Prefabricated pile spiral construction device and construction method

By installing spiral sleeves and external spiral blades on prefabricated piles, and using hydraulic and motor drives to cut and bury the prefabricated piles, the problems of low construction efficiency and large losses of traditional prefabricated piles are solved, and efficient and flexible construction and strength improvement are achieved.

CN114045829BActive Publication Date: 2024-11-19CHINA THIRD METALLURGICAL GRP
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202111354005.0
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2021-11-12
Publication Date
2024-11-19
Estimated Expiration
2041-11-12

AI Technical Summary

Technical Problem

The construction of traditional prefabricated piles is likely to cause damage accidents such as cracking and interruption of prefabricated piles, resulting in the problems of extended construction time, inefficient efficiency and low on-site efficiency.

Method used

The spiral sleeve is used to cover the custom prefabricated piles, and the prefabricated piles are sent to the predetermined position by rotating the external spiral blades. The spiral sleeve is driven by hydraulic devices and motors to cut pile driving holes to achieve efficient burial of prefabricated piles.

Benefits of technology

It improves the utilization rate and construction efficiency of prefabricated piles, shortens construction time, increases the strength of piles and the mechanical properties of the foundation, and flexibly moves construction equipment without being restricted by the site and ground.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN114045829B_ABST
    Figure CN114045829B_ABST
Patent Text Reader

Abstract

A prefabricated pile spiral construction device and construction method, including customized prefabricated piles, external spiral blades, spiral sleeves, steering boxes, speed reducers, motors, shock-absorbing frames, transmission platforms, hydraulic devices, telescopic frames, wheels, operating carriages, load-bearing platforms, prefabricated piles, transmission contact blocks, and conical pile heads, characterized in that the load-bearing platform is connected to the rear of the operating carriage, wheels are installed below, hydraulic devices and telescopic frames are installed on the load-bearing platform, the transmission platform is installed on the top of the hydraulic device, the motor, speed reducer and steering box are installed on the transmission platform in sequence, the spiral sleeve is installed in the vertical direction of the steering box, the external spiral blade is processed on the outside of the spiral sleeve, and the customized prefabricated piles are placed inside. The beneficial effects of the present invention are simple and convenient to operate, reduce the loss of prefabricated piles, improve the utilization rate of prefabricated piles, improve construction efficiency, shorten construction time, are not limited by the site ground, the prefabricated piles are buried deep, and the prefabricated piles are buried well.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of building construction, and in particular to a prefabricated pile spiral construction device and a construction method. Background Art

[0002] In construction, precast concrete piles can be prefabricated in factories or construction sites. Due to their mass production, saving construction time and improving construction efficiency, they are widely used in large-scale construction production.

[0003] At present, precast piles are usually made by drilling holes in the ground with a pile driver, and then the precast piles are hammered into the pre-drilled pile holes with the pile driver under pressure. This type of precast pile construction is prone to precast pile cracking, breaking and other precast pile loss accidents during construction, resulting in prolonged construction time, heavy construction tasks, and low efficiency on the construction site. Summary of the invention

[0004] The present invention provides a precast pile spiral construction device and a construction method. In order to solve a series of technical problems brought about by traditional precast pile construction, the present invention uses a spiral sleeve to cover the outside of a specially customized precast pile, and the outer spiral blade of the spiral sleeve is rotated and pressed down to send the precast pile to a predetermined precast hole. This construction method has high construction efficiency and high utilization rate of precast piles. It can be flexibly moved over a large range, and piling is not restricted by the ground surface of the site, so the construction time is greatly shortened.

[0005] In order to achieve the above object, the present invention adopts the following technical solutions:

[0006] A prefabricated pile spiral construction device comprises a customized prefabricated pile, an outer spiral blade, a spiral sleeve, a steering box, a reducer, a motor, a shock absorbing frame, a transmission platform, a hydraulic device, a telescopic frame, wheels, an operating carriage, a load-bearing platform, a prefabricated pile, a transmission contact block, and a conical pile head. The load-bearing platform is connected to the rear of the operating carriage, wheels are installed under the load-bearing platform and the operating carriage, a hydraulic device is installed at the center of the load-bearing platform, a transmission platform is installed on the top of the hydraulic device, and a liftable telescopic frame is installed around the hydraulic device and under the transmission platform. The motor, the reducer and the steering box are installed on the transmission platform from left to right in sequence, the shock absorbing frame is installed between the motor and the transmission platform, the spiral sleeve is installed in the vertical direction of the steering box, the outer spiral blade is processed on the outer side of the spiral sleeve, the customized prefabricated pile is placed inside the spiral sleeve, the spiral sleeve and the customized prefabricated pile are in contact and matched through the lower transmission contact block, and the customized prefabricated pile consists of a prefabricated pile, a transmission contact block and a conical pile head.

[0007] The steering box has a pair of bevel gears forming a 90° transmission structure.

[0008] The bottom radius of the conical pile head is 50 mm larger than the bottom radius of the prefabricated pile, and a transmission contact block is processed on the conical bottom surface.

[0009] The specific construction method of the prefabricated pile spiral construction device is as follows:

[0010] S1. Use a pile driver to construct a pile hole of a certain depth at the pre-designed piling position, and drive the prefabricated pile spiral construction device to the piling position.

[0011] S2. Lift the customized prefabricated pile, extend the conical pile head into the pile hole, and position the customized prefabricated pile vertically at the pile hole.

[0012] S3. Lift the transmission platform by operating the hydraulic device and telescopic frame of the carriage, and put the spiral sleeve on the outside of the customized prefabricated pile. The transmission contact block on the lower plane of the spiral sleeve and the two right-angled surfaces of the transmission contact block protrusion at the bottom of the customized prefabricated pile are in close contact.

[0013] S4, start the motor, the motor transmits torque to the reducer, the reducer transmits torque to the steering box, the steering box transmits torque to the spiral sleeve in the 90° direction through the bevel gear, the spiral sleeve rotates, the outer spiral blade cuts the outer wall foundation of the pile hole, and the hydraulic device applies downward pressure to the spiral sleeve, causing the spiral sleeve to cut downward.

[0014] S5. After the spiral sleeve cuts to the designed burial depth of the precast pile, the motor rotates in the opposite direction, the spiral sleeve rotates in the opposite direction, and the hydraulic device lifts it again. Since the spiral sleeve and the customized precast pile are contact transmission, the reverse lifting separates the spiral sleeve from the customized precast pile, and the spiral sleeve is pulled out of the pile hole, and the customized precast pile remains at the designed pile position.

[0015] S6. Pour concrete into the pile hole enlarged during the spiral sleeve piling process to fill the enlarged pile hole.

[0016] Compared with the prior art, the present invention has the following beneficial effects:

[0017] 1) The precast pile spiral construction device has a simple structure, flexible operation, low noise, small footprint, convenient processing of customized precast piles, and high processing efficiency.

[0018] 2) The spiral construction of precast piles reduces the loss of precast piles, improves the utilization rate of precast piles, improves construction efficiency and shortens construction time.

[0019] 3) The spiral construction of precast piles is flexible and can be moved to any site where precast piles are needed. It is not restricted by the ground surface of the site. The precast piles are buried deeper and the precast piles are buried well.

[0020] 4) Spiral cutting increases the diameter of the precast pile hole, and pours concrete around the custom precast pile, which increases the strength of the pile and improves the mechanical properties of the foundation. BRIEF DESCRIPTION OF THE DRAWINGS

[0021] Figure 1 The present invention is a schematic structural diagram of a prefabricated pile spiral construction device and a construction method.

[0022] Figure 2 It is an axial schematic diagram of a precast pile spiral construction device and a construction method according to the present invention.

[0023] Figure 3 The present invention discloses a precast pile spiral construction device and a construction method.

[0024] Figure 4 It is a schematic diagram of a customized precast pile structure of a precast pile spiral construction device and a construction method described in the present invention.

[0025] In the picture: 1. Custom prefabricated pile 2. External spiral blade 3. Spiral sleeve 4. Steering box 5. Reducer

[0026] 6. Motor 7. Shock-absorbing frame 8. Transmission platform 9. Hydraulic device 10. Telescopic frame

[0027] 11. Wheels 12. Operating compartment 13. Load-bearing platform 14. Prefabricated piles 15. Transmission contact block

[0028] 16. Conical pile head DETAILED DESCRIPTION

[0029] The specific implementation of the present invention will be further described below in conjunction with the accompanying drawings:

[0030] like Figure 1 , 2, 3, and 4, a prefabricated pile spiral construction device and construction method, including a customized prefabricated pile 1, an outer spiral blade 2, a spiral sleeve 3, a steering box 4, a reducer 5, a motor 6, a shock absorbing frame 7, a transmission platform 8, a hydraulic device 9, a telescopic frame 10, a wheel 11, an operating carriage 12, a load-bearing platform 13, a prefabricated pile 14, a transmission contact block 15, and a conical pile head 16. The load-bearing platform 13 is connected to the back of the operating carriage 12, and the wheels 11 are installed under the load-bearing platform 13 and the operating carriage 12. The wheels 11 are flexible to move and can be adapted to In response to any ground conditions, a hydraulic device 9 is installed at the center of the load-bearing platform 13, a transmission platform 8 is installed on the top of the hydraulic device 9, and a retractable frame 10 is installed around the hydraulic device 9 and below the transmission platform 8. The retractable frame 10 supports the transmission platform 8, and the hydraulic device 9 is responsible for lifting the transmission platform 8. The transmission platform 8 is sequentially installed with a motor 6, a reducer 5 and a steering box 4 from left to right, and the shock-absorbing frame 7 is installed between the motor 6 and the transmission platform 8. The shock-absorbing frame 7 reduces the vibration of the motor 6 and the reducer 5 during the transmission process. , so as not to affect the transmission of the bevel gear in the steering box 4, the spiral sleeve 3 is installed in the vertical direction of the steering box 4, the bevel gear transmission is installed in the steering box 4, the input shaft and the output shaft are arranged at 90 degrees, the vertical output shaft is connected to the spiral sleeve 3, the outer spiral blade 2 is processed on the outer side of the spiral sleeve 3, and the customized prefabricated pile 1 is placed inside the spiral sleeve 3. The spiral sleeve 3 and the customized prefabricated pile 1 are contacted and matched through the lower transmission contact block 15. Through gravity and the downward pressure of the hydraulic device, the lower plane of the spiral sleeve 3 and the conical pile head of the customized prefabricated pile 1 are aligned. The conical bottom surface of 16 is pressed and contacted, and the transmission contact block 15 on the spiral sleeve 3 is in contact with the transmission contact block 15 on the lower plane of the customized prefabricated pile 1. The customized prefabricated pile 1 is composed of a prefabricated pile 14, a transmission contact block 15 and a conical pile head 16. The outer spiral blade 2 processed on the outside of the spiral sleeve 3 expands the original piling hole through the rotating cutting action. The downward pressure is applied by the hydraulic device 9, and the lower conical pile head 16 of the customized prefabricated pile 1 goes deep downward, and the spiral sleeve 3 and the customized prefabricated pile 1 are transferred into the piling hole to complete the placement of the prefabricated pile.

[0031] like Figure 1 , 2 As shown, the steering box 4 has a pair of bevel gears forming a 90° transmission structure.

[0032] like Figure 4 As shown, the bottom radius of the conical pile head 16 is 50 mm larger than the bottom radius of the prefabricated pile 14, and a transmission contact block 15 is processed on the conical bottom surface.

[0033] The specific construction method of the prefabricated pile spiral construction device and construction method is as follows:

[0034] S1. Use a pile driver to construct a pile hole of a certain depth at the pre-designed piling position, and drive the prefabricated pile spiral construction device to the piling position.

[0035] S2, the customized prefabricated pile 1 is hoisted, the conical pile head 16 is extended into the pile hole, and the customized prefabricated pile 1 is vertically positioned at the pile hole position.

[0036] S3. Lift the transmission platform 8 by operating the carriage 12 to control the hydraulic device 9 and the telescopic frame 10, and put the spiral sleeve 3 on the outside of the customized prefabricated pile 1. The transmission contact block 15 on the lower plane of the spiral sleeve 3 and the two right-angled surfaces of the transmission contact block 15 protruding at the bottom of the customized prefabricated pile 1 are in close contact.

[0037] S4, start the motor 6, the motor 6 transmits torque to the reducer 5, the reducer 5 transmits torque to the steering box 4, the steering box 4 transmits torque to the spiral sleeve 3 in the 90° direction through the bevel gear, the spiral sleeve 3 rotates, the outer spiral blade 2 cuts the outer wall foundation of the pile hole, and the hydraulic device 9 applies downward pressure to the spiral sleeve 3, so that the spiral sleeve 3 cuts downward.

[0038] S5. After the spiral sleeve 3 cuts to the designed burial depth of the precast pile, the motor 6 rotates in the opposite direction, the spiral sleeve 3 rotates in the opposite direction, and the hydraulic device 9 lifts again. Since the spiral sleeve 3 and the customized precast pile 1 are contact transmission, the reverse lifting separates the spiral sleeve 3 from the customized precast pile 1, and the spiral sleeve 3 is pulled out of the pile hole, and the customized precast pile 1 remains at the designed pile position.

[0039] S6, pouring concrete into the pile hole enlarged during the pile driving process of the spiral sleeve 3 to fill the enlarged pile hole.

[0040] The following examples are implemented on the premise of the technical solution of the present invention, and provide detailed implementation methods and specific operation processes, but the protection scope of the present invention is not limited to the following examples. The methods used in the following examples are conventional methods unless otherwise specified.

[0041] [Example]

[0042] like Figure 1 , 2 As shown, according to the design requirements, the spiral sleeve 3, the steering box 4, the reducer 5, the motor 6, the shock absorbing frame 7, the transmission contact block 15, the hydraulic device 9, the telescopic frame 10, the wheel 11, the operating carriage 12, and the load-bearing platform 13 are installed together, and the external spiral blade 2 is processed outside the spiral sleeve 3.

[0043] like Figure 4 As shown, the customized prefabricated pile 1 is processed, and the conical pile head 16 and the transmission contact block 15 are processed.

[0044] like Figure 1As shown, the customized prefabricated pile 1 is vertically inserted into the pile hole at the predetermined pile hole position, the transmission platform 8 is raised, and the spiral sleeve 3 is installed on the outside of the customized prefabricated pile 1.

[0045] The motor 6 is started, and the spiral sleeve 3 rotates downward, and the customized prefabricated pile 1 is rotated and driven into the pile hole. The motor 6 rotates in the opposite direction, driving the spiral sleeve 3 to rotate in the opposite direction and upward, and the spiral sleeve 3 and the customized prefabricated pile 1 are separated, and the spiral sleeve 3 leaves the pile hole, and the customized prefabricated pile 1 remains in the pile hole.

[0046] Concrete is poured into the pile hole enlarged by the spiral sleeve 3 , and the concrete reinforces the customized prefabricated pile 1 driven into the pile hole, thereby increasing the strength of the customized prefabricated pile 1 .

[0047] Start the precast pile spiral construction device, move to other piling hole locations, and complete the precast pile driving work.

[0048] The present invention is simple and convenient to operate during use, reduces the loss of precast piles, improves the utilization rate of precast piles, improves construction efficiency, shortens construction time, is not restricted by the ground surface of the site, has a deeper burial depth of the precast piles, and is well buried.

Claims

1. A precast pile spiral construction method, which uses a precast pile spiral construction device to complete the construction. The precast pile spiral construction device includes a customized precast pile, an external spiral blade, a spiral sleeve, a steering box, a reducer, a motor, a shock-absorbing frame, a transmission platform, a hydraulic device, a telescopic frame, wheels, an operating carriage, a load-bearing platform, a precast pile, a transmission contact block, and a conical pile head, characterized in that The load-bearing platform is connected to the rear of the operating carriage, and wheels are installed under the load-bearing platform and the operating carriage. A hydraulic device is installed at the center of the load-bearing platform, and a transmission platform is installed on the top of the hydraulic device. A retractable frame is installed around the hydraulic device and under the transmission platform. The motor, reducer and steering box are installed on the transmission platform from left to right in sequence. The shock-absorbing frame is installed between the motor and the transmission platform. A spiral sleeve is installed in the vertical direction of the steering box. An external spiral blade is processed on the outer side of the spiral sleeve. A customized prefabricated pile is placed inside the spiral sleeve. The spiral sleeve and the customized prefabricated pile are in contact and matched through the lower transmission contact block. The customized prefabricated pile consists of a prefabricated pile, a transmission contact block and a conical pile head. The construction method includes the following contents: S1. Use a pile driver to construct a pile hole of a certain depth at the pre-designed piling position, and drive the prefabricated pile spiral construction device to the piling position; S2, hoist the customized prefabricated pile, extend the conical pile head into the pile hole, and vertically position the customized prefabricated pile at the pile hole position; S3, lift the transmission platform by operating the hydraulic device and telescopic frame of the carriage, put the spiral sleeve on the outside of the customized prefabricated pile, and the transmission contact block on the lower plane of the spiral sleeve and the two right-angled surfaces of the transmission contact block protrusion at the bottom of the customized prefabricated pile are in close contact; S4, start the motor, the motor transmits torque to the reducer, the reducer transmits torque to the steering box, the steering box transmits torque to the spiral sleeve in the 90° direction through the bevel gear, the spiral sleeve rotates, the outer spiral blade cuts the outer wall foundation of the pile hole, and the hydraulic device applies downward pressure to the spiral sleeve, so that the spiral sleeve cuts downward; S5. After the spiral sleeve cuts to the designed buried depth of the precast pile, the motor rotates in the opposite direction, the spiral sleeve rotates in the opposite direction, and the hydraulic device lifts again. Since the spiral sleeve and the customized precast pile are contact transmission, the reverse lifting separates the spiral sleeve from the customized precast pile, and the spiral sleeve is pulled out of the pile hole, and the customized precast pile remains at the designed pile position; S6. Pour concrete into the pile hole enlarged during the spiral sleeve piling process to fill the enlarged pile hole.

2. A precast pile spiral construction method according to claim 1, characterized in that The steering box has a pair of bevel gears forming a 90° transmission structure.

3. A precast pile spiral construction method according to claim 1, characterized in that The bottom radius of the conical pile head is 50 mm larger than the bottom radius of the precast pile, and a transmission contact block is processed on the conical bottom surface.