A super-large span arch string truss cable construction technology

By using steel strand slides and finite element simulation analysis in the construction of ultra-large-span tensioned arch trusses, the problem of construction site and environmental restrictions was solved, and an efficient and safe construction process was achieved, which is suitable for most coal yard transformation environments.

CN115199054BActive Publication Date: 2024-10-01TIANJIN XIBEI ZHONGHE PRESTRESSING ENG CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202211019659.2
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2022-08-24
Publication Date
2024-10-01
Estimated Expiration
2042-08-24

AI Technical Summary

Technical Problem

The existing construction technology cannot meet the requirements of ultra-long-span structures. It requires the cooperation of a crane for a long time, and the construction space is limited when there is large machinery under the structure. It cannot be suitable for most coal field reconstruction environments.

Method used

Steel strands are used as the hanging rope slide, which is fixed by reverse chains and anchors to provide a straight slide and reduce reliance on cranes. Finite element calculation software is used for simulation analysis to simplify the construction process and improve construction efficiency and safety. .

Benefits of technology

It achieves construction flexibility and efficiency that are not restricted by the construction site and the underlying environment. It has a wide range of applications, reduces the number of cable tension adjustments, ensures accurate stress on the structure, and improves construction efficiency and safety.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN115199054B_ABST
    Figure CN115199054B_ABST
Patent Text Reader

Abstract

The present invention discloses a cable construction process for an ultra-large span arch truss, and the construction process is as follows: S1: installation and fixation of a cable hanging slideway; S2: selection of traction equipment; S3: crane cooperation with cable hanging while spreading the cable; S4: installation and fixation of the cable head pin shaft; S5: removal of the cable hanging slideway; S6: installation of the cable clamp; S7: tensioning of the cable. The advantages of the present invention are: ① the present invention uses finite element calculation software to perform detailed simulation analysis on the cable construction process to ensure the verticality of the support rod and the structure reaches the design state after the construction is completed; ② the present invention simplifies the construction process through simulation analysis, and gives the actual tension value of each cable in one step, reducing the number of cable tension adjustment times, so that the structure is more accurately stressed; ③ the present invention uses steel strands as auxiliary cable hanging installation slideways, which are not limited by the construction site and the lower environment, do not require the cooperation of a crane throughout the process, and have a wide range of applications.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of building construction, and in particular to a super-large-span arch-string truss cable construction process. Background Art

[0002] As the situation of air pollution and haze becomes increasingly severe, open-air coal yards of thermal power plants, ports, coal mines, metallurgy, coking and other enterprises will generate dust during operation and storage in windy weather, which not only causes a large amount of material loss, but also pollutes the surrounding environment. At present, the coal yard implements full closure measures, so the large-span structure requirements of the coal yard closure renovation project are applied, and the arch truss, as a novel steel structure form, has light weight and large span, and has been well applied in these coal yard closure renovations.

[0003] At present, there are two main schemes for prestressed cables according to the construction method of steel structure:

[0004] Solution 1: For truss structures with smaller spans, after the steel structure is assembled on the frame, the prestressed cables are constructed on the frame. After the cables are constructed, they are hoisted to the structural parts along with the steel structure.

[0005] Option 2: The steel structure is assembled in situ in high altitude, and the prestressed cables are hung by multiple cranes.

[0006] Both of the above solutions have strict requirements on the engineering environment, that is, there needs to be a large enough open space under the steel structure to set up the tire frame, or to have space for the movement of the crane and the crane boom. However, in most coal yard renovations, there are piles of coal and large machinery such as stackers and reclaimers under the structure, which cannot meet the crane operation requirements for a long time. The existing construction technology cannot be applied to construction under various construction environment conditions and has a small scope of application. Summary of the invention

[0007] The technical problem to be solved by the present invention is that the existing construction technology cannot adapt to the requirements of ultra-large span structures, requires the cooperation of cranes for a long time, requires many crane shifts, and has limited construction space when there is large machinery under the structure. The present invention provides an ultra-large span arch truss cable construction technology in the field of construction engineering that is not restricted by the construction site and the lower environment, does not require the cooperation of cranes throughout the process, has flexible construction, safety and high construction efficiency.

[0008] A super-large span arch string truss cable construction process, the construction process is:

[0009] S1: Installation and fixing of hanging cable slide:

[0010] 1) Weld the steel strand slideway fixing pad at the upper chord position of the cable head ear plate truss, and the weld length meets the safety use requirements;

[0011] 2) Use two 1860-grade Ф15.2 steel strands as cable slideways to bear the weight of the cables and increase the safety reserve factor;

[0012] 3) Use the fall chain to lift the slideway steel strand to the working platform and fix it to the welded pad with the anchor clip;

[0013] 4) Use a 24-ton jack to apply a tension of 100KN to a single steel strand, so that the steel strand is tightened and kept horizontal and straight, providing a straight slide for cable installation;

[0014] 5) Finally, install the anti-drop anchor plate at the end of the anchor after tensioning to ensure the safety of the cable hanging construction;

[0015] S2: Selection of traction equipment: Determine the winch model through calculation. The required traction force F should be greater than the sum of the cable weight and friction resistance, calculated as follows:

[0016] F ≥ W(1+f)k

[0017] Where: F——traction force;

[0018] W——total weight of the cable;

[0019] f——friction coefficient, 0.16~0.19;

[0020] K——margin coefficient, take 1.1~1.4.

[0021] S3: Crane cooperates with both cable extension and cable hanging:

[0022] 1) Place the cable tray on one side of the arch string truss and fix the winch on the other side;

[0023] 2) After the truss is spliced, pull the winch wire rope to the side of the cable tray, and adjust the thread length of the cable head to the maximum, leaving about 50mm of thread connection at each end, ready to hang the cable;

[0024] 3) Every time the cable moves about 5 meters, the cable is suspended on the cable slideway using a sling and pulley. Two adjacent suspension points are alternately arranged on two steel strands to ensure that the cable is straight and reduce the difficulty of installing the cable head at the other end;

[0025] 4) As the cable lifting points are set, the crane hook changes position every 30m or so until the cable is pulled to the other end of the structure;

[0026] S4: Cable head pin installation and fixation:

[0027] 1) Install the cable head pin at one end;

[0028] 2) Use the method of using the hanging cable tooling and the fall chain to install the cable head pin at the other end;

[0029] 3) After the cable is hung, record the cable tension value and the exposed length of the screw rod, accurate to millimeters;

[0030] S5: Removal of the hanging cable slide: After the cable is installed, remove the steel strands of the hanging cable slide in time and release the steel strands onto the operating platform to facilitate the use of the next hanging cable.

[0031] S6: Cable and cable clamp installation: Affected by the manufacturing and assembly accuracy of the steel structure, after the cable is installed, first observe the vertical distance between the support rod and the cable. If the distance is close, the cable clamp can be installed directly; if the distance is far, the cable can be tensioned to a partial force value first to make the cable taut, and then the cable clamp can be installed when the cable is close to the support rod to improve construction efficiency.

[0032] S7: Cable tensioning:

[0033] 1) Select tensioning jacks of corresponding specifications and models and arrange them at the ends of the cable heads, and use symmetrical tensioning at both ends;

[0034] 2) When the cable is tensioned, the cable force and deformation are controlled to meet the requirements of controlling the node deformation and the internal force of the cable within the allowable error range;

[0035] 3) The truss cables are subjected to graded loading to simulate and calculate the actual tension value;

[0036] 4) Start the oil pump and jack for tensioning, control the loading and oil supply speed, and tighten the adjusting screw in time during the oil supply process;

[0037] 5) During the tensioning process, monitor the height of the structural arch deformation at any time, measure the exposed length of the adjusting screw, and keep records;

[0038] As an improvement, the S1 described above adopts steel strands as hanging cable slideways, and the construction is carried out on the side of the structure and on the operating platform, without being restricted by the site and operating space below the structure.

[0039] As an improvement, two steel strands are used as cable hanging slideways in the S1, and a clip-proof anchor plate is installed at the end of the anchor to prevent it from falling off. Multiple lines of defense increase the safety of cable hanging construction.

[0040] As an improvement, the cable head in S4 is installed by any one of the following methods:

[0041] Method 1: When customizing the finished cable, customize several cable head connecting rods of different lengths or lengthen the finished cable head thread to adjust the length to deal with the influence of the assembly accuracy of the on-site components on the hanging cable;

[0042] Method 2: Apply a certain initial force to the cable, tighten the cable to the structural installation position, and then install the cable head pin at that end.

[0043] As an improvement, the two ends of the cable head are fork-ear type, and a U-shaped round steel matching clamping tooling is used as a tensioning and fixing measure.

[0044] As an improvement, in the S7, according to the simulation analysis calculation results, the cable is graded as 20% → 40% → 60% → 80% → 100% and tensioned to the cable force value at one time, thereby reducing the number of cable force adjustments and making the structure more accurately stressed.

[0045] As an improvement, the oil supply time in S7 is not less than 0.5 min.

[0046] The advantages of the present invention compared with the prior art are:

[0047] ① The present invention uses finite element calculation software to perform detailed simulation analysis on the cable construction process to ensure the verticality of the support rod and that the structure reaches the designed state after the construction is completed;

[0048] ② The present invention simplifies the construction process through simulation analysis, gives the actual tension value of each cable in one step, reduces the number of cable tension adjustments, and makes the structural force more accurate;

[0049] ③ The present invention uses steel strands as hanging cables to install the slideway, which is not restricted by the construction site and the lower environment, does not require the full cooperation of cranes, and has a wide range of applications;

[0050] ④ The present invention eliminates the need for a separate cable laying construction process, and can install the cable while laying the cable, thereby improving construction efficiency;

[0051] ⑤ The present invention abandons the traditional tension connection method and adopts U-shaped round steel as a tension connection measure, making the construction more flexible and convenient.

[0052] The above summary is for illustrative purposes only and is not intended to be limiting in any way. In addition to the illustrative aspects, embodiments and features described above, further aspects, embodiments and features of the present invention will be readily apparent by reference to the accompanying drawings and the following detailed description. BRIEF DESCRIPTION OF THE DRAWINGS

[0053] In order to more clearly illustrate the embodiments of the present application or the technical solutions in the prior art, the drawings required for use in the embodiments or technical descriptions will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present application. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.

[0054] Figure 1It is a construction process flow chart of the present invention.

[0055] Figure 2 It is a schematic diagram of the installation of the hanging rope of the present invention.

[0056] Figure 3 It is a three-dimensional perspective layout diagram of the closed shed of the coal yard of the present invention.

[0057] Figure 4 It is a schematic diagram of the elevation arrangement of the prestressed cables of the present invention.

[0058] Figure 5 It is a schematic diagram of the main truss node of an embodiment of the present invention.

[0059] Figure 6 It is a large-scale drawing of the prestressed steel cables according to an embodiment of the present invention.

[0060] Figure 7 It is a large-scale drawing of the rope clamp according to an embodiment of the present invention. DETAILED DESCRIPTION

[0061] The embodiments of the present application are described in detail below, and examples of the embodiments are shown in the accompanying drawings, wherein the same or similar reference numerals throughout represent the same or similar elements or elements having the same or similar functions. The embodiments described below with reference to the accompanying drawings are exemplary and are only used to explain the present application, and cannot be understood as limiting the present application.

[0062] In the description of this application, it should be noted that, unless otherwise clearly specified and limited, the terms "installed", "connected", and "connected" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection or an indirect connection through an intermediate medium, it can be the internal connection of two elements or the interaction relationship between two elements. For ordinary technicians in this field, the specific meanings of the above terms in this application can be understood according to specific circumstances.

[0063] The present invention is further described in detail below in conjunction with the accompanying drawings.

[0064] 1. Combined with attachment Figure 1 to Figure 4 , a super-large span arch string truss cable construction process, characterized in that: the construction process is:

[0065] S1: Installation and fixing of hanging cable slide:

[0066] 1) Weld the steel strand slideway fixing pad at the upper chord position of the cable head ear plate truss, and the weld length meets the safety use requirements;

[0067] 2) Use two 1860-grade Ф15.2 steel strands as cable slideways to bear the weight of the cables and increase the safety reserve factor;

[0068] 3) Use the fall chain to lift the slideway steel strand to the working platform and fix it to the welded pad with the anchor clip;

[0069] 4) Use a 24-ton jack to apply a tension of 100KN to a single steel strand, so that the steel strand is tightened and kept horizontal and straight, providing a straight slide for cable installation;

[0070] 5) Finally, install the anti-drop anchor plate at the end of the anchor after tensioning to ensure the safety of the cable hanging construction;

[0071] S2: Selection of traction equipment: Determine the winch model through calculation. The required traction force F should be greater than the sum of the cable weight and friction resistance, calculated as follows:

[0072] F ≥ W(1+f)k

[0073] Where: F——traction force;

[0074] W——total weight of the cable;

[0075] f——friction coefficient, 0.16~0.19;

[0076] K is margin coefficient, which is between 1.1 and 1.4.

[0077] S3: Crane cooperates with both cable extension and cable hanging:

[0078] 1) Place the cable tray on one side of the arch string truss and fix the winch on the other side;

[0079] 2) After the truss is spliced, pull the winch wire rope to the side of the cable tray, and adjust the thread length of the cable head to the maximum, leaving about 50mm of thread connection at each end, ready to hang the cable;

[0080] 3) Every time the cable moves about 5 meters, the cable is suspended on the cable slideway using a sling and pulley. Two adjacent suspension points are alternately arranged on two steel strands to ensure that the cable is straight and reduce the difficulty of installing the cable head at the other end;

[0081] 4) With the setting of the cable suspension point, the crane hook changes the suspension position every 30m or so until the cable body is pulled to the other end of the structure;

[0082] S4: Cable head pin installation and fixation:

[0083] 1) Install the cable head pin at one end;

[0084] 2) Use the method of using the hanging cable tooling and the fall chain to install the cable head pin at the other end;

[0085] 3) After the cable is hung, record the cable tension value and the exposed length of the screw rod, accurate to millimeters;

[0086] S5: Removal of the hanging cable slide: After the cable is installed, remove the steel strands of the hanging cable slide in time and release the steel strands onto the operating platform to facilitate the use of the next hanging cable.

[0087] S6: Cable and cable clamp installation: Affected by the manufacturing and assembly accuracy of the steel structure, after the cable is installed, first observe the vertical distance between the support rod and the cable. If the distance is close, the cable clamp can be installed directly; if the distance is far, the cable can be tensioned to a partial force value first to make the cable taut, and then the cable clamp can be installed when the cable is close to the support rod to improve construction efficiency.

[0088] S7: Cable tensioning:

[0089] 1) Select tensioning jacks of corresponding specifications and models and arrange them at the ends of the cable heads, and use symmetrical tensioning at both ends;

[0090] 2) When the cable is tensioned, the cable force and deformation are controlled to meet the requirements of controlling the node deformation and the internal force of the cable within the allowable error range;

[0091] 3) The truss cables are subjected to graded loading to simulate and calculate the actual tension value;

[0092] 4) Start the oil pump and jack for tensioning, control the loading and oil supply speed, and tighten the adjusting screw in time during the oil supply process;

[0093] 5) During the tensioning process, monitor the height of the structural arch deformation at any time, measure the exposed length of the adjusting screw, and keep records;

[0094] Example

[0095] The two material strips A and B of a certain company's pellet yard were closed, with a closed length of 650 meters and a span of 245 meters. A single-span, column-free tube truss was used, and the material yard was fully closed by laying colored steel plates on the outside. The 245-meter span adopted an arch truss with hinged supports at both ends. The tensioning section of the truss was a spatial triangular tube truss, and the non-tensioning section adopted a triangular tube truss. In order to reduce the thrust of the arch foot, a 189.2-meter-long balancing cable was set at an elevation of about 37.2 meters while meeting the operating space of the bucket wheel machine. The cable used a φ7×91 semi-parallel steel wire cable. A total of 40 prestressed cables were arranged in the entire closed canopy, and the spacing between the trusses was 15.9 meters. The three-dimensional perspective layout of the closed canopy of the coal yard is shown as follows: Figure 3 The schematic diagram of the prestressed cable facade layout is shown in Figure 4 shown.

[0096] Since cables and steel components are both important and indispensable components of the structure, their construction requires close coordination, and the prestressed tensioning construction process directly affects the stress state of the structure, and thus affects the safety performance of the structure. Therefore, before the construction of prestressed cables, finite element calculation software must be used to perform detailed construction simulation calculation and analysis on the tensioning process, so that during the assembly and positioning of the components, the displacement of the nodes and the internal force of the components can be controlled simultaneously, and the actual tensioning force value of each cable can be finally determined.

[0097] The span of the arch string truss in this embodiment is large, and the construction method of in-situ segmented assembly is adopted. For each structural unit, it is assembled and tensioned from one end to the other end. The single main trusses in the structure are connected by secondary trusses, and the plane force transmission is mainly used. The synergy between the main trusses is not obvious. Therefore, one of the trusses can be taken for analysis. After the construction simulation analysis is performed on it using Midas software, the cable force change values ​​at each construction stage are obtained as shown in the following table:

[0098]

[0099]

[0100] 1. Slideway Fixing

[0101] 1. Weld the steel strand slideway fixing pad at the upper chord position of the cable head ear plate truss where the stay cable is installed, and the weld length meets the safety use requirements;

[0102] 2. Use two 1860-grade Ф15.2 steel strands as cable slideways to bear the weight of the cables and increase the safety reserve factor;

[0103] 3. Use the fall chain to lift the slideway steel strand to the working platform and fix it to the welded pad with the anchor clip;

[0104] 4. Use a 24-ton jack to apply a tension of 100KN to a single steel strand, so that the steel strand is tightened and kept horizontal and straight, providing a straight slide for cable installation;

[0105] 5. Finally, install the anti-drop anchor plate at the end of the anchor after tensioning to ensure the safety of the cable hanging construction;

[0106] 2. Selection of traction equipment:

[0107] The winch model for traction cable needs to be determined through calculation. The required traction force F should be greater than the sum of the cable weight and friction resistance, calculated as follows:

[0108] F ≥ W(1+f)k

[0109] Where: F——traction force;

[0110] W——total weight of the cable;

[0111] f——friction coefficient, 0.16~0.19;

[0112] K is margin coefficient, which is between 1.1 and 1.4.

[0113] 3. Cable installation:

[0114] 1. Place the cable tray on one side of the arch string truss and fix the winch on the other side;

[0115] 2. After the truss is spliced, pull the winch wire rope to the side of the cable tray, and adjust the length of the cable head to the maximum, leaving about 50mm of thread connection at each end, ready to hang the cable;

[0116] 3. Every time the cable moves about 5 meters, the cable is suspended on the cable slideway using a sling and pulley. Two adjacent suspension points are alternately arranged on two steel strands to ensure that the cable is straight and reduce the difficulty of installing the cable head at the other end;

[0117] 4. As the cable lifting point is set, the crane hook changes position every 30 meters or so until the cable body is pulled to the other end of the structure and the cable head pin at that end is installed;

[0118] 5. The installation of the cable head at the other end is affected by the assembly and installation accuracy of the steel structure. Often, the pin hole is still some distance away from the cable head. It is necessary to use the method of using a hanging cable tool in conjunction with a fall chain and a tensioning tool to apply a certain initial force to the cable, tighten the cable to the structural installation position, and complete the installation of the cable head pin at this end. The hanging cable installation diagram is shown in the figure. Figure 2 As shown;

[0119] 6. After the cable is hung, record the cable tension value and the exposed length of the screw rod, accurate to millimeters;

[0120] 4. Removal of the hanging cable slide:

[0121] After the cable is installed, the steel strands of the cable hanging slide shall be removed in time, and the steel strands shall be loosened onto the operating platform to facilitate the use of the next cable hanging.

[0122] 5. Cable clamp installation:

[0123] Affected by the accuracy of steel structure manufacturing and assembly, after the cable is installed, first observe the vertical distance between the strut and the cable. If the distance is close, the cable clamp can be installed directly; if the distance is far, the cable can be tensioned to a partial force value first to make the cable taut, and then the cable clamp can be installed when the cable is close to the strut to improve construction efficiency.

[0124] 6. Cable tensioning:

[0125] 1. The cables of the super-large span arch truss are tensioned symmetrically at both ends;

[0126] 2. Select the tensioning jacks of corresponding specifications and models according to the simulation analysis results. For the fork-ear type cable head, two devices are equipped at each end, and for the cold-cast pier head cable head, one device is equipped at each end;

[0127] 3. When the cable is tensioned, the cable force and deformation are controlled to achieve the design requirements for the control node deformation and the internal force of the cable within the allowable error range;

[0128] 4. According to the given tension value of the simulation analysis, the truss is loaded in stages, and the tension is stepped from 20% to 40% to 60% to 80% to 100% to the given tension value;

[0129] 5. Start the oil pump and jack for tensioning. Load the tensioning jack slowly and control the oil supply speed. The oil supply time should not be less than 0.5min. Tighten the adjusting screw in time during the oil supply process.

[0130] 6. During the tensioning process, monitor the arch deformation height of the structure at any time, measure the exposed length of the adjusting screw, and keep records.

[0131] The present invention and its embodiments are described above, and such description is not restrictive. The drawings show only one embodiment of the present invention, and the actual structure is not limited thereto. In short, if ordinary technicians in the field are inspired by it, without departing from the purpose of the invention, they can design a structure and embodiment similar to the technical solution without creativity, which should belong to the protection scope of the present invention.

Claims

1. A super-large span arch string truss cable construction process, characterized by: The construction process is: S1: Installation and fixing of hanging cable slide: 1) Weld the steel strand slideway fixing pad at the upper chord position of the cable head ear plate truss, and the weld length meets the safety use requirements; 2) Use two 1860-grade Ф15.2 steel strands as cable slideways to bear the weight of the cables and increase the safety reserve factor; 3) Use the fall chain to lift the slideway steel strand to the working platform and fix it to the welded pad with the anchor clip; 4) Use a 24-ton jack to apply a tension of 100KN to a single steel strand, so that the steel strand is tightened and kept horizontal and straight, providing a straight slide for cable installation; 5) Finally, install the anti-drop anchor plate at the end of the anchor after tensioning to ensure the safety of the cable hanging construction; S2: Selection of traction equipment: Determine the winch model through calculation. The required traction force F should be greater than the sum of the cable weight and friction resistance, calculated as follows: F ≥ W(1+f)k Where: F——traction force; W——total weight of the cable; f——friction coefficient, 0.16~0.19; K——margin coefficient, take 1.1~1.4; S3: Crane cooperates with both cable extension and cable hanging: 1) Place the cable tray on one side of the arch string truss and fix the winch on the other side; 2) After the truss is spliced, pull the winch wire rope to the side of the cable tray, and adjust the length of the cable head to the maximum, leaving 50mm of thread connection at each end, ready to hang the cable; 3) Every time the cable moves 5 meters, the cable is suspended on the cable slideway using a sling and pulley. Two adjacent suspension points are alternately arranged on two steel strands to ensure that the cable is straight and reduce the difficulty of installing the cable head at the other end; 4) With the setting of the cable suspension point, the crane hook changes the suspension position every 30m or so until the cable body is pulled to the other end of the structure; S4: Cable head pin installation and fixation: 1) Install the cable head pin at one end; 2) Use the method of using the hanging cable tooling and the fall chain to install the cable head pin at the other end; 3) After the cable is hung, record the cable tension value and the exposed length of the screw rod, accurate to millimeters; S5: Removal of the hanging cable slide: After the cable is installed, remove the steel strands of the hanging cable slide in time and release the steel strands onto the operating platform to facilitate the use of the next hanging cable; S6: Cable clamp installation: Affected by the manufacturing and assembly accuracy of the steel structure, after the cable is installed, first observe the vertical distance between the support rod and the cable. If the distance is close, the cable clamp can be installed directly; if the distance is far, the cable can be stretched to a partial force value to make the cable tight, and then the cable clamp can be installed when the cable is close to the support rod to improve construction efficiency; S7: Cable tensioning: 1) Select tensioning jacks of corresponding specifications and models and arrange them at the ends of the cable heads, and use symmetrical tensioning at both ends; 2) When the cable is tensioned, the cable force and deformation are controlled to meet the requirements of controlling the node deformation and the internal force of the cable within the allowable error range; 3) The truss is loaded in stages to a given tension value; 4) Start the oil pump and jack for tensioning, control the loading and oil supply speed, and tighten the adjusting screw in time during the oil supply process; 5) During the tensioning process, monitor the arch deformation height of the structure at any time, measure the exposed length of the adjusting screw, and keep records.

2. The cable construction process of the super-large span arch string truss according to claim 1 is characterized in that: In the S1 described above, steel strands are used as hanging cable slideways, and the construction is carried out on the side of the structure and on the operating platform, without being restricted by the site and operating space below the structure.

3. The cable construction process of a super-large span arch string truss according to claim 1 is characterized in that: In the S1, two steel strands are used as cable hanging slideways, and a clip anti-drop anchor plate is installed at the end of the anchor. Multiple lines of defense increase the safety of cable hanging construction.

4. The cable construction process of a super-large span arch string truss according to claim 1 is characterized in that: The cable head in S4 is installed by any one of the following methods: Method 1: When customizing the finished cable, customize several cable head connecting rods of different lengths or lengthen the finished cable head thread to adjust the length to deal with the influence of the assembly accuracy of the on-site components on the hanging cable; Method 2: Apply a certain initial force to the cable, tighten the cable to the structural installation position, and then install the cable head pin at that end.

5. The cable construction process of the super-large span arch string truss according to claim 1 is characterized in that: The two ends of the cable head are fork-ear type, and a U-shaped round steel supporting clamping tooling is used as a tensioning and fixing measure.

6. The cable construction process of a super-large span arch string truss according to claim 1 is characterized in that: In the above S7, according to the simulation analysis calculation results, the cable is graded as 20% → 40% → 60% → 80% → 100% and tensioned to the cable force value at one time, thereby reducing the number of cable force adjustments and making the structure more accurately stressed.

7. The cable construction process of a super-large span arch string truss according to claim 1 is characterized in that: The oil supply time in S7 is not less than 0.5 min.