Automatic analysis method and system for grid-connected test data of electrochemical energy storage system

By automatically analyzing the test data of the grid-connected test of the electrochemical energy storage system, the problem of low manual processing efficiency and difficult to ensure accuracy is solved, and efficient and accurate data analysis and equipment performance evaluation are achieved.

CN115201558BActive Publication Date: 2024-11-22STATE GRID HUNAN ELECTRIC POWER COMPANY LIMITED +2
View PDF 3 Cites 0 Cited by

Patent Information

Application Number
CN202210815131.X
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2022-07-12
Publication Date
2024-11-22
Estimated Expiration
2042-07-12

AI Technical Summary

Technical Problem

There are many grid-connected test projects for electrochemical energy storage systems, the test data is calculated in large quantities, manual processing and calculation efficiency are low and the accuracy is difficult to guarantee.

Method used

An automatic analysis method for grid-connected test test data of electrochemical energy storage systems, including pre-processing power test data, determining the constant power and power adjustment section through differential calculation, and determining whether the working conditions are qualified based on the specified test indicators. Processors and memory implement automatic analysis.

Benefits of technology

It realizes automatic identification of different test conditions, efficient and accurate analysis of test data, provides accurate equipment performance evaluation, and improves computing efficiency and accuracy.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN115201558B_ABST
    Figure CN115201558B_ABST
Patent Text Reader

Abstract

The present invention discloses an automatic analysis method and system for test data of an electrochemical energy storage system grid-connected test. The automatic analysis method for test data of an electrochemical energy storage system grid-connected test of the present invention includes: preprocessing the power test data of the electrochemical energy storage system grid-connected test; performing differential calculation on the preprocessed power test data, using the average value of the absolute value of the differential calculation result as a threshold, and locating the constant power section and the power adjustment section in the power test data according to the threshold; according to the working conditions of the electrochemical energy storage system grid-connected test, selecting the data of the required section in the constant power section and the power adjustment section and calculating the specified test index, and judging whether the working condition is qualified according to the calculated specified test index. The present invention can automatically identify different test conditions to analyze test data, calculate test results, provide an accurate reference for judging the specific performance of the equipment, and has the advantages of high calculation efficiency and high calculation accuracy.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention belongs to the technical field of electric power systems, and in particular relates to a method and system for automatically analyzing test data of a grid-connected test of an electrochemical energy storage system. Background Art

[0002] The grid-connected test of electrochemical energy storage system is an important technical means to evaluate the grid-connected operation performance of energy storage equipment and improve the support capacity of the power grid. With the expansion of energy storage scale, its importance becomes more and more prominent. At present, GB 36547-2018 Technical Regulations for the Access of Electrochemical Energy Storage System to the Grid, GB 36548-2018 Specifications for the Test of the Access of Electrochemical Energy Storage System to the Grid, DL / T 2246-2021 Technical Specifications for the Grid-Connected Operation and Control of Electrochemical Energy Storage Stations and other standards have made clear requirements on the grid adaptability, power control capability, charge and discharge conversion time, charge and discharge response time, charge and discharge adjustment time, low voltage ride-through capability, high voltage ride-through capability, primary frequency modulation characteristics, inertia characteristics, etc. of the energy storage system, providing a reference for the test items, test methods and test standards for the grid-connected test of the electrochemical energy storage system. Due to the large variety of grid-connected test items and complex test conditions of energy storage systems, the test data calculation is large, the manual processing calculation efficiency is low, and the accuracy is difficult to guarantee. Therefore, an efficient and accurate automatic analysis method for test data of the grid-connected test of electrochemical energy storage systems is needed to realize batch processing and analysis of test data. Summary of the invention

[0003] The technical problem to be solved by the present invention is as follows: in view of the fact that there are many grid-connected test items for energy storage systems, the amount of test data calculation is large, and the efficiency and accuracy of manual calculation are difficult to guarantee, a method and system for automatically analyzing test data of grid-connected tests of electrochemical energy storage systems are provided. The present invention can automatically identify different test conditions to analyze test data, calculate test results, and provide an accurate reference for judging the specific performance of the equipment, and has the advantages of high calculation efficiency and high calculation accuracy.

[0004] In order to solve the above technical problems, the technical solution adopted by the present invention is:

[0005] A method for automatically analyzing test data of an electrochemical energy storage system grid-connected test, comprising:

[0006] S1, preprocessing the power test data of the grid-connected test of the electrochemical energy storage system;

[0007] S2, performing differential calculation on the pre-processed power test data, taking the average of the absolute values ​​of the differential calculation results as a threshold, and locating the constant power section and the power adjustment section in the power test data according to the threshold;

[0008] S3, according to the working condition of the grid-connected test of the electrochemical energy storage system, select the data of the required section in the constant power section and the power adjustment section and calculate the specified test index, and judge whether the working condition is qualified according to the calculated specified test index.

[0009] Optionally, the preprocessing in step S1 includes filtering to reduce interference.

[0010] Optionally, the filtering refers to filtering using a moving average filtering algorithm.

[0011] Optionally, the preprocessing in step S1 further includes data truncation, wherein the data truncation includes truncation of at least one of partially invalid data at the beginning and partially invalid data at the end of the test data.

[0012] Optionally, in step S2, the preprocessed power test data is subjected to differential calculation at a specified time interval, and a difference is calculated for a pair of power test data in the preprocessed power test data and the result is divided by the time interval as the differential calculation result.

[0013] Optionally, locating the constant power section and the power adjustment section in the power test data in step S2 includes demarcating the power test data with the threshold to determine the constant power section and the power adjustment section, so that the average value of the differential calculation results within the constant power section is less than the threshold, and the absolute value of the average value of the differential calculation results within the power adjustment section is greater than or equal to the threshold.

[0014] Optionally, the operating conditions of the electrochemical energy storage system grid-connected test in step S3 include at least one of a power control test, an AGC test, a charge and discharge response time test, a charge and discharge conversion time, a charge and discharge adjustment time, an inertia characteristic test, and a low voltage ride-through test.

[0015] Optionally, step S3 includes at least one of the following tests: for any one of the power tests in the power control test and the AGC test: record the time of entering the constant power section and the time of leaving the constant power section, and calculate the power average value between the two times as the test result. If the difference between the test result and the command value is less than the set power limit, it is determined that the accuracy of the power test is qualified; for any one of the time tests in the charge and discharge response time test, the charge and discharge conversion time and the charge and discharge adjustment time: determine the time difference between the time of entering the power adjustment section and the time when the active power reaches a specified proportion of the rated active power, and add the communication delay to the time difference. The total time difference is obtained when the load is turned on and off. If the total time difference is less than the set time limit, the time test is determined to be qualified. For the inertia characteristic test: record the time of entering the power adjustment section and the time of leaving the power adjustment section, calculate the average active power between the two times, and subtract the set power value from the average value as the inertia characteristic test result. If the inertia characteristic test result is within the set range, the inertia characteristic test is determined to be qualified. For the low voltage ride-through test: record the time of entering the constant power section and the time of leaving the constant power section, and calculate the average reactive power between the two times. If the average value is greater than the set reactive power limit, the low voltage ride-through test is determined to be qualified.

[0016] In addition, the present invention also provides an automatic analysis system for grid-connected test data of an electrochemical energy storage system, comprising a microprocessor and a memory connected to each other, wherein the microprocessor is programmed or configured to execute the steps of the automatic analysis method for grid-connected test data of an electrochemical energy storage system.

[0017] In addition, the present invention also provides a computer-readable storage medium, in which a computer program is stored, and the computer program is used to be programmed or configured by a microprocessor to execute the steps of the automatic analysis method of the electrochemical energy storage system grid-connected test test data.

[0018] Compared with the prior art, the present invention mainly has the following advantages: the method for automatically analyzing test data of the grid-connected test of the electrochemical energy storage system of the present invention includes: preprocessing the power test data of the grid-connected test of the electrochemical energy storage system; performing differential calculation on the preprocessed power test data, taking the average value of the absolute value of the differential calculation result as the threshold, and locating the constant power section and the power adjustment section in the power test data according to the threshold; according to the working conditions of the grid-connected test of the electrochemical energy storage system, selecting the data of the required section in the constant power section and the power adjustment section and calculating the specified test index, and judging whether the working condition is qualified according to the calculated specified test index. The present invention can automatically identify different test conditions to analyze test data, calculate test results, provide an accurate reference for judging the specific performance of the equipment, and has the advantages of high calculation efficiency and high calculation accuracy. BRIEF DESCRIPTION OF THE DRAWINGS

[0019] Figure 1 Schematic diagram of the basic flow of the method of the embodiment of the present invention.

[0020] Figure 2 The figure is a comparison of power test data before and after pretreatment in the embodiment of the present invention.

[0021] Figure 3 It is an enlarged part of the comparison of power test data before and after preprocessing in the embodiment of the present invention.

[0022] Figure 4 It is the result of difference calculation in the embodiment of the present invention. DETAILED DESCRIPTION

[0023] The present invention will be further described in detail below using a 22.5MW / 45MWh energy storage power station as an example of an electrochemical energy storage system. The energy storage power station adopts electrochemical energy storage technology, and lithium iron phosphate batteries are selected as batteries.

[0024] like Figure 1 As shown, the method for automatically analyzing the test data of the electrochemical energy storage system grid-connected test in this embodiment includes:

[0025] S1, preprocessing the power test data of the grid-connected test of the electrochemical energy storage system;

[0026] S2, performing differential calculation on the pre-processed power test data, taking the average of the absolute values ​​of the differential calculation results as a threshold, and locating the constant power section and the power adjustment section in the power test data according to the threshold;

[0027] S3, according to the working condition of the grid-connected test of the electrochemical energy storage system, select the data of the required section in the constant power section and the power adjustment section and calculate the specified test index, and judge whether the working condition is qualified according to the calculated specified test index.

[0028] The preprocessing in step S1 of this embodiment includes filtering to reduce interference. In this embodiment, filtering refers to filtering using a moving average filtering algorithm. The test data of the energy storage system grid-connected test comes from field measurements, and there is high-frequency interference in the data. The moving average filtering algorithm can effectively reduce interference (the power control accuracy test data is not suitable for filtering). Among them, the moving average filtering algorithm refers to using a moving window of a specified size to move in the power test data, and taking the average value of the power test data in each moving window. If the difference between a certain power test data and the average value exceeds the set value, the power test data is determined to be a noise signal and filtered. In addition, during the grid-connected test of the energy storage system, the starting point and end point of the data record are determined by the tester, and it is inevitable that there are some invalid data at the beginning and end of the data. Therefore, the preprocessing in step S1 of this embodiment also includes data truncation, and the data truncation includes truncation processing for some invalid data at the beginning and some invalid data at the end of the test data (including one or two of them according to the data situation), so that some data at the beginning and end can be deleted before calculation, reducing the interference of invalid data.

[0029] The power test data before and after preprocessing of the power test data of the electrochemical energy storage system grid-connected test in step S1 of this embodiment is compared. Figure 2 As shown, the left side is the power test data before preprocessing, and the right side is the power test data after preprocessing. Figure 2 The left and right parts are placed in the same coordinate system, and the result obtained after zooming in on the part is as follows Figure 3 As shown, see Figure 3 Obviously, through the preprocessing in step S1, the power fluctuation under constant working conditions is greatly reduced, which facilitates the subsequent distinction between the stable section and the transition section, and effectively reduces the interference of invalid data.

[0030] In step S2 of this embodiment, differential calculation is performed on the preprocessed power test data according to the specified time interval, and the difference of a pair of power test data in the preprocessed power test data is calculated and divided by the time interval as the differential calculation result. The operating conditions of the energy storage grid-connected test can be generally divided into two categories, one is the constant operating condition, and the other is the transitional operating condition. In most test items of the energy storage system grid-connected test, the proportion of constant operating conditions is much larger than that of transitional operating conditions. The test data is differentially calculated, and the average value of the absolute value of the differential calculation result is used as the threshold, which can accurately distinguish the thresholds of constant operating conditions and transitional operating conditions. In this embodiment, the preprocessed data is differentially calculated, and the average value of the absolute value of the differential is used as the threshold to divide the data into data under constant conditions and data under transitional conditions, such as Figure 4 As shown, by taking the average of the absolute values ​​of the difference calculation results as the threshold, the thresholds in the positive and negative directions can be obtained, which are respectively recorded as threshold+ and threshold-.

[0031] In this embodiment, the constant power section (the constant working condition mentioned above) and the power adjustment section (the transition working condition mentioned above) in the power test data are located in step S2, which includes using a threshold value to demarcate the power test data to determine the constant power section and the power adjustment section, so that the average value of the differential calculation result in the constant power section is less than the threshold value, and the absolute value of the average value of the differential calculation result in the power adjustment section is greater than or equal to the threshold value. The threshold value can be used to simply and accurately distinguish between the constant working condition and the transition working condition, thereby providing accurate time point positioning for various working condition tests below. Figure 4 , the curve is divided based on the threshold + and threshold - lines, respectively, to determine the constant power section and the power adjustment section. For example, some power test data in the constant power section of this embodiment are shown in the following table:

[0032]

[0033] In the above table, P_set represents the power command value, P_meas represents the power measurement value, ΔP represents the deviation between the power command value and the power measurement value, and the deviation ratio refers to the ratio of the deviation ΔP to the rated power.

[0034] In this embodiment, step S3 includes at least one of the following tests:

[0035] For any power test in the power control test and the AGC test: record the time of entering the constant power section and the time of leaving the constant power section, and calculate the average value of the active power between the two times as the test result. If the difference between the test result and the command value is less than the set power limit value (the specific value in this embodiment is 2%), it is determined that the accuracy of the power test is qualified;

[0036] For any one of the time tests of the charge-discharge response time test, the charge-discharge conversion time and the charge-discharge adjustment time: determine the time difference between the moment of entering the power adjustment section and the moment when the active power reaches a specified proportion of the rated active power (for example, 90% in this embodiment), add the time difference to the communication delay to obtain the total time difference, and if the total time difference is less than the set time limit (pre-set empirical value), the time test is determined to be qualified;

[0037] For the inertia characteristic test: record the time of entering the power adjustment section and the time of leaving the power adjustment section, calculate the average value of the active power between the two times, and subtract the set power value from the average value as the inertia characteristic test result. If the inertia characteristic test result is within the set range (pre-set empirical value), the inertia characteristic test is considered to be qualified;

[0038] For the low voltage ride-through test: record the time of entering the constant power section and the time of leaving the constant power section, and calculate the average value of the reactive power between the two times. If the average value is greater than the set reactive power limit (pre-set empirical value), the low voltage ride-through test is determined to be qualified.

[0039] In summary, this embodiment includes: preprocessing the power test data of the grid-connected test of the electrochemical energy storage system; performing differential calculation on the preprocessed power test data, using the average value of the absolute value of the differential calculation result as the threshold, and locating the constant power section and the power adjustment section in the power test data according to the threshold; according to the working conditions of the grid-connected test of the electrochemical energy storage system, selecting the data of the required section in the constant power section and the power adjustment section and calculating the specified test index, and judging whether the working condition is qualified according to the calculated specified test index. The present invention can automatically identify different test conditions to analyze test data, calculate test results, provide an accurate reference for judging the specific performance of the equipment, and has the advantages of high calculation efficiency and high calculation accuracy.

[0040] In addition, this embodiment also provides an automatic analysis system for grid-connected test data of an electrochemical energy storage system, comprising a microprocessor and a memory connected to each other, wherein the microprocessor is programmed or configured to execute the steps of the aforementioned automatic analysis method for grid-connected test data of an electrochemical energy storage system.

[0041] In addition, this embodiment also provides a computer-readable storage medium, in which a computer program is stored. The computer program is used to be programmed or configured by a microprocessor to execute the steps of the aforementioned method for automatically analyzing test data of the electrochemical energy storage system grid-connected test.

[0042] Those skilled in the art will appreciate that the embodiments of the present application may be provided as methods, systems, or computer program products. Therefore, the present application may take the form of a complete hardware embodiment, a complete software embodiment, or an embodiment combining software and hardware. Moreover, the present application may take the form of a computer program product implemented on one or more computer-readable storage media (including but not limited to disk storage, CD-ROM, optical storage, etc.) containing computer-usable program codes. The present application is described with reference to the flowcharts and / or block diagrams of the methods, devices (systems), and computer program products according to the embodiments of the present application. It should be understood that each process and / or box in the flowchart and / or block diagram, as well as the combination of the processes and / or boxes in the flowchart and / or block diagram, may be implemented by computer program instructions. These computer program instructions may be provided to a processor of a general-purpose computer, a special-purpose computer, an embedded processor, or other programmable data processing device to produce a machine, so that the instructions executed by the processor of the computer or other programmable data processing device generate instructions for implementing the functions in the process. Figure 1A process or multiple processes and / or boxes Figure 1 These computer program instructions can also be stored in a computer-readable memory that can guide a computer or other programmable data processing device to work in a specific way, so that the instructions stored in the computer-readable memory produce a product including an instruction device, which implements the functions specified in the process. Figure 1 A process or multiple processes and / or boxes Figure 1 These computer program instructions can also be loaded onto a computer or other programmable data processing device, so that a series of operation steps are executed on the computer or other programmable device to produce a computer-implemented process, so that the instructions executed on the computer or other programmable device provide for implementing the process in the process. Figure 1 A process or multiple processes and / or boxes Figure 1 The steps for the functions specified in one or more boxes.

[0043] The above is only a preferred embodiment of the present invention, and the protection scope of the present invention is not limited to the above embodiments. All technical solutions under the concept of the present invention belong to the protection scope of the present invention. It should be pointed out that for ordinary technicians in this technical field, some improvements and modifications without departing from the principle of the present invention should also be regarded as the protection scope of the present invention.

Claims

1. A method for automatically analyzing test data of an electrochemical energy storage system grid-connected test, characterized in that: include: S1, preprocessing the power test data of the grid-connected test of the electrochemical energy storage system; S2, performing differential calculation on the pre-processed power test data, taking the average of the absolute values ​​of the differential calculation results as a threshold, and locating the constant power section and the power adjustment section in the power test data according to the threshold; S3, according to the working condition of the grid-connected test of the electrochemical energy storage system, select the data of the required section in the constant power section and the power adjustment section and calculate the specified test index, and judge whether the working condition is qualified according to the calculated specified test index; Step S3 includes at least one of the following tests: For any power test in the power control test and AGC test: record the time of entering the constant power section and the time of leaving the constant power section, and calculate the power average value between the two times as the test result. If the difference between the test result and the command value is less than the set power limit, the accuracy of the power test is determined to be qualified; For any of the time tests of charge and discharge response time test, charge and discharge conversion time and charge and discharge adjustment time: determine the time difference between the moment of entering the power adjustment section and the moment when the active power reaches the specified proportion of the rated active power, add the time difference to the communication delay to get the total time difference, if the total time difference is less than the set time limit, then the time test is considered qualified; For the inertia characteristic test: record the time of entering the power adjustment section and the time of leaving the power adjustment section, calculate the average value of the active power between the two times, and subtract the set power value from the average value as the inertia characteristic test result. If the inertia characteristic test result is within the set range, the inertia characteristic test is considered to be qualified; For low voltage ride-through test: record the time of entering the constant power section and the time of leaving the constant power section, and calculate the average value of reactive power between the two times. If the average value is greater than the set reactive power limit, the low voltage ride-through test is considered qualified.

2. The method for automatically analyzing test data of an electrochemical energy storage system grid-connected test according to claim 1, characterized in that: The pre-processing in step S1 includes filtering to reduce interference.

3. The method for automatically analyzing test data of an electrochemical energy storage system grid-connected test according to claim 2, characterized in that: The filtering refers to filtering using a moving average filtering algorithm.

4. The method for automatically analyzing test data of an electrochemical energy storage system grid-connected test according to claim 2, characterized in that: The preprocessing in step S1 also includes data truncation, and the data truncation includes truncation of at least one of partially invalid data at the beginning and partially invalid data at the end of the test data.

5. The method for automatically analyzing test data of an electrochemical energy storage system grid-connected test according to claim 1, characterized in that: In step S2, the preprocessed power test data is subjected to differential calculation. According to a specified time interval, a difference is calculated for a pair of power test data in the preprocessed power test data and the difference is divided by the time interval to obtain a differential calculation result.

6. The method for automatically analyzing test data of an electrochemical energy storage system grid-connected test according to claim 1, characterized in that: Locating the constant power section and the power adjustment section in the power test data in step S2 includes demarcating the power test data with the threshold to determine the constant power section and the power adjustment section, so that the average value of the differential calculation results in the constant power section is less than the threshold, and the absolute value of the average value of the differential calculation results in the power adjustment section is greater than or equal to the threshold.

7. The method for automatically analyzing test data of an electrochemical energy storage system grid-connected test according to claim 1, characterized in that: The working conditions of the electrochemical energy storage system grid-connected test in step S3 include at least one of a power control test, an AGC test, a charge and discharge response time test, a charge and discharge conversion time, a charge and discharge adjustment time, an inertia characteristic test, and a low voltage ride-through test.

8. An automatic analysis system for grid-connected test data of an electrochemical energy storage system, comprising a microprocessor and a memory connected to each other, characterized in that: The microprocessor is programmed or configured to execute the steps of the method for automatically analyzing test data of an electrochemical energy storage system grid-connected test as recited in any one of claims 1 to 7.

9. A computer-readable storage medium having a computer program stored therein, characterized in that: The computer program is used to be programmed or configured by a microprocessor to execute the steps of the method for automatically analyzing test data of an electrochemical energy storage system grid-connected test as described in any one of claims 1 to 7.

Citation Information

Patent Citations

  • Hybrid capacitor power state online estimation method and system

    CN112580289A

  • SOC interval calibration method and system based on energy window and medium

    CN114035052A

  • Method and device for detecting a photovoltaic electricity production apparatus in an electrical distribution network, and associated computer program product

    US20160161537A1