A diversion structure for a large diameter buried pipe passing through a gully
The diversion structure for large-diameter buried pipes through gullies, combining a reinforced concrete aqueduct with supporting elements, addresses the complexity and environmental impact of traditional construction methods by enabling simultaneous diversion and support, ensuring safety and reducing investment.
Patent Information
- Application Number
- CN202111311049.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2021-11-08
- Publication Date
- 2024-12-06
- Estimated Expiration
- 2041-11-08
AI Technical Summary
The construction of large-diameter buried pipes through gullies is complicated, requiring long construction periods, significant investment, and has a large environmental impact due to the need for new diversion channels, especially in mountainous areas with rapid flood rise and fall.
A diversion structure comprising a reinforced concrete aqueduct, connecting section retaining wall, anti-scouring bottom plate, temporary cofferdam, and supporting structure, allowing for simultaneous use as a diversion and support during flood and non-flood seasons, with temporary components dismantled before flood season, reducing the need for new diversion channels.
This structure ensures structural safety, simplifies construction, and reduces investment and environmental impact by utilizing existing channels during non-flood seasons and eliminating the need for large-scale diversion channels.
Smart Images

Figure CN114032846B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to a diversion open channel structure in water conservancy and hydropower engineering, and in particular to a diversion structure with a large-diameter buried pipe passing through a gully. Background Art
[0002] When a large-diameter buried pipe with a diameter of more than 2.0m passes through a gully on the basis of a thick covering layer, in order to reduce the land acquisition area for excavation and slope reduction and reduce the difficulty of policy processing, vertical support excavation such as steel sheet piles and bored cast-in-place piles is often used. When crossing the gully, construction diversion and flood safety issues must be considered.
[0003] The construction period of large-diameter buried pipe support structure is long, and diversion construction is usually carried out across the flood season, which requires the addition of diversion open channels. The flow capacity of the diversion open channel is determined according to the flood standard for flood control, and is not less than the existing gully flood discharge scale.
[0004] After adding a diversion open channel, there are usually two methods according to the construction sequence of buried pipes in the gully and diversion open channel:
[0005] Method 1: Open channel first and then gully: 1) First use the existing gully for diversion, set up diversion open channel at the proposed line change location, and complete the pile foundation support structure and buried pipe; 2) Excavate and construct diversion open channel; 3) Use the newly built diversion open channel for diversion, and complete the pile foundation support structure and buried pipe at the gully location; 4) Restore gully diversion; 5) Restore the diversion open channel to the original ground elevation.
[0006] Method 2: First gully and then open channel: 1) Build a new diversion open channel; 2) Use the newly built diversion open channel to divert water, and complete the pile foundation support structure and buried pipes at the gully location; 3) Backfill the diversion open channel after restoring the gully diversion; 4) Complete the pile foundation support structure and buried pipes at the diversion open channel location; 5) After the buried pipe construction at the diversion open channel location is completed, backfill to the original ground elevation.
[0007] Gullies in mountainous areas are characterized by rapid rise and fall of floods. The peak flow is large during the flood season, but the runoff is small or even non-existent during the non-flood season. Both of the above methods require the construction of new diversion channels. Since the flow capacity is required to be no less than the scale of the gully flood discharge, the open channel is large in scale, and the investment and environmental impact are both large.
[0008] In the dry season, it is completely possible to use small-scale earth-rock cofferdams to divert the construction of pile foundations and anti-seepage structures for the support structure in mountain gullies. Because the foundation pit for buried pipes has not yet been excavated, it does not affect the safety of buried pipe construction. Therefore, it is necessary to optimize the diversion structure for large-diameter buried pipes passing through gullies, while ensuring construction safety, optimizing the process and reducing investment and environmental impact. Summary of the invention
[0009] The purpose of the present invention is to overcome the shortcomings of complicated construction procedures, large investment and great environmental impact of newly built open channels when large-diameter buried pipes pass under gullies, and to provide a diversion structure for large-diameter buried pipes passing under gullies, by setting a reinforced concrete aqueduct structure on the top of the support piles. On the one hand, the aqueduct can be used as an open channel diversion and a restored gully flow channel, and the permanent and temporary combination is in place at one time; on the other hand, the aqueduct and the support piles are cast as a whole, which is more reliable than the frame support beam on the top of the support piles, creating conditions for the shallow buried and dark excavation construction of the lower buried pipe, and is also conducive to reducing investment and environmental impact.
[0010] The technical solution adopted by the present invention is:
[0011] A diversion structure for a large-diameter buried pipe passing under a gully, comprising an aqueduct, a connecting section retaining wall, an anti-scouring bottom plate, a temporary cofferdam, a temporary diversion pipe, a buried pipe, and a supporting structure. The aqueduct is located above the buried pipe and is a combination of permanent and temporary arrangements. It is both a diversion structure for the gully at the buried pipe position during the flood season and a supporting structure for the gully during the operation period. Both ends of the aqueduct are placed on the supporting structure of the buried pipe, and the aqueduct bottom plate also serves as the top support of the supporting structure below the aqueduct; the connecting section retaining wall is located at both ends of the aqueduct, and is a connecting structure for the aqueduct and the existing revetment of the gully; the anti-scouring bottom plate is located on the gully riverbed at the connecting section retaining wall; the temporary cofferdam is located in the gully upstream and downstream of the connecting section retaining wall, and is a water-retaining earth-rock cofferdam during the non-flood season. The temporary cofferdam provides protection for the construction of the aqueduct, the connecting section retaining wall, and the anti-scouring bottom plate during the non-flood season, and is dismantled before the flood season arrives. The temporary diversion pipe crosses the aqueduct and the gully where the connecting section retaining wall is located, so as to prevent the gully water flow from entering the aqueduct foundation pit during the non-flood season.
[0012] Furthermore, the aqueduct may adopt a cast-in-place U-shaped reinforced concrete structure. According to the traffic needs of the upper part of the aqueduct, the cast-in-place U-shaped reinforced concrete aqueduct may also be changed to a cast-in-place reinforced concrete box culvert, and the box culvert flow must meet the flood standards for diversion in the non-flood season and flood discharge in the operation period.
[0013] Furthermore, the connecting section retaining wall is a concrete gravity retaining wall.
[0014] Furthermore, the anti-collision bottom plate is a reinforced concrete bottom plate, and the anti-collision bottom plate is partially enlarged and thickened at the connection position with the aqueduct and the connecting section retaining wall.
[0015] Furthermore, the temporary diversion pipe can be a PE pipe, with both ends extending out of the temporary cofferdam to divert the water from the upstream of the gully to the downstream of the gully. Before the flood season arrives, it will be dismantled together with the temporary cofferdam, and the completed aqueduct, connecting section retaining wall, and anti-scouring bottom plate will take over the diversion function.
[0016] Furthermore, expansion joints are provided between the aqueduct and the connecting section retaining wall, and between the aqueduct and the anti-impact bottom plate, and waterstops are provided in the expansion joints. The waterstops may be copper sheet waterstops, steel edge rubber waterstops, or rubber waterstops.
[0017] Furthermore, the buried pipe is a steel pipe structure. After the support structure is completed, the conventional parts are all constructed by open excavation into trenches, but the bottom of the aqueduct needs to be constructed by dark excavation. The buried pipe is generally manufactured into standard pipe sections in the factory, and then circumferentially welded after being installed in place on site. Then, the steel bars are tied, the formwork is erected, and the buried pipe is covered with concrete, which is then backfilled to restore the original ground elevation.
[0018] Furthermore, the buried pipe outer casing concrete is located outside the buried pipe and protects the buried pipe.
[0019] Furthermore, the support structure is a protective structure for buried pipe construction into a trench, including bored cast-in-place piles, high-pressure rotary jet piles, crown beams, top supports, steel supports and steel purlins. Bored cast-in-place piles are the main load-bearing structure of the buried pipe foundation pit. There are two rows in total. They are reinforced concrete structures. Holes are formed by rotary drilling or impact drilling. Mud wall protection or casing construction is used. The top of the longitudinal force-bearing steel bars of the bored cast-in-place piles extends into the crown beam at the crown beam position and into the aqueduct at the aqueduct position; high-pressure rotary jet piles are arranged in the gap outside the bored cast-in-place piles, and double-tube rotary jetting is used to prevent seepage; the crown beam is located on the top of the bored cast-in-place pile, and is a reinforced concrete cast-in-place structure. Combined with the top support, it forms a frame structure that constrains the surface displacement of the bored cast-in-place piles; the top support is located between the crown beams. The reinforced concrete structure is cast integrally with the cap beam before the excavation of the buried pipe foundation pit. The steel support is the supporting structure of the middle and lower part of the bored cast-in-place piles, which is installed after the soil is excavated to the corresponding elevation. The two ends are connected to the steel perimeter purlin with bolts. The steel support is a temporary structure for buried pipe excavation construction, which is used to ensure that the buried pipe foundation pit is excavated into trenches to the foundation and facilitate buried pipe construction. It is generally dismantled after the buried pipe foundation is reinforced. According to the stability requirements of the supporting structure, one or more steel supports can be provided. The steel perimeter purlin is the connecting structure between the steel support and the bored cast-in-place piles, which is installed and dismantled together with the steel support.
[0020] Furthermore, according to the geological conditions of the buried pipe foundation pit, the support structure may also adopt other support structures with bearing and anti-seepage functions, such as steel sheet piles, underground continuous walls, etc.
[0021] Furthermore, in order to ensure the construction quality, a plain concrete cushion layer with a thickness of about 10 cm is provided for the retaining wall, anti-impact bottom plate and buried pipe outer concrete of the connecting section.
[0022] The beneficial effects of the present invention are:
[0023] 1) Structural safety. The cast-in-place reinforced concrete aqueduct bottom plate also serves as the top support of the supporting structure below the aqueduct. The framework of the diversion aqueduct has better stability, the top of the bored pile is less likely to deform, the stress conditions are good, and the diversion structure is safe and guaranteed.
[0024] 2) Simple construction. Taking full advantage of the fact that the flow rate of gullies is small during the non-flood season, earth-rock cofferdams and diversion pipes are used in the gullies during the non-flood season to avoid the construction of new diversion open channels with large diameter pipes, making the construction simpler.
[0025] 3) Low investment. The diversion aqueduct or box culvert during the flood season, the connecting channel and the anti-scouring bottom plate at both ends are permanent and temporary structures. In particular, the diversion open channel and the anti-seepage wall structure required for the bank protection on both sides of the diversion open channel are eliminated, which saves investment significantly.
[0026] 4) Small environmental impact. The diversion open channel excavation and slope reduction has a large impact range, and optimization and elimination is beneficial to environmental protection. BRIEF DESCRIPTION OF THE DRAWINGS
[0027] Figure 1 This is a plan view of a diversion structure for a large-diameter buried pipe passing through a gully according to an embodiment of the present invention;
[0028] Figure 2 yes Figure 1 A-A sectional view;
[0029] Figure 3 yes Figure 1 B-B sectional view;
[0030] Figure 4 yes Figure 1 C-C section view;
[0031] Figure 5 yes Figure 1 D-D section view.
[0032] In the figure: 1-aqueduct; 2-connecting section retaining wall; 3-anti-scour bottom plate; 4-temporary cofferdam; 5-temporary diversion pipe; 6-water stop; 7-buried pipe; 8-buried pipe wrapped with concrete; 9-support structure; 91-bored cast-in-place piles; 92-high-pressure rotary jet piles; 93-crown beam; 94-top support; 95-steel support; 96-steel perimeter purlin; 10-gully. DETAILED DESCRIPTION
[0033] The present invention will be further described in detail below in conjunction with the accompanying drawings.
[0034] like Figure 1 to Figure 5 As shown, the present invention is a diversion structure for a large-diameter buried pipe passing through a gully, including an aqueduct 1, a connecting section retaining wall 2, an anti-scouring bottom plate 3, a temporary cofferdam 4, a temporary diversion pipe 5, a water stop 6, a buried pipe 7, a buried pipe outer concrete 8, and a supporting structure 9.
[0035] The aqueduct 1 is located above the buried pipe 7 and is a cast-in-place U-shaped reinforced concrete structure with a permanent and temporary combination arrangement. It is both a diversion structure for the gully 10 at the buried pipe 7 during the flood season and a support structure for the gully 10 during the operation period. Both ends are placed on bored cast-in-place piles 91 of the buried pipe 7 support structure 9, and the bottom plate of the aqueduct 1 also serves as the top support of the support structure below the aqueduct 1; the expansion joints between the two ends of the aqueduct 1 and the retaining wall 2 of the connecting section are connected by water stops 6.
[0036] The connecting section retaining wall 2 is located at both ends of the aqueduct 1 and is a connecting structure between the aqueduct 1 and the existing revetment of the gully 10. Considering the anti-seepage requirements, a concrete gravity retaining wall is generally used.
[0037] The anti-scour bottom plate 3 is located on the riverbed of the gully 10 at the connecting section retaining wall 2, and is a reinforced concrete bottom plate. At the connecting part with the aqueduct 1 and the connecting section retaining wall 2, the anti-scour bottom plate 3 is partially enlarged and thickened, and a water stop 6 is set to connect with the expansion joint between the aqueduct 1.
[0038] The temporary cofferdam 4 is located in the gully 10 upstream and downstream of the connecting section retaining wall 2. It is a water-retaining earth-rock cofferdam in the non-flood season, and provides protection for the construction of the aqueduct 1, the connecting section retaining wall 2, and the anti-scouring bottom plate 3 in the non-flood season. It will be dismantled before the flood season arrives. A temporary diversion pipe 5 is set in the temporary cofferdam 4 to prevent the water flow of the gully 10 from entering the foundation pit of the aqueduct 1 in the non-flood season.
[0039] The temporary diversion pipe 5 crosses the aqueduct 1 and the gully 10 where the connecting section retaining wall 2 is located. A PE pipe can be used, with both ends extending out of the temporary cofferdam 5 to divert the water body upstream of the gully 10 to the downstream of the gully 10. Before the flood season arrives, it will be dismantled together with the temporary cofferdam 4, and the completed aqueduct 1, connecting section retaining wall 2, and anti-scouring bottom plate 3 will take over the diversion function.
[0040] The waterstop 6 is respectively located in the expansion joints between the aqueduct 1 and the connecting section retaining wall 2, and between the aqueduct 1 and the anti-collision bottom plate 3, and can be made of copper sheet waterstop, steel edge rubber waterstop or rubber waterstop.
[0041] The buried pipe 7 is a steel pipe structure. After the support structure 9 is completed, the conventional parts are all open-cut to form trenches, but dark excavation is required under the aqueduct 1. The buried pipe 7 is generally manufactured into a standard pipe section in the factory, and then circumferentially welded after being installed in place on site. Then, the steel bars are tied, the formwork is erected, and the buried pipe outer casing concrete 8 is poured, and backfill is restored to the original ground elevation.
[0042] The buried pipe outer wrapping concrete 8 is located outside the buried pipe 7 and plays a protective role for the buried pipe 7 .
[0043] The support structure 9 is a protective structure for the buried pipe 7 constructed into a trench, and includes bored cast-in-place piles 91, high-pressure rotary jet piles 92, crown beams 93, top supports 94, steel supports 95 and steel purlins 96. The bored cast-in-place piles 91 are the main load-bearing structures of the foundation pit for the buried pipe 7. There are two rows of bored cast-in-place piles 91, which are reinforced concrete structures. Holes are formed by rotary drilling or impact drilling, and mud wall protection or casing construction is used. The pile diameter can be 1.0m, and the pile center spacing is 1.2m. The top of the longitudinal force-bearing steel bar of the bored cast-in-place pile 91 extends into the crown beam 93 at the crown beam 93 position, and extends into the aqueduct 1 at the aqueduct 1 position; the high-pressure rotary jet piles 92 are arranged in the outer gap of the bored cast-in-place piles 91, and double-tube rotary jetting is used to play an anti-seepage role. The cement content should not be less than 30%; the crown beam 93 is located at the top of the bored cast-in-place pile 91, which is a reinforced concrete cast-in-place structure. It forms a frame structure in combination with the top support 94, which plays a role of about The function of restraining the surface displacement of bored cast-in-place piles 91; the top support 94 is located between the crown beams 93 and is a reinforced concrete structure. It is cast integrally with the crown beams 93 before the excavation of the foundation pit for buried pipes 7; the steel support 95 is the supporting structure of the middle and lower part of the bored cast-in-place piles 91, which is installed after the soil is excavated to the corresponding elevation, and is connected to the steel purlins 96 at both ends with bolts. The steel support 95 is a temporary structure for the excavation construction of the buried pipe 7, which is used to ensure that the foundation pit for buried pipes 7 is excavated into trenches to the foundation, facilitates the construction of buried pipes 7, and is generally removed after the foundation of buried pipes 7 is reinforced; the steel purlins 96 are the connecting structure between the steel support 95 and the bored cast-in-place piles 91, and are installed and removed together with the steel support 95.
[0044] In order to ensure the construction quality, a plain concrete cushion layer with a thickness of about 10 cm is provided on the connecting section retaining wall 2, the anti-collision bottom plate 3, and the buried pipe outer package concrete 8.
[0045] According to the traffic demand on the upper part of the aqueduct 1, the cast-in-place U-shaped reinforced concrete aqueduct 1 can also be changed into a cast-in-place reinforced concrete box culvert, and the flow of the box culvert must meet the flood standards for diversion in non-flood season and flood discharge in operation period.
[0046] According to the geological conditions of the foundation pit for burying the pipe 7, the bored piles 91 and high-pressure jet grouting piles 92 may also adopt other supporting structures with bearing and anti-seepage functions, such as steel sheet piles, underground continuous walls, etc.
[0047] According to the stability requirement of the supporting structure 9, the steel support 95 can be provided in one or more rows.
[0048] Those skilled in the art should understand that the above embodiments do not limit the present invention in any form, and any technical solutions obtained by equivalent replacement or equivalent transformation shall fall within the protection scope of the present invention.
Claims
1. A diversion structure for a large-diameter buried pipe passing through a gully, characterized in that: It includes an aqueduct, a connecting section retaining wall, an anti-scouring bottom plate, a temporary cofferdam, a temporary diversion pipe, an embedded pipe, and a supporting structure; the aqueduct is located above the embedded pipe and is a combination of permanent and temporary arrangements. The aqueduct is both a diversion structure for the gully at the embedded pipe position during flood season and a supporting structure for the gully during operation. Both ends of the aqueduct are placed on the supporting structure, and the bottom plate of the aqueduct also serves as the top support of the supporting structure below the aqueduct; the connecting section retaining wall is located at both ends of the aqueduct and is a connecting structure for the aqueduct and the existing revetment of the gully; the anti-scouring bottom plate is located on the gully riverbed at the connecting section retaining wall; the temporary cofferdam is located in the gully upstream and downstream of the connecting section retaining wall and is a water-retaining earth-rock cofferdam during the non-flood season. The temporary cofferdam provides protection for the non-flood season construction of the aqueduct, the connecting section retaining wall, and the anti-scouring bottom plate and will be dismantled before the flood season arrives; the temporary diversion pipe crosses the gully where the aqueduct and the connecting section retaining wall are located to prevent the gully water flow from entering the aqueduct foundation pit during the non-flood season.
2. The diversion structure for a large-diameter buried pipe passing through a gully according to claim 1 is characterized in that: The aqueduct adopts a cast-in-place U-shaped reinforced concrete structure or a reinforced concrete box culvert structure.
3. The diversion structure for a large-diameter buried pipe passing through a gully according to claim 1 is characterized in that: The connecting section retaining wall is a concrete gravity retaining wall.
4. The diversion structure for a large-diameter buried pipe passing through a gully according to claim 1 is characterized in that: The anti-scouring bottom plate is a reinforced concrete bottom plate, and the anti-scouring bottom plate is partially enlarged and thickened at the connection position with the aqueduct and the connecting section retaining wall.
5. The diversion structure for a large-diameter buried pipe passing through a gully according to claim 1 is characterized in that: The temporary diversion pipe adopts PE pipe, and both ends extend out of the temporary cofferdam to divert the water from the upstream of the gully to the downstream of the gully. Before the flood season arrives, it will be dismantled together with the temporary cofferdam, and the completed aqueduct, connecting section retaining wall and anti-scouring bottom plate will take over the diversion function.
6. The diversion structure for a large-diameter buried pipe passing through a gully according to claim 1 is characterized in that: Expansion joints are arranged between the aqueduct and the connecting section retaining wall, and between the aqueduct and the anti-scouring bottom plate, and water stops are arranged in the expansion joints; the water stops adopt copper sheet water stops, steel edge rubber water stops, or rubber water stops.
7. The diversion structure for a large-diameter buried pipe passing through a gully according to claim 1 is characterized in that: The buried pipe is a steel pipe structure, and an outer covering concrete is arranged outside the buried pipe to protect the buried pipe.
8. The diversion structure for a large-diameter buried pipe passing through a gully according to claim 1 is characterized in that: The support structure is a protective structure for the buried pipe construction trench, including bored piles, high-pressure rotary jet piles, crown beams, top supports, steel supports and steel purlins; bored piles are the main load-bearing structure of the buried pipe foundation pit, with 2 rows in total, which are reinforced concrete structures, using rotary drills or impact drills to form holes, mud wall protection or casing construction, and the top of the longitudinal force-bearing steel bars of the bored piles extends into the crown beam at the crown beam position and into the aqueduct at the aqueduct position; high-pressure rotary jet piles are arranged in the outer gap of the bored piles, and double-tube rotary jetting is used to prevent seepage; the crown beam is located at the top of the bored pile, which is a reinforced concrete cast-in-place structure, and is combined with the top support to form a frame structure, which plays a role in restricting the surface displacement of the bored piles; The top support is located between the crown beams and is a reinforced concrete structure. It is cast integrally with the crown beam before the excavation of the buried pipe foundation pit; the steel support is the supporting structure of the middle and lower part of the bored cast-in-place piles, which is installed after the soil is excavated to the corresponding elevation, and the two ends are connected to the steel perimeter purlin with bolts. The steel support is a temporary structure for the buried pipe excavation construction, which is used to ensure that the buried pipe foundation pit is excavated into trenches to the foundation, facilitate the buried pipe construction, and is dismantled after the buried pipe foundation is reinforced. One or more steel supports are provided; the steel perimeter purlin is the connecting structure between the steel support and the bored cast-in-place piles, and is installed and dismantled with the steel support.
9. The diversion structure for a large-diameter buried pipe passing through a gully according to claim 1, characterized in that: The supporting structure also adopts steel sheet piles or underground continuous walls.
10. The diversion structure for a large-diameter buried pipe passing through a gully according to claim 1, characterized in that: The connecting section retaining wall, anti-scouring bottom plate and buried pipe outer package concrete are all provided with plain concrete cushion layers.