Suspended and assembled segment heightened sinking double-wall steel cofferdam and construction method

Through the construction method of connecting high-sinking and laying double-wall steel cofferdams with suspension assembly sections, the problems of material loss and sinking difficulties in deep water construction are solved, and efficient and accurate cofferdam sinking and construction efficiency are achieved.

CN119041464AInactive Publication Date: 2024-11-29HANGZHOU JIANGRUN TECH LIMITED

Patent Information

Application Number
CN202411533883.2
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-10-31
Publication Date
2024-11-29
Estimated Expiration
Not applicable · inactive patent

AI Technical Summary

Technical Problem

In the construction of deep water and tall cofferdams, the rigid boom material of traditional double-wall steel cofferdams has large losses, and the deviation of anchor point position affects construction efficiency and accuracy. In addition, the complex geology of deep water rivers leads to difficulty in subsidence of cofferdams and slow progress.

Method used

The construction method of connecting the high-sinking and laying double-wall steel cofferdam with suspended assembled sections, including large-volume underwater obstacle removal, intelligent detection system installation, guide pulley limiting device, self-floating high limiting device and vertical conduit method Back cover, optimize construction process to improve efficiency and accuracy.

Benefits of technology

Through intelligent monitoring and precise assembly, the construction accuracy is improved, material losses are reduced, the stability and perpendicularity of the cofferdam deposition process is ensured, and the construction efficiency is improved, which solves the problems of difficulty in sinking the cofferdam and slow construction progress.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119041464A_ABST
    Figure CN119041464A_ABST
Patent Text Reader

Abstract

The invention provides a suspension assembly segment heightening sinking double-wall steel cofferdam and a construction method. The construction method comprises the key steps of large-size underwater obstacle removal, in-situ assembly platform building, in-situ assembly, inner support installation, guide pulley limiting, system suspension, intelligent monitoring, heightening assisting, water injection sinking, bottom sealing concrete pouring and the like. The intelligent detection system is introduced to realize real-time monitoring, and the construction precision and safety are improved; the in-situ assembly technology and the large-size underwater obstacle breaking technology are applied to improve the efficiency and overcome geological problems; a guide pulley and a steel strand suspension system guarantee vertical lowering of the cofferdam, and loss is reduced; the structure stability and perpendicularity are ensured through the self-floating height-connecting limiting device; and accurate sinking is realized by a water injection technology. The method is suitable for a deepwater complex geological environment and has a wide application prospect.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the field of steel cofferdam construction, in particular to a suspended assembled segmented high-rise sinking double-wall steel cofferdam and a construction method. Background Art

[0002] Under the background of the rapid development of infrastructure construction, the demand for the construction of cross-river and cross-sea bridges is growing. These bridge projects often face the challenges of deep water levels and high safety risks, especially the construction technology of deep-water caps has become a key difficulty. Although the traditional double-wall steel cofferdam construction method has advantages in safety and stability, in the application of deep-water and high cofferdams, the material loss of rigid hangers is large, and affected by the verticality of the casing, the deviation of the anchor point position will further affect the construction efficiency and accuracy. In addition, the geological conditions of deep-water rivers are complex, mostly hard strata, and large obstacles are prone to exist, which makes it difficult to sink the cofferdam and the construction progress is slow.

[0003] Therefore, how to propose a method for sinking a steel cofferdam in deep water areas with complex strata that is convenient for the overall sinking of the steel cofferdam and has high construction efficiency has become a technical problem that technical personnel in this field urgently need to solve. Summary of the invention

[0004] The purpose of the present invention is to provide a suspended assembled segmented high-rise sinking double-wall steel cofferdam and a construction method to solve the above-mentioned technical problems.

[0005] In order to solve the above technical problems, the present invention provides a construction method for suspended assembly of segments and high-rise sinking of double-wall steel cofferdam, comprising the following steps: Step 1: Remove large underwater obstacles: Scan the riverbed to determine the underwater bottom line and obstacles; Use the drilling platform to drill underwater; Install explosives at the drilling site and detonate; Then remove the ballast and inspect the foundation pit; Step 2: Building an assembly platform based on the steel casing; Step 3: In-situ assembly of the first section of steel cofferdam: Several first sections of steel cofferdam are assembled in blocks on the assembly platform for preliminary trial assembly, and fixed into a whole after accurate assembly; Step 4: Install the inner support of the first section of the steel cofferdam: The inner support includes a number of staggered support steel pipes. Several layers of inner support are arranged along the height direction on the inner side of the first section of the steel cofferdam. A second I-beam is arranged between the bottom of the support steel pipe and the first section of the steel cofferdam. Step 5, install the guide pulley limiting device: the pulley is rotated to the middle position of one side of the guide pulley limiting device; the guide pulley limiting device is set at the position of the edge steel casing, and the guide pulley limiting device is fixed to the lower side of the inner wall of the first section of the steel cofferdam so that the pulley contacts the surface of the steel casing; Step 6, install the suspension system and test-lift the steel cofferdam: set an anchor block in the middle and lower part of the inner side of the inner wall of the first section of the steel cofferdam; use a steel casing as a load-bearing column, and set a number of third I-beams on the steel casing; set a hydraulic jack at each end of each third I-beam; use steel strands to pass through the hydraulic jacks and the third I-beams in sequence and then connect to the anchor block; a number of winding rods are set on one side of the anchor block for winding the steel strands; after the suspension system is installed, use a hydraulic jack for test lifting; Step 7: Install the intelligent detection system: a number of first sensors are arranged in a longitudinal array in the compartment of the first section of the steel cofferdam wall, and a number of second sensors are arranged at a certain interval on the supporting steel pipe; Step 8: Lift the steel cofferdam and dismantle the assembly platform: lift the first section of the steel cofferdam as a whole and fix it in place; first dismantle the triangular embedded structure, then dismantle the I-beam distribution beam, and finally dismantle the corbel; Step 9: Lower the first section of the steel cofferdam: mark the scale line on the outer wall of the first section of the steel cofferdam before lowering it, and monitor the top of the first section of the steel cofferdam; decompress all hydraulic jacks simultaneously, and lower the first section of the steel cofferdam into the water through the steel strands; stop sinking when it sinks to the designed position; Step 10: Self-floating high limit device assists in raising the second section of the steel cofferdam: a first self-floating high limit device and a second self-floating high limit device are respectively arranged around the outer wall and the inner wall of the first section of the steel cofferdam on the water surface; the second section of the steel cofferdam is hoisted in blocks and assembled based on the top of the first section of the steel cofferdam; the first self-floating high limit device and the second self-floating high limit device limit the lateral displacement of the second section of the steel cofferdam; Step 11: Install the inner support of the second section of the steel cofferdam: The installation of the inner support of the second section of the steel cofferdam is consistent with the installation of the inner support of the first section of the steel cofferdam described in step 4; when the second section of the steel cofferdam is used for height connection, water is injected into the wall compartment using conduits on both sides of the symmetrical sides of the second section of the steel cofferdam; Step 12: Inject water into the conduit to sink the steel cofferdam to the specified elevation: insert the conduit into each wall compartment at the top of the second section of the steel cofferdam, and inject water symmetrically and synchronously to sink the second section of the steel cofferdam; stop injecting water when it sinks to the designed elevation and the blade corners are submerged in the riverbed to a certain depth; after the lowering is completed, fix the first section of the steel cofferdam and the steel casing, and remove the suspension lifting system at the same time; Step 13: pouring blade corner concrete: pour concrete into the compartment of the cofferdam wall, and stop pouring when the concrete is flush with the riverbed; Step 14: Foundation treatment before bottom sealing: block the underwater terrain and cofferdam gaps; clean up the silt after blocking; Step 15: Pouring bottom concrete: After the cofferdam is cleaned and leveled, the vertical conduit method is used to perform partitioned concrete bottom sealing; Step 16: Pump out the water inside the steel cofferdam: When the strength of the bottom concrete reaches more than 90%, pump out the water inside the steel cofferdam until the bottom concrete is exposed; after the pumping is completed, chisel off the loose layer on the surface of the bottom concrete and perform mortar leveling; Step 17: Cut off the steel casing to construct the pier body: Cut off all the steel casing along the bottom, and chisel off the pile head of the steel casing before constructing the pier body; The pier body is constructed by pouring in layers, and the internal support of the steel cofferdam at the corresponding level is removed for each layer poured; Step 18. Cut and dismantle the steel cofferdam in blocks along the riverbed: After the pier is out of water, cut the steel cofferdam along the bottom of the riverbed and cut it into blocks along the assembly seams.

[0006] The beneficial effects of the present invention are: 1) The present invention adopts the installation of intelligent detection system, and monitors the displacement of the cofferdam top, the supporting axial force, the internal force of the cofferdam, and the water level inside and outside the cofferdam by arranging automated sensor equipment; a systematic intelligent monitoring system is formed with a total station and automated detection equipment, which effectively improves the construction accuracy and ensures the construction safety; 2) The present invention adopts the in-situ assembly technology of double-walled steel cofferdam segments. The double-walled steel cofferdam can be prefabricated on-site or off-site with high processing precision and good water tightness, thus ensuring the quality of the finished product. The cofferdam can be efficiently assembled on the water surface in-situ to reduce assembly errors. It can be lowered after assembly is completed, thus significantly improving construction efficiency. 3) The present invention introduces underwater removal technology for large-volume obstacles, and solves the difficulty of sinking the cofferdam caused by complex geological conditions such as hard strata in deep-water rivers by removing obstacles through drilling and blasting; 4) The present invention adopts a new guide pulley limiting device, which reduces the number of limiting devices while playing a limiting role; by setting the pulley, the friction between the limiting device and the steel casing wall is reduced, ensuring the verticality and accuracy of the double-wall steel cofferdam during the lowering process; 5) The present invention adopts a steel strand flexible suspension system to ensure the stability of the lowering process and improve the lowering speed, solving the problems of large material loss and deviation of the anchoring position of traditional rigid hangers in deep water and high cofferdam scenarios; 6) The present invention adopts a new self-floating height limit device, which improves the accuracy of assembly, ensures the verticality of the segmental double-wall steel cofferdam during the height connection process, and enhances the overall stability of the structure; 7) The present invention optimizes the construction process. During the process of connecting and sinking, water is injected into the symmetrical side warehouse wall of the connection to balance the force during the connection of the cofferdam, and its deformation and sinking posture are effectively adjusted; 8) The present invention optimizes the construction process. After the cofferdam is cleared and leveled, the vertical conduit method is used to perform partitioned bottom sealing. The conduit layout is arranged reasonably and in detail. The intelligent detection system is linked to finely control the concrete pouring process, which greatly improves the quality of pouring bottom sealing concrete construction; 9) The present invention ensures construction safety. Oxygen acetylene cutting is used in the steel cofferdam cutting construction, abandoning the traditional solution to reduce construction risks. At the same time, when the cofferdam is burned and cut into two halves, the upper cofferdam is impacted by the water flow and moves downstream, and moves suddenly at the moment the cofferdam is disconnected. When the diver is cutting the cofferdam, connectors and inverted screws are installed above and below the cutting line to prevent the upper cofferdam from being impacted by the water flow, which will suddenly endanger the diver's safety at the moment the cofferdam is disconnected. BRIEF DESCRIPTION OF THE DRAWINGS

[0007] Figure 1 It is a partial cross-sectional view of the assembly platform of the present invention; Figure 2 A top view of the arrangement of supports and sensors inside the cofferdam of the present invention; Figure 3 It is a cross-sectional view of the arrangement of the support and sensors inside the cofferdam of the present invention; Figure 4 A three-dimensional diagram of the guide pulley limiting device of the present invention; Figure 5 A top view of the weir suspension system of the present invention; Figure 6 is a cross-sectional view of the cofferdam suspension system of the present invention; Figure 7 This is a partial cross-sectional view of the auxiliary height connection of the self-floating limiter device of the present invention; Figure 8 It is a top view of the self-floating limiting device of the present invention; Fig. 9 A three-dimensional schematic diagram of the upper and lower connectors of the cofferdam cutting seam of the present invention Fig.10 It is the overall construction flow chart of the present invention; In the figure: 1. first section of steel cofferdam; 2. steel casing; 3. corbel; 4. first I-beam; 5. triangular embedded structure; 6. angle steel; 7. supporting steel pipe; 8. first sensor; 9. second sensor; 10. second I-beam; 11. guide pulley limit device; 12. steel pulley; 13. third I-beam; 14. hydraulic jack; 15. steel strand; 16. anchor block; 17. winding rod; 18. first self-floating limit device; 19. second self-floating limit device; 20. second section of steel cofferdam; 21. connector; 22. inverted screw. DETAILED DESCRIPTION

[0008] The following will be combined with the accompanying drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field belong to the scope of protection of the present invention.

[0009] Those skilled in the art should understand that, in the disclosure of the present invention, the terms "longitudinal", "lateral", "up", "down", "front", "back", "left", "right", "vertical", "horizontal", "top", "bottom", "inside", "outside", etc., indicating the orientation or position relationship, are based on the orientation or position relationship shown in the drawings, which are only for the convenience of describing the present invention and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operate in a specific orientation. Therefore, the above terms should not be understood as limiting the present invention.

[0010] It is to be understood that the term "one" should be understood as "at least one" or "one or more", that is, in one embodiment, the number of an element may be one, while in another embodiment, the number of the element may be multiple, and the term "one" should not be understood as a limitation on the quantity.

[0011] like Figure 1-Figure 10 The present invention provides a construction method for suspended assembly of segments and height-sinking double-wall steel cofferdams, comprising the following steps: Step 1: Remove large underwater obstacles: Scan the riverbed to determine the underwater bottom line and the accurate location of obstacles; Position the drilling platform and perform underwater drilling; Load explosives at the drilling site and connect the detonation network; Evacuate the drilling platform and perform detonation; Then clear the slag and inspect the foundation pit; Step 2: Build an assembly platform based on the steel casing: Figure 1 The bracket 3 is fixed to the outer wall position of the center line of the steel casing 2 by welding, and the first I-beam 4 is set on the bracket 3 as a distribution beam; a triangular embedded structure 5 is set on the first I-beam 4 by using a steel component, and an angle steel 6 is installed at the edge of the first I-beam 4 to fix the edge angle of the steel cofferdam; the bracket 3 is assembled from a plurality of channel steels; the first I-beam 4, the bracket 3 and the triangular embedded structure 5 are all connected by bolts, so that a plurality of steel casings 2, the bracket 3, the first I-beam 4, the triangular embedded structure 5 and the angle steel 6 are spliced ​​together to form an assembly platform; Among them, structures such as the steel casing 2 and the first section of the steel cofferdam 1 are placed in the foundation pit.

[0012] Step 3: In-situ assembly of the first section of steel cofferdam 1: After each section of the steel cofferdam is processed and inspected to be qualified, it is hoisted from the processing area to the storage area, and the first section of steel cofferdam 1 is transported to the site by a transport vehicle, and a preliminary trial assembly is carried out on the assembly platform; assembly positioning pin holes or positioning horse plates are set at the connection between adjacent block components to facilitate on-site assembly and positioning; after meeting the requirements and being accurately spliced, they are welded into a whole; Step 4: Install the inner support of the first section of steel cofferdam 1: Figure 2-Figure 3 As shown, the inner support includes a plurality of staggered support steel pipes 7, and three layers of inner support are arranged along the height direction on the inner side of the first section of the steel cofferdam 1, and each layer includes three support steel pipes 7 in the horizontal and vertical directions; a second I-beam 10 is welded between the bottom of the support steel pipe 7 and the first section of the steel cofferdam 1 as a support to support the support steel pipe 7; Step 5: Install the guide pulley limit device 11: Figure 4-Figure 6 As shown, the guide pulley limiting device 11 is a steel structure as a whole, and the pulley 12 is a steel pulley, which is rotatably arranged in the middle position of one side of the guide pulley limiting device 11; the guide pulley limiting device 11 is prefabricated in advance; the guide pulley limiting device 11 is arranged at the positions of the four corner steel casings 2 to ensure that the verticality and lowering accuracy are maintained during the lowering of the steel cofferdam; the guide pulley limiting device 11 is fixed to the lower side of the inner wall of the first section of the steel cofferdam 1 by welding, and the pulley 12 is in contact with the surface of the steel casing 2 to reduce the friction during the lowering process of the steel cofferdam; Among them, the side of the guide pulley limiting device 11 close to the steel casing 2 has an arc structure matching the steel casing 2, and the pulley 12 is rotatably set in the middle position of the arc structure to ensure that during the lowering of the first section of the steel cofferdam 1, the pulley 12 rolls along the surface of the steel casing 2.

[0013] Step 6: Install the suspension system and test the steel cofferdam: Figure 5-Figure 6As shown, an anchor block 16 is welded at the middle and lower part of the inner wall of the first section of the steel cofferdam 1; a steel casing 2 is used as a load-bearing column, a cross cut with a certain width is made at the top of the steel casing 2, and then two staggered third I-beams 13 are embedded in the cut as a shoulder beam, and the two third I-beams 13 are staggered and stacked up and down and fixed with bolts; the third I-beams 13 at the bottom are welded and fixed to the steel casing 2; each third I-beam 13 is connected and erected in the cut of two adjacent steel casings 2; a hydraulic jack 14 is set at each end of each third I-beam 13; a flexible steel strand 1 is used 5 passes through the hydraulic jack 14 and the third I-beam 13 in sequence and is wound and connected with the anchor block 16; three winding rods 17 are provided on one side of the anchor block 16 to facilitate winding the steel strand 15 so as to lift the steel cofferdam; after the suspension system installation inspection is qualified, use the hydraulic jack 14 for trial lifting; lift the first section of the steel cofferdam 1 until the blade foot is 10 cm away from the assembly platform, observe whether the steel strand 15 and the lifting point are abnormal, if there is any abnormality, it needs to be repaired; before lowering the first section of the steel cofferdam 1, use the kerosene penetration method to test the cofferdam for impermeability to ensure that the steel cofferdam is welded in place and there is no leakage; Step 7: Install the intelligent detection system: Figure 2 , Figure 3 As shown, a plurality of first sensors 8 are arranged in a longitudinal array in the wall compartment of the first section of the steel cofferdam 1, and a plurality of second sensors 9 are arranged at a certain interval on the supporting steel pipe 7 to monitor the cofferdam support axial force, the cofferdam internal force and the water level inside and outside the cofferdam; a total station and automated detection equipment are used to form an intelligent monitoring system on the temporary floating platform outside the cofferdam; the intelligent monitoring system monitors the entire process of the cofferdam lowering and use; the information collected by the sensors and automated detection equipment is uniformly transmitted to the cloud system, and after system calculation and processing, the suspension lowering system, water injection equipment and other facilities are remotely controlled to ensure the accuracy and safety of the entire construction process; Step 8: Lift the steel cofferdam and dismantle the assembly platform: Figure 1 As shown, the first section of the steel cofferdam 1 is lifted by 0.5m as a whole using the suspension system and then fixed; the assembly platform and facilities that will affect the launching of the first section of the steel cofferdam 1 are removed as soon as possible; the removal sequence is to first remove the triangular embedded structure 5, then remove the I-beam distribution beam 4, and finally cut and remove the bracket 3 welded to the steel casing; Step 9: Lower the first section of steel cofferdam 1: Figure 4 , Figure 5 As shown, before lowering, the scale line is marked on the outer wall of the first section of steel cofferdam 1, and the top of the first section of steel cofferdam 1 is monitored by a total station to control the water depth; all hydraulic jacks 14 of the suspension system are decompressed synchronously, and the first section of steel cofferdam 1 is slowly lowered into the water through the steel strand 15; when it sinks to the designed position, it should stop sinking; the top surface of the first section of steel cofferdam 1 should be exposed 1m above the water surface to facilitate the connection with the second section of steel cofferdam 20; Step 10: Self-floating high limit device to assist in raising the second section of the steel cofferdam: Figure 7 , Figure 8 As shown, a first self-floating high limit device 18 and a second self-floating high limit device 19 are arranged on the water surface around the outer wall and the inner wall of the first section of the steel cofferdam 1; the first self-floating high limit device 18 and the second self-floating high limit device 19 are made of PVC material; the second section of the steel cofferdam 20 is hoisted in blocks and assembled based on the top of the first section of the steel cofferdam 1; the self-floating high limit devices 18 and 19 improve the accuracy of assembly by limiting the lateral displacement of the second section of the steel cofferdam 20, ensure the verticality of the second section of the steel cofferdam 20, and provide certain support; Step 11, installing inner support for the second section of the steel cofferdam 20: The installation of inner support for the second section of the steel cofferdam 20 is consistent with the installation of inner support for the first section of the steel cofferdam 1 described in step 4; when the second section of the steel cofferdam 20 is used for height connection, water is injected into the wall compartment using conduits on both sides of the symmetric sides of the second section of the steel cofferdam 20 to balance the weight on both sides and maintain the balance of the second section of the steel cofferdam 20; Among them, the wall warehouse compartment refers to the partition space formed by the inner wall and outer wall of the steel cofferdam supported by the steel structure.

[0014] Step 12, water is injected into the conduit to make the steel cofferdam sink to the specified elevation: the conduit is extended into each wall compartment at the top of the second section of the steel cofferdam 20, and water is injected symmetrically and synchronously; under the action of water injection, the second section of the steel cofferdam 20 begins to sink; the elevation of the top of the second section of the steel cofferdam 20 is constantly monitored by a total station, and when it sinks to the designed elevation and the blade corner is submerged in the riverbed to a certain depth, the water injection is stopped; during the water injection process, the hydraulic jack 14 in the suspension system is synchronously decompressed and lowered; observe whether the cofferdam is lowered accurately, and after ensuring that the cofferdam is lowered accurately, the first section of the steel cofferdam 1 is welded and fixed to the steel casing 2 with steel sections, and the suspension lifting system is removed at the same time; Step 13: pouring blade corner concrete: pour concrete evenly into the compartment of the cofferdam wall, and stop pouring when it is flush with the riverbed height; the amount of concrete poured should be calculated in advance based on the designed depth of the riverbed and the volume of the cofferdam; Step 14: Foundation treatment before bottom sealing: Arrange divers to check underwater conditions and seal the underwater terrain and cofferdam gaps; ensure that there is no gap between the bottom of the cofferdam and the riverbed to ensure the integrity of the subsequent concrete pouring; clean up the silt after sealing; Step 15: Pouring bottom sealing concrete: After the cofferdam is cleared and leveled, the vertical conduit method is used to perform concrete bottom sealing in different areas. Before bottom sealing, the height from the lower end of the conduit to the riverbed is measured and controlled to be about 20 cm, and it is suspended in the air. After the conduit is installed, the quality of the conduit must be inspected. At the same time, the conduit's internal and external leakage, bending condition, and tightness of the joints must also be inspected. At the same time, the welding quality of the conduit must be ensured to ensure that it does not leak water, slurry, or mud. There are a total of 22 groups of concrete conduits in this project, with 5 conduits in each group. The radius between each group of conduits is about 5. m, and the conduit must be fully covered during underwater concrete pouring; to improve the anti-seepage effect, the conduit must be evenly laid out on the inner and outer walls of the steel cofferdam, and poured tightly with concrete; the distance between the laid conduit and the outer wall of the steel cofferdam should be reasonably controlled so that the concrete can flow freely and ensure that it can be fully consolidated; a large hopper is used to pour the first batch of concrete, and then a small hopper is used; during the bottom sealing process, the same conduit is poured twice every 45 to 60 minutes to ensure continuity; the bottom sealing is carried out in columns, and after each column is completed, the conduit is pulled out and moved to the next column to continue; monitoring points are arranged before the bottom sealing to record the concrete depth and flow area, ensuring that the maximum thickness of the bottom sealing concrete is 4.0 m, and a 20 cm leveling layer is reserved; during the pouring process, the lifting height of the conduit does not exceed 0.2 m to ensure the burial depth, and at the same time, the monitoring point completes one monitoring and records; the thickness of the bottom sealing concrete is 3.0 m, considering the stress characteristics and bonding strength, φ325 mm seamless steel pipe is used as the conduit, and the design water pressure is 1.2 times the overpressure; to ensure thickness and anti-seepage, the conduit is evenly distributed, keeps a certain distance from the steel casing, moves with a radius of 3.5 m, and the bottom is 20 cm away from the bottom of the cofferdam; the final pouring depends on the concrete elevation of the monitoring point, and the conduit is lifted before the end to reduce the burial depth to ensure that there is no air retention and the surface is flat; after completion, the concrete surface elevation is measured, and the pouring amount is adjusted according to the data to ensure the top surface is flat; focus on monitoring the intersection of the conduit action radius, the surrounding of the casing, and the inner side of the cofferdam. When the requirements are met, stop pouring and move to other points; ensure the flatness of the concrete surface, the even distribution of the distribution points, and the operating radius does not exceed 3.5m. Pay special attention to the concrete surface elevation at the intersection of the distribution point radius; Step 16: Pump out the water inside the steel cofferdam: When the strength of the bottom concrete reaches more than 90%, pump out the water inside the steel cofferdam slowly; keep the pumping process slow and uniform, and pay close attention to the cofferdam force and water level through the monitoring system. Stop pumping immediately if any abnormality occurs; if there is leakage, arrange for a special person to seal it in time until the bottom concrete is exposed; after the pumping is completed, chisel off the loose layer on the surface of the bottom concrete and level it with mortar; Step 17: Cut off the steel casing 2 to carry out the pier body construction: Cut off all the steel casing 2 along the bottom, and chisel off the pile head of the steel casing 2 before carrying out the pier body construction; The pier body construction is cast in layers, and the inner support of the steel cofferdam at the corresponding level is removed for each layer cast; Step 18: Cut and dismantle the steel cofferdam along the riverbed: Fig. 9 As shown, after the pier body is out of water, divers are arranged to cut the steel cofferdam along the bottom of the riverbed, and at the same time, it is cut into blocks according to the assembly seams. Each layer of the cofferdam is divided into several unit boxes according to the assembly structure and disassembled one by one. Each unit box weighs about 10 tons, and a layer-by-layer dismantling scheme is adopted; in order to eliminate safety hazards, oxygen acetylene cutting is used in construction, and the traditional lifting scheme is abandoned to reduce construction risks; when the cofferdam is burned and cut into two halves, the upper cofferdam is impacted by the water flow and moves downstream, and it is easy to produce a sudden movement at the moment when the cofferdam is disconnected. In order to ensure the safety of the divers, a connector 21 is welded above and below the burning and cutting line, and the two adjacent connectors 21 are connected by an inverted screw 22 to enable them to withstand horizontal forces; at the same time, it is cut into blocks according to the assembly seams; and the blocks are lifted in the assembly order.

[0015] The invention also discloses a suspended assembled segmented high-sunk double-wall steel cofferdam, which is obtained by construction according to the above construction method.

[0016] The present invention is not limited to the above-mentioned optimal implementation mode. Anyone can derive other various forms of products under the inspiration of the present invention. However, no matter what changes are made in the shape or structure, all technical solutions that are the same or similar to those of the present application fall within the protection scope of the present invention.

Claims

1. A construction method for suspended assembly of segments and high-sinking double-wall steel cofferdam, characterized in that: The following steps are involved: Fixing a plurality of first-section steel cofferdams (1) into a whole on an assembly platform; The first section of the steel cofferdam (1) is provided with an internal support: the internal support comprises a plurality of staggered supporting steel pipes (7), and a second I-beam (10) is provided between the bottom of the supporting steel pipe (7) and the first section of the steel cofferdam (1); The pulley (12) is rotatably arranged at the middle position of one side of the guide pulley limiting device (11); the guide pulley limiting device (11) is arranged at the position of the edge steel casing (2), and the guide pulley limiting device (11) is fixed to the lower side of the inner wall of the first section of the steel cofferdam (1) so that the pulley (12) contacts the surface of the steel casing (2); An anchor block (16) is arranged at the middle and lower part of the inner side of the inner wall of the first section of the steel cofferdam (1); a plurality of third I-beams (13) are arranged on the steel casing (2); a hydraulic jack (14) is arranged at each end of each third I-beam (13); a steel strand (15) is passed through the hydraulic jack (14) and the third I-beam (13) in sequence and then connected to the anchor block (16); a plurality of winding rods (17) are arranged on one side of the anchor block (16) for winding the steel strand (15); The first section of the steel cofferdam (1) is placed under water via the steel strand (15); A first self-floating high limit device (18) and a second self-floating high limit device (19) are respectively arranged around the outer wall and the inner wall of the first section of the steel cofferdam (1) on the water surface; the second section of the steel cofferdam (20) is hoisted in blocks and assembled based on the top of the first section of the steel cofferdam (1); The second section of the steel cofferdam (20) is provided with an internal support, and when the second section of the steel cofferdam (20) is used for heightening, water is injected into the second section of the steel cofferdam (20); The second section of the steel cofferdam (20) is lowered, and after the lowering is completed, the first section of the steel cofferdam (1) is fixed to the steel casing (2); Pouring bottom seal concrete; The steel cofferdam is cut along the bottom of the riverbed and cut into blocks according to the assembly seams.

2. The construction method of suspended assembly segmental height-connecting and sinking double-walled steel cofferdam according to claim 1 is characterized by: The corbel (3) is fixed to the outer wall position of the center line of the steel casing (2), and the first I-beam (4) is mounted on the corbel (3); a triangular embedded structure (5) is arranged on the first I-beam (4), and an angle steel (6) is installed at the edge of the first I-beam (4), so that a plurality of steel casings (2), the corbel (3), the first I-beam (4), the triangular embedded structure (5) and the angle steel (6) are assembled together to form an assembly platform.

3. The construction method of suspended assembly segmental height-connecting and sinking double-walled steel cofferdam according to claim 1 is characterized by: The side of the guide pulley limiting device (11) close to the steel casing (2) has an arc structure matching the steel casing (2), and the pulley (12) is rotatably arranged in the middle position of the arc structure.

4. The construction method of suspended assembly segmental height connection and sinking double-wall steel cofferdam according to claim 1 is characterized by: A cross cut is made at the top of the steel casing (2), and then at least two staggered third I-beams (13) are embedded in the cut as a shoulder beam, and at least two third I-beams (13) are staggered and stacked up and down, and the third I-beams (13) at the bottom are fixed to the steel casing (2); each third I-beam (13) is connected and mounted in the cuts of two adjacent steel casings (2).

5. The construction method of suspended assembly segmental height-connecting and sinking double-wall steel cofferdam according to claim 1 is characterized by: When the first section of the steel cofferdam (1) sinks to the designed position, the top surface of the first section of the steel cofferdam (1) is exposed 1m above the water surface.

6. The construction method of suspended assembly segmental height-connecting and sinking double-walled steel cofferdam according to claim 1 is characterized by: The first self-floating high limit device (18) and the second self-floating high limit device (19) are made of PVC material.

7. The construction method of suspended assembly segmental height connection and sinking double-wall steel cofferdam according to claim 1 is characterized by: Before the bottom is sealed, the height from the lower end of the conduit to the riverbed is 20 cm, and it is suspended in the air; 22 groups of concrete conduits are set, with 5 conduits in each group; the radius between each group of conduits is about 5 m; the bottom is sealed in rows, and after each row is completed, the conduit is pulled out and moved to the next row to continue.

8. The construction method of suspended assembly segmental height connection and sinking double-wall steel cofferdam according to claim 1 is characterized by: The maximum thickness of the bottom concrete is 4.0 m, and a 20 cm leveling layer is reserved; during the pouring process, the lifting height of the conduit does not exceed 0.2 m; the thickness of the bottom concrete is 3.0 m, and a φ325 mm seamless steel pipe is used as the conduit, with a moving radius of 3.5 m and the bottom 20 cm away from the bottom of the cofferdam.

9. The construction method of suspended assembly segmental height-connecting and sinking double-wall steel cofferdam according to claim 1 is characterized by: Connecting pieces (21) are welded above and below the assembling seam, and an inverted screw rod (22) is connected between two adjacent connecting pieces (21).

10. A suspended assembled segmented high-rise double-wall steel cofferdam, characterized by: It is obtained by the construction method of suspended assembled segments and sunk double-walled steel cofferdam according to claims 1-8.

Citation Information

Patent Citations

  • Hanging and floating assembly steel cofferdam and launching construction method thereof

    CN108396754A

  • Double-wall steel cofferdam construction method

    CN114775662A

  • Inclined riverbed surface bottomless steel hanging box cofferdam limiting device and method

    CN118223514A

  • Self-standing cofferdam structure and self-standing cofferdam method

    JP2011208389A

Cited By

  • A cofferdam device for water conservancy construction

    CN119777403A