A method for connecting and circulating a group of hot dry rock wells

Through the dry-heat rock well group communication circulation method, the complex micro-fissures of the formation were gradually expanded by using low displacement injection of clean water containing scale inhibitors, which solved the damage problem of excessive displacement to the early cracks, and achieved efficient development of thermal energy of dry-heat rocks and improve heat exchange efficiency.

CN114233252BActive Publication Date: 2024-11-15THE SECOND GEOLOGICAL TEAM OF HEBEI COALFIELD GEOLOGY BUREAU +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202111650899.8
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2021-12-30
Publication Date
2024-11-15
Estimated Expiration
2041-12-30

AI Technical Summary

Technical Problem

In the existing dry-heat rock well group communication circulation method, the displacement is too large during the expansion process of the circulating operation, which can easily cause damage to the tiny and complex cracks formed by the early hydraulic fracturing, resulting in the problem of reducing heat exchange efficiency.

Method used

A dry-heat rock well group communication circulation method is adopted, through forward and reverse communication circulation, and the low displacement is used to inject clean water containing scale inhibitors to gradually expand the complex micro-fissures of the formation to ensure that the circulating liquid obtains sufficient heat exchange and pass Tracer detection verifies the effect of the connection cycle to avoid damage to the early cracks.

Benefits of technology

The efficient development of thermal energy of dry hot rocks is achieved, the sufficient heat exchange of circulating liquid is ensured, the damage to the early cracks is avoided due to excessive displacement is improved, and the well group connectivity and heat exchange efficiency are improved.

✦ Generated by Eureka AI based on patent content.
Patent Text Reader

Abstract

The invention discloses a connection circulation method for a hot dry rock well group, which adopts a one-injection-one-production mode and utilizes early hydraulic fracturing to form a complex micro-crack system. Firstly, an injection well and a production well are respectively set in two wells, and clean water containing a scale inhibitor is pumped into the injection well in multiple stages in a manner of gradually increasing injection displacement, and the next stage is entered after the water flow rate of the production well tends to a stable state, thereby completing a forward connection circulation construction operation; then, the injection well and the production well are swapped, and clean water containing a scale inhibitor is pumped into the injection well in multiple stages in a manner of gradually increasing injection displacement, and the next stage is entered after the water flow rate of the production well tends to a stable state, thereby completing a reverse connection circulation construction operation, and finally further expanding the complex fractures in the formation to maximize the utilization of thermal energy; the method performs forward and reverse connection circulation through low-displacement circulation, fully exchanges heat, and achieves the purpose of connection circulation safely and stably.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of hot dry rock development, and in particular to a hot dry rock well group connection circulation method. Background Art

[0002] Hot dry rock is a special geothermal resource with large reserves, clean and environmentally friendly, and is recognized by the international community as an efficient, low-carbon, clean energy source. At present, hot dry rock is mainly developed through enhanced geothermal systems (EGS), including hydraulic fracturing to build artificial heat storage, connected circulation tests and experimental power generation. Among them, the connected circulation test is an important link between hydraulic fracturing to build artificial heat storage and experimental power generation. If the connected circulation method is inappropriate, it is easy to cause the volume of artificial heat storage in the early stage to be unable to be fully utilized, resulting in the inability of the circulating liquid to obtain sufficient heat exchange, which in turn affects the later experimental power generation.

[0003] Based on the above analysis, the connection circulation method of hot dry rock well groups is the key to the development of hot dry rocks. How to avoid excessive displacement during the circulation operation to complete the expansion of the seam, which may cause damage to the tiny and complex cracks formed by the previous hydraulic fracturing, resulting in the formation of main crack through-channels and reduced heat exchange efficiency, has become a difficulty in the connection circulation construction of hot dry rock well groups. Summary of the invention

[0004] The purpose of the present invention is to provide a hot dry rock well group connection circulation method which ensures that the circulating liquid obtains sufficient heat exchange and realizes the efficient development of hot dry rock thermal energy.

[0005] To this end, the technical solution of the present invention is as follows:

[0006] A hot dry rock well group connection circulation method, the steps are as follows:

[0007] Step 1: Perform positive connection circulation operation on wells A and B where there are complex micro-cracks in the formation:

[0008] Set well A as the injection well and well B as the production well;

[0009] S101, with the injection displacement of Q1, inject clean water containing scale inhibitor into Well A, and the injection volume is sufficient to ensure that the water flow rate of Well B tends to be stable; Q1 is 0.3~0.4m 3 / min;

[0010] S102, with the injection displacement of Q2, inject clean water containing scale inhibitor into Well A, and the injection volume is sufficient to make the water flow of Well B tend to be stable again; Q2 = Q1 + 0.1 ~ 0.2m 3 / min;

[0011] S103, with the injection displacement of Q3, inject clean water containing scale inhibitor into Well A, and the injection volume is sufficient to make the water flow of Well B tend to be stable again; Q3 = Q2 + 0.3 ~ 0.4m 3 / min;

[0012] S104, with the injection displacement of Q4, inject clean water containing scale inhibitor into Well A, and the injection volume is sufficient to make the water flow of Well B tend to be stable again; Q4 = Q2 + 0.1 ~ 0.2m 3 / min;

[0013] Step 2: Perform reverse connection and circulation operations on the two wells that have completed step 1:

[0014] Set Well B as the injection well and Well A as the production well;

[0015] S201, inject clean water containing scale inhibitor into Well B at the injection displacement of Q5, and the injection volume is sufficient to ensure that the water flow rate of Well A tends to be stable; Q5 = 2Q1;

[0016] S202, with the injection displacement of Q6, inject clean water containing scale inhibitor into Well B, and the injection volume is sufficient to make the water flow of Well A tend to be stable again; Q6 = Q5 + 0.1 ~ 0.2m 3 / min;

[0017] S203, with the injection displacement of Q7, inject clean water containing scale inhibitor into Well B, and the injection volume is sufficient to make the water flow rate of Well A tend to be stable again; Q7 = Q2 + 0.1 ~ 0.2m 3 / min.

[0018] Preferably, the concentration of the scale inhibitor in the clean water containing the scale inhibitor is 10 ppm.

[0019] Preferably, the scale inhibitor is a polyepoxysuccinic acid scale inhibitor, a polyaspartic acid scale inhibitor or a phosphate scale inhibitor.

[0020] Preferably, after step S104 and step S203, a tracer detection method is used to detect the effect of the connected circulation operation, and the specific steps are:

[0021] i) Q i The tracer aqueous solution V is injected into the injection well. i m 3 ; Among them, Q i The same as the injection displacement in the previous step, V i =15m 3 ;

[0022] ii) Q iThe injection displacement is 25°C clean water is continuously injected into the injection well; and during the above injection process, the time is recorded from the completion of the injection of the tracer aqueous solution, the output water of the production well is continuously sampled at a frequency of 1 time / h, and the tracer concentration in the water sample is detected until the tracer concentration in the water sample is reduced to 0;

[0023] iii) Continue with Q i The injection displacement is set to pump clean water containing scale inhibitor into the injection well to ensure that the tracer is completely discharged. At the same time, the complex micro-cracks in the formation are further expanded.

[0024] Preferably, in step i), the tracer aqueous solution is a 0.1 wt % sodium bromide aqueous solution.

[0025] Compared with the existing technology, the hot dry rock well group connection circulation method adopts a one-injection-one-production mode, uses the early hydraulic fracturing to form a complex micro-crack system, and performs positive and reverse connection circulation through low-displacement circulation to fully exchange heat and achieve the purpose of connection circulation safely and stably. DETAILED DESCRIPTION

[0026] The following is a further description of the specific construction process of connecting and circulating two wells in a hot dry rock well group using the hot dry rock well group connecting and circulating method of the present application in conjunction with a specific embodiment, but the following embodiments are by no means limiting the present invention in any way.

[0027] The hot dry rock well group was surveyed in the early stage, and its reservoir temperature was about 160℃. The well spacing was 300m. In the early stage, the hydraulic fracturing method was used to create complex micro-cracks between the well groups, so that the hot dry rock well groups were connected. According to micro-seismic fracture monitoring, the reservoir transformation volume was 308×10 4 m 3 ; Since the ultimate goal of the development of the hot dry rock well group is to achieve thermal power generation, before the test power generation, it is necessary to carry out connection circulation construction work on the hot dry rock well group to further expand the seam and improve the connectivity between the two wells (Well A and Well B) in the hot dry rock well group.

[0028] Specifically, the implementation steps of the hot dry rock well group connection circulation method are as follows:

[0029] Step 1: Forward connection cycle construction work:

[0030] Set well A as the injection well and well B as the production well;

[0031] S101, pumping clean water containing scale inhibitor into Well A through the connecting pipeline of the fracturing pump truck;

[0032] Specifically, the injection volume is 2000m 3 , injection displacement is 0.4m 3 / min; the concentration of the polyaspartic acid scale inhibitor in the clean water containing the scale inhibitor is 10ppm; in addition, the clean water containing the scale inhibitor used in other steps of this embodiment is a polyaspartic acid scale inhibitor aqueous solution with a concentration of 10ppm;

[0033] After step S101, the temperature of the injected water at wellhead A is normal temperature (25°C), and the water output speed at wellhead B is 0m / s. 3 / min up to 0.21m 3 / min and the flow rate remains stable, the water temperature is about 90℃;

[0034] S102, continue to inject clean water containing scale inhibitor into Well A through the pipeline connected to the fracturing pump truck; specifically, the injection volume is 4000m 3 , injection displacement is 0.6m 3 / min;

[0035] After step S102, the temperature of the injected water at wellhead A is normal temperature (25°C), and the water output rate at wellhead B is 0.21m / s. 3 / min up to 0.48m 3 / min and the flow rate remains stable, the water temperature is about 80℃;

[0036] The reason why the outlet water temperature after step S102 is slightly lower than the outlet water temperature after step S101 is that the outlet water after step S101 is mainly the water left in the complex micro-cracks of the formation during the previous hydraulic fracturing construction process, which has reached the saturated state of heat adsorption; from another perspective, it can be explained that after the two micro-expansions of the complex micro-cracks of the formation in step S101 and step S102, the heat exchange capacity of the incoming water in the complex micro-cracks of the formation has been improved;

[0037] S103, continue to inject clean water containing scale inhibitor into Well A through the pipeline connected to the fracturing pump truck; specifically, the injection volume is 6000m 3 , injection displacement is 1.0m 3 / min;

[0038] After step S103, the temperature of the injected water at wellhead A is normal temperature (25°C), and the water output rate at wellhead B is 0.48m / s. 3 / min up to 0.8m 3 / min and the flow rate remains stable, and the water temperature is about 95°C; this phenomenon indicates that step S103 achieves further micro-expansion of complex micro-cracks in the formation, and the heat exchange capacity of the incoming water in the complex micro-cracks in the formation is further improved;

[0039] S104, continue to inject clean water containing scale inhibitor into Well A through the pipeline connected to the fracturing pump truck; specifically, the injection volume is 2000m 3 , injection displacement is 1.2m3 / min;

[0040] After step S104, the temperature of the water injected into well A is normal temperature (25°C), and the water discharged from well B is steam, and the water discharge speed is 0.8m / s. 3 / min up to 1.0m 3 / min and the flow rate remains stable, and the temperature is about 105°C; this phenomenon indicates that step S103 achieves further micro-expansion of complex micro-cracks in the formation, and the heat exchange capacity of the incoming water in the complex micro-cracks in the formation is further improved;

[0041] In order to evaluate the seepage characteristics and connectivity effect of the hot dry rock reservoir formed by the previous hydraulic fracturing and provide a theoretical basis for the subsequent hot dry rock power generation, tracers were added during the forward connection cycle operation, and tracer detection was carried out with Well A as the injection well and Well B as the production well. The specific steps are as follows:

[0042] i) 1.2m 3 / min injection rate, and inject 15m of tracer aqueous solution into Well A through the fracturing pump truck connecting pipeline. 3 ; Specifically, the tracer aqueous solution is a 0.1wt% sodium bromide aqueous solution;

[0043] ii) 1.2m 3 / min injection rate, and continuously inject clean water at room temperature (25°C) into Well A through the pipeline connected to the fracturing pump truck;

[0044] During the above injection process, the time is recorded from the completion of the injection of the tracer aqueous solution, the outflow water from the B well is continuously sampled at a frequency of 1 time / h, and the tracer concentration in the water sample is detected until the tracer concentration in the water sample decreases to 0;

[0045] iii) Continue at 1.2m 3 / min injection rate, pump at least 1000m3 of clean water containing scale inhibitor into Well A through the pipeline of the fracturing pump truck. 3 , to ensure complete discharge of the tracer.

[0046] After testing, it was found that the tracer was first detected in the water sample at the 35th hour since the start of recording. After that, the tracer concentration was reduced to 0 for another 52 hours. At the same time, the temperature of the injected water at the A wellhead was room temperature (25°C). At this time, the water discharged from the B wellhead was water vapor, and the water discharge rate was 1.0m / s. 3 / min up to 1.1m 3 / min and the flow rate remains stable, the temperature is about 108℃;

[0047] By analyzing and calculating the tracer data, the tracer migrated to the production well through different fracture channels during the reservoir migration process. The fracture space volume between Well A and Well B is 330×10 4 m 3 .

[0048] (II) Reverse connection cycle construction work:

[0049] Considering that both Wells A and B have injection and production functions in the later power generation operation, Well A is set as the production well and Well B is set as the injection well to carry out reverse-phase interconnection circulation operation;

[0050] S201, inject clean water containing scale inhibitor into Well B through the fracturing pump truck connecting pipeline; specifically, the injection volume is 1500m 3 , injection displacement is 0.8m 3 / min;

[0051] After step S201, the temperature of the injected water at wellhead B is normal temperature (25°C), and the water output speed at wellhead A is 0.7m 3 / min and the flow rate remains stable, the water temperature is about 80℃;

[0052] S202, continue to inject clean water containing scale inhibitor into Well B through the fracturing pump truck connecting pipeline; specifically, the injection volume is 2500m 3 , injection displacement is 1m 3 / min;

[0053] After step S202, the temperature of the injected water at wellhead B is normal temperature (25°C), and the water output speed at wellhead A is 0.7m / s. 3 / min up to 0.9m 3 / min and the flow rate remains stable, the water temperature is about 80℃;

[0054] S203, continue to inject clean water containing scale inhibitor into Well B through the fracturing pump truck connecting pipeline; specifically, the injection liquid volume is 2000m 3 , injection displacement is 1.5m 3 / min;

[0055] After step S203, the temperature of the water injected into the B wellhead is normal temperature (25°C), and the water output from the A wellhead is water vapor, and the water output speed is 0.9m / s. 3 / min up to 1.4m 3 / min and the flow rate remained stable, with a temperature of about 106°C. This phenomenon indicates that through multi-step expansion of complex micro-cracks in the formation, the heat exchange capacity of the incoming water from B to A in the complex micro-cracks in the formation has been further improved;

[0056] In order to verify the effect of this reverse connection circulation operation, tracer detection was carried out with Well B as the injection well and Well A as the production well. The specific steps are as follows:

[0057] i) 1.5m 3 / min injection rate, and inject 15m3 of tracer aqueous solution into Well B through the fracturing pump truck connecting pipeline. 3 ; Specifically, the tracer aqueous solution is a 0.1wt% sodium bromide aqueous solution;

[0058] ii) 1.5m 3 / min injection rate, and continuously inject clean water at room temperature (25°C) into Well B through the fracturing pump truck connecting pipeline;

[0059] During the above injection process, the time is recorded from the completion of the injection of the tracer aqueous solution, the outflow water from the A wellhead is continuously sampled at a frequency of 1 time / h, and the tracer concentration in the water sample is detected until the tracer concentration in the water sample decreases to 0;

[0060] iii) Continue at 1.5m 3 / min injection rate, pump at least 1000m3 of clean water containing scale inhibitor into Well B through the fracturing pump truck connecting pipeline. 3 , to ensure complete discharge of the tracer.

[0061] After testing, it was found that the tracer was first detected in the water sample at the 28th hour since the start of recording. After that, the tracer concentration was reduced to 0 for another 45 hours. At the same time, the temperature of the injected water at the B wellhead was room temperature (25°C). At this time, the water discharged from the A wellhead was water vapor, and the water discharge rate was 1.4m / s. 3 / min up to 1.45m 3 / min and the flow rate remains stable, the water temperature is about 110℃;

[0062] By analyzing and calculating the tracer data, the tracer migrated to the production well through different fracture channels during the reservoir migration process. The fracture space volume between Well A and Well B is 335×10 4 m 3 .

[0063] After the above-mentioned hot dry rock well group connection circulation method was used to connect wells A and B, microseismic fracture monitoring was performed again, and the results showed that the reservoir transformation volume was 330×10 4 m 3 ~335×10 4 m 3This shows that the hot dry rock well group connection circulation method of the present application can effectively further expand the complex micro-cracks in the formation, and will not cause damage to the previous hydraulic fracturing cracks due to excessive displacement, thereby forming a main crack through-channel and reducing the heat exchange efficiency.

Claims

1. A hot dry rock well group connection circulation method, characterized in that: Here are the steps: Step 1: Perform positive connection circulation operation on wells A and B where there are complex micro-cracks in the formation: Set well A as the injection well and well B as the production well; S101, with the injection displacement of Q1, inject clean water containing scale inhibitor into Well A, and the injection volume is sufficient to ensure that the water flow rate of Well B tends to be stable; Q1 is 0.3~0.4m 3 / min; S102, with the injection displacement of Q2, inject clean water containing scale inhibitor into Well A, and the injection volume is sufficient to make the water flow of Well B tend to be stable again; Q2 = Q1 + 0.1 ~ 0.2m 3 / min; S103, with the injection displacement of Q3, inject clean water containing scale inhibitor into Well A, and the injection volume is sufficient to make the water flow of Well B tend to be stable again; Q3 = Q2 + 0.3 ~ 0.4m 3 / min; S104, with the injection displacement of Q4, inject clean water containing scale inhibitor into Well A, and the injection volume is sufficient to make the water flow of Well B tend to be stable again; Q4 = Q2 + 0.1 ~ 0.2m 3 / min; Step 2: Perform reverse connection and circulation operations on the two wells that have completed step 1: Set Well B as the injection well and Well A as the production well; S201, inject clean water containing scale inhibitor into Well B at the injection displacement of Q5, and the injection volume is sufficient to ensure that the water flow rate of Well A tends to be stable; Q5 = 2Q1; S202, with the injection displacement of Q6, inject clean water containing scale inhibitor into Well B, and the injection volume is sufficient to make the water flow of Well A tend to be stable again; Q6 = Q5 + 0.1 ~ 0.2m 3 / min; S203, with the injection displacement of Q7, inject clean water containing scale inhibitor into Well B, and the injection volume is sufficient to make the water flow rate of Well A tend to be stable again; Q7 = Q2 + 0.1 ~ 0.2m 3 / min; The scale inhibitor is a polyepoxysuccinic acid scale inhibitor, a polyaspartic acid scale inhibitor or a phosphate scale inhibitor.

2. The hot dry rock well group connection circulation method according to claim 1, characterized in that: The concentration of the scale inhibitor in the clean water containing the scale inhibitor is 10 ppm.

3. The hot dry rock well group connection circulation method according to claim 1, characterized in that: After step S104 and step S203, a tracer detection method is used to detect the effect of the connected circulation operation. The specific steps are: i) Q i The tracer aqueous solution is injected into the injection well at an injection rate of 15m 3 ; Among them, Q i The injection displacement is consistent with the previous step; ii) Q i The injection displacement is 25°C clean water is continuously injected into the injection well; and during the above injection process, the time is recorded from the completion of the injection of the tracer aqueous solution, the output water of the production well is continuously sampled at a frequency of 1 time / h, and the tracer concentration in the water sample is detected until the tracer concentration in the water sample is reduced to 0; iii) Continue with Q i The injection displacement is set to pump clean water containing scale inhibitor into the injection well to ensure that the tracer is completely discharged. At the same time, the complex micro-cracks in the formation are further expanded.

4. The hot dry rock well group connection circulation method according to claim 3, characterized in that: In step i), the tracer aqueous solution is a 0.1 wt % sodium bromide aqueous solution.