Alternating construction method for secondary lining structure of large cross-section tunnel

By dividing the tunnel into first and second construction zones, alternating the construction of the invert arch and the removal of the supporting structure, and using steel frame and concrete support, the problems of safety and efficiency in the construction of large-section tunnels were solved, and safe and efficient construction was achieved.

CN115095351BActive Publication Date: 2024-11-08CHINA CONSTR EIGHTH BUREAU NORTHWEST CONSTR CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202210656302.9
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2022-06-10
Publication Date
2024-11-08
Estimated Expiration
2042-06-10

AI Technical Summary

Technical Problem

In the current technology, it is difficult to balance construction safety and efficiency during the secondary lining construction of large-section tunnels. Excessive removal of supporting structures can easily lead to tunnel collapse accidents.

Method used

The tunnel was divided into first and second construction zones. The invert arch was constructed alternately and the supporting structure was dismantled. Steel frame and concrete structure support were used. The arch wall was constructed alternately using formwork trolleys to ensure the continuity of the supporting structure and reduce the length of dismantling.

Benefits of technology

It improved construction efficiency, ensured the safety of large-section tunnel construction, avoided tunnel collapse accidents, and reduced the impact of dismantling support structures on tunnel stability.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN115095351B_ABST
    Figure CN115095351B_ABST
Patent Text Reader

Abstract

The present invention relates to an alternating construction method for a secondary lining structure of a large-section tunnel, comprising: dividing the tunnel into a first construction area and a second construction area, dividing the first construction area into a plurality of first construction sections, and dividing the second construction area into a plurality of second construction sections; constructing the inverts of the first construction section and the second construction section located in the middle of the tunnel, and removing the supporting structures of the first construction section and the second construction section located in the middle of the tunnel; constructing an arch wall on the current first construction section, and constructing the invert of the next first construction section and removing the supporting structure at the same time, and then constructing an arch wall on the current second construction section, and constructing the invert of the next second construction section and removing the supporting structure at the same time, and repeating this step to alternately construct the first construction section and the second construction section from the middle of the tunnel to both ends until the construction of the entire secondary lining structure is completed. The present application avoids the problem of collapse accidents of large-section tunnels due to excessive removal of supporting structures, and improves construction efficiency.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of tunnel construction, in particular to an alternating construction method for a large-section tunnel secondary lining structure. Background Art

[0002] At present, the secondary lining construction of domestic dark-excavated tunnels has basically achieved mechanized operation, usually using mobile formwork trolleys for formwork. It has a fast construction speed and good concrete molding quality, and has been widely used by construction units.

[0003] In the prior art, the secondary lining of a tunnel is usually constructed in sequence. For a small-section tunnel, the temporary support structure of the three construction sections can be removed at once, and then the steel bars are tied and the formwork trolley is moved to pour concrete to speed up the construction progress. However, for a large-section tunnel, the temporary support structure of the three construction sections is removed at the same time, and the settlement and deformation of the tunnel are significantly increased, which is easy to cause tunnel collapse accidents. Therefore, how to ensure the construction safety of the secondary lining of a large-section tunnel and improve the construction efficiency is an urgent problem to be solved in this application. Summary of the invention

[0004] The purpose of the present invention is to overcome the defects of the prior art and provide an alternating construction method for the secondary lining structure of a large-section tunnel, so as to solve the problem that the existing construction method for the secondary lining of a large-section tunnel cannot both ensure construction safety and improve construction efficiency.

[0005] To achieve the above object, the present invention provides an alternating construction method for a large-section tunnel secondary lining structure, comprising the following steps:

[0006] Divide the tunnel into a first construction area and a second construction area at the midpoint of the tunnel, divide the first construction area into a plurality of first construction sections, and divide the second construction area into a plurality of second construction sections, and the second construction sections correspond to the first construction sections one by one;

[0007] Construct the inverts of the first construction section and the second construction section in the middle of the tunnel, and dismantle the supporting structures of the first construction section and the second construction section in the middle of the tunnel;

[0008] An arch wall is constructed on the current first construction section and connected with the invert on the current first construction section, and at the same time, an invert of the next first construction section is constructed and the supporting structure of the next first construction section is removed, and then an arch wall is constructed on the current second construction section and connected with the invert on the current second construction section, and at the same time, an invert of the next second construction section is constructed and the supporting structure of the next second construction section is removed, and this step is repeated from the middle of the tunnel to both ends, alternating between the first construction section and the second construction section until the construction of the entire secondary lining structure is completed.

[0009] The present invention divides a tunnel into a first construction area and a second construction area, and construction is performed alternately in the first construction area and the second construction area. Except for the first construction section and the second construction section located in the middle of the tunnel, the supporting structures on the remaining first construction section and the second construction section are all discontinuous, so as to avoid the support structures of two continuous construction sections being dismantled at the same time and reduce the dismantling length of the support structures. Since each time the arch wall of a construction section on one side is cast, the invert arch of the next construction section on the side is constructed and the supporting structure of the next construction section on the side is dismantled at the same time, when the arch wall is cast and formed, the adjacent supporting structures are basically dismantled, so as to ensure that only the supporting structures of the two construction sections are always dismantled, and the problem of collapse accidents of large-section tunnels caused by excessive dismantling of supporting structures is avoided. Since casting and dismantling are performed simultaneously, the construction efficiency is greatly improved, and the safety of large-section tunnel construction is also guaranteed.

[0010] A further improvement of the alternating construction method of the secondary lining structure of a large-section tunnel of the present invention is that the support structure comprises a steel frame fixedly connected to the inner wall of the primary support and a concrete structure wrapped around the outside of the steel frame, and the steel frame is supported between the top wall, the bottom wall and the two side walls of the primary support;

[0011] When constructing the inverted arch, a portion of the concrete structure connected to the primary support bottom wall on the supporting structure is chiseled off to partially expose the steel frame to form a connecting end;

[0012] The first steel bar structure of the invert is tied, the first steel bar structure is fixedly connected to the connection end, concrete is poured to form an invert concrete layer and the first steel bar structure and the connection end are buried.

[0013] A further improvement of the alternating construction method of the secondary lining structure of a large-section tunnel of the present invention is that, when constructing the invert, part of the concrete structure on the supporting structure connected to the primary support top wall and both side walls is chiseled off to partially expose the steel frame to form an exposed end.

[0014] A further improvement of the alternating construction method of the secondary lining structure of a large-section tunnel of the present invention is that when dismantling the supporting structure, the portion of the supporting structure other than the connecting end and the exposed end is dismantled.

[0015] A further improvement of the alternating construction method of the secondary lining structure of a large-section tunnel of the present invention is that, when constructing the arch wall, the second steel bar structure of the arch wall is tied to fix the second steel bar structure to the first steel bar structure;

[0016] Concrete is poured to form an arch wall concrete layer and the second steel bar structure is embedded, so that the arch wall concrete layer and the inverted arch concrete layer are connected as a whole.

[0017] A further improvement of the alternating construction method of the secondary lining structure of a large-section tunnel of the present invention is that the support structure includes a horizontal support fixedly connected to both side walls of the tunnel and arranged horizontally, an upper support fixedly connected between the middle of the horizontal support and the top wall of the primary support, and a lower support fixedly connected between the middle of the horizontal support and the bottom wall of the primary support;

[0018] Before tying the second steel bar structure, an operating frame is provided, and the operating frame is installed and fixed on the horizontal support, and the setting direction of the operating frame is consistent with the design direction of the tunnel.

[0019] A further improvement of the alternating construction method of the secondary lining structure of a large-section tunnel of the present invention is that the operating frames are arranged in two rows and are symmetrically distributed on both sides of the upper support.

[0020] A further improvement of the alternating construction method of the secondary lining structure of a large-section tunnel of the present invention is that after the construction of the invert is completed, a support frame is provided, the top support of the support frame is fixed between the invert and the support structure, and the setting direction of the support frame is consistent with the design direction of the tunnel.

[0021] A further improvement of the alternating construction method of the secondary lining structure of a large-section tunnel of the present invention is that the support frames are arranged in two rows symmetrically with respect to the tunnel center line.

[0022] A further improvement of the alternating construction method of the secondary lining structure of a large-section tunnel of the present invention is that after the construction of the invert is completed, concrete is poured on the invert to form a backfill structure, and the top surface of the backfill structure is made horizontal.

[0023] A further improvement of the alternating construction method of the secondary lining structure of a large-section tunnel of the present invention is that an assembled formwork trolley is provided, and the casting construction of the arch wall is alternately performed on the first construction section and the second construction section by moving the formwork trolley. BRIEF DESCRIPTION OF THE DRAWINGS

[0024] Figure 1 The present invention is a flow chart of the alternating construction method of the secondary lining structure of a large-section tunnel.

[0025] Figure 2 This is a state diagram after a portion of the concrete structure connected to the primary support on the supporting structure is chiseled out in the alternating construction method of the secondary lining structure of a large-section tunnel of the present invention.

[0026] Figure 3 This is a state diagram of the alternating construction method of the secondary lining structure of a large-section tunnel of the present invention after the support frame and the operating frame are installed.

[0027] Figure 4This is a state diagram of the alternating construction method of the secondary lining structure of a large-section tunnel of the present invention when a formwork trolley is used to cast the arch wall of the first construction section located in the middle of the tunnel.

[0028] Figure 5 This is a state diagram of the alternating construction method of the secondary lining structure of a large-section tunnel of the present invention when a formwork trolley is used to cast the arch wall of the second construction section located in the middle of the tunnel.

[0029] Figure 6 This is a state diagram of the alternating construction method of the secondary lining structure of a large-section tunnel of the present invention when a formwork trolley is used to cast the arch wall of the next first construction section adjacent to the first construction section in the middle of the tunnel.

[0030] Figure 7 This is a state diagram of the alternating construction method of the secondary lining structure of a large-section tunnel of the present invention when a formwork trolley is used to cast the arch wall of the next second construction section adjacent to the second construction section in the middle of the tunnel.

[0031] Explanation of symbols: tunnel 10, first construction area 11, first construction section 111, second construction area 12, second construction section 121, supporting structure 20, steel frame 21, horizontal support 22, upper support 23, lower support 24, secondary lining structure 30, invert 31, primary support 40, operating frame 50, supporting frame 60, backfill structure 70, formwork trolley 80. DETAILED DESCRIPTION

[0032] In order to make the purpose, technical scheme and advantages of the present invention more clearly understood, the present invention is further described in detail below in conjunction with the accompanying drawings and embodiments. It should be understood that the specific embodiments described herein are only used to explain the present invention and are not intended to limit the present invention. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without making creative work are within the scope of protection of the present invention.

[0033] The present invention provides an alternating construction method for a secondary lining structure of a large-section tunnel. The template trolley is assembled in the middle part of the interval tunnel, and the secondary lining structure is constructed alternately in a first construction section and a second construction section. The dismantling length of the supporting structure does not exceed 2 sections, thereby avoiding the problem of collapse accidents of large-section tunnels due to excessive dismantling of the supporting structure. The synchronous alternating construction also improves the construction efficiency.

[0034] The alternating construction method of the secondary lining structure of a large-section tunnel of the present invention is described below with reference to the accompanying drawings.

[0035] See also Figure 1 , Figures 4 to 7 In this embodiment, a large-section tunnel secondary lining structure alternating construction method includes:

[0036] S101: Divide the tunnel 10 into a first construction area 11 and a second construction area 12 based on the midpoint of the tunnel 10, divide the first construction area 11 into a plurality of first construction sections 111, and divide the second construction area 12 into a plurality of second construction sections 121, and the second construction sections 121 correspond to the first construction sections 111 one to one;

[0037] S102: constructing the invert 31 of the first construction section 111 and the second construction section 121 located in the middle of the tunnel 10, and dismantling the supporting structure 20 of the first construction section 111 and the second construction section 121 located in the middle of the tunnel 10;

[0038] S103: construct an arch wall on the current first construction section 111 and connect it with the inverted arch 31 on the current first construction section 111, and at the same time construct the inverted arch 31 of the next first construction section 111 and remove the supporting structure 20 of the next first construction section 111, then construct an arch wall on the current second construction section 121 and connect it with the inverted arch 31 on the current second construction section 121, and at the same time construct the inverted arch 31 of the next second construction section 121 and remove the supporting structure 20 of the next second construction section 121, repeat this step from the middle of the tunnel 10 to both ends, alternately constructing on the first construction section 111 and the second construction section 121 until the construction of the entire secondary lining structure 30 is completed.

[0039] In the construction method of this embodiment, the secondary lining structure 30 is constructed alternately on the first construction section 111 and the second construction section 121 from the middle of the tunnel 10 to both ends. Compared with the method of continuously constructing the secondary lining structure 30 from one end of the tunnel 10 to the other end in the prior art, it can avoid the continuous dismantling of the supporting structure 20 for a long time and affecting the stability of the tunnel 10. Since the next invert arch 31 is constructed and the next supporting structure 20 is dismantled synchronously when the arch wall is constructed, the construction efficiency is improved, the construction progress is accelerated, and the safety of the construction of the large-section tunnel 10 is guaranteed.

[0040] See also Figure 2 In a specific embodiment, the support structure 20 includes a steel frame 21 fixedly connected to the inner wall of the primary support 40 and a concrete structure wrapped around the outside of the steel frame 21, and the steel frame 21 is supported between the top wall, the bottom wall and the two side walls of the primary support 40;

[0041] When constructing the inverted arch 31, a portion of the concrete structure on the supporting structure 20 connected to the bottom wall of the primary support 40 is chiseled off to partially expose the steel frame 21 to form a connecting end;

[0042] The first steel bar structure of the inverted arch 31 is tied, the first steel bar structure is fixedly connected to the connecting end, and concrete is poured to form a concrete layer of the inverted arch 31 and bury the first steel bar structure and the connecting end.

[0043] Since only a portion of the concrete structure connected to the bottom wall of the primary support 40 on the supporting structure 20 is chiseled out, it is ensured that the steel frame 21 of the supporting structure 20 is still supported in the tunnel 10, and the first steel structure of the invert 31 is fixedly connected to the connecting end of the steel frame 21 to ensure that the invert 31 formed by the construction is connected to the supporting structure 20 as a whole to ensure the stability of the supporting structure 20.

[0044] See also Figure 2 Furthermore, when constructing the inverted arch 31, part of the concrete structure on the supporting structure 20 connected to the top wall and the two side walls of the primary support 40 is chiseled off to partially expose the steel frame 21 to form an exposed end.

[0045] Since only a portion of the concrete structure connected to the top wall and the two side walls of the primary support 40 on the supporting structure 20 is chiseled out, it is ensured that the steel frame 21 of the supporting structure 20 is still supported in the tunnel 10 .

[0046] Preferably, the length of the end of the supporting structure 20 chiseled off is 1 m.

[0047] Furthermore, when the support structure 20 is removed, the portion of the support structure 20 except the connecting end and the exposed end is removed.

[0048] Furthermore, when constructing the arch wall, the second steel bar structure of the arch wall is tied to fix the second steel bar structure to the first steel bar structure;

[0049] Concrete is poured to form an arch wall concrete layer and the second steel bar structure is embedded, so that the arch wall concrete layer and the invert arch 31 concrete layer are connected as a whole.

[0050] Furthermore, before tying the second steel bar structure of the arch wall, the waterproof layer of the arch wall is constructed.

[0051] The second steel reinforcement structure of the arch wall is fixedly connected to the first steel reinforcement structure of the invert 31 to enhance the firmness of the connection between the arch wall and the invert 31 and form an integral secondary lining structure 30.

[0052] See also Figure 3In a specific embodiment, the support structure 20 includes a horizontal support 22 fixedly connected to the two side walls of the tunnel 10 and arranged horizontally, an upper support 23 fixedly connected between the middle of the horizontal support 22 and the top wall of the primary support 40, and a lower support 24 fixedly connected between the middle of the horizontal support 22 and the bottom wall of the primary support 40;

[0053] Before tying the second steel bar structure, an operating frame 50 is provided and fixed on the horizontal support 22, and the setting direction of the operating frame 50 is consistent with the design direction of the tunnel 10. The operating frame 50 serves as an operating platform for tying the second steel bar structure of the arch wall, which facilitates the construction operation of the workers.

[0054] See also Figure 3 Preferably, the operating frame 50 is a scaffolding, on which a platform board is provided, and on both sides of the platform board a row of height-adjustable columns are provided, and a wire rope protection net is hung on each row of columns, and the columns can be adjusted in height according to the height of the space in the tunnel.

[0055] Preferably, the operating frames 50 are arranged in two rows and are symmetrically distributed on both sides of the upper support 23 .

[0056] See also Figure 3 Further, after the construction of the inverted arch 31 is completed, a support frame 60 is provided, and the support frame 60 is supported and fixed between the inverted arch 31 and the support structure 20, and the setting direction of the support frame 60 is consistent with the design direction of the tunnel 10. The support frame 60 plays a role of temporary support for the support structure 20, ensuring the support effect of the support structure 20.

[0057] Furthermore, the support frames 60 are arranged in two rows and are symmetrically disposed about the center line of the tunnel 10 .

[0058] See also Figure 2 In a specific embodiment, after the construction of the inverted arch 31 is completed, concrete is poured on the inverted arch 31 to form a backfill structure 70, and the top surface of the backfill structure 70 is made horizontal to facilitate the installation of the support frame 60 on the backfill structure 70.

[0059] See also Figures 4 to 7 Furthermore, an assembled formwork trolley 80 is provided, and the formwork trolley 80 is moved to alternately perform the pouring construction of the arch wall on the first construction section 111 and the second construction section 121.

[0060] Preferably, the secondary lining structure 30 is arranged on the primary lining structure on the tunnel 10 .

[0061] In this embodiment, the middle part of the tunnel 10 is a construction well, and the parts of the template trolley 80 can be hoisted in the tunnel 10 through the construction well. The space required for assembling the template trolley 80 is relatively large. The supporting structure 20 of the first construction section 111 and the second construction section 121 located in the middle part of the tunnel 10 is first dismantled to provide sufficient assembly space for the template trolley 80. The length of the assembled template trolley 80 is the length of one construction section, that is, the length of the first construction section 111, the length of the second construction section 121 and the length of the template trolley 80 are all equal.

[0062] By adopting the above technical solution, the present invention has the following beneficial effects:

[0063] The present invention is particularly suitable for tunnel 10 projects with shallow buried and dark excavation, large cross-section, poor engineering geological conditions, large ground traffic flow, and strict control of settlement and deformation. For tunnel 10 projects with greater pressure on the construction period, the second lining penetration construction can be quickly realized. It is of great significance in controlling the deformation of the tunnel 10 and increasing the construction efficiency. The temporary support and then removal technology is adopted to carry out the waterproofing and reinforcement construction of the template trolley 80 sections, and no more than 2 sections are removed at a time on a single side. The temporary support is removed before the trolley cycle construction to reduce ground settlement. Due to the limited space inside the tunnel 10, this application only uses one template trolley 80, which reduces the construction cost on the one hand, and on the other hand, during the construction process, the template trolley 80 is moved to alternately perform the pouring construction of the arch wall on the first construction section 111 and the second construction section 121, avoiding the idle waiting of the template trolley 80, ensuring that the template trolley 80 can be fully utilized for back and forth pouring construction, improving the construction efficiency, and avoiding the problem of excessive removal of the support structure 20 causing the collapse of the tunnel 10.

[0064] It should be noted that the structures, proportions, sizes, etc. illustrated in the drawings of this specification are only used to match the contents disclosed in the specification for people familiar with this technology to understand and read, and are not used to limit the limiting conditions for the implementation of the present invention, so they have no substantial technical significance. Any modification of the structure, change of the proportion relationship or adjustment of the size should still fall within the scope of the technical content disclosed by the present invention without affecting the effects and purposes that can be achieved by the present invention. At the same time, the terms such as "upper", "lower", "left", "right", "middle" and "one" quoted in this specification are only for the convenience of description, and are not used to limit the scope of the implementation of the present invention. The change or adjustment of their relative relationship should also be regarded as the scope of the implementation of the present invention without substantially changing the technical content.

Claims

1. An alternating construction method for a large-section tunnel secondary lining structure, characterized in that: The steps include: Divide the tunnel into a first construction area and a second construction area at the midpoint of the tunnel, divide the first construction area into a plurality of first construction sections, and divide the second construction area into a plurality of second construction sections, and the second construction sections correspond to the first construction sections one by one; Construct the inverts of the first construction section and the second construction section in the middle of the tunnel, and dismantle the supporting structures of the first construction section and the second construction section in the middle of the tunnel; Constructing an arch wall on the current first construction section and connecting it with the invert on the current first construction section, constructing the invert of the next first construction section and removing the supporting structure of the next first construction section at the same time, then constructing an arch wall on the current second construction section and connecting it with the invert on the current second construction section, constructing the invert of the next second construction section and removing the supporting structure of the next second construction section at the same time, repeating this step from the middle of the tunnel to both ends, alternately constructing on the first construction section and the second construction section until the construction of the entire secondary lining structure is completed; The support structure includes a steel frame fixedly connected to the inner wall of the primary support and a concrete structure wrapped around the outside of the steel frame, and the steel frame is supported between the top wall, the bottom wall and the two side walls of the primary support; When constructing the inverted arch, a portion of the concrete structure connected to the primary support bottom wall on the supporting structure is chiseled off to partially expose the steel frame to form a connecting end; Binding the first steel bar structure of the inverted arch, fixedly connecting the first steel bar structure to the connecting end, pouring concrete to form an inverted arch concrete layer and burying the first steel bar structure and the connecting end; When constructing the arch wall, tying the second steel bar structure of the arch wall to fix the second steel bar structure to the first steel bar structure; pouring concrete to form an arch wall concrete layer and burying the second steel bar structure so that the arch wall concrete layer and the inverted arch concrete layer are connected as one; The support structure includes a horizontal support fixedly connected to both side walls of the tunnel and arranged horizontally, an upper support fixedly connected between the middle of the horizontal support and the primary support top wall, and a lower support fixedly connected between the middle of the horizontal support and the primary support bottom wall; Before tying the second steel bar structure, provide an operating frame, install and fix the operating frame on the horizontal support, and make the setting direction of the operating frame consistent with the design direction of the tunnel; The operating frame is a scaffolding, which is provided with a platform board. A row of height-adjustable columns are provided on both sides of the platform board. A wire rope protection net is hung on each row of the columns. The columns can be adjusted in height according to the height of the space in the tunnel.

2. The alternating construction method for the secondary lining structure of a large-section tunnel according to claim 1, characterized in that: When constructing the inverted arch, part of the concrete structure connected to the primary support top wall and the two side walls on the supporting structure is chiseled off to partially expose the steel frame to form an exposed end.

3. The alternating construction method for the secondary lining structure of a large-section tunnel according to claim 2, characterized in that: When removing the supporting structure, the portion of the supporting structure other than the connecting end and the exposed end is removed.

4. The alternating construction method for the secondary lining structure of a large-section tunnel according to claim 1, characterized in that: The operating frames are arranged in two rows and are symmetrically distributed on both sides of the upper support.

5. The alternating construction method for the secondary lining structure of a large-section tunnel according to claim 1, characterized in that: After the construction of the invert is completed, a support frame is provided, and the top support of the support frame is fixed between the invert and the supporting structure, and the setting direction of the support frame is consistent with the design direction of the tunnel.

6. The alternating construction method for the secondary lining structure of a large-section tunnel according to claim 1, characterized in that: After the construction of the inverted arch is completed, concrete is poured on the inverted arch to form a backfill structure, and the top surface of the backfill structure is made horizontal.

7. The alternating construction method for the secondary lining structure of a large-section tunnel according to claim 1, characterized in that: An assembled formwork trolley is provided, and the pouring construction of the arch wall is alternately performed on the first construction section and the second construction section by moving the formwork trolley.