A construction method for synchronous pouring of secondary structure and concrete shear wall of building

By using the construction method of building secondary structure and concrete shear wall in the concrete casting of floor slabs of commercial building outer frame steel structures, the construction method of synchronous casting of building insulation boards and steel bars is used to build an integral formwork for synchronous casting, the high construction cost in the existing technology is solved Due to the long-term problem, efficient concrete pouring and the strength improvement of secondary structure walls have been achieved.

CN114575499BActive Publication Date: 2024-11-22SHANGHAI OUYUE CONSTR & INSTALLATION ENG CO LTD +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202210240512.X
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2022-03-10
Publication Date
2024-11-22
Estimated Expiration
2042-03-10

AI Technical Summary

Technical Problem

In the casting of floor concrete for commercial frame steel structures, the existing formwork support method is costly and has a long construction time, especially in the process of refunding, dismantling and transferring the formwork, the workload is large and the loss is also large.

Method used

The construction method of synchronous casting of secondary structures and concrete shear walls is adopted. By erecting insulation boards and steel bars on the building structure, combining the overall formwork for concrete pouring, and using wire mesh to enhance the strength of the insulation board after the mold is closed, the strength of the insulation board is achieved. Simultaneous casting of secondary structure walls, structural beams and walls.

Benefits of technology

It improves construction efficiency, reduces labor consumption and cost, and enhances the strength of secondary structure walls.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure HDA0003541383740000011
    Figure HDA0003541383740000011
  • Figure HDA0003541383740000021
    Figure HDA0003541383740000021
  • Figure HDA0003541383740000031
    Figure HDA0003541383740000031
Patent Text Reader

Abstract

The invention discloses a construction method for synchronous pouring of a secondary structure and a concrete shear wall of a building, comprising: placing the N+1th layer of wall reinforcement and structural beam reinforcement on the wall and structural beam of the Nth layer of the building; erecting an insulation board between the N+1th layer of structural beam reinforcement and the Nth layer of structural beam, wherein the insulation board has holes penetrating in both the horizontal and vertical directions, and the thickness of the insulation board is less than the thickness of the structural beam; combining the structural beam template, the secondary structure wall template, and the wall template, wherein the structural beam template and the secondary structure wall template constitute an integral template; pouring concrete to realize the synchronous pouring construction of the secondary structure wall and the concrete wall. The problem of heavy workload and long construction time can be solved, thereby saving costs.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to commercial building construction technology, and in particular relates to a construction method for synchronously pouring a secondary structure of a building and a concrete shear wall. Background Art

[0002] In the pouring of floor concrete of commercial building external frame steel structure, some use corrugated steel plates for formwork, and some use disc supports for formwork. The construction costs of these two types of formwork and dismantling are also very high. In particular, the construction workload is large, the loss is also large, and the construction time is long during the process of withdrawing, dismantling and transporting the formwork.

[0003] In the pouring of floor concrete of commercial building external frame steel structure, some use corrugated steel plates for formwork, and some use disc supports for formwork. The construction costs of these two types of formwork and dismantling are also very high. In particular, the construction workload is large, the loss is also large, and the construction time is long during the process of withdrawing, dismantling and transporting the formwork. Summary of the invention

[0004] In view of the shortcomings of the prior art, the present invention designs a construction method for synchronously pouring a secondary structure of a building and a concrete shear wall to solve the problems of heavy workload and long construction time, thereby saving costs.

[0005] The technical solution disclosed in the present invention is as follows: a construction method for synchronously pouring a secondary structure of a building and a concrete shear wall, comprising:

[0006] Place the N+1th layer of wall reinforcement and structural beam reinforcement on the walls and structural beams of the Nth layer of the building;

[0007] An insulation board is erected between the N+1th layer of structural beam steel bars and the Nth layer of structural beams, wherein the insulation board has holes penetrating in both the transverse and longitudinal directions, and the thickness of the insulation board is less than the thickness of the structural beam;

[0008] Structural beam formwork, secondary structure wall formwork, and wall formwork jointing,

[0009] Among them, the structural beam formwork and the secondary structure wall formwork constitute the overall formwork;

[0010] Pouring concrete realizes the simultaneous pouring construction of secondary structure walls and concrete walls.

[0011] On the basis of the above scheme, steel wire mesh is fixed on both side surfaces of the insulation board, and a gap is retained between the steel wire mesh and the secondary structure wall after mold closing.

[0012] Based on the above scheme, the lower end of the integral formwork is clamped at the upper end of the Nth layer structural beam, and the lower end is clamped at both sides of the N+1th layer structural beam reinforcement and extends to the upper end of the structural beam reinforcement.

[0013] On the basis of the above scheme, it also includes supporting the M+1th floor slab formwork and tying floor slab reinforcement on the M+1th floor slab formwork after the structural beam formwork, secondary structure wall formwork, and wall formwork on the Mth floor are hoisted to the M+1th floor, so as to realize the simultaneous construction of floor slabs, walls, secondary structure walls and structural beams.

[0014] Compared with the prior art, the present invention has the following beneficial effects:

[0015] This scheme is based on the delayed synchronous construction method of the same layer of the building floor. In this construction, the concrete pouring construction is carried out while the concrete structure of the building is being cast, and the walls of the original secondary structure are also cast. This method can effectively realize the synchronous casting of the secondary structure walls and structural beams and walls, improve work efficiency, reduce labor consumption (compared with the traditional secondary structure walls that need to be built manually), and save costs.

[0016] By applying steel wire mesh, the strength of the insulation board is improved, thereby improving the strength of the secondary structure wall. BRIEF DESCRIPTION OF THE DRAWINGS

[0017] Figure 1 This is a schematic diagram of the structure after the wall reinforcement and structural beam reinforcement are tied at the N+1 layer;

[0018] Figure 2 It is a structural diagram of the secondary structure wall and concrete shear wall;

[0019] Figure 3 yes Figure 1 Schematic diagram of the structure in the mold closing state;

[0020] Figure 4 yes Figure 2 Schematic diagram of the structure in the mold closing state. DETAILED DESCRIPTION

[0021] In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the specific implementation methods of the present invention will be described below with reference to the accompanying drawings. Obviously, the accompanying drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other drawings and other implementation methods can be obtained based on these drawings without creative work.

[0022] like Figure 1-4 The construction method of synchronous pouring of secondary structure and concrete shear wall of building construction includes:

[0023] Place the N+1th layer of wall reinforcement 3 and structural beam reinforcement 4 on the wall 1 and structural beam 2 of the Nth layer of the building;

[0024] An insulation board 5 is erected between the N+1th layer of structural beam steel bars and the Nth layer of structural beams, wherein the insulation board has holes penetrating in both the transverse and longitudinal directions, and the thickness of the insulation board is less than the thickness of the structural beam;

[0025] Structural beam formwork, secondary structure wall formwork, and wall formwork 6 are combined.

[0026] Among them, the structural beam formwork and the secondary structure wall formwork constitute the overall formwork 7;

[0027] Pouring concrete realizes the simultaneous pouring construction of the secondary structure wall 8 and the concrete wall.

[0028] This scheme is based on the delayed synchronous construction method of the same layer of the building floor. In this construction, the concrete pouring construction is carried out while the concrete structure of the building is being cast, and the walls of the original secondary structure are also cast. This method can effectively realize the synchronous casting of the secondary structure walls and structural beams and walls, improve work efficiency, reduce labor consumption (compared with the traditional secondary structure walls that need to be built manually), and save costs.

[0029] Steel mesh is fixed on both sides of the insulation board, and a gap is left between the steel mesh and the secondary structure wall after mold closing. By applying the steel mesh, the strength of the insulation board is improved, and then the strength of the secondary structure wall is improved.

[0030] The lower end of the integral formwork is clamped at the upper end of the Nth layer structural beam, and the lower end is clamped at both sides of the N+1th layer structural beam reinforcement and extends to the upper end of the structural beam reinforcement.

[0031] It also includes supporting the M+1th floor slab formwork and tying floor slab steel bars 10 on the M+1th floor slab formwork 9 after the structural beam formwork, secondary structure wall formwork, and wall formwork on the Mth floor are hoisted together to the M+1th floor, so as to realize the simultaneous construction of the floor slab, walls, secondary structure walls and structural beams, where M is at least 2, and the walls and structural beams on the first floor are the direct construction layers.

[0032] It should be noted that the above embodiments can be freely combined as needed. The above is only a preferred embodiment of the present invention. It should be pointed out that for ordinary technicians in this technical field, several improvements and modifications can be made without departing from the principle of the present invention, and these improvements and modifications should also be considered as the protection scope of the present invention.

Claims

1. A construction method for synchronously pouring a secondary structure of a building and a concrete shear wall, characterized in that: include: Place the N+1th layer of wall reinforcement and structural beam reinforcement on the walls and structural beams of the Nth layer of the building; An insulation board is erected between the N+1th layer of structural beam steel bars and the Nth layer of structural beams, wherein the insulation board has holes penetrating in both the transverse and longitudinal directions, and the thickness of the insulation board is less than the thickness of the structural beam; Structural beam formwork, secondary structure wall formwork, and wall formwork jointing, Among them, the structural beam formwork and the secondary structure wall formwork constitute the overall formwork; Pouring concrete realizes the simultaneous pouring construction of secondary structure wall and concrete wall. Steel mesh is fixed on both sides of the insulation board, and a gap is left between the steel mesh and the secondary structure wall after mold closing. The lower end of the integral formwork is clamped on the upper end of the structural beam on the Nth layer, and the lower end is clamped on both sides of the structural beam reinforcement on the N+1th layer and extends to the upper end of the structural beam reinforcement. It also includes supporting the M+1th floor slab formwork and tying floor slab reinforcement on the M+1th floor slab formwork after the structural beam formwork, secondary structure wall formwork, and wall formwork located on the Mth floor are hoisted together to the M+1th floor, so as to realize the simultaneous construction of the floor slab, wall, secondary structure wall and structural beam.