An optimization method and system for shortening construction period

Through the optimization model of spatio-temporal grid maintenance plan of linear assets of rail transit, the problem of difficult to shorten the construction period in linear assets of rail transit is solved, the shortest construction period is optimized, and the practicality and guidance of the maintenance plan are enhanced.

CN114611749BActive Publication Date: 2024-11-26CRSC RESEARCH & DESIGN INSTITUTE GROUP CO LTD
View PDF 6 Cites 0 Cited by

Patent Information

Application Number
CN202210043363.8
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2022-01-14
Publication Date
2024-11-26
Estimated Expiration
2042-01-14

AI Technical Summary

Technical Problem

In the maintenance plan of linear assets of rail transit, it is difficult for the existing technology to effectively shorten the construction period, which makes the maintenance plan susceptible to time and space factors and it is difficult to ensure the shortest construction period.

Method used

The spatial and temporal grid maintenance plan of linear assets of rail transit is optimized and compiled. By subdividing linear assets of rail transit in time and space dimensions, establishing an objective function and constraint system based on space-time grids, and optimizing the preparation of maintenance plans to achieve the shortest construction period .

Benefits of technology

Through meticulous time and spatial resolution management, the maintenance plan is optimized, ensuring the shortest construction period, enhancing the practicality and guidance of the maintenance plan, and reducing the impact of the maintenance plan being disturbed by various factors.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN114611749B_ABST
    Figure CN114611749B_ABST
Patent Text Reader

Abstract

The present invention provides an optimization method and system for shortening the construction period, the method comprising: determining the maintenance activity execution time of each maintenance mode of each section of rail transit linear assets within a maintenance plan preparation cycle; determining the maximum value of the maintenance activity execution time in various maintenance modes of each section; determining the minimum construction period of the maintenance plan according to the maximum value of the maintenance activity execution time of all sections; optimizing the construction period of the maintenance plan according to the minimum construction period of the maintenance plan. The construction period of the rail transit linear asset maintenance plan optimized and prepared by the present invention is the shortest, and the practicality of the rail transit linear asset maintenance plan is enhanced.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention belongs to the technical field of rail transportation, and in particular relates to an optimization method and system for shortening a construction period. Background Art

[0002] For linear assets, their length plays a key role in maintenance. For example, rail transit infrastructure equipment such as tracks, roadbeds, overhead lines, tunnels, bridges, etc. are all linear assets, which have linear, continuous, and strip-shaped layout characteristics in spatial distribution. Their maintenance activities are organized in a relatively small, strip-shaped space and are easily affected by a variety of time and space factors.

[0003] Since the maintenance tasks in the rail transit linear asset maintenance plan are generally fixed, the main challenge in its preparation is to achieve the optimization of the shortest overall maintenance plan duration. However, in rail transit production practice, rail transit linear asset maintenance plans are generally manually prepared by managers based on experience, which makes it difficult to ensure that the maintenance plan duration is the shortest. Summary of the invention

[0004] In view of the above problems, the present invention provides an optimization method for shortening the construction period, the method comprising:

[0005] Determine the maintenance activity execution time for each maintenance method in each section of rail transit linear assets within a maintenance plan preparation cycle;

[0006] Determine the maximum execution time of maintenance activities in various maintenance methods for each section;

[0007] Determine the minimum duration of the maintenance plan based on the maximum execution time of maintenance activities in all sections;

[0008] Optimize the duration of the maintenance plan based on the minimum duration of the maintenance plan.

[0009] Furthermore, the maintenance activity execution time of each maintenance method for each section of rail transit linear assets within a maintenance plan preparation cycle includes:

[0010] In a maintenance plan preparation cycle, rail transit linear assets are divided into multiple sections, each of which has multiple maintenance methods;

[0011] According to the divided multiple sections, the maintenance activity execution time of each maintenance method in each section is determined.

[0012] Furthermore, the maximum execution time of maintenance activities in various maintenance modes for each section is determined to include:

[0013] According to the maintenance activity execution time of each maintenance method in each section, the maximum maintenance activity execution time among various maintenance methods in each section is selected.

[0014] Furthermore, according to the maximum execution time of maintenance activities in all sections, the minimum duration of the maintenance plan is determined, including:

[0015] Get the sum of the maximum execution time of maintenance activities in all sections;

[0016] The minimum duration of the maintenance plan is determined based on the sum of the maximum execution times of the maintenance activities in all sections.

[0017] Furthermore, the minimum duration of the maintenance plan is represented by the following shortest duration objective function:

[0018]

[0019] Among them, i represents the serial number of the section, j represents the serial number of the maintenance method, and z ij It represents the execution time of maintenance activities for each maintenance method in each section of rail transit linear assets within a maintenance plan preparation cycle. M represents the total number of maintenance method categories, and N represents the total number of sections.

[0020] On the other hand, the present invention also provides an optimization system for shortening a construction period, the system comprising:

[0021] The first determination module is used to determine the maintenance activity execution time of each maintenance method for each section of the rail transit linear asset within a maintenance plan preparation cycle;

[0022] The second determination module is used to determine the maximum execution time of the maintenance activity in various maintenance modes of each section;

[0023] The third determination module is used to determine the minimum duration of the maintenance plan according to the maximum execution time of the maintenance activities in all sections;

[0024] The maintenance plan optimization module is used to optimize the duration of the maintenance plan according to the minimum duration of the maintenance plan.

[0025] Furthermore, the maintenance activity execution time of each maintenance method for each section of rail transit linear assets within a maintenance plan preparation cycle includes:

[0026] In a maintenance plan preparation cycle, rail transit linear assets are divided into multiple sections, each of which has multiple maintenance methods;

[0027] Determine the maintenance activity execution time for each maintenance method in each section.

[0028] Furthermore, the maximum execution time of maintenance activities in various maintenance modes for each section is determined to include:

[0029] According to the maintenance activity execution time of each maintenance method in each section, the maximum maintenance activity execution time among various maintenance methods in each section is selected.

[0030] Furthermore, according to the maximum execution time of maintenance activities in all sections, the minimum duration of the maintenance plan is determined, including:

[0031] Get the sum of the maximum execution time of maintenance activities in all sections;

[0032] The minimum duration of the maintenance plan is determined based on the sum of the maximum execution times of the maintenance activities in all sections.

[0033] Furthermore, the minimum duration of the maintenance plan is represented by the following shortest duration objective function:

[0034]

[0035] Among them, i represents the serial number of the section, j represents the serial number of the maintenance method, and z ij It represents the execution time of maintenance activities for each maintenance method in each section of rail transit linear assets within a maintenance plan preparation cycle. M represents the total number of maintenance method categories, and N represents the total number of sections.

[0036] The beneficial effects of the present invention are as follows:

[0037] (1) The present invention uses the spatiotemporal grid of rail transit linear assets as the basic unit, discretizes the rail transit linear asset maintenance activities in the spatial and temporal dimensions, and thus proposes a rail transit linear asset grid maintenance plan optimization compilation model, which more carefully defines the time and space constraints and objective functions of different maintenance activities of rail transit linear assets, optimizes the compiled rail transit linear asset maintenance plan to have the shortest construction period, and enhances the practicality of the rail transit linear asset maintenance plan.

[0038] (4) The present invention establishes a model for optimizing the grid maintenance plan for rail transit linear assets. The model takes the spatiotemporal grid of rail transit linear assets as the basic unit, constructs the objective function and constraint system of the rail transit linear asset maintenance plan based on the spatiotemporal grid, takes the shortest construction period as the optimization goal, and ensures the guidance of the maintenance plan; the constraint system of the model for optimizing the grid maintenance plan for rail transit linear assets includes construction period constraints.

[0039] Other features and advantages of the present invention will be described in the following description, and partly become apparent from the description, or understood by practicing the present invention. The purpose and other advantages of the present invention can be realized and obtained by the structures pointed out in the description, claims and drawings. BRIEF DESCRIPTION OF THE DRAWINGS

[0040] In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, a brief introduction is given below to the drawings required for use in the embodiments or the description of the prior art. Obviously, the drawings described below are some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying any creative work.

[0041] Figure 1 A principle block diagram of a method for optimizing the maintenance plan for rail transit linear assets according to an embodiment of the present invention is shown.

[0042] Figure 2 A schematic diagram of a rail transit space-time grid according to an embodiment of the present invention is shown.

[0043] Figure 3 A schematic diagram of duration constraints between rail transit linear asset maintenance activities according to an embodiment of the present invention is shown.

[0044] Figure 4 A schematic diagram of construction period constraints based on rail transit space-time grid according to an embodiment of the present invention is shown.

[0045] Figure 5 A principle block diagram of a system for optimizing the maintenance plan of rail transit linear assets according to an embodiment of the present invention is shown. DETAILED DESCRIPTION

[0046] In order to make the purpose, technical solution and advantages of the embodiments of the present invention clearer, the technical solution in the embodiments of the present invention will be clearly and completely described below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0047] With the development of high-density and high-speed rail transit, the safe and uninterrupted operation of trains and the comfortable travel of passengers have put forward higher requirements for the reliability and stability of rail transit infrastructure. In order to ensure that managers can effectively maintain the quality of rail transit linear assets and reasonably arrange maintenance and repair operations, they should plan and arrange various maintenance activities of rail transit linear assets in a periodic manner according to relevant maintenance procedures and systems. At present, the maintenance of linear assets on the rail transit site in my country is mainly based on fault repair and periodic repair.

[0048] The present invention proposes to subdivide the maintenance activities of rail transit linear assets in time and space dimensions according to units of equal length, and to define the constraint system and objective function of different maintenance activities of rail transit linear assets in more detail.

[0049] The present invention proposes a method for compiling a rail transit linear asset maintenance plan with the shortest construction period as the optimization goal. When the actual progress deviates from the plan and the basic diagram of the rail transit linear asset maintenance plan needs to be recompiled, the influence of interference from various factors on the maintenance plan is reduced, thereby ensuring the guidance of actual maintenance activities on site.

[0050] like Figure 1 As shown, the present invention provides an optimization method for shortening the construction period, which is described in detail below. Establishing a rail transit time-space grid;

[0051] The optimal maintenance scheduling model for time-location grids (OMSM-TG) of rail transit linear assets with constraints and the shortest construction period objective function is established, in which:

[0052] According to the optimization model of the grid maintenance plan for rail transit linear assets, the construction period of the maintenance plan is optimized.

[0053] The construction of the optimization model for grid-based maintenance planning of rail transit linear assets is described in detail below.

[0054] Segmentation of maintenance activities for rail transit linear assets based on space-time grid

[0055] In order to consider the influence of various factors, the present invention subdivides the rail transit linear asset maintenance activities in spatial and temporal dimensions, and proposes a new optimization model for the grid maintenance plan of rail transit linear assets based on the characteristics of rail transit linear asset maintenance activities.

[0056] In the embodiment of the present invention, the rail transit lines with linear, continuous and strip layout are divided into several small sections according to certain rules. Preferably, the lines are divided into several adjacent small sections of equal length, so as to form a rail transit grid. The rail transit time-space grid refers to a number of small units formed by dividing the whole life cycle of rail transit line facilities according to certain rules based on the two dimensions of time and space. In the embodiment of the present invention, the life cycle process is a complete maintenance process. Figure 2 As shown, the horizontal axis represents mileage, the vertical axis represents time, and each space-time grid is represented by G ij Indicates that i represents the i-th rail transit grid, and j represents the time period of the grid. The rail transit space-time grid is a basic unit based on time and space. For example, the rail transit space-time grid is established based on the space dimension of the rail transit line and the time dimension of the rail transit linear asset maintenance. Specifically, the rail transit space-time grid division method is as follows:

[0057] (1) Time grid division: According to the actual work requirements of rail transit infrastructure management, the entire life cycle of rail transit infrastructure can be divided into minutes, hours, days, weeks, months, and years in the time dimension. In different application scenarios, managers can choose the size of the time grid unit according to the actual scenario requirements.

[0058] (2) Spatial grid division: As the smallest unit for segmenting linear and continuous rail transit lines in the spatial dimension, the division of spatial grids should fully consider the business characteristics of maintenance activities and the management requirements of the site. In the embodiment of the present invention, the length of the rail transit grid is set to 200 meters, and the railway 100-meter mark is selected as the dividing point between adjacent grids.

[0059] Rail transit linear asset maintenance activities have clear time span and mileage range information, and consume a certain amount of time and resources during their execution. Based on the space-time grid, rail transit linear asset maintenance activities are divided into smaller time units and space units, which can more finely define the time and space constraints of maintenance activities, and more accurately describe the impact of various time factors and space factors on maintenance activities, so that managers can manage rail transit infrastructure maintenance activities at a higher time and space resolution.

[0060] Constraints between maintenance activities of rail transit linear assets

[0061] Rail transit linear asset maintenance activities refer to the sum of a series of actions performed by applying technical means to investigate the status of rail transit linear assets. It is the basic management unit in rail transit linear asset maintenance plan management, with clear time span and mileage range information, and a certain amount of time and resources consumed during its execution. A maintenance activity refers to a maintenance task that a work group is assigned to perform within a certain time span and mileage range.

[0062] Existing related research results lack the description and definition of the constraints between rail transit linear asset maintenance activities. Combined with the analysis of the characteristics of rail transit linear asset maintenance activities, the present invention divides the constraints between rail transit linear asset maintenance activities into construction period constraints.

[0063] Duration Constraints

[0064] According to relevant repair rules, rail transit linear asset maintenance activities need to be completed within a specified time period. When managers prepare maintenance plans, due to interference from a variety of random factors, some rail transit linear assets may not be organized for corresponding maintenance activities within the specified time period, resulting in missed maintenance.

[0065] like Figure 3 As shown, mileage d i >0, mileage d i+1 >0, the construction period constraint is violated. The length of the construction period is determined by the maintenance frequency of different maintenance methods. For example, if the maintenance frequency is 1 time / month, the corresponding construction period is 1 month. In the figure, the horizontal axis represents the line mileage, the vertical axis represents time, the solid line represents the maintenance activity, and the dotted line represents the deadline of the maintenance plan.

[0066] Violation of construction period constraints may cause originally risk-free rail transit linear assets to evolve into risk hazards, and the original low risk may evolve into high risk.

[0067] Constraint system based on rail transit space-time grid

[0068] In this embodiment, the following maintenance activity constraint system will be defined in more detail based on the spatiotemporal grid of rail transit linear assets:

[0069] Duration Constraints

[0070] The duration constraints meet the following conditions:

[0071] In a planning cycle, the number of maintenance activities performed in the specified maintenance method in the specified grid in the rail transit linear asset grid is equal to the maintenance pass threshold.

[0072] The construction period constraints of rail transit linear asset maintenance activities include two aspects: ① Within a planning cycle, each type of maintenance method needs to complete a specified number of maintenance passes, usually 1; ② Each type of maintenance method requires maintenance of all grids during each maintenance to avoid missing maintenance. Therefore, within a planning cycle, the grid G i The maintenance method is C j Number of maintenance activities Q ij Should be equal to the threshold S of the number of maintenance passes ij , that is, the duration constraint is determined by the following formula:

[0073]

[0074] Among them, Q ij Represents the grid G i The maintenance method is C j The number of maintenance activities, such as Figure 4 As shown in the figure, the horizontal axis represents the line mileage, the vertical axis represents the time, the horizontal axis is divided by the grid length, and the vertical axis is divided by the time granularity required for management, forming a track time-space grid. The dotted line represents the deadline of the maintenance plan. i > 0, resulting in the dotted box area Q ij <S ij , the construction period constraint is not met.

[0075] Objective function based on rail transit space-time grid

[0076] Determine the maintenance activity execution time of each maintenance mode in each section of the rail transit linear asset within a maintenance plan preparation cycle, specifically including: within a maintenance plan preparation cycle, divide the rail transit linear asset into multiple sections, wherein each section has multiple maintenance modes;

[0077] According to the divided multiple sections, determine the maintenance activity execution time of each maintenance method in each section;

[0078] Determine the maximum execution time of the maintenance activity in various maintenance modes of each section, specifically, including: selecting the maximum execution time of the maintenance activity in various maintenance modes of each section according to the execution time of the maintenance activity in each maintenance mode of each section;

[0079] Determine the minimum duration of the maintenance plan based on the maximum execution time of maintenance activities in all sections;

[0080] Optimize the duration of the maintenance plan based on the minimum duration of the maintenance plan.

[0081] The objective function is the shortest duration objective function (the shortest duration means the shortest time to complete all activities. The shortest duration objective function means that the activity with the latest execution time should be executed as early as possible). The formula of the shortest duration objective function is as follows:

[0082]

[0083] Where i represents the serial number of the section (rail transit linear asset grid), j represents the serial number of the maintenance method (rail transit linear asset maintenance method), and z ii Indicates that within a maintenance plan preparation cycle, each section of the rail transit linear asset (i.e., grid G i) of each maintenance method (i.e. C j ), M represents the total number of maintenance methods, and N represents the total number of sections.

[0084] Furthermore, in this embodiment, the rail transit linear asset grid maintenance activity also involves constants, where the constants are constants determined based on the rail transit space-time grid and include:

[0085] SD, represents the starting mileage of the maintenance plan;

[0086] ED, represents the end mileage of the maintenance plan;

[0087] DR, which indicates the mileage length of the maintenance activity, is the difference between the end mileage of the maintenance plan and the start mileage of the maintenance plan. The calculation formula is as follows:

[0088] DR=ED-SD:

[0089] LE, represents the length of the rail transit linear asset grid, where the rail transit linear asset grid is a grid divided on the rail transit linear asset line in the spatial dimension, generally 200 meters:

[0090] N represents the total number of grids divided by the rail transit linear asset line. The total number of grids divided by the rail transit linear asset line is the ratio of the mileage length of the maintenance activity to the length of the rail transit linear asset grid. The calculation formula is as follows:

[0091]

[0092] G i (i∈[1, 2, ..., N]), represents the i-th rail transit linear asset grid, where i represents the serial number of the rail transit linear asset grid;

[0093] M, represents the total number of categories of maintenance methods for rail transit linear assets;

[0094] C j (j∈[1, 2, ..., M]), represents the jth type of maintenance method, where j represents the serial number of the rail transit linear asset maintenance method;

[0095] C ij (i∈[1,2,...,N],j∈[1,2,...,M]), represents the rail transit linear asset grid G i The jth type of maintenance method;

[0096] E represents the total number of unit time in a planning cycle, and e represents the e-th unit time, that is, e represents the sequence number of the unit time in the planning cycle;

[0097] S ij , indicating that within a planning cycle, the linear asset grid G ​​of rail transit i Maintenance method C j The maintenance pass threshold.

[0098] On the other hand, Figure 5 As shown, an embodiment of the present invention further provides an optimization system for shortening a construction period, the system comprising:

[0099] The first determination module is used to determine the maintenance activity execution time of each maintenance method for each section of the rail transit linear asset within a maintenance plan preparation cycle;

[0100] The second determination module is used to determine the maximum execution time of the maintenance activity in various maintenance modes of each section;

[0101] The third determination module is used to determine the minimum duration of the maintenance plan according to the maximum execution time of the maintenance activities in all sections;

[0102] The maintenance plan optimization module is used to optimize the duration of the maintenance plan according to the minimum duration of the maintenance plan.

[0103] The other functions and methods in the optimization system for shortening the construction period of the present invention correspond to the other functions and implementation methods in the optimization method for shortening the construction period of the present invention, so no further details are given here.

[0104] The general network planning method or Gantt chart method is not applicable to the maintenance activities of rail transit linear assets. Optimizing the preparation of rail transit linear asset maintenance plans is of great significance to avoid arranging inappropriate maintenance activities such as "over-maintenance" and "under-maintenance", reasonably allocating maintenance resources, reducing maintenance costs, and ensuring the continuous safety and smooth operation of trains. At present, domestic and foreign experts and scholars have conducted little direct research on the adjustment and optimization of adjacent maintenance activities in rail transit linear asset maintenance plans. Therefore, the present invention discloses an optimization method and system for shortening the construction period, which can ensure the optimization of the maintenance plan and the shortest construction period.

[0105] (1) The present invention proposes, describes and defines various constraints between maintenance activities of rail transit linear assets, and divides the various constraints between maintenance activities into: construction period constraints; and defines the above maintenance activity constraints in more detail based on the space-time grid.

[0106] (2) This invention proposes a subdivision of rail transit linear asset maintenance activities based on spatiotemporal grids, and discusses in detail the definition and division method of spatiotemporal grids for rail transit linear assets. The spatiotemporal grid management of rail transit linear assets can more accurately describe the degree of influence of various influencing factors on maintenance activities, and more finely define the constraints between maintenance activities, so that managers can finely manage rail transit infrastructure maintenance activities at a higher temporal and spatial resolution.

[0107] The above is only a preferred embodiment of the present invention, and does not limit the present invention in any form. Although the present invention has been disclosed as a preferred embodiment as above, it is not used to limit the present invention. Any technician familiar with this profession can make some changes or modifications to equivalent embodiments of equivalent changes using the technical contents disclosed above without departing from the scope of the technical solution of the present invention. However, any simple modifications, equivalent changes and modifications made to the above embodiments based on the technical essence of the present invention without departing from the content of the technical solution of the present invention are still within the scope of the technical solution of the present invention.

Claims

1. An optimization method for shortening a construction period, characterized in that: The method comprises: Determine the maintenance activity execution time for each maintenance method in each section of rail transit linear assets within a maintenance plan preparation cycle; Determine the maximum execution time of maintenance activities in various maintenance methods for each section; Determine the minimum duration of the maintenance plan based on the maximum execution time of maintenance activities in all sections; According to the minimum duration of the maintenance plan, optimize the duration of the maintenance plan, including: Establishing a rail transit linear asset grid maintenance plan optimization model with constraints and a shortest construction period objective function; and optimizing the construction period of the maintenance plan using the rail transit linear asset grid maintenance plan optimization model based on the minimum construction period of the maintenance plan; Among them, a rail transit linear asset grid maintenance plan optimization model with constraints and the shortest construction period objective function is established, including: Based on the time dimension and space dimension, within a maintenance plan preparation cycle, rail transit linear assets are divided into multiple sections to form a rail transit linear asset grid; Based on the linear asset grid of rail transit, the construction period constraints and the shortest construction period objective function of the maintenance plan are established; According to the construction period constraint conditions and the shortest construction period objective function of the maintenance plan, a maintenance plan optimization model for the gridded linear assets of rail transit is established; Among them, the construction period constraints of the maintenance plan are: In a planning cycle, the number of maintenance activities of a specified grid in the rail transit linear asset grid in which the specified maintenance method is executed is equal to the maintenance pass threshold.

2. The optimization method for shortening a construction period according to claim 1, characterized in that: Determine the maintenance activity execution time of each maintenance method for each section of rail transit linear assets within a maintenance plan preparation cycle, including: Each section has multiple maintenance methods; According to the divided multiple sections, the maintenance activity execution time of each maintenance method in each section is determined.

3. The optimization method for shortening a construction period according to claim 1, characterized in that: Determine the maximum execution time of maintenance activities in various maintenance methods for each section, including: According to the maintenance activity execution time of each maintenance method in each section, the maximum maintenance activity execution time among various maintenance methods in each section is selected.

4. The optimization method for shortening a construction period according to claim 1, characterized in that: According to the maximum execution time of maintenance activities in all sections, the minimum duration of the maintenance plan is determined including: Get the sum of the maximum execution time of maintenance activities in all sections; The minimum duration of the maintenance plan is determined based on the sum of the maximum execution times of the maintenance activities in all sections.

5. An optimization method for shortening a construction period according to any one of claims 1 to 4, characterized in that: The minimum duration of the maintenance plan is expressed by the following shortest duration objective function: Among them, i represents the serial number of the section, j represents the serial number of the maintenance method, and z ijj It represents the execution time of maintenance activities for each maintenance method in each section of rail transit linear assets within a maintenance plan preparation cycle. M represents the total number of maintenance method categories, and N represents the total number of sections.

6. An optimization system for shortening construction period, characterized in that: The system comprises: The first determination module is used to determine the maintenance activity execution time of each maintenance method for each section of the rail transit linear asset within a maintenance plan preparation cycle; The second determination module is used to determine the maximum execution time of the maintenance activity in various maintenance modes of each section; The third determination module is used to determine the minimum duration of the maintenance plan according to the maximum execution time of the maintenance activities in all sections; The maintenance plan optimization module is used to optimize the duration of the maintenance plan according to the minimum duration of the maintenance plan; The maintenance plan optimization module is specifically used to: establish a rail transit linear asset grid maintenance plan optimization model with constraints and a shortest construction period objective function; based on the minimum construction period of the maintenance plan, optimize the construction period of the maintenance plan using the rail transit linear asset grid maintenance plan optimization model; Among them, a maintenance plan optimization model for rail transit linear assets gridding with constraints and the shortest construction period objective function is established, including: Based on the time dimension and space dimension, within a maintenance plan preparation cycle, rail transit linear assets are divided into multiple sections to form a rail transit linear asset grid; Based on the linear asset grid of rail transit, the construction period constraints and the shortest construction period objective function of the maintenance plan are established; According to the construction period constraint conditions and the shortest construction period objective function of the maintenance plan, a maintenance plan optimization model for the gridded linear assets of rail transit is established; Among them, the construction period constraints of the maintenance plan are: In a planning cycle, the number of maintenance activities of a specified grid in the rail transit linear asset grid in which the specified maintenance method is executed is equal to the maintenance pass threshold.

7. The optimization system for shortening construction period according to claim 6, characterized in that: Determine the maintenance activity execution time of each maintenance method for each section of rail transit linear assets within a maintenance plan preparation cycle, including: Each section has multiple maintenance methods; Determine the maintenance activity execution time for each maintenance method in each section.

8. The optimization system for shortening construction period according to claim 6, characterized in that: Determine the maximum execution time of maintenance activities in various maintenance methods for each section, including: According to the maintenance activity execution time of each maintenance method in each section, the maximum maintenance activity execution time among various maintenance methods in each section is selected.

9. The optimization system for shortening construction period according to claim 6, characterized in that: According to the maximum execution time of maintenance activities in all sections, the minimum duration of the maintenance plan is determined including: Get the sum of the maximum execution time of maintenance activities in all sections; The minimum duration of the maintenance plan is determined based on the sum of the maximum execution times of the maintenance activities in all sections.

10. An optimization system for shortening a construction period according to any one of claims 6 to 9, characterized in that: The minimum duration of the maintenance plan is expressed by the following shortest duration objective function: Among them, i represents the serial number of the section, j represents the serial number of the maintenance method, and z ij It represents the execution time of maintenance activities for each maintenance method in each section of rail transit linear assets within a maintenance plan preparation cycle. M represents the total number of maintenance method categories, and N represents the total number of sections.

Citation Information

Patent Citations

  • Project management progress arranging method and project management progress arranging system

    CN103295100A

  • Method and device for determining rail maintenance sections

    CN103714228A

  • A method and system for optimizing construction plan of railway engineering

    CN109146207A