A dynamic evaluation method for the operating status of integrated energy systems

Through dynamic evaluation method, combined with group G1 method and TOPSIS method, the dual excitation control line principle is used to solve the problem that traditional static evaluation methods cannot fully reflect the operation of the comprehensive energy system, and the comprehensive dynamic evaluation and optimization of the comprehensive energy system is achieved. Operation guidance.

CN114693076BActive Publication Date: 2024-12-06CHANGSHA UNIVERSITY OF SCIENCE AND TECHNOLOGY
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202210220584.8
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2022-03-08
Publication Date
2024-12-06
Estimated Expiration
2042-03-08

AI Technical Summary

Technical Problem

The traditional static evaluation method of comprehensive energy systems does not consider development factors and cannot comprehensively reflect the current and historical levels of the evaluation objects, resulting in the evaluation results unilaterally reflect the operation of the comprehensive energy system.

Method used

Using a dynamic evaluation method for integrated energy systems, a technology, economic and environmental protection index system is constructed by collecting multi-stage data, a group G1 method and TOPSIS method are used to calculate the index weight, and dynamic evaluation is performed in combination with the principle of dual incentive control line, and the operation is adjusted. Status until expectations are met.

Benefits of technology

A comprehensive dynamic evaluation of the integrated energy system has been achieved, development factors are taken into account, the accuracy and rationality of the evaluation have been improved, and the operation and planning of the integrated energy system have been guided.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN114693076B_ABST
    Figure CN114693076B_ABST
Patent Text Reader

Abstract

A dynamic evaluation method for the operation status of an integrated energy system, firstly, collects multi-stage data of the integrated energy system, and constructs an indicator system of the integrated energy system including technology, economy, and environmental protection; secondly, analyzes the influence of the indicators on the operation status of the integrated energy system, divides the indicators into benefit-type indicators and cost-type indicators, and obtains the standard indicator matrix by calculation; furthermore, invites an expert group to rank the importance of the indicator system, comprehensively considers the influencing factors of the experts, and uses the group G1 method to obtain the indicator weight; then, uses the TOPSIS method to set the absolute ideal solution and calculate the closeness; finally, according to the operation status characteristics of the multi-stage integrated energy system, uses the dual excitation control line principle for dynamic evaluation. The present invention avoids the one-sided reflection of the operation status of the integrated energy system by a single type of indicator, takes into account the development dynamics of the integrated energy system itself, can make the evaluation result more comprehensive, and is of great significance for guiding the operation and planning of the integrated energy system.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the field of integrated energy technology, and in particular to a dynamic evaluation method for the operating status of an integrated energy system. Background Art

[0002] With the continuous development of my country's industrial system and the continuous improvement of people's living standards, the demand for energy is also increasing. At the same time, the use of fossil energy has brought about an environmental crisis, and the contradiction between pollution emissions caused by energy use and environmental protection has also deepened. Under the promotion of environmental protection and energy utilization, the integrated energy system has rapidly developed into a hot topic of current research. Accurately evaluating the operating status of the integrated energy system can timely and effectively feedback the weak links in the value of the integrated energy system and play a guiding role in the operating status of the integrated energy system.

[0003] In the evaluation of integrated energy systems, the research content in recent years has mainly focused on static evaluation methods. Among them, Huang Fei et al. proposed an evaluation model based on the anti-entropy weight method to reduce the impact of indicator data differences on the evaluation results. Hu Tao et al. proposed a cloud matter-element model, which uses entropy to increase the thickness of the cloud model, thereby increasing the ambiguity of the evaluation and avoiding the situation where the time limit of indicator data is not uniform. Jin Yanming focuses on the macroeconomic analysis of the integrated energy system and uses the computable general equilibrium model to conduct a detailed evaluation and analysis of social influencing factors. Zong Huijun proposed an evaluation model based on pressure state response to analyze the impact of construction methods such as electric energy substitution on the integrated energy system. Similar methods include matter-element analysis, genetic projection pursuit method, fuzzy neural network model, probability statistics and vector algebra method, but they all focus on static comprehensive evaluation. Electricity is the most important energy in the integrated energy system. There are many existing indicators for its evaluation, most of which are based on the indicators for evaluating the distribution network. There are fewer indicators for evaluating the operating status of the integrated energy system, such as heat, cold and natural gas. The existing indicator systems are mostly based on smart grids and the power Internet of Things. Most of the evaluation indicators are concentrated on the grid side, with fewer indicators for heat, cooling, and gas, which has certain limitations. In addition, the static comprehensive evaluation does not take development factors into consideration, cannot comprehensively reflect the current and historical levels of the evaluation object, and cannot fully reflect the operation of the integrated energy system. Summary of the invention

[0004] In order to solve the problem that the traditional static evaluation method of integrated energy system does not take development factors into consideration, cannot comprehensively reflect the current level and historical level of the evaluation object, and reflects the operation status of the integrated energy system one-sidedly, the present invention proposes a dynamic evaluation method for integrated energy system.

[0005] In order to solve the above technical problems, the present invention adopts the following technical method: a dynamic evaluation method for the operation status of an integrated energy system, comprising the following steps:

[0006] S1. Collect multi-stage data of the integrated energy system and build an integrated energy system indicator system;

[0007] S2. According to the impact of each indicator on the operation of the integrated energy system, the indicators are classified to obtain a standard indicator matrix;

[0008] S3. Rank the importance of each indicator in the comprehensive energy system indicator system and use the group G1 method to obtain the comprehensive weight of each indicator;

[0009] S4. Construct a weighted standard matrix according to the comprehensive weights of the indicators obtained in step S3, use the TOPSIS method to set the absolute ideal solution of the weighted standard matrix, and calculate the fitting degree of the reference vector;

[0010] S5. Based on the operating characteristics of the multi-stage integrated energy system, the principle of dual excitation control line is used for dynamic evaluation;

[0011] S6. If the evaluation result of the integrated energy system meets expectations, the process ends; otherwise, after adjusting the operation of the integrated energy system, the process returns to step S4;

[0012] Furthermore, in step S1, according to the characteristics of the integrated energy system, considering the relationship between multi-energy coupling and multi-party coordination, multi-stage data of the integrated energy system are collected to construct an integrated energy system indicator system including technical, economic and environmental indicators.

[0013] Among them, technical indicators include average system failure time, comprehensive energy efficiency, and centrally installed energy storage.

[0014] (1) System average failure time: refers to the average failure hours of each user during the statistical period. The system average failure time includes four indicators: system average failure time of electricity, system average failure time of heat, system average failure time of cooling, and system average failure time of natural gas. The calculation formula of system average failure time is as follows:

[0015]

[0016] Where: b is the average system failure time, in hours / household; b is the energy form, representing electricity, heat, cold, and natural gas; M b is the total number of failures of energy b; t b,c is the duration of the cth incapacity of energy source b, in hours; h b,c is the number of users affected by the cth failure of energy source b, in units of households; F is the total number of users of the target system, in units of households.

[0017] (2) Comprehensive energy efficiency: refers to the ratio of the total amount of primary energy consumed for heating, cooling and power generation in a region to the total amount of cooling, heating and electricity energy produced in the region. This indicator represents the comprehensive energy efficiency in the region and can directly reflect the degree of energy saving. The calculation formula for comprehensive energy efficiency is as follows:

[0018]

[0019] Where: C3 represents the comprehensive energy utilization rate; Q out Q is the total amount of energy used to produce heat, cooling and electricity in the region; in It is the total amount of primary energy consumed for heating, cooling and power generation in the region.

[0020] (3) Centrally installed energy storage: This is the system's ability to store electricity, heat, and cold. It is an important measurement indicator for balancing energy supply and is very important in terms of the reliability and flexibility of the energy system. This indicator is a qualitative indicator and the evaluation standard is whether it can meet the demand.

[0021] Among them, economic indicators include energy economy level and active power loss.

[0022] (1) Energy economy level: refers to the ratio of the difference between total economic benefits and energy input costs over a period of time to total energy input. The energy economy level is calculated as follows:

[0023]

[0024] Where: ρ is the economic level of the system on the energy side; D is the total economic benefit over a period of time; C b Input cost for energy type b.

[0025] (2) Active power loss: Electric energy, natural gas, and thermal energy have certain losses during the distribution process. Therefore, the economic benefits of the distribution link can be evaluated by the active power loss per unit time. The lower the index, the higher the economic benefits. The calculation formula for active power loss is as follows:

[0026]

[0027] Where: ΔP is the total active power loss, ΔP L is the active power loss of the transmission line, ΔP Γ is the active power loss of equipment such as transformers, and ΔQ is the heat loss during transmission.

[0028] Among them, environmental protection indicators include emission reduction benefits of renewable energy and carbon dioxide emissions per unit GDP.

[0029] (1) Renewable energy emission reduction benefits: refers to the sum of the reduction in carbon dioxide emissions and the sum of the reduction in pollutant gases after the use of renewable energy. The calculation formula for renewable energy emission reduction benefits is as follows:

[0030] C 36 =σλΔQ renew +θλΔQ renew (5)

[0031] Where: C 36 represents the emission reduction benefits of renewable energy; σ represents the carbon dioxide emission coefficient of standard coal; λ represents the standard coal consumption of thermal power plants; θ represents the pollutant gas emission coefficient of standard coal; ΔQ renew It represents the difference in renewable energy power generation before and after regional multi-energy coordination.

[0032] (2) Carbon dioxide emissions per unit of GDP: refers to the ratio of carbon dioxide emissions per unit time to the regional GDP per unit time. This indicator introduces the impact of GDP and is more comprehensive than a single carbon dioxide emission indicator.

[0033] Further, in step S2, each indicator is divided into a benefit-type indicator and a cost-type indicator according to its impact on the operation of the integrated energy system;

[0034] For benefit indicators:

[0035]

[0036] For cost indicators:

[0037]

[0038] Where: a mi Expressed as the standardized indicator value of indicator i in year m; c mi represents the original indicator value of indicator i in the mth year;

[0039] In step S2, the original indicator data matrix is ​​standardized to obtain the standard indicator matrix A h×n .

[0040] Furthermore, in step S3, the process of using the group G1 method to obtain the comprehensive weight of each indicator is as follows:

[0041] S31, each expert determines the order relationship of indicators;

[0042] Experts ranked the importance of each indicator based on their own experience. n}, experts select the most important indicator based on their experience, denoted as X *1; then select the most important indicator from the remaining n-1 indicators and record it as X * 2; Similarly, perform the above operation n-1 times to obtain the index ranking relationship Finally, the order of each expert is obtained It represents the ranking result of the j-th expert on the i-th indicator;

[0043] S32, comparison of relative importance between adjacent indicators;

[0044] Each expert compares the importance of adjacent indicators based on their own experience. The ratio of the importance of adjacent indicators is the importance scale, which is expressed in R k To express it, as follows:

[0045]

[0046] In the formula, ω′ k-1 It is expressed as the subjective weight of the k-1th indicator in the indicator ranking relationship, ω′ k It is expressed as the subjective weight of the kth indicator in the indicator ranking relationship; when In the case of k It is necessary to multiply the original value by the proportional coefficient to make corrections, so as to ensure The calculation formula of the proportionality coefficient ρ is:

[0047]

[0048] R′ k =R k *ρ (10)

[0049] Where: R′ k It is expressed as the corrected importance scale, and ρ represents the proportionality coefficient;

[0050] S33, calculation of weights of each indicator;

[0051] The order relationship between the indicators given by the experts and R k Then, the least important indicator weight ω is calculated according to the following formula: j n , and then according to the importance scale between each indicator and the calculation, ω is obtained j n , find the weight of each indicator under the expert's experience;

[0052]

[0053] Where: j nIt is expressed as the weight of the nth indicator of the jth expert, which is the weight of the least important indicator in the ranking;

[0054] S34, calculation of comprehensive weights of various indicators;

[0055] The weight of each indicator needs to be combined with the weight of each expert. The weight of each expert is d j , d j Satisfy 0 <d j <1, l is the number of experts, and we have:

[0056]

[0057] Where: i represents the comprehensive weight of the i-th indicator, ω j i It is represented as the i-th indicator weight of the j-th expert.

[0058] Furthermore, the method of constructing a weighted standard matrix according to the comprehensive weight of the indicators in step S4 is as follows:

[0059] First, the comprehensive weights of all indicators obtained in step S3 are combined into a weight matrix ω 1×n , and then according to the TOPSIS principle, the weighted standard matrix F h×n , the calculation formula is as follows:

[0060] F h×n =A h×n ·ω 1×n =(f mi ) h×n (13)

[0061] Where: F h×n Expressed as a weighted standard matrix; f mi Expressed as the weighted standard of the ith indicator in the mth year.

[0062] Furthermore, in step S4, when the TOPSIS method is used to set the absolute ideal solution of the weighted standard matrix and calculate the reference vector fit:

[0063] First, use the TOPSIS method to set the absolute positive ideal solution Q of the weighted standard matrix + and the absolute negative ideal solution Q — , as shown below:

[0064]

[0065] Then use the projection method to solve the absolute negative ideal solution Q - =[0,0,...,0] 1×n Set it as the origin of the space coordinates, and solve Q from the absolute negative ideal— To the absolutely positive ideal solution Q + The vector is called the reference vector, and any weighted standard matrix f is represented as any vector in space. The modulus of f is represented as f to the absolute negative ideal solution Q — The distance between f and the absolute positive ideal solution Q + The angle between them represents the absolute positive ideal solution Q + The calculation formula of the reference vector fit is as follows:

[0066]

[0067] Where: P Q+ It is expressed as the projection distance, that is, the reference vector fit, and the larger the value, the better the running state; f m It is represented as the weighted standard matrix of the mth year; f i + Represented as a positive ideal solution of index i.

[0068] Furthermore, in step S5, when the dual excitation control line principle is used to perform dynamic evaluation according to the operating status characteristics of the multi-stage integrated energy system:

[0069] Using the information aggregation method of dual incentive control lines, two incentive lines, positive incentive line and negative incentive line, are introduced. The part exceeding the positive incentive line is rewarded, and the part below the negative incentive line is punished.

[0070] First, let the evaluation object set be {O β}(β=1,2,…,z), determine the general straight line representation of the dual excitation control line as follows:

[0071] y-y0 ± =k a ± (x-x0 ± ) (16)

[0072] Where: x is the horizontal axis time variable, x0 ± is the horizontal coordinate value of the initial point; y is the vertical axis evaluation value variable, y0 ± is the ordinate value of the initial point, taking a value with strong explanatory power, requiring y0 ± ∈[min(y β,k ),max(y β,k )],y β,k For the evaluation object O β In t k Evaluation value at the moment; k a ± is the positive or negative excitation line slope;

[0073] Then calculate the maximum growth rate r of the dual excitation control line according to the following formula:max a , minimum growth rate r min a , average growth rate

[0074]

[0075] Where: x k is the horizontal coordinate value at time k, x k =x(t k ),k=1,2,…,N, the sequence {x k} are equally spaced, corresponding to N-1 time periods, y β,k+1 For the evaluation object O β In t k+1 Evaluation value at the moment; x k+1 is the horizontal coordinate value at time k+1;

[0076] Then calculate the slope k of the positive excitation line according to the following formula: a + And the slope of the negative excitation line k a - ;

[0077]

[0078] Where: v + is the slope deviation of the positive excitation line, v - is the slope deviation of the negative excitation line, v + ∈[0,1];v - ∈[0, 1];

[0079] Finally, the evaluation object О is calculated according to the following formula β In [t k , t k+1 The total dynamic comprehensive evaluation value s within ] ± β ;

[0080]

[0081] s ± βk =μ + s + βk +s βk -μ - s - βk (20)

[0082]

[0083] Where: s βk For evaluation objectβ In [t k , t k+1 ] dynamic evaluation value within; s ± βk For evaluation object β In [t k , t k+1 ] Dynamic comprehensive evaluation value of internal excitation, s + βk is the positive excitation dynamic comprehensive evaluation value; s - βk is the dynamic comprehensive evaluation value of negative excitation; μ + is the positive excitation coefficient, μ - is the negative excitation coefficient, μ + >0,μ - >0;h k is the time factor, which is set according to the needs of decision makers, and h k >0, k=1,2,…,N-1.

[0084] Preferably, in step S5, the positive excitation coefficient μ + and negative excitation coefficient μ - It is necessary to abide by the incentive conservation rules and degree incentive rules, as follows:

[0085] According to the incentive conservation rule, for all z evaluation objects, the total amount of positive and negative incentives is equal, that is:

[0086]

[0087] According to the degree incentive rule, the sum of positive and negative incentive coefficients is 1, that is:

[0088] μ + +μ - =1 (23)

[0089] In order to solve the problem that the traditional static evaluation method of the integrated energy system does not consider the development factors and is relatively one-sided, the present invention proposes a dynamic evaluation method for the integrated energy system, which avoids the one-sided reflection of the operating status of the integrated energy system by a single type of indicator, takes into account the development dynamics of the integrated energy system itself, and makes the evaluation results more comprehensive, which is of great significance for guiding the operation and planning of the integrated energy system. Specifically, the dynamic evaluation method for the operating status of the integrated energy system provided by the present invention constructs an indicator system including technical, economic, and environmental protection dimensions, avoiding the one-sided reflection of the evaluation results by a single indicator. In addition, the present invention calculates the indicator weights by the group G1 method, and uses the TOPSIS evaluation model to evaluate the operating status of the integrated energy system, so that the evaluation results are more accurate. Finally, the present invention collects the operating data of the integrated energy system in multiple time stages, and uses the principle of dual excitation control lines to dynamically evaluate the operating status of the integrated energy system, which can effectively comprehensively evaluate the historical level and the current level. BRIEF DESCRIPTION OF THE DRAWINGS

[0090] Figure 1 It is a flow chart of the dynamic evaluation method for the operation status of the integrated energy system involved in the present invention;

[0091] Figure 2 Schematic diagram of dual excitation control line information aggregation in an embodiment of the present invention. DETAILED DESCRIPTION

[0092] In order to facilitate the understanding of those skilled in the art, the present invention is further described below in conjunction with embodiments and drawings. The contents mentioned in the implementation modes are not intended to limit the present invention.

[0093] like Figure 1 As shown in the figure, a dynamic evaluation method for the operating status of an integrated energy system includes six steps, and the content of each step is as follows.

[0094] S1. Collect multi-stage data of the integrated energy system and build an indicator system for the integrated energy system.

[0095] According to the characteristics of the integrated energy system, considering the relationship between multi-energy coupling and multi-party coordination, multi-stage data of the integrated energy system are collected, and a comprehensive energy system indicator system including technical, economic and environmental protection indicators is constructed.

[0096] Among them, technical indicators include average system failure time, comprehensive energy efficiency, and centrally installed energy storage.

[0097] (1) System average failure time: refers to the average failure hours of each user during the statistical period. The system average failure time includes four indicators: system average failure time of electricity, system average failure time of heat, system average failure time of cooling, and system average failure time of natural gas. The calculation formula of system average failure time is as follows:

[0098]

[0099] Where: b is the average system failure time, in hours / household; b is the energy form, representing electricity, heat, cold, and natural gas; M b is the total number of failures of energy b; t b,c is the duration of the cth incapacity of energy source b, in hours; h b,c is the number of users affected by the cth failure of energy source b, in units of households; F is the total number of users of the target system, in units of households.

[0100] (2) Comprehensive energy efficiency: refers to the ratio of the total amount of primary energy consumed for heating, cooling and power generation in a region to the total amount of cooling, heating and electricity energy produced in the region. This indicator represents the comprehensive energy efficiency in the region and can directly reflect the degree of energy saving. The calculation formula for comprehensive energy efficiency is as follows:

[0101]

[0102] Where: C3 represents the comprehensive energy utilization rate; Q out Q is the total amount of energy used to produce heat, cooling and electricity in the region; in It is the total amount of primary energy consumed for heating, cooling and power generation in the region.

[0103] (3) Centrally installed energy storage: This is the system's ability to store electricity, heat, and cold. It is an important measurement indicator for balancing energy supply and is very important in terms of the reliability and flexibility of the energy system. This indicator is a qualitative indicator and the evaluation standard is whether it can meet the demand.

[0104] Among them, economic indicators include energy economy level and active power loss.

[0105] (1) Energy economy level: refers to the ratio of the difference between total economic benefits and energy input costs over a period of time to total energy input. The energy economy level is calculated as follows:

[0106]

[0107] Where: ρ is the economic level of the system on the energy side; D is the total economic benefit over a period of time; C b Input cost for energy type b.

[0108] (2) Active power loss: Electric energy, natural gas, and thermal energy have certain losses during the distribution process. Therefore, the economic benefits of the distribution link can be evaluated by the active power loss per unit time. The lower the index, the higher the economic benefits. The calculation formula for active power loss is as follows:

[0109]

[0110] Where: ΔP is the total active power loss, ΔP L is the active power loss of the transmission line, ΔP Γ is the active power loss of equipment such as transformers, and ΔQ is the heat loss during transmission.

[0111] Among them, environmental protection indicators include emission reduction benefits of renewable energy and carbon dioxide emissions per unit GDP.

[0112] (1) Renewable energy emission reduction benefits: refers to the sum of the reduction in carbon dioxide emissions and the sum of the reduction in pollutant gases after the use of renewable energy. The calculation formula for renewable energy emission reduction benefits is as follows:

[0113] C 36 =σλΔQ renew +θλΔQ renew (5)

[0114] Where: C 36 represents the emission reduction benefits of renewable energy; σ represents the carbon dioxide emission coefficient of standard coal; λ represents the standard coal consumption of thermal power plants; θ represents the pollutant gas emission coefficient of standard coal; ΔQ renew It represents the difference in renewable energy power generation before and after regional multi-energy coordination.

[0115] (2) Carbon dioxide emissions per unit of GDP: refers to the ratio of carbon dioxide emissions per unit time to the regional GDP per unit time. This indicator introduces the impact of GDP and is more comprehensive than a single carbon dioxide emission indicator.

[0116] After determining the indicator system of the integrated energy system, the operation data of the integrated energy system over multiple periods and stages are collected to prepare for subsequent dynamic evaluation.

[0117] S2. According to the impact of each indicator on the operation of the integrated energy system, the indicators are classified to obtain a standard indicator matrix.

[0118] The magnitudes of the indicators are different, so the data cannot be directly analyzed and calculated. In order to facilitate subsequent operations and make the indicators more feasible, it is necessary to standardize the indicators and obtain a standard indicator matrix. Therefore, according to the impact of each indicator on the operation of the integrated energy system, each indicator is divided into benefit-based indicators and cost-based indicators.

[0119] For benefit-based indicators, the larger the indicator value, the greater the benefit, as shown in the following formula:

[0120]

[0121] For cost-based indicators, the smaller the indicator data, the lower the cost, as shown in the following formula:

[0122]

[0123] Where: a mi Expressed as the standardized indicator value of indicator i in year m; c mi represents the original indicator value of indicator i in the mth year;

[0124] In step S2, the original indicator data matrix is ​​standardized to obtain the standard indicator matrix A h×n .

[0125] S3. Rank the importance of each indicator in the comprehensive energy system indicator system and use the group G1 method to obtain the comprehensive weight of each indicator.

[0126] The G1 method, also known as the ordinal relationship analysis method, is an improvement based on the hierarchical analysis method. It overcomes the problem that when there are too many evaluation indicators and the data statistics are large, the accurate method of calculating eigenvalues ​​and eigenvectors becomes too complicated, and the judgment matrix is ​​frequently adjusted due to the failure of the consistency test. However, the single G1 method is greatly affected by a single expert. The present invention introduces the idea of ​​group decision-making, considers the influence of the experience and academic level of each expert, and uses the group G1 method to solve the weight of each indicator. For n indicators, the process of using the group G1 method to obtain the comprehensive weight of each indicator is as follows:

[0127] S31, each expert determines the order relationship of indicators;

[0128] Experts ranked the importance of each indicator based on their own experience. n}, experts select the most important indicator based on their experience, denoted as X * 1; then select the most important indicator from the remaining n-1 indicators and record it as X * 2; Similarly, perform the above operation n-1 times to obtain the index ranking relationship Finally, the order of each expert is obtained It represents the ranking result of the j-th expert on the i-th indicator.

[0129] S32, comparison of relative importance between adjacent indicators;

[0130] Each expert compares the importance of adjacent indicators based on their own experience. The ratio of the importance of adjacent indicators is the importance scale, which is expressed in R k To express it, as follows:

[0131]

[0132] In the formula, ω′ k-1 It is expressed as the subjective weight of the k-1th indicator in the indicator ranking relationship, ω′ k It is expressed as the subjective weight of the kth indicator in the indicator ranking relationship; R k The reference values ​​are shown in Table 1 below.

[0133] Table 1 R k Reference assignment table

[0134]

[0135] In order to prevent the situation where the cumulative importance exceeds the extreme importance, resulting in unscientific indicator weight setting, the present invention In the case of k It is necessary to multiply the original value by the proportional coefficient to make corrections, so as to ensure The calculation formula of the proportionality coefficient ρ is:

[0136]

[0137] R′ k =R k *ρ (10)

[0138] Where: R′ k It is expressed as the corrected importance scale, and ρ is the proportionality coefficient.

[0139] S33, calculation of weights of each indicator;

[0140] The order relationship between the indicators given by the experts and R k Then, the least important indicator weight ω is calculated according to the following formula: j n , and then according to the importance scale between each indicator and the calculation, ω is obtained j n , find the weight of each indicator under the expert's experience;

[0141]

[0142] Where: j n It is expressed as the nth indicator weight of the jth expert, that is, the least important indicator weight in the ranking.

[0143] S34, calculation of comprehensive weights of various indicators;

[0144] After the weights of each expert are obtained, the weights obtained by each expert need to be integrated. The present invention uses the idea of ​​group decision-making, taking into account factors such as the expert's experience, qualifications, and academic level, and denoting the weight of each expert as d j , d j Satisfy 0 <d j <1, l is the number of experts, and we have:

[0145]

[0146] Where: i represents the comprehensive weight of the i-th indicator, ω j i It is represented as the i-th indicator weight of the j-th expert.

[0147] S4. Construct a weighted standard matrix according to the comprehensive weights of the indicators obtained in step S3, use the TOPSIS method to set the absolute ideal solution of the weighted standard matrix, and calculate the reference vector fit.

[0148] First, the comprehensive weights of all indicators obtained in step S3 are combined into a weight matrix ω 1×n , and then according to the TOPSIS principle, the weighted standard matrix F h×n , the calculation formula is as follows:

[0149] F h×n =A h×n ·ω 1×n =(f mi ) h×n (13)

[0150] Where: F h×n Expressed as a weighted standard matrix; f mi Expressed as the weighted standard of the ith indicator in the mth year.

[0151] Then use the TOPSIS method to set the absolute ideal solution of the weighted standard matrix. The positive and negative ideal solutions of traditional TOPSIS are often set to F h×n The maximum and minimum values ​​corresponding to each indicator in the TOPSIS method will change due to the change in the number of samples, resulting in a reverse sorting problem in the evaluation results. To solve this problem, the present invention uses the TOPSIS method to set the absolute positive ideal solution Q of the weighted standard matrix. + and the absolute negative ideal solution Q — , as shown below:

[0152]

[0153] Then use the projection method to solve the absolute negative ideal solution Q- =[0,0,...,0] 1×n Set it as the origin of the space coordinates, and solve Q from the absolute negative ideal — To the absolutely positive ideal solution Q + The vector is called the reference vector, and any weighted standard matrix f is represented as any vector in space. The modulus of f is represented as f to the absolute negative ideal solution Q — The distance between f and the absolute positive ideal solution Q + The angle between them represents the absolute positive ideal solution Q + The fit of , which can be converted into the projection of f on the reference vector, to overcome the problem of being unable to judge when the fit is the same. The calculation formula of the reference vector fit is as follows:

[0154]

[0155] Where: It is expressed as the projection distance, that is, the reference vector fit, and the larger the value, the better the running state; f m It is represented as the weighted standard matrix of the mth year; f i + Represented as a positive ideal solution of index i.

[0156] S5. Based on the operating characteristics of the multi-stage integrated energy system, the dual excitation control line principle is used for dynamic evaluation.

[0157] The operation data of the integrated energy system in multiple time periods are collected, and the group G1 method and improved TOPSIS are used to obtain the operation evaluation results of each time period. However, the development of the integrated energy system should also be considered to make the evaluation results more in line with the current conditions and improve the rationality and accuracy of the evaluation.

[0158] The comprehensive evaluation method based on the principle of dual incentive control line is adopted to effectively target the characteristics of each stage and consider the dynamic characteristics of the development of the integrated energy system. The information aggregation method of dual incentive control line is used to introduce two incentive lines, positive incentive line and negative incentive line. The part above the positive incentive line is rewarded, and the part below the negative incentive line is punished. This reflects the decision-making intention and highlights the differences between each stage, thereby improving the ability to distinguish evaluation objects with similar quality. In order to achieve the ideal effect, the evaluation decision maker can accurately control the evaluation process by adjusting parameters such as the slope of the dual incentive control line.

[0159] First, let the evaluation object set be {O β}(β=1,2,…,z), determine the general straight line representation of the dual excitation control line as follows:

[0160] y-y0 ± =k a ± (x-x0± ) (16)

[0161] Where: x is the horizontal axis time variable, x0 ± is the horizontal coordinate value of the initial point; y is the vertical axis evaluation value variable, y0 ± is the ordinate value of the initial point, taking a value with strong explanatory power, requiring y0 ± ∈[min(y β,k ),max(y β,k )],y β,k For the evaluation object O β In t k Evaluation value at the moment; k a ± is the positive or negative excitation line slope.

[0162] Then calculate the maximum growth rate r of the dual excitation control line according to the following formula: max a , minimum growth rate r min a , average growth rate

[0163]

[0164] Where: x k is the horizontal coordinate value at time k, x k =x(t k ),k=1,2,…,N, the sequence {x k} are equally spaced, corresponding to N-1 time periods, y β,k+1 For the evaluation object O β In t k+1 Evaluation value at the moment; x k+1 is the horizontal coordinate value at time k+1.

[0165] Then calculate the slope k of the positive excitation line according to the following formula: a + And the slope of the negative excitation line k a - ;

[0166]

[0167] Where: v + is the slope deviation of the positive excitation line, v - is the slope deviation of the negative excitation line, v + ∈[0,1];v - ∈[0, 1].

[0168] Finally, the evaluation object О is calculated according to the following formula β In [t k , tk+1 The total dynamic comprehensive evaluation value s within ] ± β .

[0169] The dual excitation control line uses the principle of information aggregation. Information aggregation believes that the development state of an evaluation object develops evenly between two adjacent points, and its development state trajectory can be represented by a straight line, such as Figure 2 As shown. The area S in the figure reflects the evaluation object О β In [t k , t k+1 ], at which point its dynamic evaluation value s βk Expressed as an integral:

[0170]

[0171] Parts other than the positive and negative excitation lines (such as Figure 2 The positive and negative excitation area S + , S - ) will be "rewarded or punished", set s ± βk For evaluation object β In [t k , t k+1 ]The dynamic comprehensive evaluation value of the internal band excitation is expressed by the formula:

[0172] s ± βk =μ + s + βk +s βk -μ - s - βk (20)

[0173] Where: s + βk is the positive excitation dynamic comprehensive evaluation value; s - βk is the dynamic comprehensive evaluation value of negative excitation; μ + is the positive excitation coefficient, μ - is the negative excitation coefficient, μ + >0,μ - >0.

[0174] For the whole process [t1, t N ] to conduct weighted comprehensive evaluation of each period in the evaluation object О β Total dynamic comprehensive evaluation value with incentives ± β for:

[0175]

[0176] Where: h k is the time factor, which is set according to the needs of decision makers, and h k >0, k=1,2,…,N-1.

[0177] Determine the positive excitation coefficient μ + and negative excitation coefficient μ - There are two rules to follow:

[0178] According to the incentive conservation rule, for all z evaluation objects, the total amount of positive and negative incentives is equal, that is:

[0179]

[0180] According to the degree incentive rule, the sum of positive and negative incentive coefficients is 1, that is:

[0181] μ + +μ - =1 (23)

[0182] S6. If the evaluation result of the integrated energy system meets expectations, the process ends; otherwise, after adjusting the operation of the integrated energy system, the process returns to step S4.

[0183] By collecting data from multiple time periods, the weights of each indicator are calculated using the group G1 method, and TOPSIS is used to obtain the degree of fit between the time period and the absolute positive ideal solution, and the evaluation results of each time period are obtained. Finally, the dual excitation control line principle is used to dynamically evaluate the operating status of the integrated energy system. The gap between the operating status of the integrated energy system and the expected results is analyzed. If the evaluation is unqualified, the integrated energy system needs to be adjusted, and steps S4 and S5 are repeated until the integrated energy system is evaluated to be qualified.

[0184] The above embodiments are preferred implementation schemes of the present invention. In addition, the present invention can also be realized in other ways. Any obvious replacement without departing from the concept of the present technical solution is within the protection scope of the present invention.

[0185] In order to make it easier for ordinary technicians in the field to understand the improvements of the present invention over the prior art, some drawings and descriptions of the present invention have been simplified, and for the sake of clarity, some other elements are omitted in this application document. Ordinary technicians in the field should realize that these omitted elements may also constitute the content of the present invention.

Claims

1. A dynamic evaluation method for the operation status of an integrated energy system, characterized in that: The steps include: S1. Collect multi-stage data of the integrated energy system and build an integrated energy system indicator system; S2. According to the impact of each indicator on the operation of the integrated energy system, the indicators are classified to obtain a standard indicator matrix; S3. Rank the importance of each indicator in the comprehensive energy system indicator system and use the group G1 method to obtain the comprehensive weight of each indicator; In step S3, the process of using the group G1 method to obtain the comprehensive weight of each indicator is as follows: S31, each expert determines the order relationship of indicators; Experts ranked the importance of each indicator based on their own experience. n }, the expert selects the most important indicator based on experience, recorded as X*1; then selects the most important indicator from the remaining n-1 indicators again, recorded as X * 2; And so on, perform the above operation n-1 times to obtain the index ranking relationship Finally, the order of each expert is obtained represents the ranking result of the j-th expert on the i-th indicator; S32, comparison of relative importance between adjacent indicators; Each expert compares the importance of adjacent indicators based on their own experience. The ratio of the importance of adjacent indicators is the importance scale, which is expressed in R k To express it, as follows: In the formula, ω′ k-1 It is expressed as the subjective weight of the k-1th indicator in the indicator ranking relationship, ω′ k It is expressed as the subjective weight of the kth indicator in the indicator ranking relationship; when In the case of k It is necessary to multiply the original value by the proportional coefficient to make corrections, so as to ensure The calculation formula of the proportionality coefficient ρ is: R k ′=R k *p (10) Where: R′ k It is expressed as the corrected importance scale, and ρ represents the proportionality coefficient; S33, calculation of weights of each indicator; The order relationship between the indicators given by the experts and R k Then, the least important indicator weight ω is calculated according to the following formula: j n , and then according to the importance scale between each indicator and the calculation, ω is obtained j n , find the weight of each indicator under the expert's experience; Where: j n It is represented as the weight of the nth indicator of the jth expert, and is the weight of the least important indicator in the ranking; S34, calculation of comprehensive weights of various indicators; The weight of each indicator needs to be combined with the weight of each expert. The weight of each expert is d j , d j Satisfy 0 <d j <1, l is the number of experts, and we have: Where: i represents the comprehensive weight of the i-th indicator, ω j i It is represented as the weight of the i-th indicator of the j-th expert; S4. Construct a weighted standard matrix according to the comprehensive weights of the indicators obtained in step S3, use the TOPSIS method to set the absolute ideal solution of the weighted standard matrix, and calculate the fitting degree of the reference vector; The method for constructing a weighted standard matrix according to the comprehensive weight of indicators in step S4 is as follows: First, the comprehensive weights of all indicators obtained in step S3 are combined into a weight matrix ω 1×n , and then according to the TOPSIS principle, the weighted standard matrix F h×n , the calculation formula is as follows: F h×n =A h×n ·ω 1×n =(f mi ) h×n (13) Where: F h×n Expressed as a weighted standard matrix, f mi It is expressed as the weighted standard of the ith indicator of the mth integrated energy system; In step S4, when the TOPSIS method is used to set the absolute ideal solution of the weighted standard matrix and calculate the reference vector fit: First, use the TOPSIS method to set the absolute positive ideal solution Q of the weighted standard matrix + and the absolute negative ideal solution Q — , as shown below: Then use the projection method to solve the absolute negative ideal solution Q - =[0,0,...,0] 1×n Set it as the origin of the space coordinates, and solve Q from the absolute negative ideal — To the absolutely positive ideal solution Q + The vector is called the reference vector, and any weighted standard matrix f is represented as any vector in space. The modulus of f is represented as f to the absolute negative ideal solution Q — The distance between f and the absolute positive ideal solution Q + The angle between them represents the absolute positive ideal solution Q + The calculation formula of the reference vector fit is as follows: Where: It is represented by the projection distance, and is the reference vector fit degree. The larger its value is, the better the running state is. m It is represented as the weighted standard matrix of the mth integrated energy system; f i + It is represented as the positive ideal solution of index i; S5. Based on the operating characteristics of the multi-stage integrated energy system, the principle of dual excitation control line is used for dynamic evaluation; Using the information aggregation method of dual incentive control lines, two incentive lines, positive incentive line and negative incentive line, are introduced. The part exceeding the positive incentive line is rewarded, and the part below the negative incentive line is punished. First, let the evaluation object set be {O β }(β=1,2,…,h), determine the general straight line representation of the dual excitation control line as follows: y-y0 ± =k a ± (x-x0 ± ) (16) Where: x is the horizontal axis time variable, x0 ± is the horizontal coordinate value of the initial point; y is the vertical axis evaluation value variable, y0 ± is the ordinate value of the initial point, taking a value with strong explanatory power, requiring y0 ± ∈[min(y β,k ),max(y β,k )],y β,k For the evaluation object O β In t k The evaluation value at the moment, k a ± is the positive or negative excitation line slope; Then calculate the maximum growth rate r of the dual excitation control line according to the following formula: max a , minimum growth rate r min a , average growth rate Where: x k is the horizontal coordinate value at time k, x k =x(t k ),k=1,2,…,N, the sequence {x k } are equally spaced, corresponding to N-1 time periods, y β,k+1 For the evaluation object O β In t k+1 Evaluation value at the moment; x k+1 is the horizontal coordinate value at time k+1; Then calculate the slope k of the positive excitation line according to the following formula: a + and the slope of the negative excitation line k a - ; Where: v + is the slope deviation of the positive excitation line, v - is the slope deviation of the negative excitation line, v + ∈[0,1];v - ∈[0, 1]; Finally, the evaluation object О is calculated according to the following formula β In [t k , t k+1 The total dynamic comprehensive evaluation value s within ] ± β ; s ± βk =μ + s + βk +s βk -m - s - βk (20) Where: s βk For evaluation object β In [t k , t k+1 ] dynamic evaluation value within; s ± βk For evaluation object β In [t k , t k+1 ] Dynamic comprehensive evaluation value of internal excitation, s + βk is the positive excitation dynamic comprehensive evaluation value; s - βk is the dynamic comprehensive evaluation value of negative excitation; μ + is the positive excitation coefficient, μ - is the negative excitation coefficient, μ + >0,μ - >0;h k is the time factor, which is set according to the needs of decision makers, and h k >0, k=1,2,…,N-1; S6. If the evaluation result of the integrated energy system meets expectations, the process ends; otherwise, after adjusting the operation of the integrated energy system, the process returns to step S4.

2. The dynamic evaluation method for the operation status of an integrated energy system according to claim 1 is characterized in that: In step S1, according to the characteristics of the integrated energy system, considering the relationship between multi-energy coupling and multi-party coordination, multi-stage data of the integrated energy system are collected to construct an integrated energy system indicator system including technical, economic and environmental indicators; technical indicators include system average failure time, comprehensive energy efficiency, and centralized installed energy storage; economic indicators include energy economy level and active power loss; environmental indicators include renewable energy emission reduction benefits and carbon dioxide emissions per unit GDP.

3. The dynamic evaluation method for the operation status of an integrated energy system according to claim 2 is characterized in that: In step S2, each indicator is divided into benefit-type indicators and cost-type indicators according to its impact on the operation of the integrated energy system; For benefit indicators: For cost indicators: Where: a mi It is expressed as the standardized index value of index i of the mth integrated energy system; c mi represents the original index value of index i of the m-th integrated energy system; In step S2, the original indicator data matrix is ​​standardized to obtain the standard indicator matrix A h×n .

4. The dynamic evaluation method for the operation status of an integrated energy system according to claim 3 is characterized in that: In step S5, the positive excitation coefficient μ + and negative excitation coefficient μ - It is necessary to abide by the incentive conservation rules and degree incentive rules, as follows: The incentive conservation rule states that for all h evaluation objects, the total amount of positive and negative incentives is equal; The degree incentive rule, the sum of positive and negative incentive coefficients is 1; m + +m - = 1 (23).