can be a series of computer program instruction segments that can complete specific functions, and the instruction segments are used to describe the execution process of the computer program in the power terminal.

[0167] The processor 10 may be a central processing unit (CPU), or other general-purpose processors, digital signal processors (DSP), application-specific integrated circuits (ASIC), field-programmable gate arrays (FPGA) or other programmable logic devices, discrete gate or transistor logic devices, discrete hardware components, etc. A general-purpose processor may be a microprocessor, or the processor 10 may be any conventional processor. The processor 10 is the control center of the power terminal, and various parts of the power terminal are connected using various interfaces and lines.

[0168] The memory 20 mainly includes a program storage area and a data storage area, wherein the program storage area can store an operating system, an application required for at least one function, etc., and the data storage area can store related data, etc. In addition, the memory 20 can be a high-speed random access memory, or a non-volatile memory, such as a plug-in hard disk, a smart memory card (Smart Media Card, SMC), a secure digital (Secure Digital, SD) card, and a flash card (Flash Card), etc., or the memory 20 can also be other volatile solid-state storage devices.

[0169] It should be noted that the above-mentioned power terminal may include, but is not limited to, a processor and a memory. Those skilled in the art will understand that Figure 5 The structural block diagram is merely an example of the power terminal and does not constitute a limitation on the power terminal, and may include more or fewer components than shown in the figure, or a combination of certain components, or different components.

[0170] The above is only a preferred embodiment of the present invention. It should be pointed out that for ordinary technicians in this technical field, several improvements and modifications can be made without departing from the technical principles of the present invention. These improvements and modifications should also be regarded as the scope of protection of the present invention.

Claims

1. A method for compiling a weekly operation plan for a multi-provincial power grid, characterized in that: The method comprises the following steps: Obtain boundary data for calculating the power grid operation cycle; Creating a long-term optimization scheduling model based on the boundary data, and obtaining daily boundary data for the next week through the long-term optimization scheduling model; Perform multi-day rolling optimization calculations on the daily boundary data for the next week to obtain a daily power generation and transmission plan; in, The method for creating a long-term optimization scheduling model according to the boundary data includes: Create a long-term objective function based on the unit's power generation, operating cost, and startup cost in the first period; According to the long-term system load balance constraints, long-term positive reserve constraints, and long-term network power transmission constraints, long-term system side constraints are constructed; Create output constraints for conventional generator sets based on the maximum / minimum power generation of conventional generator sets, the ramp rate constraints of conventional generator sets, and the minimum continuous start / stop time constraints of conventional generator sets; Create long-period cascade hydropower operation constraints based on the output of the current hydropower station in the first period and the given power value of the current hydropower station in the dispatching period; A long-term optimal dispatching model is constructed based on the long-term objective function, long-term system-side constraints, conventional generator output constraints and long-term cascade hydropower operation constraints. The long-term objective function is: Where N is the total number of optimized units; T1 is the total number of time periods that require medium- and long-term optimization; P i,t is the power generation of unit i in period t; C i,t (P i,t ), are the operating cost and startup cost of unit i in period t, and the unit operating cost C i,t (P i,t ) is a multi-segment linear function related to each power interval reported by the unit and the corresponding electric energy price; The method for performing multi-day rolling optimization calculation on the daily boundary data of the next week includes: Create a short-term objective function based on the unit's power generation, operating cost, and startup cost in the second period; According to the short-period system load balance constraint, short-period positive reserve constraint, and short-period network power flow transmission constraint, the short-period system side constraint is constructed; Create output constraints for conventional generator sets based on the maximum / minimum power generation of conventional generator sets, the ramp rate constraints of conventional generator sets, and the minimum continuous start / stop time constraints of conventional generator sets; Create end-cycle cascade hydropower operation constraints based on water balance constraints, reservoir capacity-water level relationship, water level constraints and hydropower plant water level control; According to the short-term objective function, short-term system-side constraints, conventional generator output constraints and short-term cascade hydropower operation constraints, a short-term optimization scheduling model is constructed, and a multi-day rolling optimization calculation is performed on the daily boundary data for the next week; The short-term objective function is: Where N is the total number of optimized units; T2 is the total number of time periods that require short-term optimization; P i,t is the power generation of unit i in period t; C i,t (P i,t ), are the operating cost and startup cost of unit i in period t, and the unit operating cost C i,t (P i,t ) is a multi-segment linear function related to each power range reported by the unit and the corresponding electric energy price.

2. The method for compiling a weekly operation plan for a multi-provincial power grid according to claim 1, characterized in that: The long-period system-side constraints specifically include: Long-term system load balancing constraints: Among them, P i,t is the power generation of unit i in period t; T j,t,o is the planned power of the out-of-region tie line j in time period t; N T is the total number of contact lines outside the region; D t is the system load forecast value for period t; Long-period positive standby constraints: Among them, α i,t is the operating status of unit i in period t, α i,t =0 means the unit is shut down, α i,t =1 means the unit is turned on; is the maximum power generation of unit i in period t; is the system positive reserve capacity requirement value for period t; Long-term network power transmission constraints: in, is the transmission limit of the out-of-region tie line j in time period t.

3. The method for compiling weekly operation plans for multi-provincial power grids according to claim 1 is characterized in that: The conventional generator set output constraints specifically include: Maximum / minimum power generation of conventional units: Among them, α i,t is the operating status of unit i in period t, α i,t =0 means the unit is shut down, α i,t =1 means the unit is turned on; is the maximum power generation of unit i in period t; is the system positive reserve capacity requirement value for period t; Conventional unit ramp rate constraints: Where ΔP i U , ΔP i D are the ramp-up rate and ramp-down rate of the i-th conventional unit respectively; Minimum continuous start-stop time constraints for conventional units: Among them, α i,t is the operating status of conventional unit i in period t; T U , T D The minimum continuous start-up time and minimum continuous shutdown time of conventional units; For conventional units i The continuous startup time and continuous shutdown time in period t can be expressed by the state variable α i,t To express.

4. The method for compiling weekly operation plans for multi-provincial power grids according to claim 1 is characterized in that: The long-term cascade hydropower operation constraints are: Among them, P h,t is the output of the hth hydropower station in time period t, Q h is the given power value of the h-th hydropower station in the dispatching period; The model of daily boundary data for the next week obtained through the long-term optimization scheduling model is: Among them, Z h,t is the water level of hydropower station h at time t, η h is the water consumption rate of the hydropower station h, I h,t is the natural water supply of hydropower station h at time t, S h The water surface area of ​​hydropower station h, then the water level value of hydropower station h at the end of the dispatching time on the kth day is Z h,tend , tend=24*k.

5. The method for compiling weekly operation plans for multi-provincial power grids according to claim 1 is characterized in that: The long-period network power flow transmission constraint is: Among them, P l max is the power transmission limit of line l; G l-i is the generator output power transfer distribution factor of the node where unit i is located to line l; K is the number of nodes in the system; G l-k is the generator output power transfer distribution factor of node k to line l; D k,t is the bus load value of node k in period t.

6. The method for compiling weekly operation plan of multi-provincial power grid according to claim 1 is characterized in that: Short-term cascade hydropower constraints include: Water balance constraints: what h,t =η h P h,t Among them, V h,t is the storage capacity of hydropower station h in time period t; q h,t , Q h,t are the power generation flow, abandoned water flow, and interval water flow of the hydropower station in time period t, and the interval water flow is the natural water flow I h,t and the power generation flow q of the upper hydropower station m-1,t and abandoned water flow The sum of the three; The relationship between reservoir capacity and water level is: <h2 style=";text-align:left;direction:ltr">V<h2 style=";text-align:left;direction:ltr"> h,t <h2 style=";text-align:left;direction:ltr"> =a1×Z<h2 style=";text-align:left;direction:ltr"> h,t <h2 style=";text-align:left;direction:ltr"> +a2 Among them, Z h,t is the water level of the hydropower station in time period t, a1 and a2 are the coefficient of the first-order term and the constant term respectively; The water level constraint is: in, is the upper limit of the water level of the hydropower station; is the upper limit of the water level of the hydropower station; The water level control of the hydropower station is: Among them, Z h,tend is the water level at the last moment of the hydropower station h.

Citation Information

Patent Citations

  • Multi-cycle generation scheduling coordinated optimization and closed-loop control method

    CN103886388A

  • Method for proforming arithmetic logical and related operations and anumerical arithmetic unit

    CN1059413A