Asymmetric wall-attached construction method for symmetrical double-arch tunnel structure of subway
Through the asymmetric wall-mounted construction method, the problems of multiple process conversions, long cycles and unfavorable waterproofing in the construction of subway double-continuous arch tunnels are solved, and higher construction safety and waterproofing performance are achieved.
Patent Information
- Application Number
- CN202210316452.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2022-03-29
- Publication Date
- 2024-11-22
- Estimated Expiration
- 2042-03-29
AI Technical Summary
In the construction of subway symmetric double-continuous arch tunnels, there are problems such as many construction process conversions, long cycles, many risk events, and unfavorable structural waterproofing.
Asymmetric wall-mounted construction method is adopted, and the right line and left line of the double-continuous arch tunnel is excavated through open excavation of vertical shafts. First, the first branch and second lining of the right line are completed, and then the left line is excavated by asymmetric wall-mounted method to reduce process conversion. , improve construction efficiency, and only two upper and lower construction joints are provided in the double-continuous arch tunnel structure to improve waterproof performance.
It reduces the conversion of construction processes, shortens the construction cycle, reduces risk events, and improves construction safety and waterproofing capabilities of underground structures.
Smart Images

Figure CN114856575B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of subway tunnel construction, and in particular to an asymmetric wall-attached construction method for a subway symmetrical double-arch tunnel structure. Background Art
[0002] In the subway double-line independent tunnel project, the minimum line spacing between the left and right lines is about 5m. Due to the line conditions and the line conditions of the tunnel under the important risk source, it is not possible to construct the open-cut method and the single-hole double-line dark-cut tunnel method. In order to reduce the impact on the surrounding important risk sources during the subway tunnel construction, the underpass section needs to be designed as a symmetrical double-arch tunnel. At present, most of the subway symmetrical double-arch tunnels are constructed using the conventional middle-hole method.
[0003] Although the middle-hole method is a more common construction method for double-arch tunneling, it has disadvantages such as many changes in construction procedures and a long cycle. When passing through important risk sources such as buildings and underground pipelines, there are many risk events caused by process changes, which is not conducive to risk control. In addition, the traditional middle-hole method has two construction joints at the arch crown and invert, which is not conducive to structural waterproofing. Summary of the invention
[0004] The purpose of the present invention is to provide an asymmetric wall-attached construction method for a symmetrical double-arch tunnel structure of a subway, so as to solve the problems of multiple construction process changes, long cycle, more risk events, and poor structural waterproofing in the middle hole method construction.
[0005] In order to achieve the above object, the technical solution adopted by the present invention is:
[0006] An asymmetric wall-attached construction method for a symmetrical double-arch tunnel structure of a subway, the method comprising the following steps:
[0007] Step 1: Excavate downward through the open-cut vertical shaft to the junction of the open-cut vertical shaft and the double-arch tunnel, and construct the right-line horse head gate and the left-line horse head gate of the double-arch tunnel;
[0008] Step 2: Along the designed position of the primary lining of the double-arch tunnel, a large pipe shed is built on top, and the pipe shed locking beam is constructed;
[0009] Step 3: Remove the right-line horse head gate, excavate the right-line step and the right-line lower step, construct a closed-loop right-line primary support steel frame, and set embedded connectors at the upper and lower ends of the left side of the right-line primary support steel frame;
[0010] Step 4: construct the primary lining of the right line based on the primary support steel frame of the right line, and construct the secondary lining of the right line inside the primary lining of the right line; the secondary lining of the right line includes the right line inverted arch part at the bottom, the upper left end of the right line inverted arch part is a vertical middle partition wall, and the upper right end of the right line inverted arch part is a C-shaped right line arch part;
[0011] Step 5: Remove the left-line horse head gate, excavate the left-line step and the left-line lower step, and build a C-shaped left-line primary support steel frame on the left side of the right-line primary lining. The upper and lower ends of the left-line primary support steel frame are fixed on the embedded connectors of the right-line primary support steel frame;
[0012] Step 6: Remove the primary support steel frame and primary lining of the right line located inside the left line;
[0013] Step seven: construct the left line primary lining based on the left line primary support steel frame, and construct the left line secondary lining inside the left line primary lining; the left line secondary lining includes the left line inverted arch part at the bottom, the right end of the left line inverted arch part is connected to the bottom of the middle partition wall, the left line inverted arch part has a C-shaped left line arch part above the left end, and the top right end of the left line arch part is connected to the top of the middle partition wall.
[0014] Furthermore, in step 2, along the designed position of the primary lining of the double-arch tunnel, a double row of large pipe sheds are set above, within a 180° range of the arch of the double-arch tunnel;
[0015] The double-row large pipe shed is divided into an outer row of large pipe shed and an inner row of large pipe shed. The diameter of the outer row of large pipe shed is larger than that of the inner row of large pipe shed.
[0016] Furthermore, in step 3, after the closed-loop right line primary support steel frame is constructed, an advance small conduit is installed above the upper part of the right line primary support steel frame located on the left line; as the steps on the right line are excavated, an advance small conduit is installed every two excavation advances;
[0017] Afterwards, the advance small guide tube was removed during the excavation of the left line upper step and the left line lower step.
[0018] Furthermore, in step 3, when constructing the closed-loop right-line primary support steel frame, locking foot anchor pipes are constructed on both sides of the lower part of the right-line primary support steel frame;
[0019] Afterwards, the locking foot anchor pipe on the left side is removed during the excavation of the left online upper step and the left offline lower step.
[0020] Furthermore, in step five, when constructing the C-shaped left-line primary support steel frame, a locking foot anchor pipe is constructed on the left side of the lower portion of the left-line primary support steel frame.
[0021] Furthermore, in step four, the middle partition wall and the right line arch are constructed simultaneously, and the left sides of the upper and lower ends of the middle partition wall have protrusions that can smoothly connect with the left line second lining.
[0022] Furthermore, the right line primary support steel frame and the left line primary support steel frame are both composed of multiple circumferential steel frame units spliced together;
[0023] Steel frame vertical bars are arranged on the top, bottom and right side steel frame units of the right line primary support steel frame, and steel frame vertical bars are arranged on the top, bottom and left side steel frame units of the left line primary support steel frame.
[0024] Furthermore, the embedded connection parts of the primary support steel frame of the right line include channel steel, and embedded steel bars are welded and fixed to the bottom of the channel steel;
[0025] A channel steel is provided at the end of the left line primary support steel frame, and embedded steel bars are welded and fixed at the bottom of the channel steel;
[0026] The channel steel of the embedded connecting part is connected with the channel steel of the left line primary support steel frame and then fixed with bolts.
[0027] Furthermore, the annular reinforcement in the second lining of the right line extends into the second lining of the left line and is connected to the annular reinforcement in the second lining of the left line through a reinforcement connector;
[0028] The vertical reinforcements in the middle partition wall are distributed on the left and right sides, and longitudinal reinforcements and tension reinforcements are arranged in the middle of the vertical reinforcements.
[0029] Furthermore, after the right line primary lining is applied and before the right line secondary lining is applied, the position corresponding to the middle partition wall below the right line primary lining is backfilled by anchor pipe grouting;
[0030] After the left line primary lining is applied and before the left line secondary lining is applied, the position corresponding to the middle partition wall below the left line primary lining is backfilled by anchor pipe grouting;
[0031] The grouting backfill on both sides forms a grouting reinforcement area under the middle partition wall, and the grouting reinforcement area extends to both sides to under the right-line inverted arch and under the left-line inverted arch.
[0032] Compared with the prior art, the present invention has the following beneficial effects:
[0033] The present invention proposes an asymmetric wall-adhering construction method for a symmetrical double-track underground tunnel with a small distance between subway lines. The method first simulates a standard single-hole single-track to complete the excavation and support of the right line and the secondary lining construction. After the secondary lining structure construction of the right line is completed, the asymmetric wall-adhering method is used to excavate the left line, construct the primary support and secondary lining structure of the left line, and finally complete the symmetrical double-arch subway tunnel with less process conversion and short cycle.
[0034] When passing under important risk sources such as buildings and underground pipelines, this method effectively avoids risk events caused by process conversion and improves construction safety.
[0035] At the same time, the double-arch tunnel structure of this method has only two construction joints, located at the upper and lower ends of the C-shaped structure of the left line lining. In the traditional middle-hole construction structure, each side of the lining has two construction joints, totaling four construction joints. This method improves the adverse effects of the four construction joints at the arch and invert of the traditional middle-hole construction method on the waterproofing of the structure, and significantly improves the waterproofing capacity of the underground structure. BRIEF DESCRIPTION OF THE DRAWINGS
[0036] In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, drawings of other embodiments can be obtained based on these drawings without paying creative work.
[0037] Figure 1 It is a cross-sectional view of the lining of a subway symmetrical double-arch tunnel structure according to an embodiment of the present application.
[0038] Figure 2 It is a schematic diagram of the right-line tunnel construction process of an embodiment of the present application.
[0039] Figure 3 It is a schematic diagram of the left-line tunnel construction process of an embodiment of the present application.
[0040] Figure 4 This is a schematic diagram of the setting of the primary support steel frame for the right line of an embodiment of the present application.
[0041] Figure 5 This is a schematic diagram of the setting of the left-line primary support steel frame of an embodiment of the present application.
[0042] Figure 6 yes Figure 5 A large-scale diagram of node A.
[0043] Figure 7 This is a general drawing of the second lining steel bar connection of an embodiment of the present application.
[0044] The symbols in the figure are:
[0045] 1-right line primary lining, 2-right line secondary lining, 3-left line primary lining, 4-left line secondary lining, 5-outer row large pipe shed, 6-inner row large pipe shed, 7-advance small guide tube, 8-middle partition wall, 9-right line upper step, 10-right line lower step, 11-right line arch, 12-right line inverted arch, 13-left line step, 14-left lower step, 15-left line arch, 16-left line inverted arch, 17-embedded connector, 18-locking anchor pipe, 19-steel frame unit, 20-steel frame unit connection node, 21-steel frame vertical reinforcement, 22-channel steel, 23-bolt, 24-embedded steel bar, 25-steel bar connector, 26-longitudinal reinforcement, 27-tension bar, 28-circumferential reinforcement, 29-vertical reinforcement, 30-grouting reinforcement area, 31-construction joint. DETAILED DESCRIPTION
[0046] In order to facilitate the understanding of the present invention, the present invention will be described more fully below with reference to the relevant drawings. The preferred embodiments of the present invention are given in the drawings. However, the present invention can be implemented in many different forms and is not limited to the embodiments described herein. On the contrary, the purpose of providing these embodiments is to make the disclosure of the present invention more thoroughly understood.
[0047] In the description of this patent, it should be understood that the terms "upper", "lower", "left", "right", "vertical", "horizontal", "longitudinal", "top", "bottom", "inside", "outside", etc., indicating the orientation or position relationship, are based on the orientation or position relationship shown in the drawings, and are only for the convenience of describing this patent and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as a limitation on this patent.
[0048] In the description of this patent, it should be noted that, unless otherwise clearly specified and limited, the terms "connection", "setting", etc. should be understood in a broad sense, for example, it can be fixed connection, setting, or detachable connection, setting, or integral connection, setting. For ordinary technicians in this field, the specific meanings of the above terms in this patent can be understood according to specific circumstances.
[0049] The present invention provides an asymmetric wall-attached construction method for a symmetrical double-arch tunnel structure of a subway, and designs a double-line dark-excavated tunnel with a small distance between subway lines as an "asymmetric wall-attached double-arch construction method". The "wall-attached method" is to excavate and support the left-line tunnel closely against the side wall of the built right-line tunnel, first simulate the standard single-hole single-line to complete the right-line excavation and support, and the secondary lining construction, and after the right-line secondary lining construction is completed, the "asymmetric wall-attached method" is used to excavate the left line, and the left line primary support and secondary lining are constructed.
[0050] The above method is described in the form of steps in the embodiments, but it should not be understood as limiting the order of the steps.
[0051] The asymmetric wall-attached construction method of the above-mentioned subway symmetrical double-arch tunnel structure comprises the following steps:
[0052] Step 1: Dig downward through the open-cut vertical shaft to the junction of the open-cut vertical shaft and the double-arch tunnel, and construct the right-line horse head gate and the left-line horse head gate of the double-arch tunnel.
[0053] Step 2: Along the designed position of the primary lining of the double-arch tunnel, a large pipe shed is built on top and a pipe shed locking beam is constructed. Figure 1The large pipe shed above the primary lining of the double-arch tunnel is a double-row large pipe shed, which is within the 180° range of the arch of the double-arch tunnel. The double-row large pipe sheds are the outer row large pipe shed 5 and the inner row large pipe shed 6. The outer row large pipe shed 5 has a larger diameter than the inner row large pipe shed 6. It is a double-row high-precision horizontal directional large pipe shed with an outer diameter of φ159 and an inner diameter of φ108. The circumferential spacing between the outer row large pipe shed 5 and the inner row large pipe shed 6 is 0.4m.
[0054] Step 3: Remove the right line horse head gate, excavate the right line step 9 and the right line lower step 10, and construct a closed-loop right line primary support steel frame, such as Figure 4 , embedded connectors 17 are arranged at the upper and lower ends of the left side of the right line primary support steel frame.
[0055] Step 4: Based on the right line primary support steel frame, construct the right line primary lining 1, and construct the right line secondary lining 2 inside the right line primary lining 1, and set a waterproof layer on the entire section between the primary lining and the secondary lining. Figure 2 The right line second lining 2 includes a right line arch portion 12 at the bottom, a vertical middle partition wall 8 is located above the left end of the right line arch portion 12, and a C-shaped right line arch portion 11 is located above the right end of the right line arch portion 12. The middle partition wall 8 and the right line arch portion 11 are constructed at the same time, and the left sides of the upper and lower ends of the middle partition wall 8 have protrusions that can smoothly connect with the left line second lining 4. Figure 2 In the first step, the right line arch portion 12 is constructed, and in the second step, the middle partition wall 8 and the right line arch portion 11 are constructed simultaneously.
[0056] Step 5: Remove the left line horse head gate, excavate the left line upper step 13 and the left line lower step 14, and build a C-shaped left line primary support steel frame on the left side of the right line primary lining 1, such as Figure 5 The upper and lower ends of the left line primary support steel frame are fixed on the embedded connecting pieces 17 of the right line primary support steel frame.
[0057] like Figure 6 The embedded connector 17 of the right line primary support steel frame includes a channel steel 22, and an embedded steel bar 24 is welded and fixed at the bottom of the channel steel 22. A channel steel 22 is provided at the end of the left line primary support steel frame, and an embedded steel bar 24 is welded and fixed at the bottom of the channel steel 22. The channel steel 22 of the embedded connector 17 is fixedly connected with the channel steel 22 of the left line primary support steel frame by bolts 23.
[0058] Step 6: Remove the right line primary support steel frame and right line primary lining located within the left line.
[0059] Step 7: Based on the left line primary support steel frame, construct the left line primary lining 3, and construct the left line secondary lining 4 inside the left line primary lining 3. Set a waterproof layer on the entire section between the primary lining and the secondary lining. Figure 2 The left line second lining 4 includes a left line arch portion 16 at the bottom, the right end of the left line arch portion 16 is connected to the bottom of the middle partition wall 8, and the left line arch portion 15 is C-shaped above the left end of the left line arch portion 16, and the top right end of the left line arch portion 15 is connected to the top of the middle partition wall 8. Figure 3 relay Figure 2 In the first and second steps, the third step is to make the left line arch portion 16, and the fourth step is to make the left line arch portion 15.
[0060] In step 3, when constructing the closed-loop right line primary support steel frame, a φ42 advance small conduit 7 is set above the upper part of the right line primary support steel frame located on the left line. With the excavation of the step 9 on the right line, a φ42 advance small conduit 7 is set every two excavation advances. Figure 1 After that, the advance small guide tube 7 is removed during the excavation of the left line upper step 13 and the left line lower step 14. As the excavation progresses, when the closed-loop right line primary support steel frame is constructed, a φ42 locking foot anchor pipe 18 is constructed on both sides of the lower part of the right line primary support steel frame, such as Figure 4 Afterwards, the locking foot anchor pipe 18 located on the left side is removed during the excavation of the left online step 13 and the left offline step 14.
[0061] In step 5, when constructing the C-shaped left line primary support steel frame, Figure 5 A φ42 locking foot anchor pipe 18 is installed on the left side of the lower part of the left line primary support steel frame.
[0062] like Figure 4 and Figure 5 The right line primary support steel frame and the left line primary support steel frame are both composed of multiple circumferential steel frame units 19 spliced together, and the splicing point is the steel frame unit connection node 20. Steel frame frame reinforcement 21 is set on the top, bottom and right side of the steel frame unit 19 of the right line primary support steel frame, and steel frame frame reinforcement 21 is set on the top, bottom and left side of the steel frame unit 19 of the left line primary support steel frame. The steel frame reinforcement 21 is used to fix the four main reinforcements of the steel frame unit 19, which can improve the rigidity and strength of the steel frame.
[0063] Special reinforcement is required in the right line second lining 2 and the left line second lining 4: Figure 7 The annular reinforcement 28 in the right line secondary lining 2 extends into the left line secondary lining 4 and is connected to the annular reinforcement 28 in the left line secondary lining 4 through the reinforcement connector 25. The vertical reinforcement 29 in the middle partition wall 8 is distributed on the left and right sides, and the middle part of the vertical reinforcement 29 is provided with longitudinal reinforcement 26 and tension reinforcement 27.
[0064] like Figure 1 After the right line primary lining 1 is constructed and before the right line secondary lining 2 is constructed, the position corresponding to the middle partition wall 8 below the right line primary lining 1 is backfilled by anchor pipe grouting. After the left line primary lining 3 is constructed and before the left line secondary lining 4 is constructed, the position corresponding to the middle partition wall 8 below the left line primary lining 3 is backfilled by anchor pipe grouting. The grouting backfill on both sides forms a grouting reinforcement area 30 below the middle partition wall 8, and the grouting reinforcement area 30 extends to both sides to below the right line inverted arch 12 and below the left line inverted arch 16.
[0065] Before the construction method in this embodiment is carried out, it is necessary to do advanced geological forecasting work. The advanced geological forecast can directly use horizontal drilling to explore the geological conditions ahead. Each cavern is arranged with four φ108 horizontal exploration holes (2 holes each above and below), with a hole depth of not less than 9m and an overlap length of not less than 3m.
[0066] The whole construction process is designed and constructed according to the principle of supporting and reinforcing first and then excavating. The single-pilot step method is used for excavation. The excavation cycle advance is strictly controlled to not exceed 0.6m, the step length is controlled, and temporary arch closure is performed. The foundation settlement of the residential building under the tunnel and the tilt of the house are monitored in detail, and a complete displacement monitoring system is established. According to the monitoring situation, temporary relocation of personnel is implemented when necessary. After each section of the double-arch tunnel is excavated, the primary support must be closed into a ring as soon as possible, and the secondary lining is constructed after the deformation of the primary support is stable. The construction length is determined according to the actual situation on site.
[0067] In the double-arch tunnel structure of this embodiment, there are only two construction joints 31, located at the upper and lower ends of the left line lining C-shaped structure. In the traditional middle-hole construction structure, each side of the lining has two construction joints, totaling four construction joints. This method improves the adverse effect of the four construction joints on the structural waterproofing of the traditional middle-hole construction arch and invert, and significantly improves the waterproofing ability of the underground structure.
[0068] The above specific examples are used to illustrate the present invention, which is only used to help understand the present invention and is not intended to limit the present invention. For those skilled in the art, according to the concept of the present invention, some simple deductions, modifications or substitutions can be made.
Claims
1. An asymmetric wall-attached construction method for a symmetrical double-arch tunnel structure of a subway, characterized in that: The method comprises the following steps: Step 1: Excavate downward through the open-cut vertical shaft to the junction of the open-cut vertical shaft and the double-arch tunnel, and construct the right-line horse head gate and the left-line horse head gate of the double-arch tunnel; Step 2: Along the designed position of the primary lining of the double-arch tunnel, a large pipe shed is built on top, and the pipe shed locking beam is constructed; Step 3: Remove the right-line horse head gate, excavate the right-line upper step (9) and the right-line lower step (10), construct a closed-loop right-line primary support steel frame, and set embedded connectors (17) at the upper and lower ends of the left side of the right-line primary support steel frame; Step 4: constructing a right line primary lining (1) based on the right line primary support steel frame, and constructing a right line secondary lining (2) inside the right line primary lining (1); the right line secondary lining (2) includes a right line inverted arch portion (12) at the bottom, a vertical middle partition wall (8) above the left end of the right line inverted arch portion (12), and a C-shaped right line arch portion (11) above the right end of the right line inverted arch portion (12); Step 5: Remove the left-line horse head gate, excavate the left-line upper step (13) and the left-line lower step (14), and construct a C-shaped left-line primary support steel frame on the left side of the right-line primary lining (1). The upper and lower ends of the left-line primary support steel frame are fixed to the embedded connectors (17) of the right-line primary support steel frame. Step 6: Remove the primary steel frame and primary lining of the right line located inside the left line; Step 7: constructing the left line primary lining (3) based on the left line primary support steel frame, and constructing the left line secondary lining (4) inside the left line primary lining (3); the left line secondary lining (4) includes a left line inverted arch portion (16) at the bottom, the right end of the left line inverted arch portion (16) is connected to the bottom of the middle partition wall (8), the left line inverted arch portion (16) is above the left end of the C-shaped left line arch portion (15), and the top right end of the left line arch portion (15) is connected to the top of the middle partition wall (8); In step 2, along the designed position of the primary lining of the double-arch tunnel, double rows of large pipe sheds are set above, within a 180° range of the arch of the double-arch tunnel; The double-row large pipe sheds are respectively an outer row large pipe shed (5) and an inner row large pipe shed (6), and the outer row large pipe shed (5) has a larger pipe diameter than the inner row large pipe shed (6); In step 3, after the closed-loop right line primary support steel frame is constructed, an advance small conduit (7) is installed above the upper part of the right line primary support steel frame located on the left line; as the step (9) on the right line is excavated, the advance small conduit (7) is installed once every two excavation feet; Afterwards, the advance small guide tube (7) is removed during the excavation of the left-line upper step (13) and the left-line lower step (14); In step 3, when constructing the closed-loop right-line primary support steel frame, locking foot anchor pipes (18) are constructed on both sides of the lower part of the right-line primary support steel frame; Afterwards, the locking foot anchor pipe (18) located on the left side is removed during the excavation of the left line upper step (13) and the left line lower step (14); The right line primary support steel frame and the left line primary support steel frame are both composed of a plurality of circumferential steel frame units (19) spliced together; Steel frame reinforcement bars (21) are arranged on the top, bottom and right side steel frame units (19) of the right line primary support steel frame, and steel frame reinforcement bars (21) are arranged on the top, bottom and left side steel frame units (19) of the left line primary support steel frame; The embedded connection piece (17) of the right line primary support steel frame comprises a channel steel (22), and the bottom of the channel steel (22) is welded and fixed with an embedded steel bar (24); A channel steel (22) is provided at the end of the left line primary support steel frame, and a pre-buried steel bar (24) is welded and fixed at the bottom of the channel steel (22); The channel steel (22) of the embedded connection piece (17) is butted against the channel steel (22) of the left line primary support steel frame and fixedly connected by bolts (23); The annular reinforcement (28) in the right-line secondary lining (2) extends into the left-line secondary lining (4) and is connected to the annular reinforcement (28) in the left-line secondary lining (4) via a reinforcement connector (25); The vertical reinforcement (29) in the middle partition wall (8) is distributed on the left and right sides, and the middle part of the vertical reinforcement (29) is provided with longitudinal reinforcement (26) and tension reinforcement (27); After the right line primary lining (1) is applied and before the right line secondary lining (2) is applied, the position corresponding to the middle partition wall (8) below the right line primary lining (1) is backfilled by anchor pipe grouting; After the left line primary lining (3) is applied and before the left line secondary lining (4) is applied, the position corresponding to the middle partition wall (8) below the left line primary lining (3) is backfilled by grouting with an anchor pipe; The grouting backfill on both sides forms a grouting reinforcement area (30) below the middle partition wall (8), and the grouting reinforcement area (30) extends to both sides below the right-line inverted arch part (12) and below the left-line inverted arch part (16).
2. The asymmetric wall-attached construction method of a symmetrical double-arch tunnel structure for a subway according to claim 1, characterized in that: In step 5, when constructing the C-shaped left-line primary support steel frame, a locking foot anchor pipe (18) is constructed on the left side of the lower part of the left-line primary support steel frame.
3. The asymmetric wall-attached construction method of a symmetrical double-arch tunnel structure for a subway according to claim 2, characterized in that: In step 4, the middle partition wall (8) and the right line arch (11) are constructed simultaneously, and the left sides of the upper and lower ends of the middle partition wall (8) have protrusions that can smoothly connect with the left line second lining (4).