Back wall construction method for pipe jacking construction
Through the combination method of high-pressure jet grouting piles and steel backing, the construction of the back wall for pipe jacking construction is simplified, which solves the problems of cumbersome construction procedures and material waste in the existing technology, and achieves the effect of shortening the construction period and significant economic benefits. , suitable for a variety of foundation soil types.
Patent Information
- Application Number
- CN202210781654.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2022-07-05
- Publication Date
- 2024-10-01
- Estimated Expiration
- 2042-07-05
AI Technical Summary
The construction process of the back wall in the existing pipe jacking construction is cumbersome and takes a long time, and it is difficult to ensure the pouring quality in soft soil foundations and complex environments, resulting in deviations during the pipe jacking process and a waste of resources in the removal of reinforced concrete.
The back wall method composed of high-pressure jet grouting piles and steel backing is adopted. By stripping off the topsoil, measuring with a total station, stacking woven soil bags with bulldozers, setting up high-pressure jet grouting piles for reinforcement, and installing mortar anchors and steel backings, Realize the rapid construction and reinforcement of the back wall.
It simplifies the construction process, shortens the cycle, saves materials and resources, meets the strength and stiffness requirements of pipe jacking construction, significantly improves economic benefits, and is suitable for a variety of foundation soil qualities.
Smart Images

Figure CN115094946B_ABST
Abstract
Description
Technical field:
[0002] The invention relates to a back wall construction method for pipe jacking construction. Background technology:
[0004] With the continuous improvement of infrastructure construction technology in my country, pipe jacking construction, as an advanced trenchless construction method, has been widely used in municipal pipelines, subways, public utilities, water and electricity applications and other construction fields due to its advantages of small construction area, environmental protection, and small disturbance to road traffic and buildings. Pipe jacking construction uses the back wall to support the jacking equipment, and the back wall plays a key supporting role in the jacking process.
[0005] Most of the existing back walls are cast-in-place reinforced concrete structures. During construction, processes such as steel bar binding, formwork erection, embedded parts installation, and concrete pouring are required. The process is relatively cumbersome and the construction period is long. If there are complex environmental factors such as soft soil and high water level in the jacking pit, the pouring construction quality of the back wall is difficult to guarantee, and the vertical straightness of the contact surface between the back wall and the jacking equipment cannot be guaranteed, resulting in deviations during the pipe jacking process. After the jacking construction is completed, the reinforced concrete of the back wall needs to be broken, which wastes resources. Summary of the invention:
[0007] The technical problem to be solved by the present invention is to provide a back wall construction method for pipe jacking construction which has simple construction process, low engineering cost, short construction period and meets the strength and rigidity required for pipe jacking construction.
[0008] In order to solve the above technical problems, the present invention adopts the following technical solutions:
[0009] The back wall is composed of high-pressure jet grouting piles and steel back.
[0010] The first step is to strip the original surface soil to facilitate the later reclamation and backfilling;
[0011] The excavation boundary line of the construction area was measured and marked with white lime lines using a total station. Following the principle of "blocking first and abandoning later", woven earthbags were piled up as temporary retaining walls, and bulldozers were used to strip the topsoil according to design requirements and transport it to the retaining wall for storage.
[0012] The second step is to use high-pressure jet grouting piles to reinforce the soft soil foundation;
[0013] There are two rows of high-pressure rotary jet piles in the front and back rows. The number of high-pressure rotary jet piles in the back row is one more than that in the front row. The depth of each high-pressure rotary jet pile is 15m and the diameter is 150cm. The line between the centers of all high-pressure rotary jet piles in the front row is parallel to the line between the centers of all high-pressure rotary jet piles in the back row, and the distance between them is 120cm. The distance between the centers of two adjacent high-pressure rotary jet piles in the front row is 120cm, and the distance between the centers of two adjacent high-pressure rotary jet piles in the back row is also 120cm. The center of each high-pressure rotary jet pile in the front row is aligned with the middle of the overlapping part of the two adjacent high-pressure rotary jet piles in the back row, so that there is partial overlap between the adjacent high-pressure rotary jet piles in the front row, between the adjacent high-pressure rotary jet piles in the back row, and between the adjacent high-pressure rotary jet piles in the front row and the back row. Before construction, the control points of the high-pressure rotary jet pile construction are determined with a total station to ensure that the displacement deviation of the center of the high-pressure rotary jet pile hole is less than 50mm. After the pilot hole is drilled to the designed depth, the jet grouting pipe is inserted into the hole and the jetting is performed from bottom to top. When the jet grouting pipe is lifted to the designed pile top elevation, the jetting is stopped, the drill outlet is lifted, the grouting pump and the delivery pipeline are cleaned, and then the drilling rig is moved. In order to prevent the adjacent high-jet holes from being slurried due to the close construction distance or short interval between the two adjacent piles during the jet grouting pile construction, the jet grouting piles should be constructed in alternate holes, and the construction of each jet grouting pile is completed in sequence to obtain a high-pressure jet grouting pile wall.
[0014] Step 3;
[0015] After the high-pressure jet grouting pile construction is completed, the foundation pit will be excavated after the jet grouting pile has a certain strength. The foundation pit is deep, so in order to ensure safety and arrange mechanical construction reasonably, layered excavation is adopted, and the slope is cut while excavating. The excavation is stopped when the excavation is 20 to 30 cm away from the designed foundation surface, and this part will be manually excavated before the installation of the jacking guide rail.
[0016] Step 4:
[0017] Make several holes on the jet-jet pile wall and install mortar anchor rods in the holes (fill the holes with cement mortar before installing the mortar anchor rods);
[0018] The steel back is made of the following structure: multiple HW125 steel sections are welded to form a grid rib, where the spacing between adjacent steel sections on the left and right is 1.2 meters, and the spacing between adjacent steel sections on the top and bottom is also 1.2 meters. Then, 20mm thick steel plates are welded on the six surfaces of the grid rib, and a lifting ring is welded on the top of the steel plate to facilitate the lifting and installation of the steel back.
[0019] The steel back is placed in front of the jet grouting pile wall, and the mortar anchor rod passes through the steel back and is welded to the steel back to prevent it from tipping over. The gap between the steel back and the jet grouting pile wall is filled with crushed stone to facilitate the transmission of the jacking force to all the back piles.
[0020] Then install the jacking guide rail and weld the jacking guide rail and the steel back together to prevent the jacking guide rail from shifting during the pipeline jacking process.
[0021] The advantages of the present invention are: compared with cast-in-place concrete back wall, this method saves a lot of steel, concrete and other materials, and the steel back can be used in a cyclical manner, saving resources. The project cost is low, the construction period is short, the strength and rigidity required for pipe jacking construction are met, and the economic benefits are significant.
[0022] The construction method has simple procedures and low engineering cost, and is widely applicable to soft soil foundations, and can be used for foundations such as silt, silty soil, clay, silty soil, loess, sandy soil, artificial fill and crushed stone soil. Description of the drawings:
[0024] Figure 1 It is a schematic diagram of the top view of the back wall in the present invention;
[0025] Figure 2 It is a side structural schematic diagram of the back wall in the present invention. Specific implementation method:
[0027] Combine the following Figure 1 and Figure 2 The present invention is further described;
[0028] The back wall is composed of high-pressure jet grouting piles 1 and steel back 2.
[0029] The first step is to strip the original surface soil to facilitate the later reclamation and backfilling;
[0030] The excavation boundary line of the construction area was measured and marked with white lime lines using a total station. Following the principle of "blocking first and abandoning later", woven earthbags were piled up as temporary retaining walls, and bulldozers were used to strip the topsoil according to design requirements and transport it to the retaining wall for storage.
[0031] The second step is to use high-pressure jet grouting piles to reinforce the soft soil foundation;
[0032] There are two rows of high-pressure rotary jet piles in the front and back rows. The number of high-pressure rotary jet piles in the back row is one more than that in the front row. The depth of each high-pressure rotary jet pile is 15m and the diameter is 150cm. The line between the centers of all high-pressure rotary jet piles in the front row is parallel to the line between the centers of all high-pressure rotary jet piles in the back row, and the distance between them is 120cm. The distance between the centers of two adjacent high-pressure rotary jet piles in the front row is 120cm, and the distance between the centers of two adjacent high-pressure rotary jet piles in the back row is also 120cm. The center of each high-pressure rotary jet pile in the front row is aligned with the middle of the overlapping part of the two adjacent high-pressure rotary jet piles in the back row, so that there is partial overlap between the adjacent high-pressure rotary jet piles in the front row, between the adjacent high-pressure rotary jet piles in the back row, and between the adjacent high-pressure rotary jet piles in the front row and the back row. Before construction, the control points of the high-pressure rotary jet pile construction are determined with a total station to ensure that the displacement deviation of the center of the high-pressure rotary jet pile hole is less than 50mm. The construction of jet grouting piles uses XY-150 geological drilling rigs to guide holes and XP-30B jet grouting machines. After the guide hole is drilled to the designed depth, the jet grouting pipe is inserted into the hole and jetted from bottom to top. To ensure the quality of the bottom of the pile, when the nozzle of the jet grouting pipe sinks to the designed depth, it rotates in the original position for about 15 seconds, and then the jet grouting is lifted after the grouting from the hole is normal. The jet grouting time is appropriately increased within 2m from the bottom of the pile to improve the quality of the bottom of the pile. When the jet grouting pipe is lifted to the designed pile top elevation, the jet grouting is stopped, the drill bit outlet is lifted, the grouting pump and the delivery pipeline are cleaned, and then the drilling rig is moved. In order to prevent the adjacent high-spraying holes from being constructed due to the close construction distance or short interval time between the adjacent piles during the construction of the jet grouting pile, the jet grouting pile should be constructed in alternate holes, and the construction of each jet grouting pile is completed by analogy to obtain a high-pressure jet grouting pile wall.
[0033] Step 3;
[0034] After the high-pressure jet grouting pile construction is completed, the foundation pit will be excavated after the jet grouting pile has a certain strength. The foundation pit is deep, so in order to ensure safety and arrange mechanical construction reasonably, layered excavation is adopted, and the slope is cut while excavating. The excavation is stopped when the excavation is 20 to 30 cm away from the designed foundation surface, and this part will be manually excavated before the installation of the jacking guide rail.
[0035] Step 4:
[0036] Use a YT-28 pneumatic drill to make several holes on the jet-jet pile wall, and install mortar anchor rods 3 in the holes (fill the holes with cement mortar before installing the mortar anchor rods);
[0037] The steel back is made of the following structure: multiple HW125 steel sections are welded to form a grid rib, where the spacing between adjacent steel sections on the left and right is 1.2 meters, and the spacing between adjacent steel sections on the top and bottom is also 1.2 meters. Then, 20mm thick steel plates are welded on the six surfaces of the grid rib, and a lifting ring is welded on the top of the steel plate to facilitate the lifting and installation of the steel back.
[0038] The steel back is placed in front of the jet grouting pile wall, and the mortar anchor rod passes through the steel back and is welded to the steel back to prevent it from tipping over. The gap between the steel back and the jet grouting pile wall is filled with crushed stone 4 to facilitate the transmission of the jacking force to all the back piles.
[0039] Then install the jacking guide rail 5, and weld the jacking guide rail and the steel back together to prevent the jacking guide rail from shifting during the pipeline jacking process.
[0040] The above is only a preferred embodiment of the present invention. It should be pointed out that for ordinary technicians in this technical field, several improvements and modifications can be made without departing from the technical principles of the present invention. These improvements and modifications should also be regarded as the scope of protection of the present invention.
Claims
1. A back wall construction method for pipe jacking construction, characterized by: The back wall is composed of high-pressure jet grouting piles (1) and a steel back wall (2); Construction process: The first step is to strip the original surface soil to facilitate the later reclamation and backfilling; The second step is to use high-pressure jet grouting piles to reinforce the soft soil foundation; Set front and rear two rows of high-pressure rotary jet piles, the number of the back row of high-pressure rotary jet piles is one more than the number of the front row of high-pressure rotary jet piles, the pile depth of each high-pressure rotary jet pile is 15m, the pile diameter is 150cm, the connecting line between the center of the circle of all the high-pressure rotary jet piles in the front row and the connecting line between the center of the circle of all the high-pressure rotary jet piles in the back row are parallel to each other, and the distance between them is 120cm; the distance between the center of the circle of two adjacent high-pressure rotary jet piles in the front row is 120cm, and the distance between the center of the circle of two adjacent high-pressure rotary jet piles in the back row is also 120cm, and the center of the circle of each high-pressure rotary jet pile in the front row is aligned with the middle of the overlapping part of the two adjacent high-pressure rotary jet piles in the back row, so that part of the high-pressure rotary jet piles adjacent to the front row, between the high-pressure rotary jet piles adjacent to the back row, and between the front row and the back row are partially overlapped; After the lead hole is drilled to the designed depth, the jet grouting pipe is inserted into the hole, rotary jetting is performed from bottom to top, and the rotary jet piles are constructed in intervals, and the construction of each rotary jet pile is completed by analogy to obtain a high-pressure rotary jet pile wall; Step 3; After the high-pressure jet grouting pile construction is completed and the jet grouting pile has a certain strength, the foundation pit is excavated. The foundation pit is excavated in layers, and the slope is lowered while excavating. The excavation is stopped when the excavation is 20 to 30 cm away from the designed foundation surface. This part is manually excavated before the installation of the jacking guide rail. Step 4: Making a number of holes on the jet-jet pile wall and installing mortar anchor rods (3) in the holes; The steel back is made. The structure of the steel back is: a grid rib is formed by welding a plurality of steel sections, steel plates are welded on the six sides of the grid rib, and a lifting ring is welded on the top of the steel plate; The steel back is placed in front of the jet grouting pile wall, and the mortar anchor rod passes through the steel back and is welded to the steel back. The gap between the steel back and the jet grouting pile wall is filled with crushed stone (4). Then install the jacking guide rail (5) and weld the jacking guide rail and the steel back together.