A guide device and operation method for installing a wind turbine cabin in a floating state on a crane ship

By designing the guide device for floating installation of the fan nacelle and using welding assembly and bolt fixing structure, the problem of difficulty in shaking and alignment of the cabin in floating state of the crane is solved, and the safe and efficient installation of the large megawatt fan nacelle is achieved. Filling the technological gap in the offshore wind power industry.

CN114198261BActive Publication Date: 2024-11-08CCCC FIRST HARBOR ENGINEERING CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202111598614.0
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2021-12-24
Publication Date
2024-11-08
Estimated Expiration
2041-12-24

AI Technical Summary

Technical Problem

During offshore wind power construction, when the crane ship is floating in the floating state, the cabin is increased due to excessive shaking of the cabin and difficulty in aligning the bolt holes, which has increased the difficulty of installation of the cabin, which poses safety risks, and it is difficult to successfully complete the large-scale operation in the offshore seas. Floating installation of megawatt fan nacelle.

Method used

Design a guide device for floating state installation of fan nacelle, including guide plate, anti-collision U plate, reinforcement plate, roof plate, thickening plate, clamp plate and positioning plate, forming a combination through welding and fixing it on the nacelle by bolts , provides positioning guidance and shock absorption protection, optimizes the device structure to reduce weight and facilitates installation.

Benefits of technology

Effectively reduce the shaking of the cabin during installation at high altitudes and reduce the risk of collisions. It has successfully achieved floating state installation of the large megawatt fan cabin, alleviating the tight resources of the fan installation platform ship.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN114198261B_ABST
    Figure CN114198261B_ABST
Patent Text Reader

Abstract

A guide device and operation method for installing a wind turbine cabin in a floating state on a crane ship, wherein an anti-collision U plate (2) is installed on the outer edge of the side of a guide plate (1), reinforcing rib plates (3) are installed on both sides of the guide plate (1), a top plate (4) is installed on the top of the guide plate (1) and the reinforcing rib plate (3), and a thickening plate (5) is welded on the top of the top plate (4); the clamping plate (6) is fixed to the assembly by bolts; after the assembly is installed on the cabin, the positioning plate (7) is fixed to the assembly by bolts. The guide device can provide positioning guidance and shock absorption protection functions when installing the wind turbine cabin. When installing a large-megawatt wind turbine cabin in a floating state, the shaking of the cabin can be greatly reduced, which is conducive to the high-altitude alignment of the cabin and reduces the risk of collision with the cabin. The problem that the wind turbine cabin cannot be installed in the floating state of an offshore crane ship has been successfully solved, and the shortage of wind turbine installation ships has been effectively alleviated.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the field of offshore wind power construction, and in particular to a guide device and an operating method for installing a wind turbine cabin in a floating state on a crane vessel. Background Art

[0002] With the rapid development of offshore wind power, offshore wind farms have gradually moved from nearshore to offshore, with the water depth increasing from more than ten meters to more than forty meters. The capacity of wind turbine units has also increased from the initial 4.0MW to 10MW, and the weight of wind turbine nacelles has also increased. This has posed new challenges to the length of the pile legs and the lifting weight of the crane of the wind turbine installation platform ship. At the same time, the rush to install offshore wind power in 2021 has led to a shortage of wind turbine installation platform ship resources.

[0003] Studying the construction technology of floating installation of wind turbine nacelles by crane vessels can effectively alleviate the shortage of wind turbine installation platform vessels. At present, only in the offshore with good sea conditions, the domestic use of crane vessels to successfully install small megawatt wind turbine nacelles has been successful, and there has been no successful case of using crane vessels to float and install large megawatt wind turbine nacelles in offshore waters.

[0004] The shell of the wind turbine nacelle is made of fiberglass, and the gap between the shell and the outer wall of the tower is 2-3cm. During installation, the swing amplitude of the nacelle should be controlled within 2cm. When a large crane ship is in a floating state, it is affected by wind and waves, and the hook head will shake greatly, making it difficult to align the bolts of the nacelle at high altitude, and it is easy to bump and damage the wind turbine nacelle, which poses certain safety risks. Summary of the invention

[0005] The purpose of the present invention is to use auxiliary devices to solve the problems of excessive shaking and difficulty in aligning bolt holes that occur when the cabin is installed in a floating state on a crane ship, so as to realize the floating installation of large-megawatt wind turbine cabins in offshore waters and fill the gap in the offshore wind power industry.

[0006] The purpose of the present invention is to provide a guide device for floating installation of a wind turbine cabin and an operating method.

[0007] A guide device for floating installation of a wind turbine cabin comprises a guide plate 1, an anti-collision U plate 2, a reinforcing rib plate 3, a top plate 4, a thickening plate 5, a clamping plate 6 and a positioning plate 7. The anti-collision U plate 2 is installed on the outer edge of the side of the guide plate 1, the reinforcing rib plates 3 are installed on both sides of the guide plate 1, the top plate 4 is installed on the top of the guide plate 1 and the reinforcing rib plate 3, and the thickening plate 5 is welded on the top of the top plate 4; the guide plate 1, the anti-collision U plate 2, the reinforcing rib plate 3, the top plate 4 and the thickening plate 5 are welded to form a combination;

[0008] The clamping plate 6 is fixed to the assembly by bolts;

[0009] After the assembly is installed on the nacelle, the positioning plate 7 is fixed to the assembly by bolts.

[0010] An operating method of a guide device for floating installation of a wind turbine nacelle comprises the following steps:

[0011] Step ① Engine room transfer: The transport ship transports the engine room to the construction site and then berths at the crane ship. The crane ship transfers the engine room together with the tooling to the deck of the crane ship;

[0012] Step 2: Remove the tooling: Use a hydraulic wrench or torque wrench to remove the bolts of the cabin tooling;

[0013] Step 3: Lifting the engine room: Lift the engine room by the crane of the crane ship so that the brake disc 8 is 1m away from the top of the tooling;

[0014] Step ④ Install the guide device: Use high-strength bolts to connect the clamping plate 6 and the top plate 4 of the welded body to form an assembly, then install the assembly at the screw hole of the brake disc 8, and use high-strength bolts to connect and fix the positioning plate 7 and the top plate 4;

[0015] Step ⑤ Lifting and alignment: The crane of the crane ship continues to lift the hook and lift the nacelle to the top of the top tower;

[0016] Step ⑥ Install the nacelle: Slowly lower the hook of the crane ship to insert the tooling into the upper part of the top tower until the nacelle is completely aligned with the top tower. Use stud bolts to connect the nacelle and the top tower flange, and apply the corresponding torque value as required by the wind turbine manufacturer.

[0017] Step 7: Install the cabin: After the cabin is installed, remove the guide device from the cabin.

[0018] Optimized: An elongated lightening hole 101 is provided in the middle of the guide plate 1, which can reduce the overall weight of the guide device and facilitate on-site installation.

[0019] Optimized: The anti-collision U plate 2 is a U-shaped protective plate, which is engaged with the outer edge of the side of the guide plate 1, and the guide plate 1 and the anti-collision U plate 2 are welded and connected.

[0020] Optimization: Two reinforcing rib plates 3 are provided, and the inner sides of the two reinforcing rib plates 3 are welded to the inner side of the guide plate 1; the top ends of the two reinforcing rib plates 3 and the top ends of the guide plate 1 are welded to the bottom ends of the top plate 4 respectively.

[0021] Optimization: The top plate 4 is an elliptical steel plate, and a plurality of bolt holes 401 for fixing the clamping plate 6 and the positioning plate 7 are provided on the top plate 4 .

[0022] Optimization: The clamping plate 6 is a flat steel plate, and a plurality of clamping holes are provided on the clamping plate 6, and the clamping holes are tapped holes.

[0023] Optimization: The positioning plate 7 is a flat steel plate, and a positioning hole is opened on the positioning plate 7, and the positioning hole is a tapped hole.

[0024] Compared with the prior art, the present invention has the following advantages:

[0025] The guide device can provide positioning guidance and shock absorption protection functions when installing the wind turbine nacelle. When installing a large-megawatt wind turbine nacelle in a floating state, it can greatly reduce the shaking of the nacelle, which is beneficial for the high-altitude alignment of the nacelle and reduces the risk of bumping into the nacelle. It successfully breaks the problem that the wind turbine nacelle cannot be installed in a floating state on an offshore crane ship, and effectively alleviates the shortage of wind turbine installation ships.

[0026] Additional aspects and advantages of the present invention will be given in part in the following description and in part will be obvious from the following description, or will be learned through practice of the present invention. BRIEF DESCRIPTION OF THE DRAWINGS

[0027] In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.

[0028] Figure 1 It is an overall schematic diagram of the guide device for floating installation of the wind turbine nacelle of the present invention;

[0029] Figure 2 It is a schematic plan view of a guide device for floating installation of a wind turbine cabin of the present invention;

[0030] Figure 3 It is a schematic diagram of the installation of the guide device for floating installation of the wind turbine nacelle of the present invention.

[0031] Explanation of the reference numerals: guide plate 1, anti-collision U plate 2, reinforcing rib plate 3, top plate 4, thickening plate 5, clamping plate 6, positioning plate 7, brake disc 8. DETAILED DESCRIPTION

[0032] The exemplary embodiments disclosed in the present invention will be described in more detail below with reference to the accompanying drawings. These embodiments are intended to enable a more thorough understanding of the present invention and to fully convey the scope of the present invention to those skilled in the art. Although the exemplary embodiments disclosed in the present invention are shown in the accompanying drawings, it should be understood that the present invention should not be limited by the embodiments described herein.

[0033] A guide device for floating installation of a wind turbine cabin comprises a guide plate 1, an anti-collision U plate 2, a reinforcing rib plate 3, a top plate 4, a thickening plate 5, a clamping plate 6 and a positioning plate 7. The anti-collision U plate 2 is installed on the outer edge of the side of the guide plate 1, the reinforcing rib plates 3 are installed on both sides of the guide plate 1, the top plate 4 is installed on the top of the guide plate 1 and the reinforcing rib plate 3, and the thickening plate 5 is welded on the top of the top plate 4; the guide plate 1, the anti-collision U plate 2, the reinforcing rib plate 3, the top plate 4 and the thickening plate 5 are welded to form a combination;

[0034] The clamping plate 6 is fixed to the assembly by bolts;

[0035] After the assembly is installed on the nacelle, the positioning plate 7 is fixed to the assembly by bolts.

[0036] Optimized: An elongated lightening hole 101 is provided in the middle of the guide plate 1, which can reduce the overall weight of the guide device and facilitate on-site installation.

[0037] Optimized: The anti-collision U plate 2 is a U-shaped protective plate, which is engaged with the outer edge of the side of the guide plate 1, and the guide plate 1 and the anti-collision U plate 2 are welded and connected.

[0038] Optimization: Two reinforcing rib plates 3 are provided, and the inner sides of the two reinforcing rib plates 3 are welded to the inner side of the guide plate 1; the top ends of the two reinforcing rib plates 3 and the top ends of the guide plate 1 are welded to the bottom ends of the top plate 4 respectively.

[0039] Optimization: The top plate 4 is an elliptical steel plate, and a plurality of bolt holes 401 for fixing the clamping plate 6 and the positioning plate 7 are provided on the top plate 4 .

[0040] Optimization: The clamping plate 6 is a flat steel plate, and a plurality of clamping holes are provided on the clamping plate 6, and the clamping holes are tapped holes.

[0041] Optimization: The positioning plate 7 is a flat steel plate, and a positioning hole is opened on the positioning plate 7, and the positioning hole is a tapped hole.

[0042] Installation method of the guide device for floating installation of the wind turbine nacelle:

[0043] The guide plate 1, the anti-collision U plate 2, the reinforcing rib plate 3, the top plate 4 and the thickening plate 5 are welded to form a welded body, and the clamping plate 6 is then fixed by bolts to form an assembly. After the assembly is installed on the cabin, the positioning plate 7 is detachably fixed on the assembly by bolts.

[0044] The guide plate 1 is eccentrically placed on the top plate 4, and the openings on the top plate 4 corresponding to the clamping plate 6 and the positioning plate 7 are located on the other side of the guide plate.

[0045] The openings on the clamping plate 6 are tapped holes, and the corresponding openings on the top plate 4 and the thickened plate 5 are non-tapped holes. The bolts pass through the openings of the top plate 4 and the thickened plate 5 from bottom to top, screw into the tapped holes on the clamping plate 6, and one end of the screw rod passes through the tapped holes, eliminating space for the nut.

[0046] After the assembly is installed on the brake disc 8, the clamping plate 6 is placed on top of the brake disc 8, the positioning plate 7 is inserted and bolts are used to penetrate the opening from bottom to top, and the upper part is tightened with nuts to complete the installation of the guide device.

[0047] An operating method of a guide device for floating installation of a wind turbine nacelle comprises the following steps:

[0048] Step 1: Engine room transfer: The transport ship carrying the engine room arrives at the construction site and then berths at the crane ship. The crane ship transfers the engine room together with the tooling to the deck of the crane ship;

[0049] Step 2: Remove the tooling: Use a hydraulic wrench or torque wrench to remove the bolts of the cabin tooling;

[0050] Step 3: Lifting the engine room: Lift the engine room by the crane of the crane ship so that the brake disc 8 is 1m away from the top of the tooling;

[0051] Step ④ Install the guide device: Use high-strength bolts to connect the clamping plate 6 and the top plate 4 of the welded body to form an assembly, then install the assembly at the screw hole of the brake disc 8, and use high-strength bolts to connect and fix the positioning plate 7 and the top plate 4;

[0052] Step ⑤ Lifting and alignment: The crane of the crane ship continues to lift the hook and lift the nacelle to the top of the top tower;

[0053] Step ⑥ Install the nacelle: Slowly lower the hook of the crane ship to insert the tooling into the upper part of the top tower until the nacelle is completely aligned with the top tower. Use stud bolts to connect the nacelle and the top tower flange, and apply the corresponding torque value as required by the wind turbine manufacturer.

[0054] Step 7: Install the cabin: After the cabin is installed, remove the guide device from the cabin.

[0055] In order to make the purpose, technical solutions and advantages of the embodiments of the present invention clearer, the technical solutions in the embodiments of the present invention are clearly and completely described above in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are part of the embodiments of the present invention, not all of the embodiments. Generally, the components of the embodiments of the present invention described and shown in the drawings herein can be arranged and designed in various different configurations.

[0056] Therefore, the above detailed description of the embodiments of the present invention provided in the accompanying drawings is not intended to limit the scope of the invention claimed for protection, but merely represents selected embodiments of the present invention. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

Claims

1. A guide device for floating installation of a wind turbine nacelle, comprising a guide plate (1), an anti-collision U plate (2), a reinforcing rib plate (3), a top plate (4), a thickening plate (5), a clamping plate (6) and a positioning plate (7), characterized in that: The guide plate (1) is provided with an anti-collision U-plate (2) on the outer edge of the side surface; reinforcing rib plates (3) are provided on both sides of the guide plate (1); a top plate (4) is provided on the top of the guide plate (1) and the reinforcing rib plate (3); a thickening plate (5) is welded to the top of the top plate (4); the guide plate (1), the anti-collision U-plate (2), the reinforcing rib plate (3), the top plate (4) and the thickening plate (5) are welded to form an assembly; the clamping plate (6) is fixed to the assembly by bolts; the assembly is installed on the cabin After the guide plate (1) is installed, the positioning plate (7) is fixed to the assembly by bolts; the anti-collision U plate (2) is a U-shaped protective plate, which is engaged with the outer edge of the side of the guide plate (1), and the guide plate (1) and the anti-collision U plate (2) are welded together; two reinforcing rib plates (3) are provided, and the inner sides of the two reinforcing rib plates (3) are welded to the inner side of the guide plate (1); the top ends of the two reinforcing rib plates (3) and the top end of the guide plate (1) are respectively welded to the bottom of the top plate (4).

2. The guide device for floating installation of a wind turbine nacelle according to claim 1 is characterized in that: The guide plate (1) is provided with an elongated lightening hole (101) in the middle.

3. The guide device for floating installation of a wind turbine nacelle according to claim 1 is characterized in that: The top plate (4) is an elliptical steel plate, and is provided with a plurality of bolt holes (401) for fixing the clamping plate (6) and the positioning plate (7).

4. The guide device for floating installation of a wind turbine nacelle according to claim 1 is characterized in that: The clamping plate (6) is a flat steel plate, and a plurality of clamping holes are provided on the clamping plate (6), wherein the clamping holes are tapped holes.

5. The guide device for floating installation of a wind turbine nacelle according to claim 1, characterized in that: The positioning plate (7) is a flat steel plate, and a positioning hole is provided on the positioning plate (7), wherein the positioning hole is a tapped hole.

6. An operating method of the guide device for floating installation of a wind turbine nacelle according to claim 1, characterized in that: The steps include: Step ① Engine room transfer: The transport ship transports the engine room to the construction site and then berths at the crane ship. The crane ship transfers the engine room together with the tooling to the deck of the crane ship; Step 2: Remove the tooling: Use a hydraulic wrench or torque wrench to remove the bolts of the cabin tooling; Step 3: Lifting the engine room: Lift the engine room by means of a crane on a crane ship, so that the brake disc (8) is 1m away from the top of the tooling; Step ④ installing the guide device: using high-strength bolts to connect the clamping plate (6) and the top plate (4) of the welded body to form an assembly, then installing the assembly at the screw hole of the brake disc (8), and using high-strength bolts to connect and fix the positioning plate (7) and the top plate (4); Step ⑤ Lifting and alignment: The crane of the crane ship continues to lift the hook and lift the nacelle to the top of the top tower; Step ⑥ Install the nacelle: Slowly lower the hook of the crane ship to insert the tooling into the upper part of the top tower until the nacelle is completely aligned with the top tower. Use stud bolts to connect the nacelle and the top tower flange, and apply the corresponding torque value according to the requirements of the wind turbine manufacturer; Step 7: Install the cabin: After the cabin is installed, remove the guide device from the cabin.