Construction method of reinforced concrete and ceramic particles for landscape bridge and its deck structure

Through the combined construction method of reinforced concrete and ceramic particles, the problems of high cost, poor aesthetics and difficult maintenance in landscape bridge paving technology are solved, and a wear-resistant and slip-resistant bridge deck structure is realized, which improves the landscape effect and walking texture. Reduced maintenance costs.

CN115162160BActive Publication Date: 2024-12-06YUNNAN ZHONGHANG CONSTRUCT CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202210731037.6
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2022-06-24
Publication Date
2024-12-06
Estimated Expiration
2042-06-24

AI Technical Summary

Technical Problem

The existing landscape bridge paving technology has problems such as high cost, limited equipment operating environment, poor aesthetics, poor environmental coordination, poor walking texture, and difficult to maintain after cracking and damage of the bridge deck.

Method used

Using the combined construction method of reinforced concrete and ceramic particles, by dividing grids on the bridge deck and welding shear nails, setting up precast concrete pads and steel mesh, pouring concrete layers, and laying glass fiber crack-proof mesh and PUNM on them. Polyurethane adhesive is finally spread with ceramic particles to form a wear-resistant and slip-resistant surface ceramic particle layer.

Benefits of technology

It realizes the safety and durability of the structure, avoids water seepage and rust on the base layer, improves the landscape effect and walking texture, reduces maintenance costs, and is suitable for indoor and outdoor use.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure HDA0003713469920000011
    Figure HDA0003713469920000011
  • Figure HDA0003713469920000012
    Figure HDA0003713469920000012
  • Figure HDA0003713469920000021
    Figure HDA0003713469920000021
Patent Text Reader

Abstract

The present application discloses a construction method of reinforced concrete and ceramic particles for a landscape bridge and its bridge deck structure, including the following steps: step S20: setting a shear nail layer according to the requirements of the design drawings; step S30: arranging a plurality of precast concrete pads in a plum blossom shape on the bridge deck; step S40: fully tying φ12 steel mesh on the top surface of the precast concrete pads along the longitudinal and transverse directions of the bridge deck; step S50: pouring concrete to form a concrete layer; step S60: fully paving a glass fiber anti-cracking net on the top surface of the concrete layer; step S70: using a scraping tool to evenly apply the evenly mixed PUNM polyurethane adhesive on the glass fiber anti-cracking net; step S80: evenly spreading ceramic particles on the top surface of the sealing bottom layer; step S90: paving the surface layer ceramic particle mixture and finishing the cover surface. The bridge deck composite structure obtained by the construction method has mature construction technology of base bolts + reinforced concrete, good integrity, safe structure, and reliable durability; the middle layer of glass fiber anti-cracking net + PUNM polyurethane sealant has good sealing performance, which effectively avoids water seepage, rust, alkali and other phenomena in the base layer.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the technical field, and in particular to a method for constructing a landscape bridge using reinforced concrete and ceramic particles and a bridge deck structure thereof. Background Art

[0002] With the development of science and technology, new materials are constantly emerging, and people have higher requirements for the landscape effects and walking texture of park slow-moving system paving, landscape bridge paving, square paving, etc. The landscape effects and walking texture of urban landscape bridges and park slow-moving system surface paving have also become the focus of users.

[0003] Traditional landscape bridge deck pavements are mainly divided into wood, asphalt, plastic, concrete, etc. There are various problems in terms of applicability, durability, safety, economy, environmental protection, aesthetics, and easy maintenance.

[0004] The various types of problems are: the wooden panels of outdoor landscape bridges are naturally beautiful, but because the bridge deck is only paved with wooden boards, the wooden boards themselves are prone to water absorption and expansion, water loss and cracking. When used in outdoor environments, they are prone to deformation, cracking, and even warping after being exposed to wind, rain, and sun for a long time. In addition, microorganisms are prone to grow under the wooden boards after being exposed to moisture for a long time, resulting in an uneven bridge deck, a reduced walking texture, and increased maintenance costs.

[0005] Although the outdoor asphalt bridge deck paving technology is mature and the quality is reliable, asphalt paving requires special machinery for transportation, paving and compaction. The wetland landscape bridge is a pedestrian bridge in the forest, and its bearing capacity and machinery operation space do not meet the construction requirements.

[0006] Plastic bridge deck pavements have good elasticity, a wide variety of types, and bright colors. The weather-resistant materials are expensive and difficult to repair after damage. The quality of low-priced polymer materials is unstable. The materials are easily oxidized and faded when exposed to the open air for a long time. The edges of the positive corners are weak and easily damaged. After local repairs, the overall color difference of the bridge deck is large.

[0007] Concrete bridge deck paving is cheap and of reliable quality, but the aesthetics of the bridge deck paving used for wetland landscape bridges is difficult to guarantee. The overall appearance is rigid and low-grade, and the construction time is long. It has poor water dispersion and is prone to freezing on rainy days in winter, and pedestrians are prone to slipping when walking, resulting in a poor overall landscape effect.

[0008] The above problems lead to technical problems such as slow paving speed of existing landscape bridges, poor landscape effect of the landscape bridge pavement layer and poor walking texture. Summary of the invention

[0009] The present application provides a construction method of a landscape bridge made of a combination of reinforced concrete and ceramic particles and a bridge deck structure thereof, which are used to solve the technical problems existing in the prior art, such as high cost, large restrictions on the operating environment for paving equipment, lack of aesthetics, poor environmental coordination, poor walking texture, and difficulty in maintenance and repair of cracked and damaged bridge decks.

[0010] The present application provides a method for constructing a landscape bridge with reinforced concrete and ceramic particles, comprising the following steps:

[0011] Step S20: Draw lines along the longitudinal and transverse directions of the steel box girder according to the design drawings to divide the top surface of the steel box girder into multiple grids, each grid having a size of 250 mm x 250 mm, and weld shear studs with a diameter of φ13 mm and a length of 80 mm at the intersection of each grid;

[0012] Step S30: Arrange a plurality of precast concrete pads in a plum blossom shape on the bridge deck, the precast concrete pads are accommodated in the gaps between adjacent shear nails, the horizontal and vertical spacings between any two pads are 500 mm, and the precast concrete pads are arranged on the top surface of the steel box girder and under the steel mesh;

[0013] Setting up the precast concrete pads in this way can ensure that the protective layer of the distributed steel bars meets the requirements and plays the role of padding the steel bars.

[0014] Step S40: Fully install φ12 steel mesh on the top surface of the precast concrete pad at a spacing of 100x100mm along the longitudinal and transverse directions of the bridge deck, and adjust the position where the mesh conflicts with the bolts to the left and right;

[0015] Step S50: pouring concrete to form a concrete layer, the concrete covers the top surface of the bridge deck steel box girder, the shear nails and the steel mesh are contained in the concrete layer, the poured concrete is cured, trimmed and polished, and the polished top surface of the concrete layer is cleaned;

[0016] Step S60: fully spread the glass fiber anti-cracking mesh on the top surface of the concrete layer, and the overlapping length of the glass fiber anti-cracking mesh in the longitudinal and transverse directions is 70 to 100 mm;

[0017] Following these steps can ensure that the fiberglass anti-cracking mesh is laid smoothly and firmly, and provide reliable support for subsequent stacking layers.

[0018] Step S70: Use a scraping tool to evenly apply the mixed PUNM polyurethane adhesive on the glass fiber anti-cracking net, and scrape 4.5 kg of PUNM polyurethane adhesive per square meter as a sealing bottom layer, and the average thickness of the obtained sealing bottom layer is controlled to be 2.5-3.5 mm;

[0019] Applying at this thickness can ensure the reliability of the adhesion between the sealant and the fiberglass mesh, and achieve sealing and waterproofing of the bottom layer.

[0020] Step S80: before the adhesive on the sealing bottom layer is completely dry, ceramic particles are evenly spread on the top surface of the sealing bottom layer, and 1.5-2.0 kg of ceramic particles are evenly spread per square meter to obtain a base ceramic particle layer;

[0021] Setting the ceramic particle layer according to the above conditions can help utilize the greater roughness of the ceramic particle layer to achieve effective bonding between the sealing bottom layer under the ceramic particle layer and the upper layer, while retaining the water seepage and drainage capabilities to avoid water accumulation on the bridge surface.

[0022] Step S90: Mix black ceramic particles: dark gray ceramic particles: light gray ceramic particles in a mass ratio of 6:3:1, add two-component glue, and stir until uniform to obtain mixed-color ceramic particles. After the base ceramic particle layer has the construction strength, the mixed-color ceramic particles are transported to the paving point, spread, leveled with a ruler, compacted with a spatula to obtain a surface ceramic particle layer, lay a polyurethane layer on the surface ceramic particle layer, cover the bridge deck, and complete the construction.

[0023] By setting PUNM polyurethane adhesive and glass fiber anti-cracking net, on the one hand, it can effectively prevent rainwater from seeping in and causing steel beams to rust, and on the other hand, it can prevent concrete alkali from causing the surface ceramic particles to become spotted and have color differences, effectively maintaining the color of the bridge deck to meet landscape needs; by setting a surface ceramic particle layer on the bridge deck and calcining it at high temperature, the color is stable, it is anti-slip and wear-resistant, the mixture has good fluidity, and the edges and joints are rounded; the overlay treatment enhances the adhesion of the surface particles, effectively avoiding local sanding.

[0024] The bridge deck structure constructed by this method has a surface ceramic particle layer with good wear resistance and can maintain the construction effect for a long time, meeting the viewing needs of landscape bridges.

[0025] Preferably, step S40 includes: step S41: after the steel mesh is tied, the tied mesh is inspected for quality and then washed with a high-pressure water gun to remove debris on the bridge deck, which can reduce the amount of debris on the bridge deck during subsequent construction and improve engineering reliability.

[0026] Preferably, step S50 includes: step S51: when pouring concrete, use a handheld light vibrator to vibrate and compact it, and smooth the surface of the solidified concrete. After the concrete has finally set, cover the concrete surface with a geotextile and sprinkle water on time for maintenance.

[0027] Preferably, step S50 includes: step S52: after the curing is completed, the local protrusions of the concrete layer and the hardened concrete on both sides of the edge steel plate are polished with an angle grinder and a wire brush, and then cleaned with a broom. This can provide a flat and smooth surface for subsequent construction, which is conducive to improving the force bearing capacity of the subsequent surface.

[0028] Preferably, step S50 includes: step S53: cleaning the concrete surface: thoroughly washing the bridge deck with a high-pressure water gun, drying it in the sun, and blowing away fine dust again with a hair dryer. Reducing the amount of impurities on the top surface of the concrete layer can improve the bonding reliability of the subsequent stacked layers and the concrete layer.

[0029] Preferably, the coating tool in step S70 is a scraper or a scraper.

[0030] Preferably, step S90 includes: performing edge finishing on the surface ceramic particle layer, and prohibiting the bridge deck from being stepped on after being exposed to rain within 24 hours after the surface ceramic particle layer is constructed, so as to protect the various layers of the bridge deck structure and avoid dislocation.

[0031] Preferably, the method comprises: Step S10: after the welding of the steel box beam of the bridge deck is completed and the quality inspection is passed, the sundries on the bridge deck are cleaned to reduce the sundries and improve the connection reliability between the subsequent layers and the steel box beam of the bridge deck.

[0032] Preferably, the ceramic particles have a diameter of 1 to 2 mm.

[0033] Another aspect of the present application also provides a landscape bridge deck composed of a reinforced concrete base layer and a ceramic particle surface layer, comprising:

[0034] A shear nail layer is set on the top surface of the steel box girder of the landscape bridge;

[0035] A single steel mesh layer disposed on the top surface of the precast concrete pad;

[0036] A poured concrete layer covering the shear nail layer and the steel mesh layer;

[0037] A glass fiber anti-cracking mesh layer disposed on the top surface of the concrete layer;

[0038] A PUNM polyurethane adhesive layer disposed on the top surface of the glass fiber anti-cracking mesh layer;

[0039] A base ceramic particle layer disposed on a PUNM polyurethane adhesive layer;

[0040] A surface ceramic particle layer disposed on the top surface of the base ceramic particle layer;

[0041] It comprises: a plurality of precast concrete pads, which are arranged in a plum blossom shape and accommodated between the shear nails of the bridge deck.

[0042] By setting PUNM polyurethane adhesive and glass fiber anti-cracking net between the concrete layer and the base ceramic particle layer, it can effectively prevent the surface ceramic particles from becoming spotted and having color differences due to alkali efflux in the concrete. The various colors of the surface ceramic particle layer can be used to increase the ornamental value of the landscape bridge.

[0043] Preferably, the prefabricated concrete pad is accommodated in the concrete layer. The support strength of the steel mesh layer can be improved by covering the concrete pad with the concrete layer.

[0044] The beneficial effects of this application include:

[0045] 1) The reinforced concrete and ceramic particle construction method of the landscape bridge provided in this application, the combination of the new ceramic particle surface layer and the traditional bolts and reinforced concrete base layer effectively solves some problems existing in traditional wood, asphalt, plastic, and concrete paving. The construction technology of the combined structure base bolts + reinforced concrete is mature and has good integrity, and the structure is safe and durable; the middle layer of glass fiber anti-cracking net + PUNM polyurethane sealant has good sealing performance, which effectively avoids water seepage, rust, alkali and other phenomena in the base layer; the surface ceramic particles are optional in color, well coordinated with the surrounding environment, the material itself has stable characteristics, weather resistance and environmental protection, few joints and smooth corners for large-area paving, good landscape effect, wear resistance and anti-skid, good water dispersion, excellent walking texture, and high-end and atmospheric. In particular, the surface ceramic particle material has a light weight and is suitable for a variety of material bases. After paving, the load on the original structure increases little. The durability and weather resistance of the mixture are suitable for indoor and outdoor use, and the application range is wide; the thin layer paving process is simple, material saving and money saving, and the landscape effect is obvious.

[0046] 2) The reinforced concrete and ceramic particle construction method of the landscape bridge provided in this application mainly shows the following advantages in the actual application process of the bridge deck structure: (1) The construction process is simple and does not require special, large-scale mechanical equipment; (2) The construction is convenient, the construction period is short, and the speed is fast; (3) The construction quality is reliable, and the various structural layers are tightly combined to effectively avoid water seepage, rust, alkali and other phenomena in the base layer; (4) The particle size of the surface material is uniform and the color is optional. After paving, the landscape effect is good and the walking texture is excellent; (5) The thin layer paving has a light weight and will not cause excessive load on the structure itself. The paved surface meets the normal force requirements of the landscape bridge; (6) The surface layer is beautiful and has good integrity, and the edges and joints are easy to handle and rounded.

[0047] 3) The reinforced concrete and ceramic particle construction method for the landscape bridge provided in this application is easy to purchase for the paving materials, and no large-scale mechanical equipment is required. The construction technology of the base shear nail + reinforced concrete is mature and reliable in quality, which effectively inhibits the cracking of the concrete surface layer and the infiltration of rainwater; the middle layer is paved with a glass fiber anti-cracking net and coated with PUNM polyurethane sealant, which is convenient for construction and has a good anti-seepage effect. On the one hand, it can effectively prevent the infiltration of rainwater from causing corrosion of steel beams, and on the other hand, it can prevent the alkali panning of concrete from causing the surface ceramic particles to appear spotted and have color differences; the surface ceramic particles are calcined at high temperature, with stable color, anti-slip and wear resistance, and good fluidity of the mixture, and the edges and joints are rounded; the surface treatment enhances the adhesion of the surface particles and effectively avoids local sanding.

[0048] 4) The construction method of reinforced concrete and ceramic particles for landscape bridges provided in this application has economic benefits: convenient construction, simple equipment, and surface maintenance time of only 24 hours, which effectively reduces construction period costs; the surface paving material is thin and light in weight, which greatly reduces material costs and secondary handling costs; the homogeneity and fluidity of the ceramic particles themselves effectively reduce the cost of repairing damaged parts; the surface material is durable and weather-resistant, which effectively reduces operation and maintenance costs. It has a wide range of applications and is suitable for scenic area construction, square paving, landscape bridge paving, and indoor paving.

[0049] 5) The reinforced concrete and ceramic particle construction method of the landscape bridge provided in this application has environmental benefits: the surface ceramic particles are optional in color and well coordinated with the surrounding environment; the paving material itself has stable characteristics, is weather-resistant and environmentally friendly; large-area paving has few joints, smooth edges and corners, and good landscape effects; it is wear-resistant and anti-slip, has good water dispersion, and is safe for travel; tourists feel a good walking texture, which shows high-end and grandeur. BRIEF DESCRIPTION OF THE DRAWINGS

[0050] Figure 1 A schematic diagram of the process flow of the reinforced concrete and ceramic particle construction method for the landscape bridge provided for this application;

[0051] Figure 2 The main cross-sectional structural diagram of the bridge deck provided for this application;

[0052] Figure 3 This is a photo of the shear nail construction site in the specific embodiment of this application;

[0053] Figure 4 This is a photo of the site where the shear nail construction is completed in the specific embodiment of this application;

[0054] Figure 5 This is a photo of the site where the steel mesh layer construction is completed in the specific embodiment of this application;

[0055] Figure 6 This is a photo of the site where the concrete layer pouring construction is completed in the specific embodiment of this application;

[0056] Figure 7 The following are photos of the construction site of the anti-crack net and PUNM sealant layer in the specific embodiment of this application;

[0057] Figure 8 This is a construction site photo of the base ceramic particle layer paving in the specific embodiment of this application;

[0058] Fig. 9 This is a photo of the bridge deck construction completed in the specific embodiment of this application;

[0059] Fig.10 This is a photo of the bridge deck in the specific embodiment of this application after 18 months of use; DETAILED DESCRIPTION

[0060] In order to make the purpose, technical solutions and advantages of the embodiments of the present invention clearer, the technical solutions in the embodiments of the present invention will be clearly and completely described below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are part of the embodiments of the present invention, not all of the embodiments. Generally, the components of the embodiments of the present invention described and shown in the drawings here can be arranged and designed in various different configurations.

[0061] Therefore, the following detailed description of the embodiments of the present invention provided in the accompanying drawings is not intended to limit the scope of the invention claimed for protection, but merely represents selected embodiments of the present invention. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0062] Technical features that are not used to solve the technical problems of the present application are all set or installed according to the commonly used methods in the prior art and will not be described here.

[0063] Example

[0064] The materials used in the following examples were obtained from commercial channels.

[0065] Example

[0066] See also Figures 1 to 10 The reinforced concrete and ceramic particle construction method of the landscape bridge provided in this application comprises the following steps:

[0067] 1. Clean up debris. After the steel box girder is welded and passed the quality inspection, clean up the bridge deck.

[0068] 2. Divide the grid. Assign a dedicated person to draw vertical and horizontal lines according to the design drawings, divide the grid (250x250mm), and weld shear nails with a diameter of φ13mm and a length of 80mm at the intersection of the grid. Figures 3-4 As shown;

[0069] 3. Pad installation: The bridge deck is arranged with precast concrete pads in a plum blossom shape with a spacing of 500 mm to ensure that the protective layer of the distributed steel bars meets the requirements.

[0070] 4. Fabrication and installation of steel mesh. The bridge deck is fully packed with φ12 steel mesh at a spacing of 100x100mm in the longitudinal and transverse directions, and the conflicting positions with bolts are adjusted left and right. Figure 5 As shown, Figure 5 The middle local pad rests on the bottom of the shear studs;

[0071] 5. Clean the bridge deck. After passing the quality inspection, use a high-pressure water gun to wash away debris on the bridge deck.

[0072] 6. Concrete pouring and curing: Use a handheld light vibrator to compact the concrete, and use a hand-held polisher to smooth the surface. After final setting, cover with geotextile and sprinkle water on time for curing.

[0073] 7. Finishing and grinding. After the maintenance is completed, use an angle grinder and a wire brush to grind the local protrusions and the hardened concrete on both sides of the edge steel plate, and clean them with a broom.

[0074] 8. Clean the concrete surface: Use a high-pressure water gun to thoroughly rinse the bridge surface, dry it in the sun, and use a hair dryer to blow away the fine dust again. Figure 6 shown.

[0075] 9. Laying anti-cracking net: The bridge deck is fully covered with fiberglass anti-cracking net, with a vertical and horizontal overlap length of 70-100mm to ensure that the fiberglass anti-cracking net is smooth and stable.

[0076] 10. PUNM polyurethane sealing base: Apply the mixed adhesive evenly on the bridge deck with a scraper (using a scraper or scraper), at a dosage of 4.5 kg per square meter, with an average thickness of 3.0 mm to ensure the adhesion between the sealant and the glass fiber mesh. Figure 7 shown.

[0077] 11. Spread ceramic particles: Spread them evenly before the adhesive dries, at a rate of 1.5-2.0 kg per square meter. The roughness is conducive to the effective bonding of the lower layer and the upper layer.

[0078] 12. Lay the top layer of ceramic particles: (1) After the bottom layer has sufficient strength, construct the top layer. Mix three different colors of ceramic particles (black: dark gray: light gray = 6:3:1) according to the design requirements; (2) Add two-component glue and stir again until uniform; (3) Transport them to the paving point manually and spread them as soon as possible, level them with a ruler, and compact them with a spatula. (4) Pay special attention to the quality of the edges and corners. Do not expose them to rain or step on them within 24 hours after the construction is completed. For steps 11 to 12, refer to Figure 8 shown.

[0079] 13. Surface treatment: Three days after the surface layer is completed, polyurethane surface treatment is carried out. During the surface treatment, attention should be paid to the thickness and uniformity of the surface agent spraying to avoid causing color difference on the bridge deck. Fig. 9 shown.

[0080] After the landscape bridge constructed by the above method is put into use, after 18 months of normal use, the bridge deck will be Fig.10As shown, the ceramic particles on the bridge deck did not have any efflorescence or mottling problems, and the bridge deck had a good use effect. After long-term outdoor use, no area on the bridge deck was damaged or curled, especially the edges of the external corners had high overall reliability, and the bridge deck had excellent anti-slip performance. After construction, it can be used normally without long-term prohibition of pedestrians, and the maintenance cost is low. The equipment required for the entire construction process is handheld equipment, and the construction is less affected by the environment.

[0081] Although the present invention has been described in detail with reference to the aforementioned embodiments, it is still possible for those skilled in the art to modify the technical solutions described in the aforementioned embodiments, or to make equivalent substitutions for some of the technical features therein. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principles of the present invention should be included in the protection scope of the present invention.

Claims

1. A construction method of reinforced concrete and ceramic particles for a landscape bridge. It is characterized in that The following steps are involved: Step S20: Draw lines along the longitudinal and transverse directions of the steel box girder according to the design drawings to divide the top surface of the steel box girder into multiple grids, each grid having a size of 250 mm x 250 mm, and weld shear studs with a diameter of φ13 mm and a length of 80 mm at the intersection of each grid; Step S30: Arrange a plurality of precast concrete pads in a plum blossom shape on the bridge deck, the precast concrete pads are accommodated in the gaps between adjacent shear nails, the horizontal and vertical spacings between any two pads are 500 mm, and the precast concrete pads are arranged on the top surface of the steel box girder and under the steel mesh; Step S40: Fully install φ12 steel mesh on the top surface of the precast concrete pad at a spacing of 100x100mm along the longitudinal and transverse directions of the bridge deck, and adjust the position where the mesh conflicts with the bolts to the left and right; Step S50: pouring concrete to form a concrete layer, the concrete covers the top surface of the bridge deck steel box girder, the shear nails and the steel mesh are contained in the concrete layer, the poured concrete is cured, trimmed and polished, and the polished top surface of the concrete layer is cleaned; Step S60: fully spread the glass fiber anti-cracking mesh on the top surface of the concrete layer, and the overlapping length of the glass fiber anti-cracking mesh in the longitudinal and transverse directions is 70 to 100 mm; Step S70: Use a scraping tool to evenly apply the mixed PUNM polyurethane adhesive on the glass fiber anti-cracking net, and scrape 4.5 kg of PUNM polyurethane adhesive per square meter as a sealing bottom layer, and the average thickness of the obtained sealing bottom layer is controlled to be 2.5-3.5 mm; Step S80: before the adhesive on the sealing bottom layer is completely dry, ceramic particles are evenly spread on the top surface of the sealing bottom layer, and 1.5-2.0 kg of ceramic particles are evenly spread per square meter to obtain a base ceramic particle layer; Step S90: Mix black ceramic particles: dark gray ceramic particles: light gray ceramic particles in a mass ratio of 6:3:1, add two-component glue, and stir until uniform to obtain mixed-color ceramic particles. After the base ceramic particle layer has the construction strength, the mixed-color ceramic particles are transported to the paving point, spread, leveled with a ruler, compacted with a trowel to obtain a surface ceramic particle layer, spray a polyurethane layer on the surface ceramic particle layer, cover the bridge deck, and complete the construction.

2. The method for constructing a landscape bridge with reinforced concrete and ceramic particles according to claim 1, It is characterized in that include: Step S10: After the welding of the steel box girder of the bridge deck is completed and passes the quality inspection, the debris on the bridge deck is cleaned.

3. The method for constructing a landscape bridge with reinforced concrete and ceramic particles according to claim 1, It is characterized in that The step S40 includes: step S41: after the steel mesh is tied, the tied mesh is inspected for quality and qualified, and then the debris on the bridge deck is washed with a high-pressure water gun.

4. The method for constructing a landscape bridge with reinforced concrete and ceramic particles according to claim 1, It is characterized in that The step S50 includes: step S51: when pouring concrete, a handheld light vibrator is used to vibrate and compact the concrete, and the surface of the solidified concrete is smoothed and leveled. After the concrete is finally set, the surface of the concrete is covered with a geotextile and watered on time for maintenance.

5. The method for constructing a landscape bridge with reinforced concrete and ceramic particles according to claim 3, It is characterized in that The step S50 includes: step S52: after the maintenance is completed, the local raised concrete layer and the hardened concrete on both sides of the edge steel plate are grinded with an angle grinder and a wire brush, and then cleaned with a broom.

6. The method for constructing a landscape bridge with reinforced concrete and ceramic particles according to claim 1, It is characterized in that The step S50 includes: step S53: cleaning the concrete surface: using a high-pressure water gun to thoroughly rinse the bridge surface, air-dry it, and use a hair dryer to blow away the fine dust again.

7. The method for constructing a landscape bridge with reinforced concrete and ceramic particles according to claim 1, It is characterized in that The scraping tool in step S70 is a scraper or a scraper.

8. The method for constructing a landscape bridge with reinforced concrete and ceramic particles according to claim 1, It is characterized in that The step S90 includes: performing edge finishing treatment on the surface ceramic particle layer, and prohibiting the bridge deck from being exposed to rain or stepped on within 24 hours after the construction of the surface ceramic particle layer is completed; The ceramic particles have a diameter of 1 to 2 mm.

9. A landscape bridge deck composed of a reinforced concrete base layer and a ceramic particle surface layer obtained by the construction method according to any one of claims 1 to 8, It is characterized in that include: A shear nail layer is set on the top surface of the steel box girder of the landscape bridge; A single steel mesh layer disposed on the top surface of the precast concrete pad; A poured concrete layer covering the shear nail layer and the steel mesh layer; A glass fiber anti-cracking mesh layer disposed on the top surface of the concrete layer; A PUNM polyurethane adhesive layer disposed on the top surface of the glass fiber anti-cracking mesh layer; A base ceramic particle layer disposed on a PUNM polyurethane adhesive layer; A surface ceramic particle layer disposed on the top surface of the base ceramic particle layer; It comprises: a plurality of precast concrete pads, which are arranged in a plum blossom shape and accommodated between the shear nails of the bridge deck.

10. The bridge deck according to claim 9, It is characterized in that The prefabricated concrete pad is accommodated in the concrete layer.